Documente Academic
Documente Profesional
Documente Cultură
: ZEC-MSPW-112717
METHOD STATEMENT
BRICK WORKS
METHOD OF STATEMENT
BRICK WORKS
BRICK WORKS
CONTENTS
BRICK WORKS
This procedure provides a method of control for construction of brick masonry work in order to
achieve compliance with the contract specifications and drawings.
Wire level
Plumb bob
Chisel
Concrete swivel
Aluminum bar
Steel Angle 900/450/1350
Rubber Hammer
Brush
Bucket
Wheel trolley
3. INSTALLATION PROCEDURE
Before laying, bricks will make wet and will allow units to absorb water so they are dump but not
will be wet at the time of laying the course.
Wet the floor under walls.
Mortar bed will be spread out on footings for starting the course.
BRICK WORKS
Masonry Units/Bricks will be laid with full coverage mortar on horizontal and vertical shells and
will maintain a joint thickness of 10mm minimum and 12mm maximum for joints.
Connection between walls and partition will be bonded and tied by using wall angle to be nailed in
the column before the succeeding layer is laid.
Courses will be laid to comply with specified construction tolerances, with courses accurately spaced
and coordinated with other construction.
Cores will be filled in hollow masonry units with mortar under bearing plates, beams, lintel and post,
door and window opening jambs.
Mortar will be installed in joint between top of partition and the soffit after filling gap with solid
piece blocks and install compressible filler.
Remove and replace masonry units that are loose, chipped and broken. New units will install to
match adjoining units with fresh mortar.
Curing of masonry will be for 3 days by sprinkling of water twice a day.