Sunteți pe pagina 1din 23

SKEMPTON, A. W. (1986). Geotechnique 36, No.

3, 425-447

Standard penetration test procedures and the effects in sands of


overburden pressure, relative density, particle size, ageing and
overconsolidation
A. W. SKEMPTON*

Granted that good site control is exercised in carrying corriger le nombre de coups observe N pour obtenir la
out the standard penetration test the energy delivered valeur qui aurait ete mesuree si une energie de tige
to the sampler, and therefore the blow count obtained specifique avait ete employee. Une valeur recommandee,
in any given sand deposit at a particular effective over qui devrait etre acceptee sur le plan international, est
burden pressure, can still vary to a significant extent 60 !.1 de l'energie de chute libre du poids normal du
depending on the method of releasing the hammer, on marteau. On appelle alors le nombre de coups corrige
the type of anvil and on the length of rods (if less than N60 et on peut considerer la valeur normalisee (N 1)60 a
10 m). For consistency it is essential to correct the la pression effective specifique (! kg/cm 2 ou 100 kPa)
observed blow count N to the value which would have comme une caracteristique fondamentale du sable.
been measured using a specified rod energy. A recom L'article examine de fa9on detaillee Jes facteurs qui con
mended value, which should be recognized internation trolent le rapport de l'energie de la tige et presente des
ally, is 60% of the free-fall energy of the standard methodes pour calculer des valeurs N60. Des donnees
hammer weight and drop. The corrected blow count is selectionnees obtenues in situ et en laboratoire indi
then designated as N60 and the normalized value (N 1)60 quent que le rapport entre le nombre de coups, la press
at unit effective pressure ( 1 kg/cm 2 or 100 kPa) may be ion effective du terrain de couverture a; (kg/cm2) et la
regarded as a basic characteristic of the sand. Factors densite relative D, est donne a peu pres par une equa
controlling the rod energy ratio are examined in detail tion de la forme proposee par Meyerhof: N60 =
and methods of deriving N 60 values are developed. An (a+ ba.')D,2 ou bien (N 1)60 =(a+ b)D,2 ou a et b sont
examination of selected field and laboratory data shows des constantes pour un sable specifique dans l'intervalle
that the relation between blow count, effective overbur 035 < D, < 085 et 05 kg/cm 2 <a;< 25 kg/cm 2 Les
den pressure a; (kg/cm2 ) and relative density D, is given parametres a et b, dont Jes valeurs sont donnees pour
to a close approximation by an equation of the form tous Jes cas etudies, tendent a s'accroitre au fur et a
proposed by Meyerhof: N60 = (a + bav')D,2 or (N 1)60 = mesure que le diametre des grains, !'age du depot et le
(a+ b)D,2 where a and b are constants for a particular rapport de surconsolidation augmentent. Le desaccord
sand within the range 035 < D, < 085 and 05 apparent trouve depuis longtemps entre les essais in situ
kg/cm 2 < a; < 25 kg/cm2 I The parameters a and b, et en laboratoire disparait lorsqu'on tient compte des
values for which are given fo.r all the cases studied, tend effets des rapports differents de l'energie de la tige et du
to increase with increasing grain size, with increasing 'vieillissement'. On demontre aussi que les limites du
age of the deposit and with increasing over nombre de coups donnees par Terzaghi et Peck pour
consolidation ratio. The long-standing apparent dis differentes fourchettes de densites relatives, comme men
crepancy between field and laboratory tests is resolved tionnees par Gibbs et Holtz, representent de bonnes
when the effects of differing rod energy ratios and of valeurs moyennes pour des depots naturels de sable
'ageing' are taken into account. Also, the Terzaghi-Peck normalement consolides, a condition que Jes nombres
limits of blow count for various grades of relative de coups soient corriges pour obtenir l@s valeurs (N 1)60.
density, as enumerated by Gibbs and Holtz, are shown
to be good average values for normally consolidated
natural sand deposits, provided that the blow counts KEYWORDS: field tests; liquefaction; relative density;
are corrected to (N 1)60 values. sands.

Pourvu que le chantier soit bien controle !ors de 'stan


dard penetration test' l'energie transmise a l'appareil de
INTRODUCTION
prise de chantillon et done le nombre de coups donnes
In connection with investigations of the River
dans un depot de sable a une pression effective de Indus alluvium, for the Kalabagh Dam project in
terrain de couverture specifique peuvent encore varier Pakistan, the Author has carried out an ancillary
de fa9on importante selon la methode de declanchement study of the standard penetration test (SPT) with
du marteau, le type d'enclume et Ja longueur des tiges regard to the influence of various test procedures
(si moins de I O m). Pour etre correct ii est essentiel de and the relationship between blow count, relative
density and overburden pressure. Much use is
Discussion on this Paper closes on 1 January 1987. For made of recent research involving measurements
further details see inside back cover. of rod energy ratios and field investigations in
* Imperial College of Science and Technology. Japan.
425
426 SKEMPTON

The 'dynamic efficiency' of the hammer-anvil There is a further loss of energy on impact.
system is introduced as a new parameter. Some of This can be expressed by the dynamic efficiency
the confusion surrounding comparisons between 'Id where
laboratory and field tests is dispelled, and the
(6)
effects of particle size, 'ageing' and over
consolidation are quantified. Thus finally
(7)
INFLUENCE OF TEST PROCEDURES If the rod stem has a length of I O m or more
General considerations the sampler receives the full rod energy E,. With
To obtain reliable results the SPT should be shorter rods the sampler receives less than E, and
carried out under controlled conditions. These a correction has to be made for this effect: see
include later.

(a) the use of the wash boring technique or rotary Velocity energy ratio
drilling with a tricone drill bit and mud flush, In general practice four methods of releasing
water or mud in the borehole to be main the hammer are used
tained up to groundwater level (a) a trigger mechanism, such as the Japanese
(b) tests to be made from the bottom of boreholes 'Tombi'
not less than 65 mm (2t in) or greater than (b) a trip hammer, such as the Pilcon or Dando
150 mm (6 in) and preferably not more than hammers
100 mm (4 in) diameter, with the casing (if (c) manual (lifting) and release of the rope
used) not advanced below the bottom of the passing over the crown sheave of the drilling
borehole rig
(c) the blow count (N value) to be determined (d) the 'slip-rope' method of rapidly slackening
between 6 in and 18 in penetration, the first the rope on the winch cathead: it is usual to
6 in being regarded as a possible zone of dis have two turns of rope on the cathead for
turbance from drilling operations. lifting the hammer, sometimes three turns and
Even with good site control there are still two rarely one turn, and it is these turns of rope
major variables, depending on the method of re which have to be cast off to release the
leasing the hammer and the type of anvil. These hammer.
together control the energy E, delivered into the Measurements of the impact velocity of a
rod stem which can be expressed as a ratio of the Borras trip hammer, similar in type to the Dando
theoretical free-fall energy of the hammer, '. hammer, show (Kovacs, 1979) that ERv = 099.
Thus Trigger release mechanisms also impart very
E, = ER,E' (1) nearly a free fall.
In method (c) and still more in method (d) there
where ER, is the 'rod energy ratio' and is some retardation even though the rope may
seem to have been completely freed. Frydman
1w 2
E' = - - v (2) (1970) briefly reported alternate tests in boreholes,
2g in Israel, performed either with trigger release or
For free fall by the two-turn slip-rope method, using the same
hammer. The results, plotted in Fig. 1, show an N
v = (2gh) 1 12 (3) ratio of about 1-4 or ERv 07. Comparative
tests by Douglas (1982) in a sand fill at San Diego
so are also plotted in Fig. 1, the points being site
E' = wh = 140 x ?1 = 350 ft lb (4) averages at various depths from tests with a trip
release or with a two-turn slip-rope. They show
for the standard weight (140 lb) and height of on average a slightly lower ERv value of about
drop (30 in) of the hammer. 066 or an N ratio of l 5. Diameters of the
However, owing to frictional losses, the cathead in both cases were probably about 8 in, a
hammer velocity at impact is less than the free typical dimension in American and American
fall velocity. The actual hammer energy Eh can be influenced practice.
expressed as A thorough investigation at Niigata (Yoshimi
Eh = ERvE' (5) & Tokimatsu, 1983) compared a donut hammer
released by the Tombi trigger and by a two-turn
where ERv is the 'velocity energy ratio'. slip-rope. The results, together with similar tests
STANDARD PENETRATION TEST PROCEDURES 427

80 with trip release hammers of the same form and


found
N(manual);::::: 115N(trip)
or
60
ER.;::::: 087
This is largely a measure of the retarding effect of
the crown sheave. The value is in agreement with
Q)
Cl. special tests (used sometimes in Japan) in which
2 40 the rope is thrown sideways completely off the
.9- cathead, when on average ER. = 088 (tests sum
<n
<'. marized in Seed, Tokimatsu, Harder & Chung
(1984)).
Frydm a n (1970)
Direct measurements of hammer velocity at the
20 D ougl as (1982) instant of impact (Kovacs, Evans & Griffith,
O Yoshimi & 1977; Kovacs & Salomone, 1982) confirm the N
Tokimatsu (1983) ratios of around 1-4 found by comparative tests
o Ohoka (1984)
with trigger release and the American two-turn
slip-rope and also provide information on ER.
for one turn and three turns of rope; see Fig. 2
0 20 40 60 where the foregoing data are assembled, with
N trigger re l ease
manual release and 'special throw' velocity ratios
Fig. 1 being counted as zero turns.
Experience at Kalabagh has shown no practi
by Ohoka (1984) are shown in Fig. 1, the average cal difference in average N values obtained by
N ratio being 12 or ER. = 083. manual release and one turn of rope on a small
The higher velocity ratio of the Japanese slip (80 mm) cathead. This fact is taken into account
rope method, compared with American practice, in drawing the uppermost curve in Fig. 2.
is explained by the smaller cathead diameter of
130 mm (5 in) used in the Niigata tests (100- Rod energy ratio
130 mm is usual in Japan) and partly by the By means of dynamic load cells inserted in the
thinner manila rope; 12-17 mm diameter com rod stem it is possible to determine the energy E,
pared with 19-25 mm in America. in the rods (Schmertmann & Palacios, 1979) and
Shi-Ming (1982) compared the traditional therefore the rod energy ratio. These researchers
Chinese manual operation of donut hammers showed that the blow count in a given sand is

Trip hamm e r (Kova cs, 1979)


10 / Manu al releas e (Shi-Ming, 1982) 1 0
e o a a d
:: : : Sm all
c ath ead
-;,c. __ 12
08 i.._

06 16

cl
lJ.J () Frydm an (1970)
0-4 I"'- Dougl as (1982) a 25
Yoshimi & Tokimatsu (1983)
o Kova cs & S al am on e (1982)
a Kova cs et al. (1977)
02

0
0 2 3
Nomina l numbe r o f turns of ro pe on ca th ea d
Fig. 2. Velocity--i!nergy ratio
428 SKEMPTON

Table 1. Blow count N and rod commonly used American hammers, donut and
energy ratio ER, in two series of field safety, is presented in Table 2, in all cases with
tests the two-turn slip-rope release. The lower effi
ciency of the donut hammer, Fig. 4(b), is to be
Shammer, F hammer, attributed to the heavy anvil associated with this
AW rods N rods type of hammer in America, compared with the
N 88 142 small anvil of the safety hammer.
ER, 052 031 Similar data from Japan for donut hammers
operated by the Tombi and slip-rope methods are
given in Table 3. The higher rod energy ratios,
inversely proportional to ER,. For example, five compared with the relevant values in Table 2, are
or six tests in adjacent borings, at depths between due partly to the more efficient Japanese slip-rope
10 ft and 30 ft, gave the average results for two technique (i.e. a higher ERv) and also to the light
different hammers and drill rods given in Table 1 weight anvils used in Japan.
and to a close approximation Trip hammers, Fig. 4(c), despite having vir
142 x 031 = 88 x 052 tually a free fall, impart a rod energy ratio of only
about 06 (Table 4) because of a low dynamic
In another example (Robertson, Campanella & efficiency which is due to their heavy anvils (see
Wightman, 1983) alternate tests with two different next section). Comparative tests by Serota &
hammers were carried out in the same borehole, Lowther (1973) show no significant difference
using the same rig and a two-turn slip-rope between N values obtained in tests with a Pilcon
release. The results, Fig. 3(a), show considerable hammer and the basically similar Dando trip
differences both in N values and rod energy hammer.
ratios, but if the N values are normalized to a In other tests Serota and Lowther found
single energy ratio (chosen here as ER, = 055) almost identical N values with a Pilcon hammer
the results, Fig. 3(b), fall into a consistent pattern. and the original British type of SPT hammer,
A collection of rod energy ratios for the two Fig. 4(a), released by one turn of rope on a small

N N55
o .--4rO -so 0 .--- 20 -40-60

o Donut hammer
11. Safety hammer
N 55 - N ER,/55
Sliprope, 2 turns
10

5 N ER, ER,
a._
' 20
'p
I
E
{ I

'?
I
' 30
I
)
10 9 I
6
I
I
I

40
I
\
\
ll
1 - 50
5
40 8 0
ER,.%
(a ) (b)
Fig. 3. Alternate tests in a borehole with varying N values and rod
energy ratios ER, measured with the donut and safety hammers (after
Robertson et al., 1983) (Fraser River delta)
STANDARD PENETRATION TEST PROCEDURES 429

Table 2. American average rod energy ratios for two types of hammer and anvil, with the two-turn
slip-rope release method

Do nut Safety Notes Reference

ER,: Number ER,: Number


% of o/t1 of
tests tests
53 4 72 9 'Laboratory' tests Kovacs & Salomone (1982)
48 8 52 9 Various field rigs Kovacs & Salomone (1982)
55 24 See Fig. 5 Schmertmann & Palacios (1979)
52 5 Schmertmann & Palacios (1979)
48 23 For N = 1 5-45 Robertson et al. (1983)
43 8 62 8 See Fig. 3 Robertson et al. (1983)
45 55 Typical field values

Table 3. Japan: rod energy ratios for the donut-type hammer and small anvil with the Tombi and two-turn
slip-rope release methods

ER,:% N ratio Notes Reference

Tombi Slip-rope
80-90 63-72 (l 25) N ratio deduced Nishizawa, Fuyuki & Uto (1982)*
80 67 (l 2) I} from ER, values Kovacs & Salomone (1982)
76 Mean of 10 tests Kovacs, Yokel, Salomone & Holtz (1984)t
12 See Fig. 1

78 65 12 Typical values
* Summarized by Tokimatsu & Yoshimi (1983).
i Quoting Decker (1983).

Table 4. Rod energy ratios for trip hammers

Hammer ER,:% Reference


Pilcon type 58 Liang (1983)
Pilcon 62 Douglas & Strutznsky (1984)
Pilcon 55 Kovacs et al. (1984)*
* Quoting Decker (1983).

Table 5. Energy ratios and dynamic efficiency

Release Hammer system ER,:%

Type Cathead ER.:% Hammer Anvil 'la


weight: kg
Waterways Trip - 1 00 Vicksburg 0 083 83
Experiment
Station
Japan Tombi - 100 Donut 2 078 78
Japan Slip-rope (2 turns) Small 83 Donut 2 078 65
USA Slip-rope (2 turns) Large 70 Safety 25 079 55
UK Slip-rope (1 tum) Small 85 Old standard 3 071 60
USA Slip-rope (2 turns) Large 70 Do nut 12 064 45
UK Trip - 100 Pilcon 19 060 60
430 SKEMPTON

No doubt other factors are involved but until


further information is available the assumption
can be made that 'Id is about 07-08 for light
Hammer weight anvils and between 06 and 07 for heavy
anvils.
Standard rod energy ratio
It is clearly necessary to normalize the N values
n
Anv1l measured by any particular method to some stan
dard rod energy ratio. In the USA ratios of 50%
11Jl-orill rod
or 55% have been suggested, but a better value is
(a) 60% as proposed by Seed et al. (1984).
N values measured with a known or estimated
Hammer
ER, value can be normalized to this standard by
the conversion
ER,
N6o = N 60 (8)

(c)
The foregoing data are assembled in Table 6
I: along with conversion factors for normalizing to
1 ! Hammer ER, = 60%, the factors being rounded off to the
l( nearest 5%.

Effect of rod length


Values of ER, in Table 6 are for rod lengths of
10 m or more. Wave equation studies
(b) (Schmertmann & Palacios, 1979) indicate that the
theoretical maximum ratio thereafter decreases
Fig. 4. SPT hammers: (a) old standard; (b) donut;
with decreasing rod length as shown in Fig. 5.
(c) trip
Test results, also plotted in Fig. 5, follow this
trend. Appropriate correction factors are given in
(100 mm) cathead. The latter system therefore Table 7. The weight or stiffness of the rod stem,
gives a rod energy ratio of about 60%. of a given length, appears to have little effect
(Brown, 1977; Matsumoto & Matsubara, 1982).
Dynamic efficiency
If the velocity and rod energy ratios are known Sampler without liners
the dynamic efficiency 'Id can be deduced from The modern American sampler is equipped
equation (7) with liners. Often these are omitted, giving an
ER, = r,dER. internal diameter of lt in instead of the standard
lj in. Comparative tests (summarized in Seed
Values of 'Id found in this way are listed in et al. (1984)) show on average that the sampler
Table 5. They lie between 083 and 06, and with liners requires about 20% more blows per
appear to depend principally on the anvil weight. foot penetration than does a sampler with the

Table 6. Summary of rod energy ratios

Hammer Release ER,:% ER,/60


Japan Donut Tombi 78 13
Donut 2 turns of rope 65 1 1
China Pilcon type Trip 60 10
Donut Manual 55 09
USA Safety 2 turns of rope 55 09
Donut 2 turns of rope 45 075
UK Pilcon, Dando, Trip 60 10
old standard 2 turns of rope 50 08
STANDARD PENETRATION TEST PROCEDURES 43 1

ER, Table 7. Approximate corrections to mea


o
.-
A'--__,06"-------.:0-s'"------'-,
o-2____,,o 10 sured N values
Theoretical
' , maximum Rod length : > 10 m 1 0
\ ..
\.
' ./'
''
6--10 m
4--6 m
095
085
.'
... .(
5 3-4 m 075
20 \
I
\ Standard sampler 1 0
\
.j \ US sampler without liners 12
in
u . . .. I
\ .
\
I 10
I
Borehole diameter : 65-1 1 5 mm
150 mm
1 0
1 05
1
1 I 200 mm 115
40 E
5,
c
. ! . .:

II
(l)
...J
15 12 k g anvil, and two turns of rope o n a large
diameter cathead: N 60 = 20 x 075 = 1 5
I Mean - 55 (b) a s i n (a) but using a modern American
60
i----(30-75 ft) sampler without liners in a 6 in borehole :
N 60 = 20 x 075 x 1 2 x 1 05 = 19
I 20
(c) in Pakistan with a standard sampler, 100 mm
.. \. borehole, donut hammer with 7 kg anvil
(l'/d = 07) and manual release (ERv = 085):
80 N 60 = 20 x 1 0 = 20
Fig. S. Effect of rod length for a safety hammer with (d) in the UK with a standard sampler, 6 in bore
two-turn slip-rope (after Schmertmann & Palacios, 1979) hole and a Pilcon or Dando hammer : N 60 =
20 x 1 0 x 1 05 = 21
(e) in Japan with a standard sampler, 86 mm
liners omitted : rather fewer in loose sands and borehole, donut hammer with 2 kg anvil and
rather more in dense sands. two turns of rope on a small diameter
cathead : N 60 = 20 x l l = 22
Effect ofborehole diameter (!) as in (e) but with a Tombi trigger release:
In its original form the SPT was carried out N 60 = 20 x 1 3 = 26
from the bottom of 2t in or 4 in dia. wash
borings. The best modern practice still adheres to Finally, if in any of these tests the rod length had
these dimensions. In Japan, for example, tests are been 5 m (i.e. the test carried out at a depth of
mostly made from 66 mm (26 in) or 86 mm about 4 m below ground level), instead of 10 m
(34 in) boreholes and virtually never in holes or more, N60 would be 15% lower. For instance
larger than 1 1 5 mm (Yoshimi & Tokimatsu, in case (c)
1983). However, in many countries 150 mm (6 in) N60 = 085 x 20 x 1 0 = 1 7
test boreholes are common, and even 200 mm
(8 in) boreholes are permitted (Nixon, 1982). Now the difference between N6 0 = 1 7 and
The effect of testing from relatively large bore N 60 = 22, for example, could mean the difference
holes in cohesive soils is probably negligible, but between liquefaction or no danger of liquefaction
in sands there are indications that appreciably in a sand subjected to a cyclic stress ratio of 02
lower N values may result (Lake, 1974; Sanglerat in a 7! magnitude earthquake (Seed, Idriss &
& Sanglerat, 1982). More information is urgently Arango, 1983). The importance of making proper
required on this aspect of the subject but, for the corrections to measured N values is therefore
present, minimum (and therefore conservative) apparent, but it will also be noted that, as a fortu
correction factors to allow for the effect of testing nate consequence of compensating effects, several
in over-large boreholes may be suggested, as of the modern test procedures, e.g. cases (b), (d)
given in Table 7. and (e), give rather similar results.
Illustrative examples
LABORATORY TESTS ON NORMALLY
Consider six tests each with a measured N
CONSOLIDATED SANDS
value of 20 and the same rod length of more than
Full-scale laboratory tests have been made on
lO m
two sands (GHC and GHF) at the US Bureau of
(a) in the USA with the original standard Reclamation (Gibbs & Holtz, 1957) and on three
sampler, a 4 in borehole, donut hammer and sands (PR, SCS and RBM) at the Waterways
432 SKEMPTON

200
sieve

80

60

20

O f--
-"""=----
C- o-a-rs-e Gravel

Fines
Sand
0005 042 20
Particle size: mm
Fig. 6. Grading curves of sands in laboratory tests

60
u; 2 88
GHF

40 0 50 03 mm
<'. 1 44

20

0 20
:" 40
o,
60 80 1 00

0 20 40 60 0 80

N,

10 \ \ \

X O 6

20

25
40 60

30
Fig. 7. Laboratory tests
STANDARD PENETRATION TEST PROCEDURES 433

Experiment Station (WES) (Bieganousky & Mar parameter N i/D.2 where, as in equation (9), D, is
cuson, 1976; Bieganousky & Marcuson, 1977). expressed as a ratio, not a percentage. In the tests
Grading curves are plotted in Fig. 6, the division N 1 is found simply by interpolation (see Fig. 7).
between 'fine' and 'coarse' sands being taken at Values of N 1 and N i/D/ are listed in Table 8 for
D 50 = 04 mm as in Japanese practice (Japanese each sand at relative densities of 40%, 60% and
Society of Soil Mechanics and Foundation 80%.
Engineering, 1979). At the WES the maximum void ratio emax was
The tests, as illustrated in Fig. 7, show in any determined by pouring air-dry sand through a
particular sand for effective overburden pressures 1 in dia. spout with a free fall of 1 in, and the
less than 2 ton/ft 2 and for relative densities in the minimum void ratio emin was found by vibrating
range 40-80% : dry sand on a shaking table for eight minutes.
The relative density is then calculated from the
(a) the blow count N increases almost linearly
usual expression
with overburden pressure a; at a constant
relative density D, emax - e
(b) at a constant overburden pressure, N (10)
increases roughly as D,2 : thus to a first
approximation, as pointed out by Meyerhof where e is the void ratio of the sand under test.
(1957) An American sampler was used without liners,
and a short rod typically about 8 ft long, employ
N ing a hydraulically operated Vicksburg trip
- = a + bav' (9)
D r2 hammer falling directly on the head of the rod
stem. Measurements of the rod energy ratio of
but when the whole set of tests is considered it this system for the WES by Schmertmann in 1979
is seen that gave ER, = 083, but factors of about 065 and
(c) at a given relative density and overburden 120 respectively have to be applied to allow for
pressure, N is higher for sands with a larger 8 ft rods and the larger than standard internal
mean grain size (D 50).
diameter of the sampler. The appropriate conver
Average values of the parameters a and b, sion factor to obtain N60 values is therefore 1 1.
within the limited range of a.' and D, mentioned, The normalized values (N 1 )60 and (N 1 ) 60/D,2
are given in Table 8. are given in Table 8 together with the corre
It is convenient to characterize a sand by the sponding corrected parameters a and b.
blow count N 1 normalized to an overburden Insufficient information is available to allow an
pressure of 1 ton/ft 2 (which can be taken also as estimate to be made of the rod energy ratio
1 kg/cm2 or 100 kPa) or, more generally, by the applicable to the US Bureau of Reclamation tests.
Table 8. Laboratory tests
Sand Tested Dso: UC* Fines: D,: N, N, N ER, (N,)60 (N,) 60 N6o
mm % D,2 D,2 60 D,2
PR Wet 20 53 0 04 75 47 11t 8 52
06 19 53 30 + 22a; 21 58 33 + 24a.'
08 37 58 41 64
GHC Dry and 1 5 55 0 04 65 40
moist 06 145 40 18 + 22a;
08 25 39
scs Wet 051 25 4 04 7 44 1-lt 75 48
06 16 44 21 + 24a.' 18 48 23 + 26a.'
08 29 45 32 49
RBM Wet 023 18 2 04 55 34 1 1t 6 37
06 12 33 16 + 17a; 13 36 17 + 19a.'
08 21 33 23 36
GHF Dry 03 7 14 04 45 28
06 12 33 15 + 1 8a;
08 23 36
* Uniformity coefficient.
t Includes a correction for no liners.
434 SKEMPTON

1 20
Sizewell OC
N i igata N C
o Kawag ishi
Ogishima } fill

o
Laboratory tests
80 WES
Coarse sands
(Peck & Bazaraa, 1 969)
2- _ _ _ _ _ _ _,.,..-


0
40
0

0 50 : mm

Fig. 8. Effect of particle size, ageing and overconsolidation

However, the results of these tests are broadly The effect of overconsolidation is considered
compatible with those at the WES. later.
Average values of (N 1 )60/D,2 for the three WES
sands are plotted against D 50 in Fig. 8. The ten FIELD DATA ON NORMALLY CONSOLIDATED
dency to increase with increasing grain size is ' SANDS
clearly seen; it is probably related to a similar Investigations in Japan during the past few
trend in </> (at a given relative density). years have yielded reliable measurements of rela
For sands RBM and SCS the relationship tive density and grain size coupled with well
between (N i )60 and D, , and the increase in defined SPT procedures.
N6 0/D,2 with effective overburden pressure, are
shown in Figs 9 and 10. These curves can be Ogishima Island
taken as typifying laboratory tests on fine and Samples from Ogishima Island, in a fine sand
medium-coarse normally consolidated sands. fill (Saito, 1 977), were taken with a compressed air

Very Loose Medium Dense Very


loose dense

Field data

60 Coarse sands
OC
fine
NC } sands
o Fill

Terzagh1 & Peck (1 948)


'\ /
0 = 0 5 mm
/ 50
a = 023 mm
20
/ /-- Laboratory
tests
/
_,,,,.- o

0 20 40 60 80 1 00

Fig. 9. Effect of relative density


STANDARD PENETRATION TEST PROCEDURES 435

sampler of the Bishop type but equipped with a


piston. The penetration and hence the sample
volume can therefore be measured, and from the
dry weight of the whole sample its average void
Og1sh1ma 0 50 = 0 3 mm ratio is known.
} fill Maximum and minimum void ratios were
Kawagishi 0 50 = 035 mm
N i igata ( N C) 0 50 = 029 mm
determined respectively by the tilting test and by
tapping a 120 cm 3 container filled with dry sand
05 N 1 igata (NC) 0 50 = 0-45 mm 50 under a load of 1 kg/cm2 .
The SPT procedure followed usual Japanese
practice : a standard sampler, 66-86 mm dia.
boreholes stabilized with drilling mud and casing,
a donut hammer with a lightweight (2 kg) anvil,
"' released by a two-turn 15 mm manila slip-rope
1 00 0..
-"' on a 120 mm cathead. The tests were made in
N
1974 soon after most of the reclamation work had
c
been completed.
The relative density, below water level, remains
almost constant at 52- 55% and the N values
increase steadily from 8 to 14, at depths from
1 50 about 5 m to 15 m: see Fig. 1 1 where each point
is the average of several tests.
The ER,/60 ratio is well established at around
l 1 , but rod length corrections are applicable to
the two uppermost points in Fig. 1 1 . The results
conform to a linear relationship
20 200 N
Fig. 10. Effect of overburden pressure = 17 + 17av' (a/ in kg/cm 2 )
D r2

0 50 0 3 m m UC 4 Fines 1 0%

N o, N60 / 0 ,2
0 10 20 0 04 08 0 20 40 60

With rod length


correction
05

;i, 0
)o N, = 9

\
0

E1o
0 0
-"'
\

\
0 0
b
1 5
0
0 0
1 7 + 1 7 r,;

20
o, = 054 ER/60 = 1 1

25

o Average field values x With rod leng1h correction

Fig. 11. Results from Ogishima Island, sand fill


436 SKEMPTON

Hence 1979) in two closely spaced boreholes adjacent to


the SPT borehole.
(N 1 )60/D/ = 34 Both types of sample were allowed to drain for
(N 1 )60 = 10 24 hours. Small brass tubes (50 mm
dia. x 1 00 mm long) were then pushed into the
for D, = 0.54. large diameter samples and these, and also the
The results, plotted in Figs 8-10, are similar to Osterberg samples, were frozen on site to prevent
those from laboratory tests on sand RBM, which disturbance during transport to the laboratory.
has a comparable D 50 grain size but a smaller The SPT procedure conformed to modern Japa
content of fines. However, an exact comparison is nese methods using the two-turn slip-rope release,
not possible since different methods were used for as described previously for the Ogishima site. The
determining the limiting void ratios, tests which N values, plotted in Fig. 1 2, are results of individ
unfortunately are not internationally stan ual tests.
dardized. Natural void ratios were determined from the
dry density. To measure the maximum void ratio
Kawagishi-cho oven-dry sand was carefully spooned into a
The tests at Kawagishi-cho were made in land mould 60 mm in diameter and 40 mm deep with
reclaimed between 1930 and 1950 (approximately) a negligible height of drop. The procedure for
by depositing about 15 m of sand in a natural determining the minimum void ratio consisted of
inlet close to the mouth of the Shinano River in placing the sand in a water-filled mould 52 mm in
Niigata. Recent investigations (Ishihara & Koga, diameter and 80 mm high, applying a load of
1981) include sampling by means of a large 1 kg/cm 2 and vibrating on a shaking table with a
(200 mm) diameter sampler (Ishihara & Silver, single amplitude displacement of 7 mm at a fre
1977) and a 76 mm piston sampler of the quency of 17 Hz for three minutes.
Osterberg type (Ishihara, Silver & Kitagawa, Each relative density point in Fig. 12 is the

0 50 "' 035 m m U C = 2A Fines = 5%


N D, N60 !D/
0 --1 0 __=2,o o.-__o,...
A__os o.--2,.c-
0___40_ _"""'6'-i'o_
.- ,... T

O Large diameter With rod length


sampler correction
O Osterberg
sampler

O A2
O A2
O A7
0 35


0 52


0 26
0 35
0 25

ER/60 1 1
l\ 0 5 1

N values: o measu rerl; >< with rod length correction

Fig. 12. Results from the Kawagishi-cho site, sand fill


STANDARD PENETRATION TEST PROCEDURES 437

mean from three or four specimens from the sand by the in situ freezing method (Yoshimi,
samples. There is a considerable scatter, but Tokimatsu, Kaneko & Makihara, 1984).
average values from both types of sampler, for On specimens cut out from the block and hand
depths between 5 mm and 14 mm, are almost trimmed to size, cyclic triaxial tests and density
identical at 5 1 %. Between these depths no measurements were made, and on the dried sand
obvious trend exists in D, or in the mean particle maximum and minimum density tests were
size. It is therefore reasonable to treat this body carried out in accordance with the new Japanese
of sand as having broadly uniform properties, standard (Japanese Society for Soil Mechanics
and the results correspond approximately to the and Foundation Engineering, 1979). For the
equation minimum density, sand was poured through a
small ( 1 2 mm) diameter funnel, with effectively
N 60 zero height of fall, into a mould 60 mm in diam
= 1 8 + 26uv' (u,' in kg/cm 2)
Dr 2 eter and 40 mm high. For the maximum density
the sand was placed in the same mould in ten
Hence layers, the mould being tapped 100 times with a
( N 1 )60/D, 2 = 44 wooden hammer after placing each layer. Compa
rative tests on a standard (Toyoura) sand showed
(N 1 ) 6o = 1 1 5 only minor differences in emax and em,n determined
for D, = 05 1 . by these procedures and the methods adopted
These values, plotted in Figs 8-10, are higher before 1 979 by Ishihara and co-workers.
than those for the Ogishima sand fill. The differ Average results from several specimens at each
ence may be attributed partly to a somewhat of three depths at the station, between 925 m and
larger grain size at Kawagishi and probably also 98 m, are given in Table 9 together with the rele
to the fact that the fill had been deposited at least vant N values, each of the latter being the mean
25 years before being tested. of three tests by Tombi and three by slip-rope
release. The results can be taken as having a high
Niigata station reliability. It may be added that the triaxial tests
At a site near Niigata railway station SPTs show <f/ = 4 1 4 at the maximum stress ratio.
were made at six equally spaced boreholes on the
circumference of a 4 m dia. circle, three by the Niigata, south bank site
slip-rope method with two turns of 15 mm Large diameter and Osterberg samples were
manila rope on a 1 30 mm cathead and three by taken in a medium dense fine sand of Pleistocene
the Tombi release method, using in all cases a age near the south bank of Shinano river at the
standard sampler, 66 mm boreholes stabilized Shoma Bridge, about 1 2 km from Niigata station
with drilling mud and a donut hammer with a (Ishihara & Koga, 1981 ). The techniques of sam
3 kg anvil (Yoshimi & Tokimatsu, 1 983). Below pling and testing were as described for the Kawa
3 m there is a fine sand, becoming dense at a gishi site. Results are given in Table 10 along
depth around 6 m. At the centre of the test circle with N values derived by interpolation from tests
a large block sample was obtained in the dense in an adjacent borehole.

Table 9. Niigata station*

Mean a/ : N N 6o e emax emin D, D,o:


depth : kg/cm 2 mm
m Tombi Slip-rope Tombi Slip-rope
9 1 1 05 30 39 39 43
925 084 1 22 076 082 029
96 082 1 20 075 087 028
98 084 1 20 078 086 030
99 11 1 32 39 42 43
95 1 08 31 39 405 43 083 l 21 076 085 029
-----,.---
416
* ER,/60 = 1 -3 (Tombi) and ER,/60 = 1 1 (slip-rope); rod length correction, 1 0; at a; = 1 08 kg/cm 2
CN = 2/(1 + a;) = 096 ; N 60/D ,2 = 575 ; (N 1)60 = 40 ; (N 1)60/D,2 = 55.
438 SKEMPTON

Table 10. Niigata, south bank*

Depth : (Jv' N N 6o e emax emin D, N 6o (N,)6ot (N,)60 D,o:


m kg/cm 2 D,2 [)/ mm
42 0-43 13
445 0-45 18+ 18 080 110 065 067 40 25 55 028
49 050 27 t 27 072 108 064 082 40 36 54 029
52 052 33
* ER,/60 = l l; rod length correction, 09.
t CN taken as 2/(l + u.').
t By interpolation.
N iigata, road site at the south bank and station sites strongly indi
The same techniques were used to investigate cate that they also are in this condition.
an ancient alluvial deposit of the River Shinano Comparisons with the Kawagishi fill, of rather
at a site beside a road situated on an old flood similar grain size and tested by identical pro
bank of the river, about l 5 km upstream of the cedures, clearly show the effects of ageing (Figs
Showa Bridge. Under 4 m of fill, dating from the 8-10).
early years of this century, the alluvial sand has a
Ageing of sands
relative density typically around 50% and the
grain size tends to increase with depth. Direct evidence of the increased resistance of
Two groups of results from depths of about sands which have long been under consolidation
8-9 m and 1 3-14 m are given in Table 1 1. pressure is provided by cyclic triaxial tests on
The grading and mean grain size of the 8-9 m samples from the station site (Yoshimi et al.,
samples is closely similar to the sand at Niigata 1984). The stress ratio required to cause a double
station and the south bank, although the relative amplitude strain of 5%, at ten cycles, is found to
densities range from 45% to 85% at the three be at least 60% greater in the undisturbed
sites. Nevertheless the parameter (N 1 )60/D,2 is samples than in freshly reconstituted samples at
constant, equal to 55, and the sands can be taken the same density. Similar results have been found
as belonging geotechnically to a single group. The for alluvial sand in Niigata with a relative density
results, plotted in Fig. 13, lead to the relationship around 52% (Ishihara, 1985) but, significantly, a
smaller difference is measured in the Kawagishi
N60 fill.
= 27 + 28av' (a; in kg/cm 2) There is little doubt that the effect is time con
D/
trolled. Seed (1979) reported a 25% increase in
The alluvium is normally consolidated, and the resistance to the development of initial liquefac
mutually consistent characteristics of the deposits tion in laboratory samples tested after 100 days
Table 11. Niigata road site

Depth : (Tv ' . N Rod N 6o e emax emin D, N 6o CN (N 1160 (N,)60 D,o: UC


m kg/cm 2 length D,2 D,2 mm
correction
81 098 12 098 129
84 100 087 1 1 5 059 030 1 8
84 100 084 1-15 061 028 16
91 107 10 099 109
92 1 09 096 1 16 067 034 1 4
93 109 1 01 1 18 068 030 18
1 04 1 1 9 092 1 16 064 046 56 098 1 1 -7 55 030 1 7
128 1 -40 077 099 055 0-48 17
128 1 -40 077 1 01 056 048 1 8
1 3-1 1 45 17 100 187
138 1-50 079 107 058 039 18
138 1-50 086 105 056 065 19
143 1 -55 20 100 220
147 203 080 1 -03 056 0-49 84 085 173 72 045 18
STANDARD PENETRATION TEST PROCEDURES 439

N50 o, N 60 !0/
0 20 40 0 04 08 0 20 40 60 80 1 00
:g_ D
+v 0 South bank
6 Road site
o Station
v River site

0 50 : m m
o
---- 6
D 0-28 D
0 0-29 0
05

1 v 0-46 v

.,
_:,:
27 + 28u/
"tt v 0-63 v
72 \

.,.
,. - - - -
- - - -
1 0
" 0-30 t.
0
00 0-29

1 -5 0-45

Fig. 13. Niigata sand strata

consolidation and briefly presented some field D 50 ;::::; 045 mm and relative densities around
data indicating an increase of 50---100% for con 45%. If the data are combined (Fig. 13) they give
solidation periods of the order of 100---1000 years.
N
Laboratory tests by Daramola (1980) indicate 6i = 46 + 260";
that the mechanics of the process is essentially an D,
increase in stiffness. In drained triaxial tests on a
river sand, with D 50 = 03 mm, he found that the (N 1 ) 60/D/ = 72
secant modulus increased by 60% and 1 00% The coarser sand (D 50 ;::::; 065 mm) at depths
respectively in tests made after 30 days and 150 around 9 m at the river site has a still higher
days consolidation under 400 kPa, compared value of (N 1 ) 60/D/ = 84, but the relative density
with the results of freshly prepared samples, all at is only 36% and comparisons on the basis of
virtually the same relative density of 67%. The N/D/ may not be exact.
strains to failure were correspondingly reduced, The results are given in Table 12.
from 55%, to 35% and 25% at 30 days and 150
days, but interestingly the angle of internal fric Dense coarse sands
tion was scarcely changed (at <// = 39-395), the Peck & Bazaraa ( 1969) plotted a large number
interparticle bonds presumably having been of N values against a; for very dense coarse
broken on the approach to failure. sands tested below groundwater level, and they
Niigata, river site drew a line for D, = 100%. This is expressed by
Situated close to the road site, the Niigata river the equation
site had been in the Shinano flood plain until
1955, when the area was reclaimed by dumping !!__ = 60 + 25av
Dr 2
about 4 m of fill. From borings adjacent to an
SPT borehole large diameter samples were taken for a; > 0-75 ton/ft 2
(Ishihara, Silver & Kitagawa, 1978) and tested by It can be assumed that most of the tests will
the techniques described for the south bank and have been made with the original standard
river sites. The alluvial sand here is somewhat sampler and hammer using a two-turn slip-rope
coarser, and at depths around 7 m compares with release on a large diameter cathead. The appro
the deeper sand at the road site, both having priate value of ER,/60 is therefore about 075 : see

Table 12. Niigata river site*

Depth: '.
(I ' N Rod N 6o e emax emin D, N6o CN (N 1 )60 (N 1 )60 D so : UC Fines
m kg/cm 2 length D'2 D,2 mm
correction

65 065 11 095 1 1 5 084 1 06 053 046 20 0


70 069 9 096 95 ;,,:
75 073 13 0965 1 3-8 079 097 055 0-45 2 1 1 m
::::
069 1 1 6 08 1 1 02 054 0425 64 112 1 3-0 72 046 20 1
10 108 084 099 055 'Z
85 082 098 055 27 1
90 086 9 0985 97
95 090 9 099 98 080 1 -()() 0-48 070 30 3
086 101 082 099 05 1 0355 80 l05 t 106 84 063 28 2
* ER,/60 = l l .
t Assuming CN = 3/(2 + u,').
STANDARD PENETRATION TEST PROCEDURES 441

the section on illustrative examples earlier. Thus, Table 13. Values of K0 and C.., from equations (15)
in round numbers and (16)

N60 OCR </>' = 32 </>' = 36 </>' = 400


= 45 + 2011v
Dr2
Ko c.e Ko Coe Ko Coe
( N 1)60/D/ = 65
1 0-47 1 00 0-41 1 00 036 100
This result, although approximate, gives a useful 2 068 1 22 062 123 056 1 23
check on SPT results in. coarse-grained sands. 3 084 138 078 1-41 073 1 -43
4 098 1 53 093 157 087 1 59
6 121 176 1 17 184 J , 14 1 91
EFFECTS OF OVERCONSOLIDATION 10 1 59 215 1 -58 228 1 58 242
General considerations
It is reasonable to suppose, and model tests
confirm (Clayton, Hababa & Simons, 1985), that 20 0
penetration resistance in a given sand is con RSM sand
trolled by the mean effective stress
050 023 mm UC 1 8
50
1
a' = !{11; + 211h')
or
OCR = 3

t (1 + 2K
........----
11 ' x
a' = 0) (11) 42
/x
OCR = 1
50
where : / D, = 0 6

(12)
Thus if KoNc is the in situ stress ratio in a nor 0
mally consolidated sand, with an over 20 0
consolidation ratio OCR of 1 0, the same sand
when overconsolidated (OCR > 1) will have an
increased N value given by the expression
50
1

(13)

where OC R = 1

1 + 2K0
coc = ---- (14) 50
1 + 2KoNc
An analysis of tests on many soils has shown 34 D, = 0-4
(Mayne & Kulhawy, 1982) to a first approx 0
riy' : ton/ft 2
2 4 6
imation that
(15) Fig. 14. Effect of overconsolidation
KoNc = 1 - sin </>'
Ko = KoNcfOCR)'in 4>' (16) effect of increasing OCR from 1 to 3 (Fig. 14).
Values of K 0 and C0c are given in Table 13 from For 11; < 2 ton/ft2 the tests show on average
which it can be seen that quite a modest degree of N
overconsolidation may be expected to increase - = 16 + 1 711v'
Dr2
the coefficient of 11; in equation (13) by 20--40%,
and for heavy overconsolidation the increase for OCR = 1 and
could be at least 100%, corresponding to K0
values in excess of 1 0. - = 16 + 2711v'
Dr 2
Laboratory tests
Some experimental results on sand RBM for OCR = 3. From Table 1 3, for sand with
(Bieganousky & Marcuson, 1976) illustrate the rj,' = 32-36 (as in the tests) and OCR = 3, the
442 SKEMPTON

coefficient C00 is about 1 4; thus standard SPT hammer (Fig. 4(a)), released by two
turns of 22 mm rope on a 5 in dia. cathead. From
bCOC = 1 7 x 1 4 = 24 tests with this type of hammer and anvil (Serota
which is close to the measured value of 27. & Lowther, 1 973) the dynamic efficiency can be
estimated at about 07 (Table 5) and the velocity
Sizewe/1 energy ratio for the method of release would be
Tests have been reported (Meigh & Nixon, around 70% (see Fig. 2). Thus ER, ::::: 50% and
1961) on a fine uncemented sand of the Norwich ER,/60 ::::: 08, to which a minimum correction of
Crag, at Sizewell in Suffolk. This deposit was 5% has to be added for the 6 in borehole effect.
formed in Lower Pleistocene times and has been All the tests were made above the water-table.
heavily overconsolidated by the weight of an ice The effective overburden pressure is therefore
sheet of the Anglian glaciation, more than 250 OOO (17)
years ago. In situ densities were determined at
three levels in a test pit 34 ft deep, giving an where uc is the capillary tension. In sand with
average relative density of about 50%, and the D 10 = 0 1 mm, as at Sizewell, the capillary rise he
SPT N values measured in two adjacent borings is of the order of 80 cm (Terzaghi, 1 942). Hence
show a fairly uniform increase with depth Uc =
- ywhc =
- 008 ton/ft 2
(Fig. 1 5).
The tests were carried out in 6 in dia. boreholes The N 60 values (corrected where necessary for
using a standard sampler and the original British rod length) and effective overburden pressures

F i nes = 4%

N ton/ft2 Nrw/D/
0 20 40 0 1 2 0 50 1 00 1 50

o Measured With correction


for rod length
x With rod and borehole
length di a meter
correction

10 05


% 20
<1l
0

30 .
\
Relative
density
tests

\
40
\
Fig. 15. Sizewell : Lower Pleistocene sand
STANDARD PENETRATION TEST PROCEDURES 443

can now be calculated, and the results (Fig. 15)


give
N60
= 38 + 50uv'
Dri
Thus

N 1 0
E
and for D, = 05
OJ '/
(N 1 ) 60 = 22. I
Since D, is known only approximately these c
N
r
I
"II
values must be subject to appreciable variation,
but when compared with the normally consoli b" 2 0 o Fill
N C } fine
dated Niigata sand of similar grain size they sands
OC
clearly indicate a much greater penetration resist
I
Coarse sands
ance. This is due largely to the higher coefficient ........- Laboratory tests
of u; (50 compared with 28), which can be attrib I 3112 + er;1
uted to overconsolidation, and in part to the
great age of the Sizewell sand.
30
EFFECT OF OVERBURDEN PRESSURE Fig. 16
In the field and laboratory tests described each
of the sands (with one exception) is sufficiently medium relative density to 20 for dense coarse
uniform with regard to grain size and relative sands when normally consolidated. The corre
density to be treated as a unit, and the blow sponding limits for CN (plotted in Fig. 16) are
count at u; = 1 ton/ft 2 is found by direct inter
polation. In general, however, it is necessary to be c -- -
able to estimate the N 1 value for any particular N 1 + O": (20)
test, and this is done by means of the formula
c - -
3
(18)
N - 2 + O": (2 1)
Now if
These expressions are numerically similar to
N = a + bu curves derived by Seed et al. (1983) from the WES
-2 v laboratory tests for sands with D, = 0-4---06 and
D,
D, = 06---08 respectively, and equation (2 1)
then differs little from the well-known formula of Peck,
Hanson & Thornburn (1974)

G)
a/b + 1
CN = (19)
--
a/b + u; CN = 077 log (22)
From the data given in this Paper it will be seen
that a/b varies roughly from l O for fine sands of For detailed comparisons, see Table 14.

Table 14. Normally consolidated sands: values of CN

a,/:
ton/ft 2
--
2
1 + er.'
D,
From Seed et al. (1983)
= 40--60% D, = 60--80%
3
--
2 + er;
077 log G)
05 133 1 36 1 36 1-20 1 23
075 1 14 1 14 114 1 09 1-10
10 1 -00 1 00 1 00 1 00 100
15 080 080 084 086 087
20 068 069 074 075 077
25 057 060 067 067 069
30 050 054 061 060 063
444 SKEMPTON

For overconsolidated fine sands the a/b ratio they could not have been better chosen. Equally
lies between about 06 and 08. Thus to a first there is nothing wrong with the laboratory tests ;
approximation they apply to cases where the effects of ageing are
minimal.
l 7 Finally it is interesting to note a statistical
CN = (23)
07 + a; analysis of more than 50 field tests in sands by
Schultze & Menzenbach (1961). Their data,
although presented as a logarithmic relationship,
TERZAGHI AND PECK'S fit closely to the equation
CLASSIFICATION
Terzaghi & Peck (1948) gave the first classi
fication of relative density in terms of the SPT; !!..._ = 17 + 22a v'
Dr 2
see Table 15. Values of D, were assigned to this
classification by Gibbs & Holtz (1957) who in the range a; = 05-15 kg/cm 2 and for D, =
pointed out that the resulting N-D, relationship 04-09. Professor Schultze later questioned the
corresponded, more or less, to their laboratory accuracy of the relative density measurements,
tests at an overburden pressure of 40 lb/in 2 or but if the SPT procedure had a moderately high
nearly 3 ton/ft 2 . Clearly something was amiss, for efficiency (e.g. ER,/60 = 11) the results would
the field experience from which Terzaghi and conform quite well with recent tests on normally
Peck formulated the classification had been consolidated sands.
derived from tests at the normal depths for ordi
nary foundations corresponding to an overbur SUMMARIZING REMARKS AND
den pressure typically around 075 ton/ft 2 (Peck CONCLUSIONS
& Bazaraa, 1969). Experience shows that wide variations in N
Now at a; = 075 ton/ft 2 the coefficient CN values can occur as between different sands, even
11 and an appropriate rod energy ratio for the at a given overburden pressure and constant rela
original American test procedure can be taken as tive density. Part of the variation is arbitrary,
about 0-45. Hence the (N 1)60 values in Table 15 being due simply to the use of different test pro
are determined. A plot of these against the D, cedures. This effect can be eliminated by normal
values assigned by Gibbs and Holtz, see Fig. 9, izing the results to a standard rod energy ratio.
gives about the best single line that could be The variations which remain are intrinsic to
drawn through the field data, falling midway the nature of the sands being tested and fall into a
between points for normally consolidated fine consistent pattern when the effects of ageing, par
and coarse sand deposits. For D, > 035 the cor ticle size and overconsolidation are taken into
relation can be expressed to a good approx account.
imation by the parameter Tables 8 and 16, and Figs 8-10 and 16, sum
( N 1 )60/D/ = 60 marize the results of laboratory and field tests.
The main conclusions are as follows.
which from the data already given in this Paper Measured N values must be normalized to a
can be recognized as highly typical. standard rod energy ratio, and ER, = 60% is a
Thus, despite repeated criticisms, there is suitable standard.
nothing wrong with the N and D, values; indeed The relationship between blow count, relative

Table 15. Terzaghi and Peck's classification*

D, Classification N(u; = 075) NI (N 1 )60 (N 1 )60/D/


Very loose
0 15 4 44 3 -
Loose
035 10 11 8 65
05 Medium (18) 20 15 60
065 30 33 25 59
Dense
085 50 55 42 58
Very dense
100 (70) 77 58 58
* CN = ll ; ER,/60 = 075.
Table 16. Summary of field data

Site Type* D,o: UC Fines e emax emin D, (Jv' . N6o N6o CN (N 1l60 (N1l60
mm kg/cm 2 D,2 D,2 "'-I
>
Ogishima Island Fill 03 4 10 080 1 08 057 054 075 9 30 1 14 z
1 00 10 34 } 1 7 + 1 7u; 1 00 10 34 0
>
1 75 1 3 5 47 073 "'
0
Kawagishi-cho Fill 035 24 t 086 1 08 063 051 07 95 36 1 22 'tl
l O 1 1 5 44 } 1 8 + 26u; 1 00 1 1 5 44 ztT1
tT1

14 14 54 082
"'>
-I

''}
083 1 21 1 08 42 096

}
Niigata station NC 029 l 8 2 076 085 40 -I
Niigata, south bank 028 2 -4 t 080 l 10 065 067 045 18
+ 28uv
1 39 25 5 i5
Niigata, south bank 029 15 t 072 1 08 064 082 050 27 40 27 134 36 54
55 z
Niigata, road site 030 l 7 t 092 l 16 064 046 1 04 12 56 098 12 55 -I
"'
tT1

Niigata, road site NC 045 18 t 080 1 03 056 0-49 1 47 20 085 17 72 -I

Niigata, river site 046 20 1 081 1 02 057 043 069 1 15 : } 46 + 26u; l12 13 72 }
72
"'0
'tl

Niigata, river site NC 063 28 2 082 099 05 1 036 086 10 80 l 05t 105 84 l'"l
tT1

"'"'
0
Sizewell oc 02 20 4 072 094 050 050 060 17 68 1 29 c::
1 00 22 68 } 38 + sou: 1 0 22 88 tT1
1 50 28 1 13 078
* NC, normally consolidated ; OC, overconsolidated.
t Fines less than 5 % .
t Assuming C N = 3/( 2 + u;).

t
v,
446 SKEMPTON

density and effective overburden pressure in a Overconsolidation increases the coefficient b by


given sand can be represented by the expression the factor
1 + 2K0
N6o
-- = a + b r,v ' 1 + 2KoNc
Dr 2
where K 0 and K oNc are respectively the in situ
(r,; in ton/ft 2 or kg/cm 2 or kPa/1 00). stress ratios for the overconsolidated and nor
The parameters a and b are nearly constant for mally consolidated sand.
035 < D, < 085 and 05 kg/cm2 < r,; < 25
kg/cm 2 .
A sand can conveniently be characterized by ACKNOWLEDGEMENTS
the parameters (N 1 )60 and (N 1 ) 60/D,2 where It is a pleasure to record the generous help
(N 1 )6 0 is the normalized blow count at r,; = l given by Professor Ishihara and Dr Saito in
kg/cm 2 . answering detailed questions about the sites and
N 1 can be evaluated from the equation N 1 = test methods in Japan. Mr Marcuson and Mr
CN N where, in normally consolidated sands, CN W. G. H. Hodges kindly provided information on
ranges from CN = 2/(l + r,;) for fine sands of SPT procedures used at the WES and at Sizewell.
medium density to CN = 3/(2 + r,;) for dense The inspiration to prepare this Paper came from
coarse sands. the work of Professor Seed with whom the
For normally consolidated natural sand depos Author was associated in the Kalabagh Dam
its the best average correlation between blow project.
count and relative density is
REFERENCES
D, = 0 15 35 50 65 85 100% Bieganousky, W. A. & Marcuson, W. F. (1 976). Labor
atory standard penetration tests on Reid Bedford
Very Loose Medium Dense Very model and Ottawa sands. Research Report S-76-2,
loose dense No. 1, Waterways Experiment Station, Vicksburg.
3 8 15 25 42 58 Bieganousky, W. A. & Marcuson, W. F. (1 977). Labor
atory standard penetration tests on Platte River sand
and standard concrete sand. Research Report S-76-2,
This is derived from the Terzaghi-Peck classi No. 2, Waterways Experiment Station, Vicksburg.
fication. For D, > 035 it corresponds to Brown, R. E. ( 1977). Drill rod influence on standard
penetration test. J. Geotech. Engng Div. Am. Soc.
Civ. Engrs 103, 1332-1336.
Clayton, C. R. I., Hababa, M. B. & Simons, N. E.
For fine sands the N values should be reduced (1 985). Dynamic penetration resistance and the pre
in the ratio 55/60, and for coarse sands the N diction of the compressibility of a fine-grained
values should be increased in the ratio 65/60. The sand-a laboratory study. Geotechnique 35, No. 1,
second case corresponds to data given by Peck & 19-3 1.
Bazaraa ( 1 969). The tendency for N values to Daramola, 0. ( 1980). Effect of consolidation age on
stiffness of sand. Geotechnique 30, No. 2, 2 1 3-216.
increase with increasing particle size is probably Decker, M. D. (1983). Dissertation, Purdue University.
related to the same trend in (/>, for a given relative Douglas, B. J. (1982). SPT blowcount variability corre
density. lated to the CPT. Proc. 2nd Eur. Symp. Penetration
There is evidence that the resistance of sand to Testing, Amsterdam 1, 41 -46.
deformation is greater the longer the period of Douglas, B. J. & Strutznsky, A. ( 1984). SPT hammer
consolidation. This 'ageing' effect is reflected in energy measurements. Report to the US Geological
higher blow counts, and appears to cause an Survey.
increase in the parameter a. Typical results for Fletcher, G. F. A. ( 1965). Standard penetration test : its
normally consolidated fine sands are given in uses and abuses. J . Soil Mech. Fdns Div. Am. Soc.
Civ. Engrs 91, 67-75.
Table 1 7. Frydman, S. ( 1970). Discussion on The dynamic pen
etration test : a standard that is not standardized.
Geotechnique 20, No. 4, 454-455.
Table 17. Effect of ageing Gibbs, H. J. & Holtz, W. G. ( 1957). Research on deter
mining the density of sands by spoon penetration
Age : years (N,) 60/D/ testing. Proc. 4th Int. Conf Soil Mech. Fdn Engng,
London I, 35--39.
Laboratory tests 10- 2 35 Ishihara, K. ( 1985). Stability of natural deposits during
Recent fills 10 40 earthquakes. Proc. llth Int. Conf Soil Mech. Fdn
Natural deposits > 102 55 Engng, San Francisco I, 321-376.
STANDARD PENETRATION TEST PROCEDURES 447

Ishihara, K. & Koga, Y. (1981). Case studies of liquefac Proc. 19th A. Meet. lap. Soc. Soil Mech. Fdn Engng
tion in the 1964 Niigata earthquake. Soils Fdns 21, (in Japanese).
No. 3, 35-52. Peck, R. B. & Bazaraa, A. R. S. (1969). Discussion on
Ishihara, K. & Silver, M. L. (1977). Large diameter sand Settlement of spread footings on sand. 1. Soil Mech.
sampling to provide specimens for liquefaction Fdns Div. Am. Soc. Civ. Engrs 95, 905-909.
testing. Proc. 9th Jnt. Conf Soil Mech. Fdn Engng, Peck, R. B., Hanson, W. E. & Thornburn, T. H. (1974).
Tokyo. Soil sampling volume, pp. 1-6. Foundation engineering, 2nd edn. New York : Wiley.
Ishihara, K., Silver, M. L. & Kitagawa, H. ( 1978). Cyclic Robertson, P. K., Campanella, R. G. & Wightman, A.
strengths of undisturbed sands obtained by large (1 983). SPT-CPT correlations. 1. Geotech. Engng
diameter sampling. Soils Fdns 18, No. 4, 61-76. Div. Am. Soc. Civ. Engrs 109, 1449-1459.
Ishihara, K., Silver, M. L. & Kitagawa, M. ( 1979). Saito, A. ( 1977). Characteristics of penetration resistance
Cyclic strength of undisturbed sands obtained by a of a reclaimed sandy deposit and their change
piston sampler. Soils Fdns 19, No. 3, 61-76. through vibratory compaction. Soils Fdns 17, No. 4,
Japanese Society for Soil Mechanics and Foundation 31-43.
Engineering (1979). Soil testing manual (in Japanese), Sanglerat, G. & Sanglerat, T. R. A. (1982). Pitfalls of the
2nd revised edn, pp. 172-188. Tokyo : JSSMFE. SPT. Proc. 2nd Eur. Symp. Penetration Testing,
Kovacs, W. D. ( 1979). Velocity measurement of free-fall Amsterdam I, 143-145.
SPT hammer. 1. Geotech. Engng Div. Am. Soc. Civ. Schmertmann, J. H. & Palacios, A. (1979). Energy
Engrs 105, 1-10. dynamics of SPT. 1. Geotech. Engng Div. Am. Soc.
Kovacs, W. D., Evans, J. C. & Griffith, A. H. ( 1977). Civ. Engrs 105, 909-926.
Towards a more standardised SPT. Proc. 9th Int. Schultze, E. & Menzenbach, E. (1961). Standard pen
Conf Soil Mech. Fdn Engng, Tokyo 2, 269 - 276. etration test and compressibility of soils. Proc. 5th
Kovacs, W. D. & Salomone, L. A. (1982). SPT hammer Int. Conf Soil Mech. Fdn Engng, Paris 1, 527-532.
energy measurement. 1. Geotech. Engng Div. Am. Seed, H. B. (1979). Soil liquefaction and cyclic mobility
Soc. Civ. Engrs 108, 599-620. evaluation for level ground during earthquakes. 1.
Kovacs, W. D., Yokel, F. Y., Salomone, L. A. & Holtz, Geotech. Engng Div. Am. Soc. Civ. Engrs 105, 201-
R. D. (1984). Liquefaction potential and the interna 255.
tional SPT. Proc. 8th World Conf Earthquake Seed, H. B., Idriss, I. M. & Arango, I . (1983). Evaluation
Engineering, San Francisco 3, 263-268. of liquefaction potential using field performance
Lake, L. M. (1974). Discussion on Granular materials. data. 1. Geotech. Engng Div. Am. Soc. Civ. Engrs 109,
Proc. Conf Settlement of Structures, Cambridge, 458-482.
p. 663. Cambridge : Pentech. Seed, H. B., Tokimatsu, K., Harder, L. F. & Chung,
Liang, N. (1983). An examination of the SPT. Thesis, R. M. (1984). The influence of SPT procedures in soil
University of British Columbia. liquefaction resistance evaluations. Report No. UCB/
Matsumoto, K. & Matsubaru, M. ( 1982). Effects of rod EERC-84/15, Berkeley. (Reprinted in 1. Geotech.
diameter in the standard penetration test. Proc. 2nd Engng Div. Am. Soc. Civ. Engrs 1 1 1 , 1 425-1445, but
Eur. Symp. Penetration Testing, Amsterdam 1 , 107- without tabulated data on SPT- liquefaction correla
122. tion.)
Mayne, P. W. & Kulhawy, F. H. (1982). K0-0CR Serota, S. & Lowther, G. (1 973). SPT practice meets
relationships in soil. 1. Geotech. Engng Div. Am. Soc. critical review. Ground Engng 6, 20--22.
Civ. Engrs 1 08, 85 1-872. Shi-Ming, H. (1982). Experience on a standard penetra
Meigh, A. C. & Nixon, I. K. (1961). Comparison of in tion test. Proc. 2nd Eur. Symp. Penetration Testing,
situ tests for granular soils. Proc. 5th lnt. Conf Soil Amsterdam 1 , 61-66.
Mech. Fdn Engng, Paris I, 499-507. Terzaghi, K. (1942). Soil moisture and capillary pheno
Meyerhof, G. G. ( 1957). Discussion on Research on mena in soils. In Physics of the earth : hydrology (ed.
determining the density of sands by spoon penetra 0. E. Meinzer), pp. 331-363. New York : McGraw
tion testing. Proc. 4th lnt. Conf Soil Mech. Fdn Hill.
Engng, London 3, 1 10. Terzaghi, K. & Peck, R. B. (1948). Soil mechanics in
Nishizawa, Y., Fuyuki, S. & Uto, K. (1 982). In-situ tests engineering practice. New York : Wiley.
and efficiency concerning SPT. Proc. Sounding Symp. Tokimatsu, K. & Yoshimi, Y. ( 1983). Empirical correla
lap. Soc. Soil Mech. Fdn Engng (in Japanese). tion of soil liquefaction based on SPT N-value and
Nixon, I. K. (1982). Standard penetration test, state-of fines content. Soils Fdns 23, No. 4, 56--74.
the-art report, and Recommended standard for the Yoshimi, Y. & Tokimatsu, K. (1983). SPT practice
SPT by the Subcommittee on Standardisation of survey and comparative tests. Soils Fdns 23, No. 3,
Penetration Testing in Europe. Proc. 2nd Eur. Symp. 106--1 1 1.
Penetration Testing, Amsterdam 1 , 3-24. Yoshimi, Y., Tokimatsu, K., Kaneko, 0. & Makihara,
Ohoka, H. (1984). Comparison of SPT N-values by Y. (1984). Undrained cyclic shear strength of a dense
cathead-and-rope method and trip monkey method. Niigata sand. Soils Fdns 24, No. 4, 131-145.

S-ar putea să vă placă și