AGENCY/COMMITTEE INTERVENTION REPORT

Agency/Sub-Committee: DPWH Period Ending: November 16, 2017

Estimated Issues Status


Activity/Program Beneficiaries &
Date Rendered Amount / Funding Encountered/Identified Proposed Solution (Completed, Remarks
Description Area
Source Gaps Ongoing)

Rehabilitation and Reconstruction Activities at Marawi City

Turnover of 6 units Water Tank Trucks under DOH


11/17/2017 Trucks to Task Force Bangon IDPs of Marawi City Ongoing Inspection and
Marawi Iligan Field Office Disinfection Procedures

Use of Heavy
Arrival of 6 units Water Tank
Equipments donated by
11/16/2017 Trucks from DPWH-NCH IDPs of Marawi City Ongoing
the People's Republic of
Taguig
China

Road Clearing
Use of Heavy
* going to DPWH 1st DEO
Equipments donated by
11/16/2017 Ramain IDPs of Marawi City Ongoing
the People's Republic of
* going to LASURECO
China
* Clearing of Roads in
Rurugagus

Page 1 of 15
AGENCY/COMMITTEE INTERVENTION REPORT

Agency/Sub-Committee: DPWH Period Ending: November 16, 2017

Estimated Issues Status


Activity/Program Beneficiaries &
Date Rendered Amount / Funding Encountered/Identified Proposed Solution (Completed, Remarks
Description Area
Source Gaps Ongoing)

3 Remaining Tractor-
Mobilization of Heavy
Dozer in the Port of
Equipments donated by the
11/7/2017 IDPs of Marawi City Ongoing Iligan; Completion
People's Republic of China
schedule on November
from Iligan Port to Marawi City
18, 2017.

Return of IDPs to their


10/30/2017 IDPs of Marawi City Ongoing
Cleared Homes

10/23/2017 Clearing of Roads IDPs of Marawi City Ongoing

Actual
Assessment
Based on assesment, the
Completed/
10/15/2017 Post Conflict Needs initial cost of damage on
IDPs of Marawi City
Assessment (PCNA) various infrastructure is
Data
Php 1.117 Billion
Processing
Ongoing

Page 2 of 15
AGENCY/COMMITTEE INTERVENTION REPORT

Agency/Sub-Committee: DPWH Period Ending: November 16, 2017

Estimated Issues Status


Activity/Program Beneficiaries &
Date Rendered Amount / Funding Encountered/Identified Proposed Solution (Completed, Remarks
Description Area
Source Gaps Ongoing)

Arrival of Heavy Equipment donated by the People's Republic of China for the Quick Recovery of Marawi City

Official Handover of
Equipment by the
October 9, 2017 Arrival of 47 Heavy Accepted Ambassador of the
IDPs of Marawi City
Equipments 10/10/2017 People's Republic of
China and DPWH held
last October 24, 2017

Emergency Response Activities

IDPs of Sta. Elena Completed


10/23/2017 Repair of Latrines at Sta.
(October 23,
Elena Evacuation Center Evacuation Center 2017)

Page 3 of 15
AGENCY/COMMITTEE INTERVENTION REPORT

Agency/Sub-Committee: DPWH Period Ending: November 16, 2017

Estimated Issues Status


Activity/Program Beneficiaries &
Date Rendered Amount / Funding Encountered/Identified Proposed Solution (Completed, Remarks
Description Area
Source Gaps Ongoing)

Completed
10/20/2017 Clearing/grass cutting at Sta. IDPs of Sta. Elena (October 23,
Elena Evacuation Center Evacuation Center 2017)

IDPs of Buruun
Fisheries; Sta.
Elena; Buruun Completed
10/20/17 Fabrication of Footbath (October 23,
Gym; Ma. Cristina; 2017)
Evacuation
Centers

IDPs of Buruun Completed


Construction of 10 units
October 4, 2017 Additional Latrines Fisheries (October 8,
Evacuation Center 2017)

Improvement of all
July 3, 2017 IDPs of All PHP 5,156,430.60 / Ongoing
Evacuation Centers Access Evacuation Centers DPWH QRF Savings
Roads and Premises
Construction of Latrines at IDPs of All PHP 980,000.00 /
July 3, 2017 Various Evacuation Centers Evacuation Centers DPWH QRF Savings Ongoing

Page 4 of 15
AGENCY/COMMITTEE INTERVENTION REPORT

Agency/Sub-Committee: DPWH Period Ending: November 16, 2017

Estimated Issues Status


Activity/Program Beneficiaries &
Date Rendered Amount / Funding Encountered/Identified Proposed Solution (Completed, Remarks
Description Area
Source Gaps Ongoing)

IDPs of All PHP 225,000.00 /


July 3, 2017 Provision of Water Supply Ongoing
Evacuation Centers DPWH QRF Savings

Submission of lot
September 4, 2017 Site development for Pantao-Ragat not yet started documents for
transitional shelter Temporary Shelter
verification

August 22, 2017 Expansion of area from IDPs of Landa Additional Latrines Construction of Partially
Mahad Abdul Asis Madrasa to Gadungan Requested by DSWD additional on October Completed
Landa, Balo-i Evacuation Center / 18, 2017
Mahad Abdul Asis
Madrasa Evacuation
Center

September 15, 2017 Construction of 10 units IDPs of Balo-I Completed


Latrines Evacuation Center

Page 5 of 15
AGENCY/COMMITTEE INTERVENTION REPORT

Agency/Sub-Committee: DPWH Period Ending: November 16, 2017

Estimated Issues Status


Activity/Program Beneficiaries &
Date Rendered Amount / Funding Encountered/Identified Proposed Solution (Completed, Remarks
Description Area
Source Gaps Ongoing)

Transitional Shelter Activities

November 8, 2017 Road Concreting Sagonsongan Site Drainage not yet started
(Cluster A / Area 4 Transitional Shelter Development
Expansion) Ongoing With slow
(85%) accomplishment due to
inclement weather
Ongoing condition
Road
Component:
(25 %)

Drainage:
NYS

November 8, 2017 Road Concreting Sagonsongan On-going With slow


(Cluster B / Area 3 & 4 ) Transitional Shelter Road accomplishment due to
Component: inclement weather
(90%) condition

Drainage:

(28%)

Page 6 of 15
AGENCY/COMMITTEE INTERVENTION REPORT

Agency/Sub-Committee: DPWH Period Ending: November 16, 2017

Estimated Issues Status


Activity/Program Beneficiaries &
Date Rendered Amount / Funding Encountered/Identified Proposed Solution (Completed, Remarks
Description Area
Source Gaps Ongoing)

November 8, 2017 Road Concreting Sagonsongan Ongoing With slow


(Cluster C / Area 2 ) Transitional Shelter Road accomplishment due to
Component: inclement weather
(82%) condition

Drainage:
(15%)

November 8, 2017 Road Concreting Sagonsongan On-going


(Cluster D & E / Area 5 ) Transitional Shelter Site
Development
(80%)

Road
Component:
(85 %)

Drainage:
(18%)

Page 7 of 15
AGENCY/COMMITTEE INTERVENTION REPORT

Agency/Sub-Committee: DPWH Period Ending: November 16, 2017

Estimated Issues Status


Activity/Program Beneficiaries &
Date Rendered Amount / Funding Encountered/Identified Proposed Solution (Completed, Remarks
Description Area
Source Gaps Ongoing)

November 8, 2017 Road Concreting Sagonsongan On-going With slow


(Cluster F / Area 1 ) Transitional Shelter Site accomplishment due to
Development inclement weather
(80%) condition
Road
Component:
(NYS)

Drainage:
NYS

Page 8 of 15
AGENCY/COMMITTEE INTERVENTION REPORT

Agency/Sub-Committee: DPWH Period Ending: November 16, 2017

Estimated Issues Status


Activity/Program Beneficiaries &
Date Rendered Amount / Funding Encountered/Identified Proposed Solution (Completed, Remarks
Description Area
Source Gaps Ongoing)

November 8, 2017 Road Concreting Sagonsongan Site With slow


(Cluster G / Area 6 ) Transitional Shelter Development accomplishment due to
Completed inclement weather
(100%) condition

Road
Component:
(92%)

Reported By:

MARIA B. DAVID MIKUNUG R. MACABANTOG


PE III, DPWH - X PE III, DPWH - X
09162329642 09177161602
mayang4167@yahoo.com macabantog_mikunug@yahoo.com

Notes:
a.This report will be the basis of the periodic report to the President Submitted by:
b.This is due every Friday morning.
c. Enumerate agencies with their respective accomplishments. VIRGILIO C. EDUARTE
Regional Director, DPWH - X
Page 9 of 15
AGENCY/SUB-COMMITTEE INTERVENTION REPORT

Agency/Sub-Committee: DPWH Period Ending: November 16, 2017

Supporting Photos

Road Shoulder Clearing at

* going to DPWH 1st DEO Ramain


* going to LASURECO
* Brgy. Rurugagus
AGENCY/SUB-COMMITTEE INTERVENTION REPORT

Agency/Sub-Committee: DPWH Period Ending: November 16, 2017

Supporting Photos

Road Shoulder Clearing at

* going to DPWH 1st DEO Ramain


* going to LASURECO
* Brgy. Rurugagus
AGENCY/SUB-COMMITTEE INTERVENTION REPORT

Agency/Sub-Committee: DPWH Period Ending: November 16, 2017

Supporting Photos

Road Shoulder Clearing at

* going to DPWH 1st DEO Ramain


* going to LASURECO
* Brgy. Rurugagus
AGENCY/SUB-COMMITTEE INTERVENTION REPORT

Agency/Sub-Committee: DPWH Period Ending: November 16, 2017

Supporting Photos

Arrival of 6 units Water Truck Tanks from DPWH - NCH Taguig to


Iligan City
AGENCY/SUB-COMMITTEE INTERVENTION REPORT

Agency/Sub-Committee: DPWH Period Ending: November 16, 2017

Supporting Photos

Arrival of 6 units Water Truck Tanks from DPWH - NCH Taguig to Iligan City
AGENCY/SUB-COMMITTEE INTERVENTION REPORT

Agency/Sub-Committee: DPWH Period Ending: November 16, 2017

Supporting Photos