Use of Heavy
Arrival of 6 units Water Tank
Equipments donated by
11/16/2017 Trucks from DPWH-NCH IDPs of Marawi City Ongoing
the People's Republic of
Taguig
China
Road Clearing
Use of Heavy
* going to DPWH 1st DEO
Equipments donated by
11/16/2017 Ramain IDPs of Marawi City Ongoing
the People's Republic of
* going to LASURECO
China
* Clearing of Roads in
Rurugagus
Page 1 of 15
AGENCY/COMMITTEE INTERVENTION REPORT
3 Remaining Tractor-
Mobilization of Heavy
Dozer in the Port of
Equipments donated by the
11/7/2017 IDPs of Marawi City Ongoing Iligan; Completion
People's Republic of China
schedule on November
from Iligan Port to Marawi City
18, 2017.
Actual
Assessment
Based on assesment, the
Completed/
10/15/2017 Post Conflict Needs initial cost of damage on
IDPs of Marawi City
Assessment (PCNA) various infrastructure is
Data
Php 1.117 Billion
Processing
Ongoing
Page 2 of 15
AGENCY/COMMITTEE INTERVENTION REPORT
Arrival of Heavy Equipment donated by the People's Republic of China for the Quick Recovery of Marawi City
Official Handover of
Equipment by the
October 9, 2017 Arrival of 47 Heavy Accepted Ambassador of the
IDPs of Marawi City
Equipments 10/10/2017 People's Republic of
China and DPWH held
last October 24, 2017
Page 3 of 15
AGENCY/COMMITTEE INTERVENTION REPORT
Completed
10/20/2017 Clearing/grass cutting at Sta. IDPs of Sta. Elena (October 23,
Elena Evacuation Center Evacuation Center 2017)
IDPs of Buruun
Fisheries; Sta.
Elena; Buruun Completed
10/20/17 Fabrication of Footbath (October 23,
Gym; Ma. Cristina; 2017)
Evacuation
Centers
Improvement of all
July 3, 2017 IDPs of All PHP 5,156,430.60 / Ongoing
Evacuation Centers Access Evacuation Centers DPWH QRF Savings
Roads and Premises
Construction of Latrines at IDPs of All PHP 980,000.00 /
July 3, 2017 Various Evacuation Centers Evacuation Centers DPWH QRF Savings Ongoing
Page 4 of 15
AGENCY/COMMITTEE INTERVENTION REPORT
Submission of lot
September 4, 2017 Site development for Pantao-Ragat not yet started documents for
transitional shelter Temporary Shelter
verification
August 22, 2017 Expansion of area from IDPs of Landa Additional Latrines Construction of Partially
Mahad Abdul Asis Madrasa to Gadungan Requested by DSWD additional on October Completed
Landa, Balo-i Evacuation Center / 18, 2017
Mahad Abdul Asis
Madrasa Evacuation
Center
Page 5 of 15
AGENCY/COMMITTEE INTERVENTION REPORT
November 8, 2017 Road Concreting Sagonsongan Site Drainage not yet started
(Cluster A / Area 4 Transitional Shelter Development
Expansion) Ongoing With slow
(85%) accomplishment due to
inclement weather
Ongoing condition
Road
Component:
(25 %)
Drainage:
NYS
Drainage:
(28%)
Page 6 of 15
AGENCY/COMMITTEE INTERVENTION REPORT
Drainage:
(15%)
Road
Component:
(85 %)
Drainage:
(18%)
Page 7 of 15
AGENCY/COMMITTEE INTERVENTION REPORT
Drainage:
NYS
Page 8 of 15
AGENCY/COMMITTEE INTERVENTION REPORT
Road
Component:
(92%)
Reported By:
Notes:
a.This report will be the basis of the periodic report to the President Submitted by:
b.This is due every Friday morning.
c. Enumerate agencies with their respective accomplishments. VIRGILIO C. EDUARTE
Regional Director, DPWH - X
Page 9 of 15
AGENCY/SUB-COMMITTEE INTERVENTION REPORT
Supporting Photos
Supporting Photos
Supporting Photos
Supporting Photos
Supporting Photos
Arrival of 6 units Water Truck Tanks from DPWH - NCH Taguig to Iligan City
AGENCY/SUB-COMMITTEE INTERVENTION REPORT
Supporting Photos
Turnover of 6 units Water Truck Tanks to Task Force Bangon Marawi Iligan Field
Office