Documente Academic
Documente Profesional
Documente Cultură
RTM COLUMBUS
VERIFIED BY:
Safety
Dos and Donts to be followed before attempting any maintenance on
electrical equipment.
DO
Know the ships electrical system and equipment. Familiarize with the
normal indications on the switchboard instruments so that any
abnormal change can be identified easily.
Operate the equipment according to manufacturers instructions.
Ensure appropriate personnel protective equipment is used.
Ensure that all doors, covers and guards are secured and tight.
Inform the officer in watch before shutting down equipment for
maintenance.
Switch off and display warning signs on the breakers before opening up
any equipment.
Understand and Use the Lock Out Tag Out kit available.
Confirm and double check that the circuit is dead using a voltage tester.
DONT
Touch any live conductor without proper isolation.
Touch rotating parts
Leave any live conductor exposed without appropriate warning signs
Overload the equipment
Work on any equipment without proper knowledge
2|Page
Electrical system
The responsible officer has full responsibility to see that all personnel
are clear of any involved circuits before re-energizing the circuit
Insulated tools and specialized tools such as fuse pullers shall be used
when carrying out maintenance on electrical equipment, even if
isolated.
Emergency Work
In the event of an emergency situation, work may be carried out on live
equipment or circuits only after careful review of the job is made and
no safer alternative can be found.
The Chief Engineer must supervise the task including the preparation
stages and initial testing.
A person carrying out the work shall wear electricians gloves, which
must be in good condition, clean, dry and have not been used for any
other purpose. The gloves must be rated for a higher voltage than the
live equipment being worked on, face shield or goggles shall be worn.
Rubber blankets shall be used to isolate the immediate work area from
live components.
3|Page
Electrical system
At least one additional person must at all times standby to observe the
work, assist in assuring the safety of the person doing the work and
respond in case of an accident.
A. C. Generator
The AC generator (Alternator) is a machine that converts Mechanical
Energy into Electrical Energy using the principle of Electromagnetic
Induction.
Brushless A. C. Alternator
Stator Frame and Winding: The stator frame is of welded design. The
stator winding is of a two layer coil design with an insulation class F.
The insulation is made up of mica and enamel coated impregnated
with cast resin. It has a high dielectric strength, resistance to moisture,
gasses and vapors as well as rigidity and long life.
Rotor and Windings: The rotor core of the main machine is mounted on
the shaft, tensioned axially and supports the field and damper
windings. The damper winding bars lie in the slots of the rotor core and
are welded to the rings
(Damper windings are necessary for alternators that run in parallel.
The frequency of an alternator must not change. These damper
windings prevent hunting during parallel operation. They are short
circuited at each end so as to allow currents to circulate so a magnetic
field can be produced to oppose any change in prime mover motion.)
4|Page
Electrical system
The rotor core of the exciter is mounted on the shaft and supports the 3
phase exciter winding; also the rectifier support wheel is mounted on
the dynamically balanced shaft.
Safeties Employed:
o OCIT (Over Current Inverse Time relay)
The Over Current Inverse Time relay monitors general balanced
overloading and has current/time setting determined by the overall
protective discrimination scheme.
5|Page
Electrical system
o RP (Reverse Power)
Generators intended to operate in parallel must have Reverse Power
protection (RP).
The pick-up power level setting and time-delay setting are adjustable
and are pre-set to suit the prime mover. If the prime mover is a
turbine, very little power is absorbed when motoring and a reverse-
6|Page
Electrical system
o Preferential Trip
To maintain generator operation during an overload, a preferential
load shedding arrangement is employed. This is achieved by a special
overload relay, called a 'preference trip relay'.
Each generator will have its own circuit breaker that is typically high
set at 150% with a 20 seconds delay.
In addition, each generator has its own preference overload trip, this
being low set generally at 110% current, instantaneous operation.
Working: The alternator has two separate coils of wire. One will carry
D.C. and produce a magnetic field for use inside the alternator. This coil
of wire is wrapped around an iron core so as to concentrate its
magnetic effects. This coil is called as the Field and is the Rotor.
7|Page
Electrical system
The other coil is the Armature and is called as a Stator. This consists of
six individual windings. Two windings as a pair are connected to each other.
Each of this winding pair is then connected to the other two pairs in wye or
delta combination and spaced 120 degrees apart. Each pair of winding
produces a single phase emf, so the three pairs produce three phase output
from armature windings.
An emf is induced in this stator when its conductors cut the rotor flux
(field). As the armature windings are directly connected to the electrical
system through the main switch board the AVR receives its input which in
turn controls the input to the exciters stationary field.
8|Page
Electrical system
9|Page
Electrical system
PARALLELLING OF ALTERNATORS
The main generator will have to be run in parallel to share a total load
that exceeds the capacity of one generator. The three main conditions
essential for synchronising are
Same Voltage
Same Frequency
Same Phase Sequence
The generator already on the bus bar is called the Running Generator
and the generator to be synchronised is the Incomer.
10 | P a g e
Electrical system
o Auto Operation
Confirm the voltage & frequency of the incomer is normal.
Confirm Mode Select switch is in AUTO position.
Turn the engine control knob to AUTO position the incoming
alternator will come on load and auto load sharing takes place
o Manual Operation
Confirm mode select switch is in manual position
Confirm the voltage & frequency of the incomer is normal. Switch ON
the Synchroscope by bringing its selector switch to the incomer.
Raise/lower the frequency to match with frequency on the bus bar.
Pull the ACB control switch outwards and turn towards CLOSE
when Synchroscope is at 11oclock position.
The incomer will be on load on the bus bar.
Operate the governor control switch of the alternator towards raise
to increase the load on it and operate towards lower to decrease the
load on them.
o Load Sharing
Automatic load sharing in a power management system compare
the kW loading of each generator, and any difference is used to
provide an Error Signal to raise or lower the governor signal of
each prime mover as necessary.
Manual load sharing is achieved by raising the governor setting of
the incoming machine while lowering the setting on the running
machine.
11 | P a g e