Documente Academic
Documente Profesional
Documente Cultură
CL
LU
2
3 EP 0 318 264 A1 4
these have to be spaced about 55 feet apart (48 normal single beam crane, it would nevertheless be
foot container plus 3.5 feet clearance at each end). narrower than two separate single beam cranes
In addition to this 55 foot space, the gantry struc- side-by-side, and this provides the possibility that a
ture itself occupies further space on each side of second such crane can be brought up to the first
the centre space. 5 crane, providing a more intensive working of the
Further, as is well known, the gantry legs usu- containers than two single beam cranes side-by-
ally run on the ground rails be means of a system side.
of rocker beams, wheel bogies and wheels, the In a particularly preferred embodiment of the
rocker beams ensuring an equal distribution of the invention, a third mobile trolley and associated
cumulative vertical loading of the crane between io spreader is supported between the two beams on
the various wheels. A typical large container crane further rails fixed to the two beams, whereby the
has 8 wheels per leg, and it is the distance apart of third trolley may move to and fro along the space
the outermost ends of the rocker beams and bog- between the beams on the said further rails.
ies which determines the overall width of the gan- Clearly with suitable beam spacing this ar-
try. 75 rangement will permit three adjacent rows of 20
Despite crane manufacturers' attempts to keep foot containers to be worked simultaneously by the
the overall crane width to a minimum so that two or single crane or, as before, two adjacent rows of 40
more cranes standing side-by-side can approach foot containers.
as closely as possible to each other in order to A further advantage is that if one trolley is
"work" the ship more intensively, practical con- 20 subject to mechanical or other breakdown, there
straints such as leg spacing as referred to above will still be at least one operative trolley.
and crane stability mean that in practice the closest In the preferred embodiment referred to above,
that two cranes can get is about 80 feet as mea- it is advantageous that rather than having one oper-
sured from the centre lines of the beams of each ator per trolley as in single beam cranes, there
crane. 25 may be one mobile operator cabin supported be-
Accordingly, two side-by-side cranes can only tween the two beams in the same manner as the
work every fourth row of 20 foot containers or third trolley and which during operation of the
every second row of 40 foot containers at the same crane is located towards the front end of the beams
time. for controlling all three trolleys during loading and
It is therefore an object of the present invention 30 unloading of containers from, for example, a vessel,
to provide a construction of travelling container and a second operator cabin (which may likewise
crane which can provide more intensive working of be mobile and supported between the beams) to-
cargo containers arranged in layered matrix fashion wards the rear of the beams for controlling loading
as described above, whether on a vessel or else- and unloading on the land side of the beams,
where, for example in a freight storage depot. 35 control of each trolley being passed from one oper-
Accordingly, the present invention provides a ator to the other at an intermediate point along the
travelling container crane of the kind comprising a beam. The second operator cabin may alternatively
mobile gantry mounted for sideways movement on be fixed to the gantry structure.
fixed ground rails, a beam supported by and ex- Thus not only does the multiple beam structure
tending horizontally from the gantry in a direction 40 of the preferred embodiment permit more intensive
perpendicular to the direction of motion of the working, this can be achieved with one less oper-
gantry, a mobile trolley supported under the beam ator than using separate single beam cranes.
on rails fixed to the beam for to-and-fro movement Naturally, since there will be little clearance
of the trolley along the beam on the beam rails, between adjacent containers being simultaneously
and a hoistable container-lifting device suspended 45 worked, they will need to be lifted to different
from the trolley, wherein at least two parallel beams heights for transport along the beams to avoid
are provided supported in spaced apart side-by- collision by sideways swaying. This can be con-
side relationship by the gantry, each beam having trolled either automatically or by the operators, and
a respective mobile trolley and associated hoista- an automatic safety system can readily be devised
ble container-lifting device. so which would monitor and correlate the heights of
The advantage of the invention is that by pro- the containers and their positions along the beams
viding two beams on a common gantry, these can to provide an automatic cut-out or alarm if sufficient
be located closer together than two beams on the separation of the containers or of the trolley struc-
gantries of two separate cranes, so that with suit- tures was not maintained at all times.
able beam spacing alternate rows of 20 foot con- 55 Clearly the principle described above can be
tainers and adjacent rows of 40 foot containers can extended to cranes having more than two parallel
be worked simultaneously by a single crane. beams supported by the gantry, with a respective
Although such a crane would be wider than a mobile trolley supported under each beam and a
3
5 EP 0 318 264 A1 6
respective trolley supported in the space between rear legs 12 travel on the rail 14 furthest from the
each adjacent pairs of beams. quayside.
As mentioned previously, the invention is par- As mentioned above, the gantry legs 11 and 12
ticularly applicable to quayside cranes, and there- run on the ground rails by means of a system of
fore it is additionally preferred that the gantry is of 5 rocker beams, wheel bogies and wheels. However,
generally arched configuration having two front and these are not shown in the Figures for simplicity
two rear legs respectively which travel on the fixed and because they may be of generally conven-
ground rails, wherein the beams extend at least tional construction, except that there would typi-
under the front of the arch and preferably also cally need to be ten to sixteen wheels per leg
project beyond the rear of the arch, and wherein 10 rather than the conventional eight in order to carry
the portion of each beam forwardly of the arch is a the extra weight.
derrick boom which can be raised from its horizon- Two parallel beams' 16 and 17 are supported
tal position to provide clearance to allow the dock- by and extend side-by-side horizontally from the
ing of ships to be unloaded and vice versa. gantry 10 in a direction perpendicular to the direc-
An embodiment of the invention will now be 75 tion of sideways motion of the gantry. In particular,
described, by way of example, with reference to the beams 16 and 17 extend under the cross
the accompanying drawings wherein: member 13 joining the tops of the front legs 11,
Figure 1 is a perspective view of a quayside fully through the arched gantry 10, and finally to
travelling container crane having two parallel emerge from under the cross member 13 joining
beams, 20 the tops of the rear legs 12 to project beyond the
Figure 2 is a side view of the crane of Figure rear of the arch.
1, The portion of each beam forwardly of the
Figure 3 is a plan view of the front part of arched gantry 10 is a derrick boom which can be
the crane of Figure 1, raised from the horizontal position shown to a near-
Figure 4 is a partial front view illustrating the 25 ly vertical position to provide clearance for masts,
crane of Figure 1 in operation loading and/or un- etc. to allow the docking of ships to be unloaded
loading 20 foot containers, and vice versa.
Figure 5 is a partial front view illustrating the The derrick booms, i.e. the forward portions of
crane of Figure 1 in operation loading and/or un- the beams 16 and 17, rotate upwardly about the
loading 40 foot containers, and 30 hinge points 18 and 19 respectively during
Figure 6 is a schematic front view of a "derricking". However, during normal operation
modification of the crane of Figure 1. they are maintained horizontal by holding arms 20
attached to A-frames 21. The beams are approxi-
In the Figures it will be appreciated that the mately 20 feet in width in this embodiment, and are
crane drive and control mechanisms are not shown, 35 spaced apart by the same distance. However, in
but they may be of conventional design and their order to accomodate the side-shift to be described
adaptation to the embodiment shown would not with reference to Figure 6, the width of the beams
present any great difficulty for the person skilled in would need to be increased by an amount which
the art. Thus they are usually electro-mechanical depends on the length of side-shift required. Each
with either solid state or Ward Leonard speed 40 beam 16 and 17 forms a runway for a respective
regulation. Power supply to the crane may be by mobile trolley 22 and 23 supported under the beam
diesel generator or conductor rails or may be taken on two rails fixed longitudinally on the beam,
from the port's mains supply and fed to the crane whereby each trolley may travel along its rails to
by a flexible cable which is reeled/unreeled on a and fro along substantially the full length of the
cable reeling drum on the crane. Power is distrib- 45 beam.
uted to the individual trolleys by further flexible In particular, a respective inverted T-beam 24
cables which "concertina" along the length of the is fixed to and depends from each outer edge of
beams. each beam 16 and 17, and wheels 25 on each side
Referring first to Figures 1 to 3, the crane of each trolley 22 and 23 run on rails 26 supported
comprises a mobile gantry 10 of generally arched so by the two inward facing limbs 27 of the two T-
configuration, having two front legs 11 and two rear beams 24 supported by the outer edges of the
legs 12, and various bracing and cross members associated beam 16 and 17. A detailed view of this
13. The gantry 10 is adapted for sideways move- arrangement is shown at the top of figure 4, but
ment on a pair of rails fixed in or to the ground generally this detail is omitted for simplicity.
parallel to the quayside 15 (Figure 2), only the rail 55 Further rails 28 are fixed along the two outward
14 most remote from the quayside 15 being facing limbs 29 of the T-beams 24 at the opposing
shown. In particular, the front legs 11 travel on the edges of the two beams 16 and 17, and these form
rail (not shown) nearest the quayside 15, while the a runway for a third mobile trolley 30 having
4
7 EP 0 318 264 A1 8
wheels 31 on opposite sides thereof which engage ers, and the two beams 16 and 17 on either side
these rails 28. Thus this third trolley 30 is sup- are located centrally over two rows C and B of 20
ported between the two beams 16 and 17 in a foot containers immediately on either side of the
similar manner as each of the trolleys 22 and 23 is first row (see also figure 3).
supported below its respective beam 16 and 17, 5 It is clear that provided that the containers 35
and may thus travel along its rails 28 to and fro from the row A are lifted to a different height to the
along substantially the full length of the space containers 34 and 36 from the rows C and B, they
between the beams 16 and 17, i.e. between and may travel freely back and forth along the beams
parallel to the paths of travel of the two trolleys 22 in the same direction or in different directions, and
and 23. 10 loading may be combined with unloading (i.e. con-
A similar supporting effect to that given by the tainers carried in both directions). However, since
T-beams as above described can be obtained in there is not enough clearance to permit all three
alternative ways, for example by having each of the containers to be lowered or raised at the same
two trolley support beams consist of two outer I- time, it is safer if the centre trolley 30 moves
beams located vertically, with their upper portions 75 seawards as the outer trolleys 22 and 23 move
braced together with a lattice construction, allowing landwards, and vice versa. This also tends to re-
the bottom of each I-beam to support two trolley duce the maximum load on the ends of the beams.
rails. Figure 5 illustrates how 40 foot containers are
Each of the three trolleys 22, 23 and 30 has a handled. In this case the centre trolley 30 is not
respective container hoist allocated thereto. These 20 used and is parked on the land side of the beams
hoists may be entirely conventional, and comprise 16 and 17. The beams 16 and 17 are positioned
a winch/rope system 32 by which a so-called pul- centrally over adjacent rows D and E of 40 foot
ley frame and spreader 33 may be raised and containers, and containers 37 from row D may be
lowered. Spreaders are known in the art, and are carried inwardly to the land side simultaneously or
lifting frames which can be attached to the four 25 alternately vith containers 38 from row E. Again,
corners at the top of .a container by twistlocks. the containers are kept at different heights, and
Spreaders either have fixed dimensions, so that loading may be combined with unloading.
they have to be changed for different container In the case of the less common 35, 45 and 48
dimensions, or they can be telescopic to handle a foot containers, trolleys 22 and 23 are parked, and
range of container sizes. 30 only the centre trolley 30 is used. However, by
For controlling the crane, there is a first mobile incorporating a side-shift facility as described be-
operator cabin 39 (shown only in figure 3) sup- low, it is also possible to design the crane so that it
ported for travel along and between the two beams can handle two 35 or 45 or 48 foot containers with
16 and 17 in the same manner as the third trolley the outer trolleys 22 and 23 in a manner similar to
30 and which during operation of the crane is 35 that described above for handling two 40 foot con-
located towards the front end of the beams for tainers.
controlling all three trolleys during loading and un- One possible problem arising out of the afore-
loading of containers from a vessel shown. If re- said crane with mulitple beams and trolley supports
quired for operational reasons, this cabin may be is that of "side-shift". Containers are not normally
equipped with a side-shift facility to give the oper- 40 stacked on board ship with their ends touching,
ator a clearer vertical view into the particular hold although this is theoretically possible and thus
being served. Since the first operator cannot ac- must be designed for. The spacing between the
curately control from his position the motion of the ends of adjacent containers is, therefore, a variable
trolleys as they approach the gantry 10, a second with a minimum value of 0 ft. and a maximum of
operator cabin (which is not shown but may either 45 about 6 ft., where container bays are separated
be fixed to the gantry structure or mobile and from each other by ship's bulkheads or hatch cover
supported between the beams like the trolley 30) is mechanisms.
located towards the rear of the beams for control- It is therefore, advantageous to provide a
ling loading and unloading on the land side of the "side-shift" facility on the spreader 33 carried by
beams, control of each trolley being passed from so the two outer trolleys 22 and 23 to allow them to
one operator to the other at an intermediate point operate on containers spaced by up to 6 ft., or
along the respective beam. more on either side of a centre container. One
Figure 4 illustrates how the two beam/three possible type of side-shift mechanism would be
trolley arrangement described can handle three 20 one where each of the two outer trolleys 22 and 23
foot cargo containers in a continuous cycle of load- 55 are equipped with a separate machinery house 40
ing and/or unloading. In figure 4 it is assumed that (figure 6) containing the hoist drums 41 and asso-
the gap between the two beams 16 and 17 is ciated gear for that trolley (such machinery house
located centrally over one row A of 20 foot contain- trolleys are relatively common on conventional con-
5
9 EP 0 318 264 A1 10
tainer cranes). The machinery house can be made between the beams and locatable towards the front
to travel left-to-right and vice versa (i.e. sideways) of the beams, and a second operator cabin located
on the trolley by fitting it with wheels 42 travelling towards the rear of the beams.
on rails (not shown) mounted on the trolley proper. 4. A travelling container crane according to
The overall width of the beams 16 and 17 is 5 Claim 1, 2 or 3, wherein the gantry is of generally
increased, in the direction away from the centre arched configuration having two front and two rear
gap which remains at 20 foot, to permit the centre- legs (11, 12) respectively which travel on the fixed
line 43 of each hoist to be displaced outwardly by ground rails, (14) wherein the beams (16, 17) ex-
up to a distance L, e.g. at least 6 and preferably up tend at least under the front of the arch, and
to 11 feet. By this means it is possible to greatly 10 wherein the portion of each beam forwardly of the
increase the flexibility of the crane for container arch is a derrick boom which can be raised from its
handling purposes. If side-shift is required for the horizontal position to provide clearance to allow the
centre trolley 30, the mechanism for achieving this docking of ships to be unloaded and vice versa.
side-shift may be incorporated either on the trolley 5. A travelling container crane according to any
itself or between the pulley frame (headblock) and 75 preceding Claim, wherein at least one of the mobile
the spreader. It will be understood that in figures 1 trollies has an associated hoistable container-lifting
to 5 the machinery house 40 and drums 41 are not device (33) which is shiftable sideways.
explicitly described but may be either located in a 6. A travelling container crane according to
fixed position on or between the beams 16 and 17 Claim 5, wherein the mobile trolley comprises a
or fixed to each trolley 22, 23 and 30, rather than 20 sideways shiftable housing (40) containing hoisting
being a separately movable part as shown in figure means (41 ) for the container-lifting device (33).
6.
The major advantage of the invention is that it
provides a construction of crane which enables a
substantial increase in the efficiency of container 25
handling resulting in major cost and time savings.
Claims
30
1. A travelling container crane of the kind com- .
prising a mobile gantry (10) mounted for sideways
movement on fixed ground rails (14), a beam (16)
supported by and extending horizontally from the
gantry (10) in a direction perpendicular to the di- 35
rection of motion of the gantry, a mobile trolley (22)
supported under the beam (16) on rails (26) fixed
to the beam for to-and-fro movement of the trolley
along the beam on the beam rails, and a hoistable
container-lifting device (33) suspended from the 40
trolley, characterised by at least two parallel beams
(16, 17) supported in spaced apart side-by-side
relationship by the gantry (1 0), each beam having a
respective mobile trolley (22, 23) and associated
hoistable container-lifting device (33). 45
2. A travelling crane according to Claim 1,
further including a third mobile trolley (30) and
associated container-lifting device (33) supported
between the two beams (16, 17) on further rails
(28) fixed to the two beams, whereby the third 50
trolley may move to and fro along the space be-
tween the beams on the said further rails.
3. A travelling container crane according to
Claim 1 or 2, further including a first mobile oper-
ator cabin (39) supported between the two beams 55
(16, 17) for movement to and fro along the space
6
EP 0 318 264 A1
P 0 318 264 Al
EP 0 318 264 A1
EP 0 318 264 A1
LO
EP 0 318 264 A1
Application Number
EP 88 31 1078
D O C U M E N T S C O N S I D E R E D TO BE R E L E V A N T
category Citation of document with indication, where appropriate, Relevant CLASSIFICATION OF THE
of relevant passages to claim APPLICATION a. C1.4)
EP-A-0 236 976 (P.H.B. WESERHUTTE AG)
* Figures; a b s t r a c t ; column 4, l i n e s B 66 C 19/00
1-12; claim 1 *
The present search report has been drawn up for all claims
-iace ot searcft Date of completion of the search Examiner
THE HAGUE 24-02-1989 GUTHMULLER J . A . H .
CATEGORY OF CITED DOCUMENTS T : theory or principle underlying the invention
E : earlier patent document, but published on, or
X : particularly relevant if taken alone after the filing date
Y : particularly relevant if combined with another D : document cited in the application
document of the same category L : document cited for other reasons
A : technological background
O : non-written disclosure &: member of the same patent family, corresponding
P : intermediate document document