Documente Academic
Documente Profesional
Documente Cultură
INTRODUCTION
SUBSTATION
Substations transform voltage from high to low, or the reverse, or perform any of
several other important functions. Between the generating station and consumer,
electric power may flow through several substations at different voltage levels. A
substation may include transformers to change voltage levels between high
transmission voltages and lower distribution voltages, or at the interconnection of
two different transmission voltages.
COMPONENTS OF SUBSTATION
1.Supply line
2.Transformer
3.Busbar
4.Switchgear
5.Outcoming Feeder
6.Switching apparatus
a) Switches
b) Fuses
c) Circuit breaker
8.Grounding
1
NEA is also engaged in an ambitious program of improving the situation by both
enhancing access and improving the quality of electricity service. A key aspect of
this program is to curtail power system losses to acceptable levels. Currently, the
system loss of NEA stands to 24.4 percent, which incorporates both technical and
non-technical losses. Many activities have been carried out to reduce the system
losses: such as conductor upgrade work for 132 kV cross border TL, and capacitor
banks installation in some substations as initiatives to reduce the system losses.
What persist are the non-technical losses, such as leakages, and NEA has been
trying hard to address these critical issues through introduction of electricity
leakage control act. NEA now wishes to understand more fully the nature and
incidence of existing system losses and to develop a focused reasonable period of
time.
2.PROBLEM STATEMENTS
a. TECHNICAL LOSS
2
Causes:
i) Harmonics distortion
b. Nontechnical losses
Causes:
3.OBJECTIVES
4.METHODOLOGY
Visiting the substation to get familiar with that substation components and
operation.
Note down daily peak and maximum demand of substation and observe the
variations.
4.1Literature review
According to Electricity Regulation (1993 AD), the following criteria must be
fulfilled by NEA.
-The standard voltage should be 230V for ac single phase and 400 V in 3 phase for
general consumer.
-Power factor should not be allowed not less than 0.8 lagging and not more than
unit leading.
5.PROJECT SCHEDULE
5
6.REFRENCES