G/F 1052 MPI Building Magallanes Village Makati City
Tel. # 851-0230 / 851-2314
Email add: rvn_enterprises@yahoo.com
REF #: RVN-HHB-LET018
Date: February 8, 2017
Project: Hue Hotel Boracay Location: Sitio Manggayad, Manoc-Manoc, Boracay Island, Malay, Aklan
Attention: Engr. Nicholas A. Magarzo
Project Manager Hue Hotel Boracay
Thru: Arch. Romeo C. Reroma Jr.
Project Architect Hue Hotel Boracay
Subject: List of Pending Works
Sir,
Good day!
We would like your good office to be informed of the following pending works for us to push through with our construction schedule.
A. SECOND FLOOR (14 rooms)
- 8 rooms remaining of MJ Aluminum Corp.s glass partition between shower and toilet rooms for ceiling closure and wall tile installation - Ceiling leak on Shower & Toilet at room 200 & 202
B. THIRD FLOOR (36 rooms)
- Only 31 rooms were turned over as of December 1, 2016. - MEPF guest room turnover for remaining 5 is not yet known. - 23 Rooms Remaining of MJ Aluminum Corp.s glass partition between shower and toilet rooms for ceiling closure and wall tile installation - OSM Materials
C. FOURTH FLOOR (38 rooms)
- No guest room MEPF turnover as of this date for all the 38 rooms. - December 10, 2016 MEPF guest rooms turnover as per Sir Caloy. Until now still no update.
D. FIFTH FLOOR (38 rooms)
- No guest room MEPF turnover as of this date for all the 38 rooms. - December 20, 2016 MEPF guest rooms turnover as per Sir Caloy. Until now still no update. - OSM Materials
Thank you and God bless.
G/F 1052 MPI Building Magallanes Village Makati City Tel. # 851-0230 / 851-2314 Email add: rvn_enterprises@yahoo.com
Sincerely, Approved by:
Aceboy Sibbaluca Arch. Jerome Raymond F. Garcia
Project-In-Charge Project Manager RVN Construction & Trading Intl. Inc. RVN Construction & Trading Intl. Inc.
Noted by:
Engr. Rodolfo Barcellano Jr.
Operations Manager RVN Construction & Trading Intl. Inc.