PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION

Best Practice Procedures


in the transition from
Construction to Commissioning

Deniz Metin Kaya


Director of Construction Operations
Foster Wheler Italiana

2012 F
Foster Wh
Wheeler.
l All rights
i h reserved.
d

Milan. Italy, Ooctober 12, 2012 THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUM
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION

Why transition from Construction to Commissioning is so


important?

Safety environment is complex and difficult to manage

Tight schedule: margins are usually eaten up by upstream project phases and little float to cope
with unexpected events

Major over-laps between various activities

Number of participants are quite high compared to other project phases

Stakeholders priorities sometimes conflict with each others

Require very skilled and experienced personnel

Milan. Italy, Ooctober 12, 2012 THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUM
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION

What is Mechanical Completion ?

Construction is completed in accordance with drawings, specifications, vendor instructions,


applicable codes and regulations and authority requirements

All inspection, checking and testing works are completed

System(s) and/or facilities are ready for pre


pre-commissioning
commissioning and commissioning

Milan. Italy, Ooctober 12, 2012 THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUM
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION

What is Pre
Pre-Commissioning
Commissioning and
Commissioning?

Non-operating adjustment adjustments and cold alignment checks (such as cleaning, drying and testing
without introducing process and auxiliary fluids prior to equipment energization )

Pre-startup, check-out, system adjustment, equipment and system activation activities to prepare
system(s) and/or facilities for operation (by introducing auxiliary fluids and with equipment energization)

Milan. Italy, Ooctober 12, 2012 THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUM
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION

Completion & Turnover Map

Project
j Completion
p Data Base

System Completion
Group of Systems

Reaady for Plaant


Area Driven Completion
System Completion
Construction
E
Engineering

Start-up
S
System Completion

System Completion Group of


Systems
y
g

Area Driven Construction Completion


System Completion

Perform (pre)
Preparation Perform
f iinspection
i andd Punch-Out
Punch-Out & commissioning
& Data Measure construction progress test requirement &
Acceptance inspection and test.
Validation Measure progress. Acceptance
Measure progress.

Milan. Italy, Ooctober 12, 2012 THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUM
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION

Road Map for MC by Systems and


Handover to Commissioning
Pre Commissioning
Pre-Commissioning
Construction Commissioning
Final
TOS Test Punch Initial Walkdown MC Check-out
List Pack List
i Walkdown Punch List TOD Testing

Milan. Italy, Ooctober 12, 2012 THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUM
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION

Construction Completion Milestones


TOS Self-contained portion of a facility/system for hand over
(Turn Over System)

Milan. Italy, Ooctober 12, 2012 THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUM
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION

Construction Completion Milestones


TOS Self-contained portion of a facility/system for hand over

Test Package Set of documentation demonstrating the MC of a system or its subsystems


or sections that can be isolated for test purposes

Milan. Italy, Ooctober 12, 2012 THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUM
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION

Construction Completion Milestones


TOS Self-contained portion of a facility/system for hand over

Test Package Set of documentation demonstrating the MC of a system or its subsystems


or sections that can be isolated for test purposes

Punch List Formal inspection and identification of remaining outstanding works

Milan. Italy, Ooctober 12, 2012 THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUM
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION

Construction Completion Milestones


TOS Self-contained portion of a facility/system for hand over

Test Package Set of documentation demonstrating the MC of a system or its subsystems


or sections that can be isolated for test purposes

Punch List Formal inspection and identification of remaining outstanding works

Initial Walkdown Identification and closure of all category A punch items

Milan. Italy, Ooctober 12, 2012 THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUM
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION

Construction Completion Milestones


TOS Self-contained portion of a facility/system for hand over

Test Package Set of documentation demonstrating the MC of a system or its subsystems


or sections that can be isolated for test purposes

Punch List Formal inspection and identification of remaining outstanding works

Initial Walkdown Identification and closure of all category A punch items

Final Walkdown Demonstration and acceptance of a pre-checked system for hand over
& Punch List

Milan. Italy, Ooctober 12, 2012 THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUM
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION

Construction Completion Milestones


TOS Self-contained portion of a facility/system for hand over

Test Package Set of documentation demonstrating the MC of a system or its subsystems


or sections that can be isolated for test purposes

P
Punch
h List
Li t F
Formal
l inspection
i ti and
d id
identification
tifi ti off remaining
i i outstanding
t t di works
k

Initial Walkdown Identification and closure of all category A punch items

Final Walkdown Demonstration and acceptance of a pre-checked system for hand over
& Punch List

TOD Final dossier including all applicable as-built engineering documents and
(Turn Over Dossier) construction certificates as per Inspection & Test Plan attesting the
readiness for
f turn over
Milan. Italy, Ooctober 12, 2012 THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUM
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION

Construction Completion Milestones


TOS Self-contained portion of a facility/system for hand over

Test Package Set of documentation demonstrating the MC of a system or its subsystems


or sections that can be isolated for test purposes

Punch List Formal inspection and identification of remaining outstanding works

Initial Walkdown Identification and closure of all category A punch items

Final Walkdown Demonstration and acceptance of a pre-checked system for hand over
& Punch List

TOD Final dossier including all applicable as-built engineering documents and
construction certificates as per ITP attesting the readiness for turn over

Milan. Italy, Ooctober 12, 2012 THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUM
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION

Breakdown of Systems

System
y
Process Standard
Systems Systems

Sub-Systems Sub-Systems

Disciplines Disciplines

Milan. Italy, Ooctober 12, 2012 THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUM
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION

Typical TOS List

BLACKUTILITIESTOSLIST
SYSTEMNUMBER
SYSTEM RUNNING DESCTRIPTION TOSSUBSYSTEM TOSDESCRIPTION AREA
TOS05.41BS10001 BLACKSTEAM10BARBASEMENT BASEMENT
TOS05.41BS8001 BLACKSTEAM8BARDISTR.BASEMENT BASEMENT
TOS05.41BS3001 BLACKSTEAM3BARDISTR.BASEMENT BASEMENT
05.41BS10/8/3 010 BLACKSTEAM TOS05.41BS3002 BLACKSTEAM3BARDISTR.BULK1 BULK1
TOS05.41BS3003 BLACKSTEAM3BARDISTR.BULK2 BULK2
TOS05.41BS3004 BLACKSTEAM3BARDISTR.STERILEFILTRATION STERILEFILTRATION
TOS05.41BS3005 BLACKSTEAM3BARDISTR.CASA CASA
TOS05.41BSC10001 CONDENSATE10BARBASEMENT BASEMENT
TOS05.41BSC8001 CONDENSATE8BARBASEMENT BASEMENT
TOS05.41BSC3001 CONDENSATE3BARBASEMENT BASEMENT
05.41-BSC10/8/3 011 CONDENSATE TOS05.41BSC3002 CONDENSATE3BARBULK1 BULK1
TOS05.41BSC3003 CONDENSATE3BARBULK2 BULK2
TOS05.41BSC3004 CONDENSATE3STERILEFILTRATION STERILEFILTRATION
TOS05.41BSC3005 CONDENSATE3BARBULK2 CASA
TOS05.41CAI001 CAI10BARDISTRIBUTIONBASEMENT BASEMENT
TOS05.41CAI002 CAI10BARDISTRIBUTIONBULK1 BULK1
05 41-CAI
05.41-CAI 012 CAI TOS05
TOS 05.41
41CAI003
CAI 003 CAI 10 BAR DISTRIBUTION BULK 2
CAI10BARDISTRIBUTIONBULK2 BULK 2
BULK2
TOS05.41CAI004 CAI10BARDISTRIBUTIONCASA CASA
TOS05.41CAI005 CAI12BARGENER.ANDDISTR.CASA CASA

Milan. Italy, Ooctober 12, 2012 THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUM
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION

Test Pack Identification

Milan. Italy, Ooctober 12, 2012 THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUM
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION

Punching and Walkdown

Milan. Italy, Ooctober 12, 2012 THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUM
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION

Punch List Management


Punch List Register
PUNCH LIST RESUMING FOR
WN158-11.23-LIS-0001
SUBCONTRACTOR
Date 28-apr-12

CONTRACTOR or A B C NO GR. TOTAL


VENDOR To Close To Close To Close To Close To Close Closed Hold
CONTRACTOR # 1 43 88 6 1 138 301 0
CONTRACTOR # 2 117 100 23 43 283 23 0
CONTRACTOR # 3 3 32 0 0 35 0 0
CONTRACTOR # 4 17 89 12 4 122 232 0
CONTRACTOR # 5 13 59 8 0 80 336 0
CONTRACTOR # 6 28 135 15 0 178 248 0
CONTRACTOR # 7 60 58 8 0 126 106 0
CONTRACTOR # 8 0 0 0 13 13 0 0
CONTRACTOR # 9 0 0 0 1 1 0 0
VENDOR #1 23 10 1 0 34 27 0
VENDOR #3 4 0 0 0 4 6 0
VENDOR #4 49 18 0 0 67 33 0
VENDOR #5 29 11 0 0 40 38 0
VENDOR #6 48 21 0 0 69 31 0
VENDOR #7 0 0 0 0 0 28 0
VENDOR #8 0 0 0 16 16 87 0
434 621 73 78 1206 1496 1
TOT
1180 1341 105 188 2814

Milan. Italy, Ooctober 12, 2012 THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUM
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION

Punch List by Discipline & Category

Milan. Italy, Ooctober 12, 2012 THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUM
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION

MC & Turnover Progress

Milan. Italy, Ooctober 12, 2012 THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUM
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION

Typical Project Statistics

Project 1 Project 2 Project 3 Project 4


Systems 350 340 140 250
Units 3 37 13 7
Isometrics 3,400 4,000 22,000 1,500
Test packs 1,000 1,500 7,000 600
Inst Tags 3,500 4,200 17,000 5,000
Loop Dossiers 600 850 4,750 2,000
Check Sheets 60 000
60,000 50 000
50,000 200 000
200,000 45 000
45,000

Milan. Italy, Ooctober 12, 2012 THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUM
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION

What is needed to administer this


Transition Phase
S d di d preparation
Standardised i ffor mechanical
h i l completion
l i andd commissioning
i i i

Maximization of electronic data transfer from engineering and project controls

C ti
Continuous and
d auditable
dit bl progress measurementt (physical vs. QC achievements)

Management of system-wise completion

St t d and
Structured d certified
tifi d h
handover
d ffor allll disciplines
di i li

Controlling tool for the creation and management of all QC and MC forms

Milan. Italy, Ooctober 12, 2012 THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUM
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION

Basis of TAG Assignment

At initial phase of engineering, each physical Object of the plant subject to a control:

shall be TAG ged

shall belong to a family (Object Class)

shall be defined in case it does not represent an object (e.g: Hydrotest Circuit, Loop Folder, etc)

Milan. Italy, Ooctober 12, 2012 THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUM
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION

Typical Project Tree for TAG ging

1st Level Systems Project

2nd Level Sub-Systems

3rd Level Disciplines

4th Level TAGs

Milan. Italy, Ooctober 12, 2012 THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUM
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION

Assignment of Discipline TAGs


TOS
Civil:
Instrument:
Foundation List
Instrument List
Steel Structure List
Cable List
Underground List (Pits,
Fire & Gas
Duct, Sewer, etc.)
More
Buildingg

Piping: Equipment:
Engineering Line List Rotating
TAG s
Disciplines ISO List Pressure Vessels
Hydro Test Pack Heat Exchanger
More

Electrical: HVAC:
Cable List Piping List
Equipment List Cable List
Grounding Instrument List
More Equipment List

Milan. Italy, Ooctober 12, 2012 THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUM
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION

Turnover Vision
System
System Acceptance
C tifi t
Certificate

S b
Sub
System
System Ready
INPUT OUTPUT for Pre-
Data Base Commissioning

Disciplines

Mechanical
TAGs Completion
Certificate

Milan. Italy, Ooctober 12, 2012 THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUM
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION

Data Flow & Interfaces

Data Base

Milan. Italy, Ooctober 12, 2012 THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUM
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION

Overview
Commissioning Systems Engineering TAG List Construction Areas
Unit Plant Area
Group of Systems Constr Area

G
Group off S
Systems
t Constr Area

System

System

Select Quality Pack Type Select Quality Steps

Milan. Italy, Ooctober 12, 2012 THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUM
28
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION

Recommendations

All stakeholders must be continuously kept up-to-date with the safety requirements of changing
site conditions

Phased system-wise completion and turnover scheme requires very efficient planning and
scheduling

The achievement of highest coordination standards between construction and commissioning


teams is essential

Construction contracts need to be structured with focus and incentives on system turn over and
completion
p

The administration of voluminous turnover documentation necessitate the implementation of a


structured and tag oriented approach and application of software tools

Milan. Italy, Ooctober 12, 2012 THIRD ANIMP CONSTRUCTION CONFERENCE & ECI AUTUMN FORUM
PUSHING THE LIMITS OF ENGINEERING CONSTRUCTION

THANK YOU