Sunteți pe pagina 1din 6

A Practical Method for Evaluating

Rig Performance
Bahram A. Sheikholeslami, SPE, Amoco Production Co.
James D. Miller, SPE, Amoco Production CO.
R.E. Strong, SPE, Amoco Production Co.

Summary
This paper introduces a practical method of calculating time required to perform the component drilling opera-
rig efficiency incorporating both mechanical perfor- tions directly controlled by the rig and crew is used as a
mance and the performance of the contractor's person- basis for evaluating overall rig performance. Rig effi-
nel. By developing a concept called "contractor- ciency is then a function of both the rig and rig crew's
controlled time" (CCT), the effect of the rig crew on mechanical and operational ability _ The theory implies
various drilling operations can be included in the effi- that any rig should be able to equal the optimal or fastest
ciency calculation. Several example calculations of rig time-if a particular rig is as efficient-both mechanical-
efficiency involving actual field data are presented. This ly and operationally_
paper also addresses the effective cost of a rig to the Drilling a well involves many individual operations in-
operator based on efficiency and the normal fixed costs fluenced by the contractor, the operator, and outside
of the drilling operation. This new approach to rig effi- sources. This paper identifies the operations directly
ciency can be applied to development drilling areas, with controlled by only the rig and rig crew. The time re-
some limited application elsewhere. The results of this quired to perform these operations is defined as "total
study have provided a means of comparing rigs and contractor-controlled time" (TCCT) (see Relationship 1,
determining which is the most efficient and cost effec- Appendix A). Appendix B lists the contractor-controlled
tive. The results also can pinpoint those operations categories used in this study and defines them as they
where a particular rig is inefficient. This information relate to CCT. Routine operations such as rigging up and
provides a method of evaluating rigs on a uniform and down, nippling up and down, cutting drilling line, and
consistent basis. lubricating and repairing the rig are controlled directly
by the rig's design and condition, and the crew's ex-
Introduction perience and ability. Drilling, trip, and connection time
have also been considered in this study as CCT.
The concept of drilling rig efficiency has historically
As a basis for comparison, rigs were selected from
been associated with a rig's mechanical capability.
various drilling areas (Fig. 1), with total depth and
Generally a rig's size, mechanical condition, horsepower
geology essentially the same for each well. This
rating, and maximum load have been considered by
equalizes drilling, trip, and connection time between
many as determining efficiency. This concept of effi-
wells. Additionally, these drilling areas were standard-
ciency has ignored the rig crew and their ability to per-
ized such that the drilling program was the same for each
form routine drilling operations.
well. Drilling parameters such as hole configuration, bit
This paper describes a new method of evaluating drill-
type, weight on bit, and rotary speed are therefore essen-
ing rig efficiency incorporating performance of the con-
tially identical. This normalizes operator and outside in-
tractor's personnel and mechanical capability of the rig.
fluence on the drilling, trip, and connection time.
Efficiency is calculated on the basis of the time it takes a
Following these basic assumptions, drilling, trip, and
rig to perform various drilling operations. An inefficient
connection time becomes a function of the rig and rig
rig costs the operator or contractor both time and money.
crew's ability to carry out the drilling program.
This paper also presents a method to calculate daily rig
It is important to note that any CCT associated with
cost based on efficiency. Equations for rig efficiency and
adjusted daily rig cost are included with a comparison of trouble or nonroutine drilling operations is not included
in the TCCT relationship. It is recognized that TCCT is
rig efficiencies.
not limited to the categories listed in Appendix B.
The concepts and equations discussed in this paper
However, for the sake of uniformity and to provide a fair
provide a practical method for both operator and contrac-
comparison, nonroutine operations have been ignored in
tor to evaluate and compare drilling rigs.
our analysis.
After the concept of CCT had been developed, an op-
Theory timal or 100% level of rig performance had to be defined
A complete evaluation of drilling rig efficiency should to allow calculation of rig efficiency. The "optimal
include the effect of contractor personnel on the overall contractor-controlled time" (OCCT), Relationship 2, is
drilling operation. To account for rig crew influence, the defined as the sum of the fastest time achieved by any rig
0149-2136/84/0031-1364$00.25
for each contractor-controlled category. Therefore, each
Copyright 1984 Society of Petroleum Engineers of AIME drilling area has its own OCCT. When greater efficiency
MARCH 1984 489
Soutbern
Fa'r.a,

Fig. 1-Location of fields.

TABLE 1-TIME DISTRIBUTION (hours)


Condition
Rig Up! and Cut
Tear Circulating Lubricating Repair Drilling Deviation
Down Drilling Reaming Coring Mud Trip Rig Rig Line Survey Logs
-------
East Texas-Field A
Contractor A, Rig 1 41.00 595.00 4.50 0 18.00 81.50 2.75 8.50 3.00 6.75 29.00
Contractor B, Rig 1 3JLOP' !i7Q&Q 3.50 0 19.00 100.75 8.75 7.0Q 2.00 7.75 19.00
Contractor C, Rig 1 50.00 697.50 20.75 0 29.25 152.00 2.50 16.00 5.00 8.75 8.00
Contractor D, Rig 1 47.00 652.00 4.50 0 37.50 100.00 14.25 27.50 4.00 5.25 33.50
OCCT 38.00 570.00 81.50 2.50 7.00 2.00
Optimal operating
time for field 38.00 570.00 3.50 0 18.00 81.50 2.50 7.00 2.00 5.25 8.00
East Texas-Field B
Contractor D, Rig 2 2~JlP :,3.6.!iQ 2.50 0 10.50 57.00 6.75 9.75 1.00 4.75 16.25
Contractor E, Rig 1 39.00 474.00 3.50 0 16.00 78.50 11.25 13.00 2.75 6.25 17.00
Contractor F, Rig 1 32.50 369.00 2.50 0 19.75 99.25 5.25 7.25 2.25 5.25 28.00
OCCT 29.00 366.50 57.00 5.25 7.25 1.00
Optimal operating
time for field 29.00 366.50 2.50 0 10.50 57.00 5.25 7.25 1.00 4.75 16.25
East Texas-Field C
Contractor A, Rig 1 33.00 429.00 3.50 0 16.00 Q.1? 1.50 3.00 7.00 8.25 21.00
Contractor B, Rig 1 3JJlO 39~QQ 2.50 0 15.00 92.75 5.00 4.50 1.75 6.75 14.50
Contractor E, Rig 1 41.00 497.75 5.50 0 38.50 106.00 11.75 33.00 3.00 8.75 17.00
OCCT 31.00 399.00 68.75 1.50 3.00 1.75
Optimal operating
time for field 31.00 399.00 2.50 0 15.00 68.75 1.50 3.00 1.75 6.75 14.50
North Michigan
Contractor G, Rig 1 2~.JlP 162~5 0 0 5.00 34.50 3.25 6.75 8.75 29.25
Contractor G, Rig 2 39.00 204.25 1.00 0 9.00 49.00 6.00 30.25 2.00 12.50 18.00
Contractor H, Rig 1 50.00 223.75 1.50 0 7.00 114.00 5.00 23.00 9.50 12.00
Contractor H, Rig 2 43.50 200.50 0 0 8.25 104.00 7.50 10.50 3.50 8.50 8.75
OCCT 24.00 162.25 34.50 3.25 6.75 2.00
Optimal operating
time for field 24.00 162.75 0 0 5.00 34.50 3.25 6.75 7.00 8.50 8.75
South Michigan
Contractor H, Rig 3 33.00 186.50 0.50 0 7.50 60.00 3.50 9.50 2.00 19.00 16.00
Contractor H, Rig 4 l2&0 t;<~Q 0 0 5.00 ~.OO 5.50 4.50 2.00 21.50 15.00
OCCT 19.00 125.50 35.00 3.50 4.50 2.00
Optimal operating
time for field 19.00 125.50 0 0 5.00 35.00 3.50 4.50 2.00 19.00 15.00
Underlined numbers indicate optimal time

490 JOURNAL OF PETROLEUM TECHNOLOGY


is achieved for any contractor-controlled category, the ing soft line, rigging up surface equipment, laying down
OCCT is changed to reflect the new optimal perfor- drillpipe and collars, waiting on service companies,
mance level. cleaning mud tanks, blowout preventer (BOP) drills, and
Rig efficiency is calculated by use of Relationship 3 as changing bottomhole assemblies. Table 1 also presents
the OCCT divided by the TCCT for each rig. The OCCT the TCCT for each rig. The OCCT for each drilling area
may seem unattainable by a particular rig, but if one rig is shown in Table 1 as the sum of the underlined values
has achieved the optimal time, then rigs of equal effi- in each contractor-controlled category. Rig efficiency for
ciency should be able to duplicate this time. each rig studied is calculated in Table 2. Although none
In the eatly development of our theory it became ap- of the rigs studied operated at 100% efficiency, several
parent it was impossible to attain 100% efficiency in all were operating very close to the optimum. The efficien-
fields. However, a comparison could be made between cies calculated in Table 2 are based on past performance
rigs regardless of the efficiency obtained in a particular and can be used to predict future performance in each
field. This method of calculating rig efficiency provides drilling area.
a relative measure of rig performance. Poor performance
in any category can be identified and hopefully improved
through discussion with the rig personnel while the well Effective Daily Rig Cost. Table 2 shows that at least
is being drilled. one rig is operating inefficiently in each drilling area
studied. This inefficient rig is costing the operator and
Rig Efficiency. Table 1 presents the time distribution for contractor more to operate on a daily basis. The real dai-
each rig used in this study. The time distribution was ob- ly cost of a rig to the operator or contractor can be
tained directly from the daily IntI. Assn. of Drilling Con- calculated by use of Relationship 4. This "effective dai-
tractors reports for a single well in each field. The table ly rig cost" is simply the rig's actual daywork price
includes contractor-controlled operations and additional divided by its efficiency for the particular drilling area.
routine drilling operations experienced while drilling. When rigs are compared, the effective daily rig cost can
The "Other" column includes time spent on reveal substantial cost differences and can be a useful
miscellaneous operations like working stuck pipe, pump- tool in rig selection.

TABLE 1-TIME DISTRIBUTION (hours) CONTINUED


Nipple-
Up
and
Casing Waiting Nipple- Total
and on Down Testing Drillstem Squeeze Directional Operating
Cementing Cement BOP BOP Test Plugback Cement Fish Work Connection Other TCCT Time
----- ----- ----- - - - -----
24.00 8.00 11.75 8.50 0 0 0 0 0 32.75 25.25 776.25 900.25
22.00 8.50 10.00 7.00 0 0 0 0 0 27.75 31.00 764.25 882.00
25.00 12.00 11.50 9.00 0 0 0 0 0 28.25 84.25 962.75 1,161.75
26.00 12.50 18.00 9.75 0 0 0 50.50 0 29.25 62.50 892.00 1,134.00
10.00 27.75 738.75

22.00 8.00 1000 7.00 0 0 0 0 0 27.75 25.25 835.75

18.50 9.50 13.00 7.50 0 0 0 0 25.75 67.00 508.75 645.25


19.50 10.50 23.50 6.50 0 0 0 0 0 32.50 9.00 674.50 762.75
22.00 12.00 24.25 8.50 0 0 0 0 0 27.25 40.50 567.00 705.50

13.00 25.75 504.75


18.50 9.50 13.00 6.50 0 0 0 0 0 25.75 9.00 582.25

20.50 8.50 17.50 8.50 0 0 0 0 0 31.25 13.00 591.00 690.25


22.25 9.50 17.00 5.50 0 0 0 0 0 29.50 73.75 580.50 730.25
6.50 14.00 5.50 0 0 0 0 0 30.00 16.00 736.50 834.25

14.00 29.50 548.50


20.50 6.50 14.00 5.50 0 0 0 0 0 29.50 13.00 632.75

8.00 9.50 19.50 6.50 0 0 0 0 0 10.00 22.00 260.25 349.25


12.00 14.50 24.00 6.00 0 0 0 0 16.75 26.00 371.25 470.25
19.50 16.00 37.50 7.00 0 0 0 0 0 16.75 31.00 470.00 573.50
9.50 18.00 16.25 5.00 0 0 0 0 0 10.50 25.75 396.25 480.00

16.25 10.00 259.00


8.00 9.50 16.25 5.00 0 0 0 0 0 10.00 22.00 331.25

10.25 12.00 14.25 5.00 0 0 0 0 0 19.50 25.50 328.25 424.00


9.50 9.00 14.50 3.00 0 0 0 0 0 24.75 24.00 230.75 317.75

14.30 19.50 223.25


9.50 9.00 14.25 3.00 0 0 0 0 0 19.50 24.00 307.75

MARCH 1984 491


TABLE 2-RIG EFFICIENCY

Rig
OCCT CCT Efficiency
(hours) (hours) (%)
East Texas-Field A RIG EFFICIENCY (%)
Contractor A, Rig 1 738.75 776.25 95
Contractor S, Rig 1 738".75 764.25 96
Contractor C, Rig 1 738.75 962.75 77
WEll No.1
Contractor D, Rig 1 738.75 892.00 83
East Texas-Field S
WELL No.2
Contractor D, Rig 2 504.75 508.75 99
Contractor E, Rig 1 504.75 674.50 75
Contractor F, Rig 1 504.75 567.00 89 0 50 65 83 00
18% ICREASED EFflCIENCY
East Texas-Field C EFFECTIVE DAILY RIG COST ($ 1000/DAY)
Contractor A, Rig 1 548.50 591.00 93
Contractor S, Rig 1 548.50 580.50 94
8307
Contractor E, Rig 1 548.50 736.50 74 t WEll No.1
North Michigan I
I
Contractor G, Rig 1 259.00 260.25 99 650~
: WELL No.2
I
Contractor G, Rig 2 259.00 371.25 70 I I
I I
Contractor H, Rig 1 259.00 470.00 55 I I
Contractor H, Rig 2 259.00 396.25 65 7
$1800/DAY REDUCTION
South Michigan
Contractor H, Rig 3 223.25 328.25 68
Contractor H, Rig 4 223.25 230.75 97 Fig. 2-Field results-Contractor H, Rig 2.

Effective Daily Fixed Cost. Other daily costs besides can be calculated from Relationships 7 and 8 by using
rig costs are associated with drilling wells. These other the minimum times shown in Table 1. The ratio of total
costs are called a rig's "daily fixed cost" and include operating days to optimal operating days indicates
such items as fuel, water, mud, rental equipment, labor, overall efficiency of the entire drilling operation, in-
mud logging, and any other daily drilling expense. This cluding both contractor-controlled and operator-
fixed cost is incurred every operating day and is influenced operations. The "effective daily fixed cost"
therefore a function of the operating time for each well. (Relationship 9) therefore represents the real fixed cost
A rig's daily fixed cost can be calculated with Relation- associated with the rig's overall drilling efficiency.
ship 5. The total operating time for each rig studied is
summarized in Table 1 and is the sum of the time spent Effective Daily Drilling Cost. The bottom line in
in every category listed in the table. Total operating days evaluating drilling performance is the overall cost to the
can then be calculated for each rig by Relationship 6. If operator or contractor. Relationship 10 combines the ef-
the concept previously used in calculating rig efficiency fective daily rig cost and the effective daily fixed cost to
is applied, optimal operating time for a particular field provide a daily measure of overall drilling cost. This ef-

TABLE 3-EFFECTIVE DRILLING COST

Effective Effective Effective


Daily Daily Daily Daily Daily
Rig Rig Rig Fixed Total Optimal Fixed Drilling
Cost Efficiency Cost Cost Operating Operating Cost Cost
($) (%) ($) ($) Days Days ($) ($)
East Texas-Field A
Contractor A, Rig 1 6,250 95 6,578 3,500 37.50 34.8 3,771 10,349
Contractor S, Rig 1 6,500 96 6,771 3,500 36.75 34.8 3,696 10,467
Contractor C, Rig 1 6,400 77 8,311 3,500 48.41 34.8 4,869 13,180
Contractor D, Rig 1 6,700 83 8,072 3,500 47.25 34.8 4,752 12,824
East Texas-Field S
Contractor D, Rig 2 7,158 99 7,230 3,500 26.89 24.3 3,873 11,103
Contractor E, Rig 1 7,330 75 9,773 3,500 31.78 24.3 4,577 14,350
Contractor F, Rig 1 5,600 89 6,292 3,500 29.40 24.3 4,235 10,527
East Texas-Field C
Contractor A, Rig 1 6,250 93 6,720 3,500 28.76 26.4 3,812 10,533
Contractor S, Rig 1 6,500 94 6,915 3,500 30.43 26.4 4,034 10,949
Contractor E, Rig 1 7,330 74 9,905 3,500 34.76 26.4 4,608 14,513
North Michigan
Contractor G, Rig 1 5,800 99 5,859 3,500 14.55 13.8 3,690 9,549
Contractor G, Rig 2 5,800 70 8,286 3,500 19.59 13.8 4,968 13,254
Contractor H, Rig 1 5,400 55 9,818 3,500 23.90 13.8 6,062 15,880
Contractor H, Rig 2 5,400 65 8,308 3,500 20.00 13.8 5,072 13,380
South Michigan
Contractor H, Rig 3 5,400 68 7,941 3,500 17.67 12.8 4,832 12,773
Contractor H, Rig 4 5,400 97 5,567 3,500 13.24 12.8 3,620 9,187

492 JOURNAL OF PETROLEUM TECHNOLOGY


fective daily drilling cost can be used by the operator or BOP's) + (cut drilling line) + (rig up) + (tear
contractor to evaluate rigs on a complete cost basis. down)
These costs are summarized in Table 3 for the rigs in- 2. OCCT (hours) = total of minimum times in:
cluded in this study. (drill) + (trip) + (lubricate rig) + (repair rig) +
(connection) + (nipple-up BOP's) + (nipple-down
Investigation of Results BOP's) + (cut drilling line) + (rig up) + (tear
From the data contained in Table 2 we have been able to down)
determine that rig efficiency varies greatly. We also have 3. Rig efficiency = OCCT/contractor-controlled time
seen that a rig's efficiency remains relatively constant = (Relationship 2/Relationship 1)
when it is operated in different fields. Table 3 shows the 4. Effective daily rig cost ($/day) = daily rig rate/rig
combined effect of rig efficiency and the efficiency to efficiency) = (daily rig rate/Relationship 3)
perform all other drilling operations as the effective daily 5. Daily fixed cost ($/day) = (mud) + (supervisory
drilling cost, which is a practical measure of the overall labor) + (contract labor) + (fuel) + (water) +
drilling performance. (mud logger) + (rental) + (miscellaneous)
Fig. 2 shows an example of results obtained with this 6. Total operating days = total operating time
method of evaluating rig efficiency. Contractor H, Rig (hours)!24 hours
No.2, achieved 65% efficiency and $8,307 effective 7. Optimal operating time (hours) = total of minimum
daily rig cost after drilling Well No. 1. A meeting was time in:
held with the contractor to discuss the concept and the Relationship 2 + (summation of minimum time not
performance of Rig No.2 in each contractor-controlled included in OCCT)
category. After the meeting, Contractor H was con- 8. Optimal operating days = optimal operating time
vinced that improvements could be made. Fig. 2 shows (hours)/24 hours
that Rig No.2 efficiency improved 18% in a subsequent 9. Effective daily fixed cost ($/day) = (daily fixed cost
well and that the effective daily rig cost decreased x total operating days/optimal operating days)
$1,800. Thereafter the improved efficiency of Rig No.2 10. Effective daily drilling cost ($/day) = effective dai-
has been maintained. ly rig cost + effective daily fixed cost

Conclusions APPENDIX B
The effect of the contractor's personnel on the drilling Glossary of Contractor-Controlled Time
operation should be included when rig efficiency is
evaluated. This method of calculating rig efficiency in- Drilling Time. Drilling time is the total rotating hours
cludes both rig and rig crew performance. This provides required to drill a well, excluding reaming time. This
a practical measure of drilling rig performance, which time is influenced by the operator's decisions.
can aid in rig contract negotiation and rig selection. Therefore, it should be excluded from the total rotating
The concepts discussed are currently applicable in hours. Drilling time is considered a contractor-controlled
development drilling areas, with limited use in wildcat item in a drilling area where the drilling program is
drilling areas. Work is under way to develop a relatively uniform.
mathematical model of this type of rig evaluation for use
in rank wildcat drilling areas. Trip Time. Trip time is the total hours required for nor-
This method of calculating rig performance requires a mal drilling operations associated with changing the drill
data base for accurate calculations. A larger data base bit. Trip time associated with a drillstem test should not
will improve accuracy of the results. However, we have be included unless it is a normal part of the drilling pro-
used this method effectively in areas where limited data gram or the trip coincides with a scheduled bit change.
are available. A computer program would greatly aid in Trip time resulting from washouts in the drillstring are to
evaluating rigs, especially in areas of high activity. be included because they reflect the condition of the rig
equipment and the contractor's operating practices. Note
The concepts discussed in this paper are intended to that increasing trip speed may lead to unsafe drilling
provide the groundwork for developing a more uniform practices such as excessive swab or surge pressures, and
method of evaluating rig performance. This should result is not recommended for improving efficiency. Trip time
in more efficient rig operations, thereby reducing overall is considered contractor-controlled because it is directly
drilling cost throughout the industry. associated with drilling time and is a function of the rig
and crew.
Acknowledgments
We thank the management of Amoco Production Co. for Lube Rig Time. Lubrication time is the time required to
permission to publish this paper. We also appreciate the grease the rig to maintain proper rig operation. Rig
support of the drilling staff in helping compile some of lubrication is controlled and performed solely by con-
the data needed for this paper. tractor's personnel.
APPENDIX A
Rig Repair Time. Rig repair includes the time to repair
Relationships Used in Analysis any component of the drilling rig that directly effects
1. CCT (hours) = total of rig time in: proper continuous operation of the rig. Rig repair time is
(drill) + (trip) + (lubricate rig) + (repair rig) + contractor-controlled because it reflects the condition
(connection) + (nipple-up BOP's) + (nipple-down and operating practices of the rig and rig crew.
MARCH 1984 493
Cutting Drill Line Time. This category includes the Nipple-Down Time. This category includes time to
time it takes to slip and to cut the drill line. This practice disassemble and disconnect the BOP's to change
is contractor-controlled and should be included if it is a preventer size or rig-down. Nippling down the BOP's
normal practice on each well studied. usually is performed by the rig crew and is, therefore, a
contractor-controlled item.
Connection Time. Connection time starts when the kel-
Rig-Up Time. Rig-up time begins when the derrick and
ly is picked up for making a connection and ends when
rotation begins for drilling new hole. Reaming and substructure are on location and ends when the rig is
washing to bottom should not be considered as connec- ready to begin drilling operations. Rigging up is usually
tion time. Connection time is contractor-controlled performed by contractor's personnel. However, if a
because it is a function of the rig crew and equipment. delay is caused by outside service personnel, this delay
should be omitted.

Nipple-Up Time. This operation is defined as the time it Tear-Down Time. Tear-down time starts when the rig is
takes to assemble and to conn~ct the BOP system for released by operator and ends when the derrick is laid
operationally safe drilling. Excessive testing time down. Rigging down is also usually performed by the
because of leaks or faulty connections should be includ- contractor's personnel.
ed. However, excessive time because of failure of the JPT
BOP test equipment should be excluded because this Original manuscript received in Society of Petroleum Engineers office Jan. 25, 1983.
Paper accepted for publication June 8, 1983. Revised manuscript received Nov. 14,
function usually is performed by someone other than the 1983. Paper (SPE 11364) first presented at the 1983 IADCISPE Drilling Conference
drilling contractor. held in New Orleans Feb. 20-23.

494 JOURNAL OF PETROLEUM TECHNOLOGY

S-ar putea să vă placă și