Documente Academic
Documente Profesional
Documente Cultură
In Article " Design Process for Lightning Protection Systems ", I indicated that the Design Process for
Lightning Protection Systems is commonly broken into discrete phases, allowing the lightning protection
designer to present an integrated design package. These phases can be listed as follows:
1. Planning phase,
2. Consultation phase,
3. Detailed Design phase.
Also, in Article " Design Calculations of Lightning Protection Systems Part One ", I explained an
Introduction to design calculations of lightning protection systems.
Today, I will Continue explaining Design Calculations of Lightning Protection Systems.
The Lightning Protection Design Process involves a number of design steps as in Fig.1.
Lightning affecting a structure can cause damage to the structure itself and to
its occupants and contents, including failure of internal systems. The damages and
failures may also extend to the surroundings of the structure and even involve the
local environment.
The scale of this extension depends on the characteristics of the structure and
on the characteristics of the lightning flash.
Type Of Structure
According To Function Effects Of Lightning
and/or Contents
Dwelling-house Puncture of electrical installations, fire and material
damage
Damage normally limited to structures exposed to the
point of strike or to the lightning current path
Failure of electrical and electronic equipment and
systems installed (e.g. TV sets, computers, modems,
telephones, etc.)
Farm building Primary risk of fire and hazardous step voltages as well
as material damage
Secondary risk due to loss of electric power, and life
hazard to livestock due to failure of electronic control
of ventilation and food supply systems, etc.
Firework factory Consequences of fire and explosion to the plant and its
Munitions works surroundings
The benefits from performing the risk assessment study are to:
Important Notes:
There are some minor differences to the procedures, parameters and
parameters values between national standards of different countries like
IEC 62305-2, BS EN 62305-2 and NFPA 780 due to different lightning activity
from country to country coupled with each countrys interpretation and
perception of risk.
These differences occurred to better reflect the localized conditions
and acceptable local tolerable risk. These differences will be highlighted in
next articles.
The decision to provide lightning protection may be taken regardless
of the outcome of risk assessment where there is a desire that there be no
avoidable risk. Lightning protection can be installed even when the risk
management process may indicate that it is not required. A greater level of
protection than that required may also be selected.
Local regulations requirements, if any, may be applicable and have to
be taken into account.
The risk assessment study can be done by (4) different methods as follows:
2-Software Method,
3- Excel Sheets Method,
4-Online Calculators Method.
First: Manual Method (Equations And Tables Method) as per IEC 62305-2
Procedure for performing the risk assessment study includes three parts as
follows:
Step#2-3: For each loss to be considered, identify the tolerable level of risk
RT (tolerable means still acceptable).
Step#2-4: For each type of loss to be considered , identify and calculate the
risk components Rx that make up risk Rn which are: RA, RB, RC, RM, RU, RV,
RW, RZ.
Step#2-5: Calculate Rn = Rx
Case#1: If the calculated risk Rn is equal or less than the respective tolerable
risk RTi.e. Rn RT , then Structure is adequately protected for this type of loss
and no lightning protection is required for this type of loss,
Case#2: If the calculated risk Rn is higher than the tolerable risk RT i.e. Rn >
RT, then Install lightning protection measures in order to reduce Rn.
Step#2-7: go back to step#2-4 and make a series of trial and error calculations
until the risk Rn is reduced below that of RT (Rn RT).
Note:
In cases where the risk cannot be reduced to a tolerable level, the site
owner should be informed and the highest level of protection provided to the
installation.
The following flow diagram in Fig.2 shows this procedure for evaluating Need
of lightning protection.
Fig.2: Procedure for Evaluating Need of Lightning Protection
Step#2-8: if the lightning protection measure is needed, then we have (3) cases:
Case#1: check if the risk components RA+RB +RU+RV> RT. if yes, Install an
adequate type of LPS. Otherwise, install adequate type of LPMS. Then go back to
step#2-4 to calculate new values of risk components and make a series of trial and
error calculations until the risk Rn is reduced below that of RT (Rn RT).
Otherwise go to case#2.
Case#2: If the structure under study had LPS installed but the Risks still need to be
reduced, you will need to install LPMS. Then go back to step#2-4 to calculate new
values of risk components and make a series of trial and error calculations until the
risk Rn is reduced below that of RT (Rn RT). Otherwise go to case#3.
Case#3: If the structure under study had both LPS and LPMS installed but the Risks
still need to be reduced, you will need to install other protection measures. Then
go back to step#2-4 to calculate new values of risk components and make a series
of trial and error calculations until the risk Rn is reduced below that of RT (Rn
RT).
The other protection measures that can reduce and influence the values of the risk
components are shown in Table-2:
Characteristics of structure or of
internal systems Protection RA RB RC RM RU RV RW RZ
measures
Collection area X X X X X X X X
Surface soil resistivity X
Floor resistivity X X
Physical restrictions, insulation,
warning notice, soil X X
equipotentialization
LPS X X X Xa Xb Xb
Bonding SPD X X X X
Isolating interfaces Xc Xc X X X X
Coordinated SPD system X X X X
Spatial shield X X
Shielding external lines X X X X
Shielding internal lines X X
Routing precautions X X
Bonding network X
Fire precautions X X
Fire sensitivity X X
Special hazard X X
Impulse withstand voltage X X X X X X
a
Only for grid-like external LPS.
b
Due to equipotential bonding.
c
Only if they belong to equipment.
Table-2: Factors influencing the Risk Components
Notes:
In step#2-8, case#1: If RA+ RB < RT, a complete LPS is not necessary; in this
case SPD(s) according to IEC 62305-3 are sufficient.
In cases where the risk cannot be reduced to a tolerable level, the site
owner should be informed and the highest level of protection provided to the
installation.
The following flow diagram in Fig.3 shows this procedure for Determination of
Required Protection measure.
In any case, the installer or planner should identify the most critical risk
components and reduce them, also taking into account economic aspects.
Selected Protection measures shall be considered effective only if they
conform to the requirements of the national relevant standards which may be: