Intervention Points (# - Engineer's Assistant to be notified by Contractor of readiness of Hold Point and Witness Intervention Points)
Legend: H= Hold Point - IRE to be issues and work shall not proceed without approval/waiver from responsible party ; W= Witness Point - IRE to be issued and work may proceed if responsible party does not attend ; R="Record Review"- (The documents to be submitted for review);
S="Surveillance"
3rd Party
Checking Activity to be Responsible
Acceptance Criteria Required Frequency
Mastro
Performed Job function
GSIC
KEO
LPS
Vol. Sec 21 part 2
1.0 Pre-Commencement
Q11017-0100D-LPS-STA
PKS-ELE-QMS-MDS-
Each delivery
Inspection Request (MDS 01) QCS 2014, Sect. 2, QA/QC Insp./ 00001"
2.2 Working Sheet 7.1.4 24 hours notice Before starting the H H W NA W
Part 7 Site Supervisor Material Inspection check
work
list - Q11017-0100D-LPS-
GEN-PKS-QMS-FRM-
00003
Q11017-0100D-LPS-STA
PKS-ELE-QMS-MDS-
QCS 2014 9 ,9.1.4 & 9.2.1 Approved material submittal
Site Supervisor 00001"
2.3 Material Inspection after delivery Working Sheet Sect 1,Part 9. material delivered on site must be new & Each Delivery H H w NA w
/ QC Inspector Material Inspection check
bear complete identification as per specification
list - Q11017-0100D-LPS-
GEN-PKS-QMS-FRM-
00003
Intervention Points (# - Engineer's Assistant to be notified by Contractor of readiness of Hold Point and Witness Intervention Points)
Legend: H= Hold Point - IRE to be issues and work shall not proceed without approval/waiver from responsible party ; W= Witness Point - IRE to be issued and work may proceed if responsible party does not attend ; R="Record Review"- (The documents to be submitted for review);
S="Surveillance"
3rd Party
Checking Activity to be Responsible
Acceptance Criteria Required Frequency
Mastro
Performed Job function
GSIC
KEO
LPS
Vol.
QCS 2014
Sec 21 part 2
Sect. 1 , Part 9. sec
21 part 1
9.2.4
1.1.12 Q11017-0100D-LPS-STA
PKS-ELE-QMS-MDS-
Storage of MV/LV, MCC, SMDB & Manufacturer's Recommendations / Approved Site Supervisor 00001"
2.4 Visual Inspection Each Delivery H H S NA S
VFD PANEL Method Statement / QC Inspector Material Inspection check
list - Q11017-0100D-LPS-
GEN-PKS-QMS-FRM-
00003
* Project
1. Latest Coordination drawings along with Latest
Specifications "Check List for
Shop drawings and as per Manufacturer
Sect. 21, Part-2 Installation of Electrical
recommendations.
* Approved Method Panels
QCS Sec 21 Part 2 2 "For wall mounted
Statement Q11017-0100D-LPS-
Marking / Preparation before _________ assemblies, mounting should be accessible for Site Supervisor / Before starting a
3.2 In process Check * KAHRAMAA H H H NA S GEN-PKS-QMS-FRM-
Installation Electrical Panels Project spec 21 Part maintenance purpose. 3. Civil QC Insp. specific acitivity
Regulations QCS 00047A for MAIN PANEL
2 clerance is ready for installation - floor / wall
Sec 21 part 2 Q11017-0100D-LPS-
GEN-PKS-QMS-FRM-
4. door provided for lock
00047B for MCC Panel
* Project
Specifications "Check List for
1. Installation as per method statement , latest
Sect. 21, Part-2 Installation of Electrical
drawings and as per manufacturer
* Approved Method Panels
recommendations.
Statement Q11017-0100D-LPS-
Installation / positioning of Electrical Project spec 21 2. Check the clerance Site Supervisor / after completio of
3.3 In process Check * KAHRAMAA H H W NA W GEN-PKS-QMS-FRM-
Panels Part 2 between other electrical panels QC Insp. installation
Regulations 00047A for MAIN PANEL
.
*QCS 2014 Sec 21 Q11017-0100D-LPS-
3. steadiness of fixing.
Part 2 GEN-PKS-QMS-FRM-
00047B for MCC Panel
Intervention Points (# - Engineer's Assistant to be notified by Contractor of readiness of Hold Point and Witness Intervention Points)
Legend: H= Hold Point - IRE to be issues and work shall not proceed without approval/waiver from responsible party ; W= Witness Point - IRE to be issued and work may proceed if responsible party does not attend ; R="Record Review"- (The documents to be submitted for review);
S="Surveillance"
3rd Party
Checking Activity to be Responsible
Acceptance Criteria Required Frequency
Mastro
Performed Job function
GSIC
KEO
LPS
Vol. Sec 21 part 2
* Project
Specifications "Check List for
Sect. 21, Part-2 Installation of Electrical
1. Interconnection to be as per manufacturer
* Approved Method Panels
recommadation.
Statement sec 21 part 2 ______ Q11017-0100D-LPS-
2. Bolt tigthness should be as per Site Supervisor / after completio of
3.4 Interconnection of feeders/ Cubicles In process Check * KAHRAMAA Peoject H H W NA W GEN-PKS-QMS-FRM-
manufacturer recommendations. QC Insp. installation
Regulations spec 21 part 2 00047A for MAIN PANEL
3.Phase to phase clerance to be
*QCS 2014 Sec 21 Q11017-0100D-LPS-
maintained.
Part 2 GEN-PKS-QMS-FRM-
00047B for MCC Panel
* Project
Specifications "Check List for
1.Double earthing for panels
Sect. 21, Part-2 Installation of Electrical
2. All ACB , VCB Cradle should to
* Approved Method Panels
sec 21 part 2 ______ earthed 3.
Statement Q11017-0100D-LPS-
Peoject Individual earth for all feeders/ Compartments. Site Supervisor / after completio of
3.5 Earthing for panels In process Check * KAHRAMAA H H W NA W GEN-PKS-QMS-FRM-
spec 21 part 2 .2.1 4. Size of earth conductor should be QC Insp. installation
Regulations 00047A for MAIN PANEL
mmm as per drawing
*QCS 2014 Sec 21 Q11017-0100D-LPS-
5. Door earthing and gland
Part 2 GEN-PKS-QMS-FRM-
earthing.
00047B for MCC Panel
* Project
Specifications "Check List for
1. Instruments , relays, meters are provided
Sect. 21, Part-2 Installation of Electrical
2. Electrical control inter panel wiring
* Approved Method Panels
3. Double Earthing for panels
Statement sec 21 part 2 ______ Q11017-0100D-LPS-
4. All breaker ON/OFF Site Supervisor /
3.6 Final inspection of Electrical panel In process Check * KAHRAMAA Peoject Final inspection H H H NA W GEN-PKS-QMS-FRM-
operations 5. Name plate QC Insp.
Regulations spec 21 part 2 00047A for MAIN PANEL
details as per SLD. 6.
*QCS 2014 Sec 21 Q11017-0100D-LPS-
Phase to phase clerance
Part 2 GEN-PKS-QMS-FRM-
7. No access for live parts.
00047B for MCC Panel
QCS 2014
Sect. 21
"Check List for
Part 02
Installation of Electrical
*
Panels
Approved Method QCS sec 21
Contract Requirements, Design specifications Q11017-0100D-LPS-
Protection of work during remainder of Statement 4.2.1 Site Supervisor /
3.7 In process Check Approved Materials and Approved Method Statement in process H H S NA S GEN-PKS-QMS-FRM-
construction * KAHRAMAA ________ QC Insp.
and Manufacturer recommendations. 00047A for MAIN PANEL
Regulations Project spec 21 Part
Q11017-0100D-LPS-
* Project 13 .4.4
GEN-PKS-QMS-FRM-
Specifications
00047B for MCC Panel
Intervention Points (# - Engineer's Assistant to be notified by Contractor of readiness of Hold Point and Witness Intervention Points)
Legend: H= Hold Point - IRE to be issues and work shall not proceed without approval/waiver from responsible party ; W= Witness Point - IRE to be issued and work may proceed if responsible party does not attend ; R="Record Review"- (The documents to be submitted for review);
S="Surveillance"
3rd Party
Checking Activity to be Responsible
Acceptance Criteria Required Frequency
Mastro
Performed Job function
GSIC
KEO
LPS
Vol. Sec 21 part 2
4.0 Record Arising
Q11017-0100D-LPS-STA-
PKS-ELE-QMS-IRE-0001
QCS 2014, Sect. 2, QA/QC Insp./
4.1 Inspection Request (IRE) 01 Working Sheet 7.1.2 & 7.1.4 24 hours notice After Installation H H W NA W ''Inspection Request form"
Part 7 Site Supervisor
(IRE)