Documente Academic
Documente Profesional
Documente Cultură
48.5 Part II provides an optional clause for the situation where the Tests on
Completion cannot be carried out prior to taking-over. It introduces a deemed
taking over on the date established by the Engineer's taking-over certificate as
the date on which the Tests on Completion would have been completed.
Compared with the normal taking-over certificate, which states the date on which
The tests are to be carried out in the Defects Liability Period. It may have been
sensible to give the Employer the option to dispense with that, particularly as the
Contractor can claim additional costs for carrying the tests out later. This
proposed sub-clause is ambiguous as to whether the Employer is being granted
an option to dispense with the requirement that the tests are carried out prior to
the taking over certificate. This could be important as, for example, an Employer
whose actual losses were greater than the liquidated damages provided for delay
to the works could increase his recovery by taking over the works as soon as
possible. This sub-clause is, it is submitted, ill thought-out and parties would be
unwise to use it without substantial amendments.
This clause defines the Defects Liability Period as an agreed period, usually six
or twelve months running from the date or dates of the Taking-Over
Certificate(s).
The Contractor is obliged to complete any outstanding work and remedy any
defects during or shortly after this period.
Unless any remedial work undertaken by the Contractor was due to a cause
which was not the Contractor's responsibility, he receives no extra payment for
works executed during this period. If the Contractor remedies defects not of his
making, he is paid as if the work was a variation.
If the Contractor fails to carry out the remedial works within a reasonable time,
the Employer can take on alternative contractors to execute the works and
charge the Contractor the cost of remedying the Contractor's defects.
In the 4th Edition, the "Period of Maintenance" has become the Defects Liability
Period. This change in name appears to have occurred to avoid any suggestion
that the Contractor is obliged to carry out maintenance as distinct from remedial
works after substantial completion. Clause 49 has retained the structure and the
broad principles of the 3rd Edition but the vocabulary has changed extensively.
The reference to design in item (b) of sub-clause 49.3 is the most material
addition.
"...the expression "the Works" shall be construed accordingly". It is far from clear
what effect these words are intended to have or indeed have. The definition of
Works at clause 1.1(f)(i) includes the Permanent Works. It is also qualified by the
phrase in the opening sentence of clause 1.1 "except where the context
otherwise requires". The draftsman is no doubt addressing here the conflict
arising at first sight from the definition of the Defects Liability Period as starting
on "the date of completion of the Works".
The Defects Liability Period most frequently seen in the Appendix to civil
engineering contracts is one year.
Sub-clause (b) contains no time limit upon the Contractor for executing the
remedial works save by implication from the statement of intent. Nevertheless,
failure to carry out works instructed within a reasonable time has the
consequence that the Employer may employ others under sub-clause 49.4
below.