1 - 10 (2016)
Ingeniera y Competitividad, Volumen 19, No. 1, P. 195 - 206 (2017)
ELECTRICAL ENGINEERING
*Grupo de Investigacin en Alta Tensin GRALTA, Universidad del Valle. Cali, Colombia.
ricardo.echeverri@correounivalle.edu.co, diego.echeverry@correounivalle.edu.co,
carlos.a.lozano@correounivalle.edu.co
Resumen
El objetivo de este trabajo es presentar una metodologa para obtener los costos y beneficios socioeconmicos
y medioambientales que trae consigo la implementacin de proyectos de medicin inteligente de energa a
la empresa de servicios energticos y a sus clientes residenciales. La metodologa empleada para cuantificar
los costos y monetizar los beneficios de implementacin de la nueva infraestructura, fue la establecida por
la Unin Europea pero ajustada al caso: Cali-Colombia. Cabe mencionar que esta metodologa podr ser
tomada para evaluar el costo-beneficio de cualquier tipo de proyecto Smart Grid. Se estimaron beneficios
sociales y econmicos entre ellos la generacin de empleo, reduccin del consumo y la reduccin de
prdidas no tcnicas. Se cuantific las reducciones de emisiones de CO2 para el caso de estudio. En este
trabajo se presentan los costos y beneficios de los involucrados en la medicin inteligente y un anlisis
econmico usando el valor presente neto.
Palabras clave: AMI, costo-beneficio, medicin avanzada de energa, medidor inteligente, redes inteligentes
de energa.
Abstract
The aim of this paper is to present a methodological approach to obtain the cost-benefit impact
at environmental and socioeconomic level, related to the integration of Advanced Measurement
Infrastructure into utilities and their residential customers. The methodology used to quantify the costs
and benefits of implementing such technology was established by the European Union and adjusted to
the local context. It is worth highlighting that this methodology can be used to evaluate any kind of
Smart Grid project. The socioeconomic benefits estimated in this research were related to job creation,
energy consumption decrease, reduction of non-technical losses, and the reduction of CO2 emissions. An
economic analysis using the net present value is presented here for assessing the impact caused by smart
metering implementation.
Keywords: AMI, advantage measurement infrastructure, cost-benefits analysis, smart meters, Smart Grids.
1951
Ingeniera
Ingeniera Yy Competitividad,
Ingeniera Volumen
Y Competitividad, 19,18,
Volumen No. 1, 2,
No. 186
P. P.
195 197(2016)
1 -- 10
206 (2017)
196
2 187
Ingeniera y Competitividad,
Y
Ingeniera Volumen
Y Competitividad, 19,18,
Volumen No. 1, 2,
No. P. P.
195
1861 -- 10
206 (2017)
197(2016)
Figure 1 shows the methodology used in the countries at the European Union, in which the average
study in order to obtain the socioeconomic and deployment is in this range (Eurelectric, 2013).
environmental impact of smart meter integration
into an electricity network in Cali city. The analysis 2.2 Step 2 and 3: Map functionalities onto
was divided into the following three stages: Project benefits
descriptions, estimate of the potential benefits, and
costs-benefits analysis. In this study, the process of transforming func-
tionalities into benefits starts with general
2.1 Step 1: Project characteristics aspects that are involved in smart metering and
have socioeconomic and environmental impact
This project involves the installation and sub- that are described in the next list: Energy price;
sequent operation of 529,292 smart meters for a Load management; Management demand curve;
local utility residential customers. The equipment Energy losses; Annual employment; Reduction of
would be required to work under TWACS AMI CO2 emissions.
communication infrastructure (Mak & Reed, 1982;
Figure 3 shows the map of functionalities onto
Mak & Moore, 1984), which is based on two-way
benefits developed in this work. Each benefit points
Automatic Communication System. Such a system
out to an indicator that quantifies success and the
uses electrical distribution lines to send data from the
beneficiaries.
meters to equipment located at the substation, where
then, other communication systems are used for the
flow of information to the control centers. The AMI
TWACS infrastructure is composed by three levels,
shown in Figure 2.
188 1973
Ingeniera
Ingeniera Yy Y
Ingeniera Competitividad, Volumen
Competitividad, 19,18,
Volumen No. 1,2,
No. 195
P.P.
186 206
1 --10
197 (2017)
(2016)
2.4 Step 5: Monetize benefits modified to consider AMI TWACS system infras-
tructure as the system adopted by local utility.
The benefits presented in Figure 3 were monetized by
a numerical simulation tool, which was per-formed Table 1 and 2 shows the most relevant parameters,
by Smart Region (SR, 2013) and adjusted to the local equations and assumptions used to monetize
context. The tool calculates new scenarios of energy benefits and quantify the costs of implementing
measurement considering a hybrid communication the new energy measurement technology in the
infrastructure composed by meter and data con- Cali city. Regarding the annual costs and benefits
centrator via PLC/GSM, and communication from estimation, an increase in both the number of
data concentrator to utility via GSM. The tool was customers and inflation rate were considered.
4198 189
Ingeniera
Ingeniera Yy Y
Ingeniera Competitividad, Volumen
Competitividad, 19,18,
Volumen No. 1, 2,
No. P. P.
186
1951 -- 10
197 (2017)
206(2016)
*Continue Table 2
Non-Technical losses reduction Figure 6 shows savings that could be passed through
to customers in the event of implementing smart
One of the main reasons for the local utility to meters. The perceived savings in Scenario B was
adopt the new smart metering infrastructure is about $7 dollar per year for each customer. Although
the high non-technical losses in its network. The customers savings is observed in the new scenario,
results from conducted analysis showed that in the it is considerable low, and that is because per capita
first model year, economic losses were in the order electricity consumption in Colombia is relatively low
of 21.5 million dollar per year (Carrillo, 2011), if compared with other countries.
190 199
5
Ingeniera
Ingeniera YCompetitividad,
Competitividad,
yY Competitividad, Volumen
Volumen
Volumen 18,
19,
19, No.
No.
No. 1,2,
1, P.P.
P. 1 ---10
195
186 206(2016)
197 (2017)
(2017)
Social acceptance
200
6 191
Ingeniera
Ingeniera Yy Y
Ingeniera Competitividad, Volumen
Competitividad, 19,18,
Volumen No. 1,2,
No. 195
P. P.
186 206(2016)
1 --10
197 (2017)
Table 3. Qualified personnel to handle As in the case study, a 30-year model implies the
the AMI technologies in Cali city. periodical investment for upgrading, replacing, and
acquisition of components for AMI technology.
Institution # People Figure 9 illustrates cyclic expenditures in order to
Academy 15 maintain optimal functionality of the system to be
Public Sector 7 implemented in Cali city. As shown in the graph,
Private Sector 12 there are two replacement periods: the first, during
the first 6 years (2016-2021), representing the
smart meters roll out to all end users; and a second,
Reduction of CO2 emissions for the case study that begins on the 18-year model and ends in
(2038), corresponding to the renewal of previously
To determine reduction of CO2 emissions due to installed equipment.
the use of smart meter technology in Cali city,
a methodology for calculating emissions that is
specified in (Oficina Catalana del Canvi Climtic,
2011) was used. Such methodology considered the
annual electricity consumption by customers, the
smart meter consumption, and average emission
factor of 126 gCO2/kWh (XM, 2012) associated to
electricity generation in Colombia. Figure 8 shows
the expected annual reduction of CO2 emissions Figure 9. Meters and substation costs
for the new scenario. The consumption information for both scenarios.
in Cali comes from the National Interconnected
System, and therefore, decreasing CO2 emissions
will not only benefit the city but the whole country, During the first year of implementation (2016),
especially those regions where electricity come from it can be observed a progressive increase in costs
thermo-plants. It is important to highlight that CO2 due to the fact that implementing smart meters
emissions in Colombia are very low in comparison is massive. For the period of time involving
with other countries. equipment renewal, the years 2032-2037, the
behavior is similar to 2016-2021.
Figure 8. Reduction tons of CO2 due to the It is important to notice that utilitys smart meter
implementation of smart meters. price is higher than the reference price found in
the market, due to the particularities of Colombian
public companies as this utility is.
2.6 Step 7: Economical quantification of benefits
Installation equipment and maintenance costs
The cost analysis included the meters and equipment
in substations acquisition, as well as other costs To estimate costs associated with installation and
associated with the installation and maintenance of maintenance for new smart meter technology,
those advanced technology devices thereafter. information provided by Proyectos de Ingeniera
S.A company was collected. That company won
Meters and substation equipment costs the public bidding carry out by local utility for the
192 201
7
Yy Competitividad,
Ingeniera
Ingeniera Volumen
Y Competitividad, 19,18,
Volumen No. 1, 2,
No. P. P.
195
1861 -- 10
206 (2017)
197(2016)
implementation of advanced metering technology The three methods are the following: Annual
in Cali city. comparison, cumulative comparison, Net Present
Value (NPV). In this research, the net present value
The results for annual installation and maintenance method was applied.
costs are shown in Figure 10 shown below.
Table 4 shows a positive net present value for
customers due to savings. Those savings are
counting on customers having better management
on their consumption habits. Nevertheless, it is
important to note that saving is relatively low and
is strongly conditioned by customers sociocultural
education. A negative NPV for the local utility
would be observed in the first 15 years of this model,
Figure 10. Installation costs of equipment
and maintenance for both scenarios. due to the implementation cost. After that period,
a larger collection can be seen in relation to the
implementation cost, bringing a profit gained during
To determine maintenance cost, this study relied in the rest of the model. The above is supported by
failure rate found in the literature which is 1.5 % strong reduction of non-technical losses. According
for smart meters. For the current situation (Scenario to engineers at the local utility, the project would not
A), it is assumed 1% as reported by the local utility. be viable if the investment recovery is not within the
The cost difference between the current situation first 5 years of implementation. For this case study,
and the new scenario is mainly due to two aspects: such recovery occurs only after the first 15 years.
first, cost while deploying AMI for the first 6 years
of the program (2016-2021) and during equipment Table 4 shows net present value for 10, 20 and 30
upgrade (2032-2037). The second aspect is due years projects.
to the cost difference between electromechanical
and smart meters, and that the latter has a higher Table 4. Financial analysis for the
probability of failure. customers and local utility.
2.7 Step 8: Compare the costs and benefits NPV (Retail Energy
supply company and
NPV Customers
Figures 11 show the stakeholders total economic Distribution System
benefits (Customers and utility) for the new Year Operator)
scenario considered. Scenario B Scenario B
[Million dollars] [Million dollars]
10 25.4 -14.7
15 45.4 -40.1
20 78.4 46.7
30 166.6 304
3. Sensitivity analysis
Figure 11. Stakeholders benefits due to
install smart meters Scenario B. The goal of the sensitivity analysis is to find the
range of variables that may lead to a positive result
Once costs and benefits have been estimated, the in the cost-benefit analysis. For this, it is necessary
methodology suggests three ways to compare them to identify the critical variables commutation
in order to evaluate the cost-benefit of the project. values, i.e., the value that it would occur for the
202
8 193
Ingeniera Y
Ingeniera Y Competitividad,
y Competitividad, Volumen
Volumen 19,18,
No.No.
1, 2, 186
P. P.
195 197(2016)
1 -- 10
206 (2017)
NPV to be zero, or more generally, that the projects assumptions about the sectors where the highest
result is not under certain minimum acceptability energy consumption and losses are presented, would
level. A flow chart of sensitivity analysis loop (in help to determine the optimal zones of installation.
red) application is shown in Figure 12. This could be done using georeferenced systems.
For this study, the full or sectorized implementation For the actual project, it was possible to identify
as well as smart meter lifetime were considered as certain customers who might be potentially
the most important variables. The main reasons for responsive to a smart meter implementation.
these variables to be selected are: in the previous A certain zone is more convenient if meets the
study, full implementation was evaluated leaving following:
the sectorized for evaluation. The local utility has
as a main goal to reduce the energy losses, which Residential customers having an energy
means they have identified certain geographic consumption level above the urban average (about
places at the city there, where there is a high 1000kWh/year per capita) and a sector with the
tendency for this to occur. In the previous study, highest socio economic level, since there is a
a lifetime of 20 years was considered, being the correlation between these two variables.
most convenient for the company. However, in the
literature a lifetime for smart meters is linked to Implementation of the smart meter technologies in
software update, which is not longer than 12 years. low income socio economic zones, where a highest
non-technical losses are presented.
Quantifiable benefits
194 2039
Ingeniera
Ingeniera
Ingeniera Yy Y Competitividad,
Competitividad, Volumen
Volumen 19,18,
No.No.
1,2,
P. P.
195
1861 --10
197(2016)
206 (2017)
emissions will change due to the sensitivity analysis, consumption management. For the local utility, the
which it is expected since there are social aspects economic scenario improves considerably having a
like the skills gap, qualified personnel and the social positive balance in the seventh year, a year after the
acceptance are not altered by the analysis. From the full implementation finishes.
analysis related to the job generation, it is concluded
that the impact is negative. For the CO2 emissions is The analysis for both cases in this research is shown
also observed a reduction year by year as in the full in Table 6. It shows the economic and social impacts
implementation. for all stakeholders related to smart metering in Cali.
Cost quantification In this case, two factors are considered negative and
two positive for the social scenario. It is important to
The results showed that the associated costs related say that despite that the job generation variable has a
to the smart meter installation, the substation negative impact, it will present a positive economic
equipment and installation and maintenance, present impact for the company. From the skills gap
a significantly important reduction compared to perspective and qualified personnel, it is appreciated
the situation where there is a full implementation. a positive impact due to the new job opportunities
Compared to both scenarios, in the first 6 years of for the energy smart metering implementation.
implementation, a 54% reduction on the installation Finally, it is evident a positive impact in the annual
and maintenance, and the smart meter infrastructure CO2 reduction. However, it is important to mention
costs is presented. that total CO2 emissions in Colombia are still too
low compared to those in other countries.
Costs and benefits comparison
From the economic variables, it is observed that
The cost comparison was done using the NPV there is a positive benefit if a sectorized and a not
method as in the analysis where there is a full a full implementation is carried out. The results
implementation. The results for the different years for the sectorized implementation led to full NPV
are shown in Table 5. recovery in the seventh year, right after the full
implementation for all customers.
Table 5. Financial analysis for the costumers and
local utility with sensitivity analysis. Table 6. Social and economic impact.
10
204 195
Ingeniera Yy Competitividad,
Ingeniera Volumen
Y Competitividad, 19,18,
Volumen No. 1, 2,
No. 186
P. P.
195 197(2016)
1 -- 10
206 (2017)
196 205
11
Ingeniera
Ingeniera Y Competitividad,
y Competitividad,
Y Volumen
Volumen 19,18,
No.No.
1, 2,
P. P.
195
1861 -- 10
197(2016)
206 (2017)
SR (Smart Regions). (2013). Promoting Best XM, (2012). Produccin de energa limpia en
Practices of Innovative Smart Metering Services Colombia, la base para un crecimiento sostenible.
to European Regions. https://ec.europa.eu/energy/ http://www.xm.com.co/BoletinXM/Documents/
intelligent/projects/en/projects/smartregions. MDLColombia_Feb2013.pdf.
SUI (Sistema nico de Informacin). (2013). Yan, Y., Qian, Y. & Sharif, H., (2011). A secure
Indicadores de Servicios Pblicos. http://www. data aggregation and dispatch scheme for
sui.gov.co/SUIAuth/logon.jsp. home area networks in smart grid. In Global
Telecommunications Conference, Houston, TX,
USA, p. 1-6.
Revista Ingeniera y Competitividad por Universidad del Valle se encuentra bajo una licencia Creative
Commons Reconocimiento - Debe reconocer adecuadamente la autora, proporcionar un enlace a la
licencia e indicar si se han realizado cambios. Puede hacerlo de cualquier manera razonable, pero no
de una manera que sugiera que tiene el apoyo del licenciador o lo recibe por el uso que hace.
206
12 197