Project Name:
Project Number:
Prepared By: Date:
Risk Level
Risk Factors Criteria
Low Med High
PROJECT SIZE
5,000 or less
Man Hours for Project 5,001 20,000
Over 20,000
4 months or less
Calendar Time (Estimated) for Project 5- 12 months
Over 12 months
< 4 members
Team Size at Peak 5-15 members
> 15 members
1
Sites (Numbers of Locations Affected) 1-3
Over 3
0
Number of Interfaces Considered to
1-3
Existing System Affected by Project
Over 3
1
Organizations Affected by Project 2-4
Over 5
PROJECT DEFINITION
Well-defined
Project Scope Defined, but high-level
Vague
Well-defined
Project Deliverables Defined in name, not content
Not defined
Well-defined
Project Benefits Defined in general
Not defined or unclear
Clearly defined
Use Requirements Complexity Somewhat known, but complex
Vague and complex
Knowledgeable of IT & user areas
Responsible User Knowledge Knowledgeable of user area only
Lack adequate user knowledge
All
Business Knowledge of Team Half
None
Complete and current
More than 75% complete/current
Availability/Status of Documentation
Less than 75% complete, non-
existent or out-of-date
0
Dependence on Other Projects &
1
Development Efforts
2 or more
0
Dependence of Other Systems on This
1
Project
2 or more
Project Name:
Project Number:
Prepared By: Date:
Risk Level
Risk Factors Criteria
Low Med High
Completed documented/proven
Cost/Benefit Analysis of Estimates Approximations used
Estimates not documented/proven
SPONSORSHIP
EFFECT ON ORGANIZATION
Is new to IS
Replaces some subsystems
Conversion or New System
Complete conversion from old to
new subsystem
Little change
Effects on Computer Operations Moderate change
Severe change
Little change
Procedural Changes Imposed by New
Moderate change
System
Severe change
Little change
Changes to Organizational Structure to
Moderate change
Support New System
Severe change
None
Policy Changes Required Moderate changes
Extensive changes
PROJECT STAFFING
PROJECT MANAGEMENT
PROJECT HARDWARE/SOFTWARE
None
Requirements for New or Non-Standard
Existing plus additional
Hardware or System Software
All new
Guaranteed availability
Availability of Hardware for Development
Reasonable availability
and Testing
No assurance of availability
Very familiar
New Tools and Techniques Used by Team Somewhat familiar
Used for the first time
No new languages
New Language Required by Project Somewhat new languages
New language(s), used 1st time
Well-established in organization
New Database Management System Established but new for application
New DBMS of organization
Project Name:
Project Number:
Prepared By: Date:
Risk Level
Risk Factors Criteria
Low Med High
SYSTEM COMPLEXITY
SOFTWARE PACKAGE
Previous experience
Knowledge of Package to be Installed Conceptual understanding
No knowledge or expertise
3 or more times
ISDs Prior Work with Vendor 1 or 2 times
Never
Well (minimal customization req.)
Functional Match to System Fairly well (mod. customization)
Requirements Not well (major customization
required)
High involvement in selection
ISD Involvement in Package Selection Helped select from short list
Not involved
Approved By: Date: