DRILLING PROGRAM

DEVELOPMENT VERTICAL WELL


AZRAFIL SOUTH EAST-4
AZSE-4
Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 2 of 2


PS-2100-0549-003-E-00

APPROVAL SHEET

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 3 of 3


PS-2100-0549-003-E-00

Program Revision History
Date Revision Details
09/07/2017 0 Structure revised. Basis of Design included.
13/08/2017 0 Draft completed. Sent for revision
Formation evaluation strategy reviewed and updated.
18/08/2017 1
Dispensation attachment added. Issued for final revision.
20/08/2017 1.1 Final revision updated. Issued for signatures
22/08/2017 1.1 Program signed and distributed

Dispensations for AZSE-4 Well Design

Document Description of Deviation Justification

The proposed Policy Dispensation initiated for relaxation in


Requirement requirement of Casing, Wellhead and BOP Pressure Test as
of Wellhead stated in the oil and gas industry standards.
and BOP
Pressure Test
as stated in the The 13 5/8", 10Kpsi Section B of the Wellhead and 13 5/8", Technical
oil and gas 10Kpsi BOP stack can't be tested to the shut-in pressure
industry (6,827psi) and design pressure (7,446 psi) respectively as per
standards such NORSOK standard D-010 because exceeds the 80% of the Burst
NORSOK D10 Pressure (6,728 psi) of the 13 3/8" intermediate casing . This
change will be permanent during the life of the well.

Requirement The proposed Policy Dispensation initiated for relaxation in


of Casing requirement of Casing Pressure Test as stated in the oil and gas
Pressure Test industry standards.
as stated in the
The pressure test of the 13 3/8" casing shall be limited to 5000psi Technical
oil and gas
industry due to equipment limitation i.e. 5K Cementing Head, which is
standards such lower than the maximum design pressure expected of 5850psi
NORSOK D10 (Displacement to Gas with Fracture at Casing Shoe).

The Azrafil South East-4 well has been designed based on the statement of requirements indicated
in the Pre-Drill-Data-Package document (PS-2000-0053-002-E-00_PDDP-AZSE-04.xls).
This Drilling Program is based on the GRN Well Construction Process and has been prepared as a
set, of well conditions and specific instructions to be followed during the drilling of the well, fifth
development well to be drilled by the T-45 KCA Deutag Rig, working for GRN in the Reggane block.
Open discussion about any elements of the program is encouraged and any perceived errors or
contradictions should be brought to the attention of GRN Drilling and Completion Group.
The quality of the drilling program will improve with constructive input from the operations
personnel. Field input is therefore strongly encouraged during the on-site planning and operations
stages.
It is imperative that any proposed deviations from the program are reviewed and agreed upon
between the rig and office teams prior to implement following Management of Change process with
corresponding approval.


Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 4 of 4


PS-2100-0549-003-E-00

TABLE OF CONTENTS
1. GENERAL INFORMATION............................................................................................................. 7
1.1. INTRODUCTION .......................................................................................................................... 7
1.2. ABBREVIATIONS ....................................................................................................................... 14
1.3. UNITS CONVENTION ................................................................................................................. 15
1.4. BASIC WELL DATA ................................................................................................................... 16
1.5. DRILLING RIG........................................................................................................................... 17
1.6. WELL SCHEMATIC .................................................................................................................... 18
1.7. PRESSURE AND TEMPERATURE ................................................................................................ 19
2. WELL ESTIMATED TIME ............................................................................................................. 21
2.1. TIME BREAK DOWN BY PHASE .................................................................................................. 21
2.2. TIME BREAK DOWN BY PHASE .................................................................................................. 21
3. HSE ............................................................................................................................................... 22
3.1. SAFETY OPERATIONAL RESPONSIBILITIES ................................................................................. 23
3.2. MODIFICATIONS TO PROGRAM .................................................................................................. 23
3.3. PRE-JOB SAFETY MEETING ...................................................................................................... 23
4. PRE-SPUD PREPARATION ......................................................................................................... 24
4.1. RIG INSPECTION ...................................................................................................................... 24
4.2. GENERAL PREPARATION .......................................................................................................... 24
5. 24 HOLE SECTION. OBJECTIVES & OVERVIEW .................................................................... 25
5.1. 24 SECTION OBJECTIVE .......................................................................................................... 25
5.2. 24 SECTION HAZARDS & RISKS ............................................................................................... 25
5.3. 24 SECTION DRILLING OPERATIONS ........................................................................................ 25
5.4. 24 SECTION DRILLING FLUIDS ................................................................................................. 29
5.5. 24 CUTTING SAMPLING MUD LOGGING PROGRAM ................................................................. 29
5.6. 24 SECTION ELECTRIC LOGGING OPERATIONS ......................................................................... 29
5.7. 18 SURFACE CASING OPERATIONS ..................................................................................... 30
6. 16 HOLE SECTION OBJECTIVES & OVERVIEW ..................................................................... 38
6.1. 16 SECTION KEY POINTS ........................................................................................................ 38
6.2. 16 SECTION HAZARDS & RISKS ............................................................................................... 38
6.3. 16 SECTION DRILLING OPERATIONS ........................................................................................ 39
6.4. 16 SECTION DRILLING FLUIDS ................................................................................................. 44
6.5. 16 CUTTING SAMPLING MUD LOGGING PROGRAM ................................................................. 44
6.6. 16 SECTION ELECTRIC LOGGING OPERATIONS ......................................................................... 45
6.7. 13 CASING OPERATIONS ..................................................................................................... 45
7. 12 HOLE SECTION OBJECTIVES & OVERVIEW ................................................................. 54
7.1. 12 SECTION KEY POINTS .................................................................................................... 54
7.2. 12 SECTION HAZARDS & RISKS ........................................................................................... 54
7.3. 12 SECTION DRILLING OPERATIONS..................................................................................... 54
7.4. 12 SECTION DRILLING FLUIDS ............................................................................................. 58
7.5. 12 CUTTING SAMPLING MUD LOGGING PROGRAM.............................................................. 58
7.6. 12 SECTION WIRELINE LOGGING OPERATIONS ..................................................................... 58
7.7. 9 CASING OPERATIONS ....................................................................................................... 59
Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 5 of 5


PS-2100-0549-003-E-00

8. 8 HOLE SECTION OBJECTIVES & OVERVIEW ................................................................... 67
8.1. 8 SECTION KEY POINTS ....................................................................................................... 67
8.2. 8 SECTION HAZARDS & RISKS .............................................................................................. 67
8.3. 8 SECTION DRILLING OPERATIONS....................................................................................... 67
8.4. 8 SECTION DRILLING FLUIDS ............................................................................................... 71
8.5. 8 CUTTING SAMPLING MUD LOGGING PROGRAM................................................................ 71
8.6. 8 SECTION ELECTRIC LOGGING OPERATIONS ....................................................................... 71
8.7. 7 LINER OPERATIONS ............................................................................................................. 72
9. ANNEXES ..................................................................................................................................... 74
9.1. ANNEX I CASING SPECIFICATIONS ........................................................................................ 74
9.2. ANNEX II 10K PSI W.P. WELLHEAD SPECIFICATIONS............................................................. 75
9.3. ANNEX III BOP, WELLHEAD AND CASING PRESSURE TEST.................................................... 76
9.4. ANNEX IV DRILLING BITS SPECIFICATION. ............................................................................ 77
9.5. ANNEX V MUD PROGRAM SUMMARY ................................................................................... 100
9.6. ANNEX VI CEMENT PROGRAM SUMMARY ............................................................................ 101
9.7. ANNEX VII LCM DECISION TREE........................................................................................ 102
9.8. ANNEX VIII - RISK ASSESSMENT ........................................................................................... 103
9.9. ANNEX IX WELL DIAGRAM (A3 FORMAT) ............................................................................ 111
9.10. ANNEX X OFFSET WELLS ................................................................................................... 112
9.11. ANNEX XI DRILLING JAR CHANGE OUT RECOMMENDATIONS ................................................ 117

LIST OF FIGURES
Figure 1 Reggane Location Map....................................................................................................................7
Figure 2 AZSE-4 General Location................................................................................................................8
Figure 3 Reggane Nord Exploration Perimeter............................................................................................9
Figure 4 AZSE-4 Structural map...................................................................................................................10
Figure 5 Cross-Seismic Sections.................................................................................................................11
Figure 6 Rig KCAD T45 Characteristics......................................................................................................17
Figure 7 Well Schematic................................................................................................................................18
Figure 8 Pore Pressure, Fracture and Overburden Gradient Profiles.....................................................19
Figure 9 AZSE Field Temperature Profile...................................................................................................20
Figure 10 Time vs. Depth Curve...................................................................................................................21
Figure 11 30 Conductor Stack Up Diagram (24 Section).......................................................................28
Figure 12 30 Conductor & 18 Casing Cut............................................................................................33
Figure 13 18 Casing Head Housing (Section A)....................................................................................35
Figure 14 30 Conductor Stack Up Diagram (16 Section).......................................................................37
Figure 15 13 Casing Cut and Casing Head Housing.............................................................................50
Figure 16 13 Casing Spool........................................................................................................................51
Figure 17 12 Section BOP Stack Diagram............................................................................................53
Figure 18 9 Casing Cut..............................................................................................................................63
Figure 19 Casing Head Spool, Section C....................................................................................................64
Figure 20 8 Section BOP Stack Diagram..............................................................................................66
Figure 21 Cameron Wellhead System 10K.................................................................................................75

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 6 of 6


PS-2100-0549-003-E-00

LIST OF TABLES
Table 1 Formation estimated tops................................................................................................................12
Table 2 Lithological sequences and corresponding pressure profile......................................................13
Table 3 - Basic Well Data..................................................................................................................................16
Table 4 AZSE-4 Expected temperatures at formation tops......................................................................20
Table 5 AZSE-4 Time break down by phase..............................................................................................21
Table 6 24 Recommended Bits...................................................................................................................25
Table 7 24 Recommended Drilling Parameters........................................................................................26
Table 8 24 Rotary BHA Assembly...............................................................................................................26
Table 9 24 Recommended Drilling Fluids Properties...............................................................................29
Table 10 18 Casing String.......................................................................................................................30
Table 11 16 Recommended Bits.................................................................................................................39
Table 12 16 Recommended Drilling Parameters......................................................................................39
Table 13 16 RSS BHA Assembly................................................................................................................40
Table 14 16 Rotary BHA Assembly..............................................................................................................41
Table 15 16 Planned FIT..............................................................................................................................42
Table 16 16 Recommended Drilling Fluids Properties.............................................................................44
Table 17 13 Casing String.......................................................................................................................45
Table 18 12 Recommended Bits.............................................................................................................54
Table 19 12 Recommended Drilling Parameters..................................................................................55
Table 20 12 RSS BHA Assembly............................................................................................................55
Table 21 12 FIT.........................................................................................................................................56
Table 22 12 Recommended Drilling Fluids Parameters.....................................................................58
Table 23 9 Casing String..........................................................................................................................59
Table 24 8 Recommended Bits...............................................................................................................67
Table 25 8 Recommended Drilling Parameters....................................................................................68
Table 26 8 RSS BHA................................................................................................................................68
Table 27 8 Packed BHA...........................................................................................................................69
Table 28 8-1/2 Expected ExLOT.................................................................................................................70
Table 29 8 Recommended Drilling Fluids Parameters........................................................................71
Table 30 7 Liner Specifications...................................................................................................................72
Table 31 Casing Specifications.....................................................................................................................74
Table 32 - BOP, Wellhead and Casing Pressure Test Activity Outline......................................................76

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 7 of 7


PS-2100-0549-003-E-00

1. General Information
1.1. Introduction
Groupement Reggane Nord Project (GRN) is planning to drill a development well AZSE-4 vertically in
the Azrafil area, Algerian Sahara in the Wilaya of Adrar southwestern Algeria, in the development of
first gas drilling campaign.
This well will be the second development gas producer to be drilled by GRN in Azrafil SE Field with
target of Lower Devonian reservoirs. This well will drain gas reservoirs in the central part area of the
field and it will confirm the quality of Lower Devonian formations mainly Gedinnian A, Gedinnian B and
Siegenian C. The location is selected on the basis on integrated evaluation of geophysics, geology
and reservoir engineering.
In order to reach the objective, AZSE-4 well will be drilled down to 3,914m TVDRT. The well is
expected to encounter Siegenian-C at 3668m, before reaching its final-depth including roughly 50m of
rat hole for logging operations and having enough length inside the 7 liner to avoid cement clean out
operations.

1.1.1. Location

AZSE-4 development well will be located at Latitude: 2644'19.32029"N Longitude: 015'36.03728"E


(Y-Northing: 2961409.100 m and X-Easting: 824300.928 m using Datum: North Sahara 1959 Zone 30
(Clarke1880). The well is located approximately at 1.95 Km from AZSE-3 ST and 4.28 km from AZSE-
21.

Figure 1 Reggane Location Map



Groupement Reggane


Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 8 of 8


PS-2100-0549-003-E-00

Figure 2 AZSE-4 General Location

1.1.2. Drilling Objectives

Drill AZSE-4 with zero lost time accidents and zero environmental accidents.
Drill AZSE-4 through Sieg-C, Ged-B and Ged-A reservoirs down to planned TD at
3914mTVDRT (~70m below bottom of reservoir as per Production department requirement),
within 50m radius tolerance.
Facilitate the acquisition of a comprehensive wireline logging suite across the reservoir.
Case off hydrocarbon reservoirs to use the well as a future producer.
Drill within the proposed time and budget ensuring HSE standards.
Complete the well.

1.1.3. Subsurface Objectives

Develop the Devonian Reservoirs (Sieg-C, Ged-A & Ged-B)


Prove the Lower Devonian reservoir (Sieg-C, Ged-A & Ged-B), petrophysical characteristics
and the hydrocarbon potential.
Retain AZSE-4 as a producer.

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 9 of 9


PS-2100-0549-003-E-00

1.1.4. Background Information

As part of the third International Licensing Round called by the Algerian Ministry of Energy and Mines
together with SONATRACH in 2002, GRN Exploration Algeria S.A. in Joint Venture with RWE Dea AG
and Edison International were awarded the Reggane Nord license with a total perimeter area of
12,217.5 Km, and a contract signed with SONATRACH for the Exploration, Appraisal and Exploitation
of Reggane Nord blocks 351c and 352c (referred to later as PSA).
Prior to the award, SONATRACH had explored the blocks resulting in the discovery of Lower
Devonian reservoirs in Reggane structure in Apr-64 (with well RG-102) and Azrafil structure (with well
AZSE-1) in Sep-2000. SONATRACH also drilled wells RG-3 (weak gas, low WHP, in 1983) and RG-4
(weak gas, low WHP, in 1985) in Reggane and TIO-1 (dry, 1980) and TIO-2 (dry, 1981) in Tiouliline
structure.
Several exploration works at various fields within the perimeter of the Reggane Nord blocks were
completed during the period 2002-2009 by GRN acting as operator of the JV formed by GRN (45%),
RWE (30%) and Edison International (25%). Exploration works included 2D/3D seismic acquisition
and the drilling of exploration wells with a positive result of dry gas flow in the Reggane (RG), Azrafil
SE (AZSE), Kahlouche (KL), Kahlouche Sud (KLS), Sali (SLI) and Tiouliline (TIO) fields and negative
results in the prospect areas of Djebel Herane (DJHN) and Anzeglouf (AZF). In all cases, the nature
of the discovered hydrocarbons is dry gas with very low liquid content. A total of 15 wells were drilled
(see Figure 3 below):
Reggane: RG-5, RG-6 and RG-7 Sali: SLI-1 and SLI-2
Azrafil: AZSE-2 and AZSE-3. Tiouliline: TIO-3
Kahlouche: KL-2, KL-3 and KL-4. Djebel Hirane: DJHN-3
Kahlouche South: KLS-1 and KLS-2 Azenglouf: AZF-1


Figure 3 Reggane Nord Exploration Perimeter
Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 10 of 10


PS-2100-0549-003-E-00

1.1.5. Formation Tops / Reservoir Target

In general, the seismic time interpretation has a reasonable and reliable quality for structural
interpretation in the flanks of Reggane and in most of Azrafil. The structural uncertainty increases in
the structural crest of Reggane where seismic imaging deteriorates severely as a consequence of
geological complexity caused by the Reggane Master Fault and associated faulting.
Dolerites are seismically identifiable. However, since dolerites generates some degree of various
seismic diffractions and multiples, the seismic interpretation become challenging and complicated in
the areas below the dolerite intrusions, particularly where dyke intrusions occur sub-horizontally to the
formation layering.

Figure 4 AZSE-4 Structural map

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 11 of 11


PS-2100-0549-003-E-00

Figure 5 Cross-Seismic Sections


The expected reservoir pressures are as follows: SIEG-C: 6,209psi, GED-B: 6,224 psi, GED-A:
6,250psi. And summary table of Formation tops is illustrated below:

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 12 of 12


PS-2100-0549-003-E-00

AZSE4ESTIMATEDTOPS
TVDSS DEPTH GROSS DIP AZIM
SURFACE
(mSS) (mMD) (m) (deg) (deg)
HERC_UNC 96 385 4 285
NAMURIAN 96 385 143 1 31
VISEAND 239 528 173 1 31
VISEANC 412 701 240 3 291
VISEANB 652 941 380 3 265
VISEANA 1032 1321 296 2 311
TOURNAISIAN 1327 1616 316 3 3
TOURN_DOLERITE 1469 1758 138 4 71
STRUNIAN 1643 1932 115 3 49
FAMENNIAN 1758 2047 1253 4 357
FAM_DOLERITE#1 1764 2053 30 11 360
FAM_DOLERITE#2 1863 2152 11 3 300
FRASNIAN 3011 3300 143 3 295
GIVETIAN 3154 3443 48 3 291
COUVINIAN 3202 3491 63 3 341
EMSIAN 3265 3554 65 3 341
MDECHINE 3330 3619 25 4 332
SIEGENIAND 3355 3644 24 4 329
SIEGENIANC 3379 3668 59 4 327
GEDINNIANB 3438 3727 90 5 359
GEDINNIANA 3529 3818 26 9 13
SILURIAN 3555 3844 70 9 14
TD 3625 3914

Table 1 Formation estimated tops


Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 13 of 13


PS-2100-0549-003-E-00

Interval Depth
Formation/ Marker/Fault Description
m (RT)
HOLOCENE 280 Loose sand. Cenezoic and Mesozoic deposits are not present.
Upper section: interbedded sequence of Claystone and
NAMURIAN 385
Sandstone with occasional Anhydrite beds. Lower section:

VISEAN D 528 Limestone Interbedded with Claystone and Anhydrite

Upper part: interbedded Claystone and Sandstone. Lower part:


VISEAN C 701
mostly Limestone intercalated with claystones
Upper part: mostly Claystone interbedded by Sandstone.
VISEAN B 941 Lower part: Claystone interbedded with Sandstone with
occasional Limestone stringers.

Mostly Claystone interbedded with Sandstone with occasional


VISEAN A 1321
Limestone stringers.
Massive, homogenous, dark grey to black Claystone with
TOURNAISIAN 1616
Sandstone and occasional Siltstone beds
TOURN_DOLERITE 1758 Dip Angle 4
STRUNIAN 1932 Claystone with Sandstone beds, together with Siltstone.
Upper part: Claystone, Siltstone and Sandstone, possibly with
indications of thermal alteration by the Dolerite intrusion.
FAMENNIAN 2047 Middle part: Claystone grading to Siltstone interbedded with
Sandstone. Lower part: Claystone grading to Siltstone with
Limestone stringers.
FAM_DOLERITE #1 2053 Dip Angle 11
FAM_DOLERITE #2 2152 Dip Angle 3
Claystone occasionally grading to Siltstone with common
FRASNIAN 3300
Limestone stringers.

GIVETIAN 3443 Interbedded Limestone and Claystone.

Claystone grading to Argillaceous Siltstone with Limestone


COUVINIAN 3491
stringers and rare Sandstone.
Upper part: Sandstone interbedded Claystone. Lower part:
EMSIAN 3554
Claystone interbedded with Limestone.
Intercalations of hard limestone and claystone. Possible traces
MURAILLE DE CHINE 3619
of sandstones. At the bottom: Claystone, dark grey.
Upper part mostly Sandstones, lower part claystones
SIEG - D 3644
interbedded with sandstones.
Upper part mostly Sandstones, lower part claystones
SIEG - C 3668
interbedded with siltstone.
Upper part mostly tight Sandstones, middle consists of
GED - B 3727 productive sandstone and the lower part contains of claystones
intercalated with sandstones.
GED - A 3818 Mostly sandstones intercalated with thin bed shally layers.
SILURIAN 3844 Mostly claystones with streaks of sandstones.
TD 3914 70m below top of Silurian formation

Table 2 Lithological sequences and corresponding pressure profile


Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 14 of 14


PS-2100-0549-003-E-00

1.2. Abbreviations
API: American Petroleum Institute OD: Outside Diameter
BBL: Barrels OEDP: Open Ended Drill Pipe
BHA: Bottom Hole Assembly OLC: Operations Liaison Coordinator
BOCP: Blow Out Contingency Plan OWC: Oil Water Contact
BOP: Blow Out Preventer PDDP: Pre Drilling Data Package
BPM: Barrels Per Minute Pg: Probability of Geological Success
CHH: Casing Head Housing POB: Personnel On Board
CHS: Casing Head Spool POOH: Pull Out Of the Hole
CP: Conductor Pipe PP: Pore Pressure
DEMOB: Demobilization ppm: Parts per million
ECD: Equivalent Circulating Density PUW: Pick Up Weight
EIA: Environmental Impact Assessment P/U: Pick Up
ERP: Emergency Response Plan PV: Plastic Viscosity
EMW: Equivalent Mud Weight RIH: Run In Hole
FF: Friction Factor R/U: Rig Up
FCP: Final Circulating Pressure R/D: Rig Down
FIT: Formation Integrity Test ROP: Rate of Penetration
FP: Fracture Pressure RPM: Revolutions Per Minute
GOC: Gas-Oil Contact RT: Rotary Table
GSA: Geo-hazards Study Agreement SCR: Slow Control Rates
HC: Hydrocarbon SICP: Shut In Casing Pressure
HWDP: Heavy Weight Drill Pipe SIDPP: Shut In Drill Pipe Pressure
IB: Integral Blade SG: Specific Gravity
ID: Inside Diameter SOW: Slack-Off Weight
KT: Kick Tolerance SPP: Stand Pipe Pressure
L/D: Lay Down STB: Stabilizer
LOT: Leak-Off Test TCP: Tubing Conveyed Perforating
LPM: Liters Per Minute TD: Total Depth
LWD: Logging While Drilling TDS: Top Drive System
md: Milidarcies THS: Tubing Head Spool
MOB: Mobilization TVDRT: True Vertical Depth below Rotary Table
MSL: Mean Seal Level TVDGL: True Vertical Depth below Ground Level
MDRT: Measure Depth below Rotary Table UR: Underreamer
MDGL: Measure Depth below Ground Level WH: Well Head
M/U: Make Up WOB: Weight On Bit
NB: Near Bit WOC: Wait On Cement
N/A: Not Applicable WP: Working Pressure
N/U: Nipple Up XO: Cross-Over
N/D: Nipple Down YP: Yield Point

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 15 of 15


PS-2100-0549-003-E-00

1.3. Units Convention

Length/Height: m
Depth: m
Measure Depth below RT: m MDRT
True Vertical Depth below RT: m TVDRT
Measure Depth below GL: m MDGL
True Vertical Depth below GL: m TVDGL
Rotary Table Elevation: m
Coordinates N/S E/W: m
Rate of Penetration: m/h
Mud Weight: sg
Torque: lb-ft
WOB: Ton
Flow Rates: liters per minute (lpm)
bbl/min (only for pumping cement with cement unit; for
displacements with Rig Pump to use lpm)
Temperature: C
Temperature Gradient: C/100 m
Angle: ()
Diameter (OD/ID): Inches ()
Linear Weight: lb/ft
Pressure: psi
Pore Pressure: psi
Pressure Gradient: psi/ft
Fracture Pressure: psi
Inclination/Azimuth: deg ()
ECD: sg
Volume: m3
Linear Capacity/Displacement: liters/meter (l/m)

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 16 of 16


PS-2100-0549-003-E-00

1.4. Basic Well Data

Generic Name Azrafil South East-4 (AZSE-4)

Area Reggane

License / Block Number 351c

Classification Development Vertical Well

Rig T-45

Rotary Table Elevation (RT) 9.37 m

Ground Level (GL) 279.4 m (GL), 288.78 m (RTKB)

Planned Total Depth 3914 m TVDRT / 3914 m TMDRT

UTM Northing Easting

UTM30NNSahara1959:UTM zone
2961409.10 m 824300.928 m
30N / Spheroid Clarke 1880_RGS
Surface Location
Latitude Longitude

2644'19.32029" N 015'36.03728" E

Geodetic Datum Nord Sahara 1959, Zone 30

Geological Target Lower Devonian Reservoir (Ged-A, Ged-B & Sieg-C)

Tolerance 50 m radius

Bottom Hole Temperature 132 C (approx.)

Hydrocarbon Gradient Gas Gradient (0.1 psi/ft) for well design

H2S / CO2 Not Expected / +- 3.8%

Planned Final Well Status Production

Key Offset Wells AZSE-1, AZSE-2 ST1, AZSE-3 ST, AZSE-21

Total Estimated Cost 19.8 M USD (Mobilization and Completion included)

Total Estimated Time 132.2 days (Mobilization and Completion included)

Table 3 - Basic Well Data

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 17 of 17


PS-2100-0549-003-E-00

1.5. Drilling Rig


Figure 6 Rig KCAD T45 Characteristics

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 18 of 18


PS-2100-0549-003-E-00

1.6. Well Schematic


Figure 7 Well Schematic

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 19 of 19


PS-2100-0549-003-E-00

1.7. Pressure and Temperature
1.7.1. Pore Pressure and Fracture Gradient Estimate

Figure 8 shows the calculated Pore Pressure profiles for AZSE-4.


Figure 8 Pore Pressure, Fracture and Overburden Gradient Profiles

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 20 of 20


PS-2100-0549-003-E-00

1.7.2. Temperature Profile


Figure 9 AZSE Field Temperature Profile

FORMATION EXP. TOPS EXP. TEMP C (MIN) EXP. TEMP C (AVG) EXP. TEMP C (MAX)
NAMURIAN 385 23 30 37
VISEAN D 528 27 34 41
VISEAN C 701 32 39 46
VISEAN B 941 39 46 53
VISEAN A 1321 50 57 64
TOURNAISIAN 1616 59 66 72
TOURN_DOLERITE 1758 63 70 77
STRUNIAN 1932 68 75 82
FAMENNIAN 2047 72 79 86
FAM_DOLERITE #1 2053 72 79 86
FAM_DOLERITE #2 2152 74 81 88
FRASNIAN 3300 108 114 121
GIVETIAN 3443 112 119 125
COUVINIAN 3491 113 120 127
EMSIAN 3554 115 122 129
MURAILLE DE CHINE 3619 117 124 131
SIEG - D 3644 118 124 131
SIEG - C 3668 118 125 132
GED - B 3727 120 127 134
GED - A 3818 123 129 136
SILURIAN 3844 123 130 137
TD 3914 125 132 139

Table 4 AZSE-4 Expected temperatures at formation tops

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 21 of 21


PS-2100-0549-003-E-00

2. Well Estimated Time
2.1. Time Break Down by Phase
Estimatedtimetodrillthewellis102.3days,withoutMobilizationandCompletion.Figurebelow
showsthetimevs.depthcurve,including6.8daystocompletethewell.


Figure 10 Time vs. Depth Curve

2.2. Time Break Down by Phase


The estimated duration of the well can be break down per phase and main activity as follows:

Planned AZSE-4 Base Case T P50 Time


Mobilization 23,10 day(s)
24" Hole Section / 18-5/8" Casing 7,65 day(s)
16" Hole Section / 13 3/8" Casing 45,3 day(s)
12-1/4" Hole Section / 9-5/8" Casing 27,3 day(s)
8 1/2" Hole Section / 7" liner 22,1 day(s)
Completion and Suspension 6,77 day(s)
TOTAL with mob 132,22 day(s)
TOTAL without mob 109,11 day(s)

Table 5 AZSE-4 Time break down by phase

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 22 of 22


PS-2100-0549-003-E-00

3. HSE
All activities must be planned and executed taking into account the safety, health and environmental
protection in line with OHSAS 18001, ISO 14001 and the best OGP practices.
As a complementary document of this Drilling Program a specific HSE plan will be also available
describing in details the different HSE activities to be performed during the drilling activities of the
well.
An Emergency Response Plan is developed taking into account operation local conditions and the
different emergency levels.
The Emergency Response that will be developed for this well will include GRN Emergency
Response Plan (Emergencies Level II and Level III).
HRA and Medevac Response Plan.
Evacuation Plan for Security reasons.
Blow Out Contingency Plan.
Diesel and Chemical Spill Response Plan.
KCAD T-45 ERP.
A combined document (Bridging document) is already approved and signed. This document has the
purpose of establishing the interphase between GRN Policies and Rules with HSE Policies of the
Drilling Contractor.
The following are, but not limited, some safety guidelines to govern the operations:
The safety of personal, environment and equipment is vital for GRN.
It should exist in the Well site, an archive with all Safety, Health and Environment relevant
documents (HSE Plan, Bridging Document, ERPs, etc.).
The GRN Safety, Health and Environment policy should be available and arranged in such a
way that is easy to view it.
Health, Safety and Environmental issues should be part of the daily coordination meetings in the
Drilling Site and HMD Drilling Offices.
Weekly meetings should be undertaken with all staff including GRN Company Man to discuss
HSE issues.
Any incident and personnel or environmental accidents must be reported within the first 24 hours
in accordance with current GRN normative.
Safety cards (STOP) can be filled by personnel from any service company involved in the
operations.
Every critical activity during the drilling operation must be withstood with safety meetings before
and after work.
The use of Permit to Work (PTW) is mandatory which must be reviewed and approved by the
service companies supervisors and ultimately by the Tool Pusher and Company Man.
In every safety meeting, a personnel record should be signed by all participants.
Periodic emergency drills (Well control, Medevac, others) should be undertaken according to the
instructions of the GRN Company Man. The crew participation and response time will be
recorded in the Daily Drilling Report.
The Rig site personnel meeting areas should be clearly defined and be communicated directly
by the Company Man to the entire crew.
A control of personnel and vehicles entering and exiting the location should be adopted.

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 23 of 23


PS-2100-0549-003-E-00

Clear procedures and rules should be followed for land transport including but not limited at
journey management, speeds limits, defense driving course, vehicle standard and minimum
vehicle equipment.

3.1. Safety Operational Responsibilities


The Company Man has primary responsibility for ensuring safe implementation of the operations
detailed in this program and will directly supervise all drilling operations.

3.2. Modifications to Program


Due to unpredictable hole conditions and potential for equipment problems during drilling operations
stated in this Program, Management of Change Procedure has been implemented. Prior to changing
the program, an initial assessment of the impact of the proposed change should be undertaken to
establish if there is any increase in safety and/or environment risk. If concluded that risks are
increased due to a required change to the program and/or if the pressure boundary of the well will
be materially changed from the planned status then the change must be reviewed, justified and
agreed between Operational Supervisors and the Superintendent then confirmed in writing by a
Management of Change document that should be signed by the parties.
According with the nature and magnitude of the change, MOC document could require the signature
and approval of the Drilling Manager and GRN Co-Administrators.

3.3. Pre-job Safety Meeting


Prior of the commencement of each operation, a pre job safety meeting, based on the Risk
Assessment, will be held with all personnel involved in the operation. A technical briefing will be
given on the operation to be carried out, and any hazards and precautions to be taken will be
reviewed. If required, additional pre job meetings will be held either due to crew changes occurring
or because of additional personnel or services becoming involved in the operations.
As the drilling operations will continue to change focus through the various stages of the well,
personnel must be kept fully briefed and continually updated as the various work tasks change.
At the pre job safety meetings, all aspects of the particular operation to be performed should be
discussed, including any contingency plans. Suggested topics to be included in the meeting agenda:
Work permit required for the site.
Non-essential personnel to be restricted from the work site.
Allocation of personnel responsible for opening, closing of all valves and depressurizing
equipment.
Review the pertinent risk assessment documents for each individual stage of the
operations,
Securing, handling and operation of lines under pressure,
Handling of fluids and pressure testing.

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 24 of 24


PS-2100-0549-003-E-00

4. Pre-spud Preparation
4.1. Rig Inspection
The rig inspection will be performed by Drilling Superintendent and Company Man, according to the
last GRN Land Rig Checklist. HSE pre-spud inspection shall be performed by the GRN HSE
representatives.
Prior to the start of operations, the rig must be in good working order with all essential equipment,
including critical spare parts, present and functioning properly.

4.2. General Preparation


Ensure the planned quantity of crossover subs, their size, material grade and inspection
certificates, are available according with operation as planned in the present Drilling
Program. The service suppliers shall provide to the GRN Company Man their tools
specifications (i.e. dimensions, thread, material grade and copy the last inspection
certificates) and supply the appropriate crossover subs to fit the drill string as required.
Ensure the planned quantity, type, size of fishing tools and the required accessories are
available on site and thoroughly inspected.
Ensure the required equipment and materials (main and backup) from both GRN and
appointed Service Suppliers are available on site prior to spud the well, such as bits and
nozzles, casing, mud chemicals, cementing unit and float equipment (i.e. floats, plugs,
centralizers, stop collars, cementing heads, downhole tools, etc.).
Carry out the cementing unit hydrostatic testing. The hydrostatic test should be performed
with water as clean as possible and recorded with a calibrated chart recorder. The
hydrostatic testing acceptance criteria is zero (0 psi) pressure drop over 15 minutes after
the stabilization period.
Ensure the length of the DPs, HWDPs and DCs, is taken in meters by using a metallic
measuring tape (plastic measuring tape, and units conversion are NOT ACCEPTABLE).
Continuous water supply haulage from Reggane area (adjacent water well of RG-06) or from
Moulay Nadjem water well, so the location water pit (2500 m3 usable volume) have to be full
before spud-in date. A minimum safety stock of 100 m3 of diesel has also to be onsite in
order to ensure operations continuity.
Perform training on surface hole emergency response.
Heavy mud and LCM must be available on-site:
o 50m3 of Heavy mud, 1.5 sg MW to be available in tanks prior to spud for displacement
of the entire hole volume.
o Have ready LCM batches to pump in case of losses (an approximate volume of 10 m3
LCM pills at 150 kg/m3 & 300 kg/m3 concentration will be prepared for the 24 phase).
o For 16, 12 and 8 phases LCM products will be ready at site just in case but no
batch will be pre mixed.
Pick up only enough 5 DP to get to 450 m and rack back in derrick.
Measure and report on DDR the Rig Rotary Table (RT) to Ground-Level (GL) distance.

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 25 of 25


PS-2100-0549-003-E-00

5. 24 Hole Section. Objectives & Overview
5.1. 24 Section Objective
1. The objective of this interval is to safely drill a 24 vertical hole throughout the Cretaceous /
Namurian formation to a section TD of +-450 m (to be adjusted accordingly with casing tally).
2. Maintain good hole cleaning and wellbore stability.
3. Run and cement 18 casing safely to isolate possible aquifers and achieve adequate
formation integrity test to drill the next 16 phase.

5.2. 24 Section Hazards & Risks


Possible mud losses and washouts below 30 conductor.
Possible bit and stabilizer balling while drilling throughout the claystones.
Claystones reactivity can affect the wellbore stability issues due to plastic shale and or
unconsolidated sands.
Refer to Annex VIII Risk Assessment to see all the preventive and mitigation actions for this
phase.
Refer to Annex X Offset wells information for more details about field experience.

5.3. 24 Section Drilling Operations


5.3.1. Recommended Bit & Hydraulics
A tricone bit (IADC 515) with center jet will be used to drill in rotary mode with expected average
ROP of 7 m/h once full parameters are applied.

Bit Primary (IADC) Back Up (IADC)

24 Varel TCI - ETR24JMRS (515) Varel MT - ETR1GJMRS (115)

Table 6 24 Recommended Bits

5.3.2. Recommended Drilling Parameters


The section will be drilled with 100-140 rpm, flow will be increased as the section is drilled. To avoid
washing out the cellar flow rate will be limited to 1500lpm for first 5-10m at least, then it will be
increased progressively up to 3200 lpm if no losses are present. ROP will be controlled and Hi-Vis
pills will be pumped as required avoiding cuttings overloading in the annulus.

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 26 of 26


PS-2100-0549-003-E-00

RPM FlowRate
Section Mode Bit WOB(Ton) SPP(psi) TFA(in2) HSI(HP/in2)
Rotary (lpm)
0.941
24" Rotary TCI 520 60140 27003300 9001500 1,2
3x18"+1x16"CJ

Table 7 24 Recommended Drilling Parameters

5.3.3. Recommended BHA


Objective of this interval is to keep the wellbore as near to vertical as possible while maintaining an
optimum ROP.
In order to do so a pendulum BHA will be run. A shock Sub will be used/located near the bit in order
to isolate axial vibration from the bit to drill string.
The dimensions of all tools and BHA components must be checked prior to RIH.

24"RotaryBHA#1
OD (in)/ Max OD Bottom/ Length Cum. Length
Item Name
ID (in) (in) Top Connection (m) (m)
1 TCI Bit 24 7 " Reg Pin 0,6 0,6

9 7 " Reg Box


2 Bit Sub (with Float Valve + Totco ring) 9 0,9 1,5
3 7 Reg Box
9 7 Reg Pin
3 Shock Sub 9 3,52 5,02
2 4/5 7 Reg Box
9 7 Reg Pin
4 1 x 9 DC 9 9,3 14,32
3 7 Reg Box
9 7 Reg Pin
5 String Stab - SLB 23 2,43 16,75
3 7 Reg Box
9 7 Reg Pin
6 1 x 9 DC 9 9,3 26,05
3 7 Reg Box
9 7 Reg Pin
7 String Stab - SLB 23 2,43 28,48
3 7 Reg Box
9 7 Reg Pin
8 2 x 9 DC 9 18,6 47,08
3 7 Reg Box
9 7 Reg Pin
9 XO 9 0,45 47,53
2 6 " Reg Box
8 6 " Reg Pin
10 6 x 8 " DC 8 54,86 102,39
2 6 " Reg Box
8 6 " Reg Pin
11 Jar 8 10,2 112,59
3 6 " Reg Box
8 6 " Reg Pin
12 2 x 8 " DC 8 18,92 131,51
2 6 " Reg Box
8 6 " Reg Pin
13 XO 8 0,9 132,41
2 NC-50 Box
5 NC-50 Pin
14 15 x 5" HWDP 5 139,5 271,91
3 NC-50 Box
15 5" DP S135, 24.21 lb/ft, Premium 5 5 NC-50 Pin

Table 8 24 Rotary BHA Assembly

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 27 of 27


PS-2100-0549-003-E-00

Note: Estimated lengths only, final lengths to be checked on location.

5.3.4. Recommended Drilling Procedure


1. A flow riser will be installed in order to have returns through the bell nipple. A centrifugal pump
has to be kept as backup in case returns will be taken through the cellar (see figure 11).
2. Make up the 24 rotary BHA. Include a float valve and Totco ring. Record weight below jar.
RIH to tag cement.
3. Drill 24 hole to 30m using a lower flow rate (max. 1500 lpm) when around the 30 conductor
shoe area, until the upper 24 stabilizer is 5 m below the shoe.

If any sign of losses stop drilling and decrease pump rate. Inform Drilling Superintendent
to define the way forward.
Keep Mud Weight Out 1.10 SG by continuously:
Checking Mud Weight-out before Shale Shakers. Record every 15 min.
Bring up pumps gradually to avoid surge.
Hard reaming drilled hole twice before each connection.
Monitoring cuttings volume to track any sign of big washout with ROP trend.
Monitor hole fill up behavior on connections.

4. Once 24 top stabilizer is 5 m below shoe (+/- 30 m), increase flow rate to 2300 lpm to drill the
next 30m and to 3200 lpm for the rest of the section.
5. Continue drilling ahead 24 hole to section TD +/- 450m m MDRT. TD to be adjusted to suit
Casing tally and minimize landing joint stick up on rotary table.
6. Monitor closely drilling parameters in order to minimize BHA vibrations and bit bouncing effect.
7. Detergent will be added if required for bit and stabilizers balling prevention.
8. At TD, pump high viscosity sweep and circulate one bottoms up or until well is clean. Before
POOH, spot Hi-Vis pill and drop Totco.
9. POOH to surface, rack back BHA and break out 24 bit.
If overpull/tight spots observed work out string first and then back reaming with low
parameters not more than 30rpm and minimum flow rate 1000 to 1500 lpm.
If bit and stabs come out balled up, clean BHA and discuss with town the following plan:
a. RIH back to TD and monitor hole fill.
b. Circulate out bottoms up and spot 8 m3 of Hi-Vis sweep.
c. POOH, rack back BHA and break out 24 bit.

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 28 of 28


PS-2100-0549-003-E-00

5.3.5. Conductor Stack Up Diagram


Figure 11 30 Conductor Stack Up Diagram (24 Section)

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 29 of 29


PS-2100-0549-003-E-00

5.4. 24 Section Drilling Fluids
Amine Polymer mud will be used to drill this section with mud weight vary from 1.05 to 1.10 s.g. to
enhance the hole condition especially thru the Namurian formation. High viscosity sweeps &
Detergent will be pumped as necessary while drilling this section to avoid bit balling.

Units 24HoleSection
IntervalDepth meters +/450
MudType AminePolymermud
MudWeight sg 1.051.10
pH 9.510
PlasticViscosity cP ALAP
YieldPoint lb/100sqft 3540
Gels10sec/10min/30min 18/20/25
APIFluidLoss cc/30min 10ccinNamurian
SectionTDStaticTemperature C 45

Table 9 24 Recommended Drilling Fluids Properties

5.5. 24 Cutting Sampling Mud Logging Program


Set of samples will be collected from surface to section TD. Two types of samples will be collected
every 10 meters:

Set-1 GRN: Washed & Dried / Unwashed / Geochemical as per requirement


Set-2 SONATRACH: Washed & Dried / Unwashed / Geochemical as per requirement

Mud Sampling:

At the beginning of this section


Every mud change
Before every wireline job

5.6. 24 Section Electric Logging Operations


No electrical logging planned for this section.

18-5/8 cased logs will be compiled with the 16 hole logging program.

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 30 of 30


PS-2100-0549-003-E-00

5.7. 18 Surface Casing Operations
5.7.1. 18 Casing String
Weight Centralization
Item Qty Description Size Grade Connection
(lb/ft) (Tobeconfirmed)
StabinFloat
1 1 18 87.5 K55 BTC
Shoe

FloatShoe 1NWFlexible
2 1 18 87.5 K55 BTC
CasingJoint Centralizer

1NWFlexible
3 +35 CasingJoint 18 87.5 K55 BTC Centralizerea.3
Joints

Table 10 18 Casing String

5.7.2. 18 Casing Preparations


1. All personnel and equipment for casing run is on location:
+-50 joints to be received at location (At least 10% contingency to be available)
Pre-assembled Stab-in float Shoe Track
Halliburton Cement Stinger with spare of O-rings.
Flexible Centralizer (5 x 18-) for Cement Stinger.
False rotary table and C-plate (KCA provided).
Running compound and thread lock.
18-5/8 BTC circulating swedge.
Casing running equipment from Weatherford TRS: Power units, Power tongs 20K,
Side door elevator 150 T and single joint elevator, 18 casing cutter. Equipment
to be checked on location by the TRS supervisors 3 days before the job starts.
2. All casing joints should be measured and tallied. The tally should be approved by the drilling
superintendent.
3. All casing joints must be drifted. Ensure proper drift is on location (ID of casing 17.75in)
4. Clean and visually inspect all casing threads.

5.7.3. 18 5/8 Running Procedure:


1. Hold pre job safety meeting.
2. Rig up Casing running equipment. 132 350T rig bails to be used.
3. Pickup stab in float shoe, 1 joint, and M/Up the shoe (Thread lock), fill-up with mud and test
that the floating device is working ok.
4. Install 2 Bow spring Centralizers in float shoe and 1 per each 3 stands (Final Centralizer
program to be proposed by Schlumberger Cementing and reviewed and approved by CM
and drilling superintendent). Company man should confirm the proper installation of the stop
collars and centralizers.

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 31 of 31


PS-2100-0549-003-E-00

5. Centralization must be assured close to surface using rigid centralizers inside 30 pre-
installed conductor pipe.
6. Continue running 18 joints filling up the string every 5 joints. Refer to Annex I for MUT
requirements.
7. +/- 2 meter of Rat Hole to be considered.
8. Space out the Casing Landing Joint at Rig Floor level to have the minimum possible stick up.
9. Count number of Casing remaining on the rack versus Casing Tally.
10. If hole fill is observed space out 18 Casing according to pipe tally and availability of pup
joints at the site.
11. Condition mud to required properties as per Mud Program.

5.7.4. 18 Casing Cementing Procedure


A detailed cement procedure will be prepared and issued prior to the casing operations based on
drilling conditions observed and according to the following guidelines.
Objectives:
Bring cement to surface to provide adequate structural support for the next well sections and
to provide isolation to the shallow aquifers.
Minimize wait on cement (WOC) time.
Avoid losses but if losses are encountered while cementing the 18 Casing. CBL-VDL-GR
log could be run before drilling ahead the next section.

All the slurry properties have to be defined by Schlumberger cementing company and to be included
in wellsite procedures.

All the properties are to be confirmed through lab tests using rig samples at least 3 days before the
job.

Procedure:
Cementing for this section will be done with a stinger (Stab in).
1. Perform a pre-job safety meeting.
2. Install a false rotary table on top of 18 LJ in preparation for running the inner string.
3. Make up and run in hole to 5m above shoe with cement stinger (check O-rings) string (5
DP) using two DP Centralizers for 18 casing. Check with drilling superintendent if running
some HWDP is required.
4. Break circulation prior to stab in.
5. Stab in gently without circulation and set 5K onto shoe.
6. R/U TIW-SES-TIW and lock 500psi above top TIW.
7. Sting into the casing shoe and confirm circulation up the annulus.

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 32 of 32


PS-2100-0549-003-E-00

a. If full returns are seen, check if the inner annulus (between 5 DP & 18 casing) is
filled to enable detection of leak around drill pipe stinger and proceed with the cement
job.
b. If total or severe partial losses are noted while circulating, record the pressure at the
planned pumping rate.
8. Circulate while rigging down casing running tools. Try to use the same annular velocity than
during drilling.
9. Hold a safety meeting prior to pressure testing cement lines and starting the cement job.
10. There should be enough cement on location to permit pumping 300% excess of the primary
job, plus top up slurries.
11. Pump +/- 15 m3 of spacer (Fresh water 1.00sg), Mix & pump on fly +/- 130 m3 of 1.58 SG
lead slurry. When the cement reach surface pump +/- 37 m3 of 1.90 SG tail slurry, under
displace the inner volume of the 5 DP by 1 m3 and taken into account the follows:
Consider to use CemNet in the slurry at 5.0 Kg/m3 in order to minimize losses. To be
confirmed in the final cementing program.
All the volumes to be verified with the Cementing Program.
An excess of 200% for open hole volume is considered on the above figures (300% for
Lead Slurry and 100% for Tail Slurry). TOC lead: Surface. TOC tail: 300m.
Measure slurries density with pressurized balance at the Batch Mixer.
Collect mix water and cement slurry samples
12. Check for backflow by releasing pressure and observing volume of flow-back, allowing for
aeration:
If float valve is holding, clear the drill floor and cellar area and sting out, circulate the
excess of slurry. Then POOH one joint above the shoe and circulate one volume if
possible.
If float does not hold, do not sting out, re-pump 4 bbls plus amount flowed back to
cement tanks, leaving 1bbl inside drillpipe and bleed off again.
If Back flow still exists, pump back the same volume and over displace 0.5bbls to ensure
DP is clear of cement and shut in at surface until surface sample is hard.
13. Wait on cement until surface samples are set.
14. If no cement at surface or cement drops a remedial top job will be performed with a 2 hose /
spaghetti pipe (check availability at rig site during the preparation for cementing operations).

Note: Refer to Annex VI for more details about cementing job.

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 33 of 33


PS-2100-0549-003-E-00

5.7.1.Wellhead Operation Sequence

1. Perform safety meeting for Wellhead operations.


2. Cameron rep. and GRN representative to ensure all required material is in place (Wellhead
section A, running tools and required spares).
3. While waiting on cement, drain the 30 x 18 annular from the cement through the drain
Valve.
4. After cement is set up, cut window on 30'' Casing above final cut depth to allow access to cut
the 18 Casing.
5. Rough cut the 18 Casing at 762 3mm above conductor pipe and L/D the cut joint.
6. Final cut the 30 Conductor by having 0.40 m stick up above the bottom of the Cellar and L/D
the 30 Riser. Final stick up to be confirmed by Company Man.
Note: The Cellar Height should be confirmed/reported to office ahead of time prior to
carry out the cut. (AZSE-4 Cellar depth is 2.4 m, to be confirmed by CM on new
location)
7. Final cut and bevel the 18 Casing by using Weatherford Cold Cutter by having 587.51.5
mm elevation above conductor in order to the set the detachable Base Plate on top of the
30 Casing

Figure 12 30 Conductor & 18 Casing Cut

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 34 of 34


PS-2100-0549-003-E-00

8. Install the detachable Base Plate (PN 255133-32, OD 45) over the 18- casing and land it
on the conductor ensuring it is leveled.
9. Install Cameron 21-1/4" Casing Head Housing, (P/N 2263490-48-01) section A over the 18
stub and land it on landing base. Verify that the Sliplock connection is down.
10. If required fill up the cellar with cement up to the base plate (+/- 30 cm).
11. Split and remove the Landing Base assembly.
12. Locate the four ports on the bottom flange of the casing spool for injecting plastic packing
into the P-seals. Inject Cameron Seal packing.
13. Locate the test port labeled as 9/16 AE TEST PORT and remove the fitting. Attach test
pump and inject fluid to 500psi (80 % of the 18 Collapse pressure)
14. Once the Casing Head is properly tested, remove the four slip retaining screws from the OD
of the slip bowl. This will allow the slips to drop and settle around the casing stub.
15. Tighten the (16) sixteen, 1-3/8" nuts on the bottom of the Casing Head flange in an
alternating cross fashion to 740 ft/lbs.
16. Reinstall the split landing base. Tighten same.

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 35 of 35


PS-2100-0549-003-E-00

Figure 13 18 Casing Head Housing (Section A)


Note: For more detail the Cameron document included within the appendix available at Rig in
hard and soft copy.

5.7.2. 20 BOP Stack Installation and Testing Procedure


1. Held pre-job safety meeting.
2. Using BX-165 ring gasket, make up 21 x 20 5K psi W.P. Double stud adapter on the
wellhead housing.

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 36 of 36


PS-2100-0549-003-E-00

3. Install spacer spool 20 3K psi W.P x 20 5K psi W.P..
4. N/U 20 5K psi W.P. BOP stack (single blind rams, single pipe rams and annular
preventer).
5. Function test BOP.
6. Make up and RIH following assembly: 18 tester cup, 1 x 5 DP joint, pup joint, side entry
valve and safety valve.
7. Set 18 tester cup below wellhead. Connect test pump to choke manifold 2 outlet. Align
valves to pump through side outlet of drilling spool.
8. Close upper pipe rams and test wellhead and wellhead valve to 200 / 1,100 psi (5/10 min)
against upper pipe rams.
9. Remove test cup.
10. Open the housings annulus valve.
11. Run 20 BOP combination tool / test plug (P/N 238875-16-01-01). Orientate the tool with the
LS seal toward the bottom. Ensure test port of tester plug is clear and open. Lower the tool
down through the BOP/Riser until it lands on the load shoulder in the casing head housing.
12. Connect test pump to side entry of test assembly.
13. Pressure test BOP (as per Annex III indications):
a. Test Annular preventer to 200 psi for 5 min, and at high pressure (1,400 psi) for 10
min
b. Test kill line check valve, choke hose connections, valve #1 of choke manifold and
upper pipe rams to 200 psi for 5 min, and at high pressure (2,400 psi) for 10 min.
Ensure kill line is disconnected from check valve, to verify any leaking. Downstream
valve from valve #1 of choke manifold should be open, so leaking can be verified.
c. With upper pipe rams closed. Test Outside kill line valve, outside choke line valve to
200 psi for 5 min, and 2,400 psi for 10 min.
d. With upper pipe rams closed. Test Inside kill line valve , Inside choke line valve to
200 psi for 5 min, and at high pressure (2,400 psi).
e. Back out test assy from test plug. Remove test assy from BOP.
f. Connect test pump to choke manifold and pump through drilling spool. Test Blind
rams to 200 psi for 5 min, and 2,400 psi for 10 min.
g. Note: Record all tests on a chart recorder, the Daily Drilling Report and the IADC
Report and need to be signed by GRN Company man.
h. Close annulus valve, release pressure and open the rams. Retrieve combination
tool.
i. Install Wear bushing in section A as per Cameron procedure.
14. Close annulus valve, release pressure and open the rams. Retrieve combination tool.
15. Install 18 wear bushing in section A as per Cameron procedures.

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 37 of 37


PS-2100-0549-003-E-00

5.7.3. 20 BOP Stack Up Diagram


Figure 14 30 Conductor Stack Up Diagram (16 Section)

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 38 of 38


PS-2100-0549-003-E-00

6. 16 Hole Section Objectives & Overview
6.1. 16 Section Key Points
1. The objective of this interval is to safely drill a 16 vertical hole throughout the Namurian,
Visean D, Visean C, Visean B, Visean A, Tournaisian, Strunian and the Famennian
formation to a section TD of +/- 2,300m. The 13 3/8 casing should cover the overpressure
formation expected from 2200m to 2250m.
Maximum Expected Pore Pressure at section TD is 3320psi.
2. Maintain good Wellbore Stability maintaining the proper mud properties while drilling the
entire section. Mud engineer to check and report MW in/out every 30 min and mud viscosity
every hour.
3. Maintain good hole cleaning. Pump hi-vis pills if needed.
4. Run and cement 13 Casing safely to isolate possible aquifers and achieve an adequate
formation integrity test to drill the next 12 phase.

6.2. 16 Section Hazards & Risks


- High probability to have partial to total losses in Tournasian formation around the Dolerite
layers. Partial & total losses encountered in AZSE-21 where LCM Pills and Thixotropic
Cement plug were required to cure losses. Whereas losses have been reported on Visean
D in AZSE-1. Find LCM decision tree on the ANNEX VII.
- Possible bit and stabilizer balling while drilling throughout the claystones.
- Claystones reactivity can affect the wellbore stability due to plastic shale and or
unconsolidated sands.
- Building tendency is expected, especially in Dolerites, Strunian and Famennian
formations.
- Cavings while drilling and while performing POOH prior to Casing running operations.
- Several tight hole, pack off tendency and stuck pipe incidents were reported in RG-5 ,RG-
6 AZSE-2. Especially in Dolerites. Whereas in AZSE-21; tight spots & pack off tendency
observed in many intervals.
- Low ROP also expected while drilling Dolerite layers.
- Potential Gas migration while cementing from Visean package. (600 psi Annulus B has
been reported on AZSE-3)

Note: Refer to Risk Assessment Annex VIII to see all the preventive and mitigation actions for this
phase.

Refer to Annex X Offset wells for more details about field experience.

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 39 of 39


PS-2100-0549-003-E-00

6.3. 16 Section Drilling Operations
6.3.1. Recommended Bit & Hydraulics

This section is expected to be drilled in seven runs due to presence of three Dolerite layers with
different thickness. So Packed BHA & Autotrak BHA will be utilized accordingly by deploying TCI bits
along with packed BHA to drill dolerite layers and Autotrak V BHA for the rest of intervals.

BitRun# Size Model Type Remarks


Main - NOV PDC TUHI916S
1st 16" PDC Drill from 450 to 1200m
Backup - Varel R719SPDGHX

Main - RR - NOV PDC TUHI916S


nd Drill from 1200 to 1758m
2 16" Backup - Smith MDSI619HBPX PDC
( top of 1st Dolerite)
PDC

Main - NOV TCI T52


rd Backup - Varel TCI HR34DJMRS Drill 1st dolerite layer from
3 16" TCI
Backup - Smith TCI 1758m to +-1827m
GF30YBODV
Main - NOV TCI T52
Continue Drill 1st dolerite
Backup - Varel TCI HR34DJMRS
4th 16" TCI layer from 1827m to
Backup - Smith TCI
1896m
GF30YBODV

Main - Smith Si913 PDC Drill from Through Strunian


5th 16" Backup - NOV TUHI916S PDC and Famenian untill top of
Backup - Smith MDSI619HBPX 2nd Dolerite at 2053m
Main - NOV TCI T52 Drill 2nd dolerite layer &
6th 16" Backup - Varel TCI HR34DJMRS TCI Famenian from 2053m to
Backup - NOV PDC TUHI916S +- 2100m
Drill Famenian from
Main - MDSI619HBPX PDC
7th 16" PDC 2100m to 2300m Section
Backup - Varel R719SPDGHX
TD (including 3rd Dolerite)

Table 11 16 Recommended Bits

6.3.2. Recommended Drilling Parameters


The section will be drilled according with recommended parameters as per Table 12.

WOB FlowRate HSI


Section Mode Bit RPM SPP(psi) TFA(in2)
(Ton) (lpm) (HP/in2)

T52or
16" PackedBHA 1525 90100 28003200 37004700 0.746 2.0
equivalent
TUHI916Sor
16" RSSBHA 1015 100145 28003200 37504500 1,325 1.9
equivalent
Table 12 16 Recommended Drilling Parameters

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 40 of 40


PS-2100-0549-003-E-00

6.3.3. Recommended RSS BHA
Objective of this interval is to keep the wellbore as near to vertical as possible while maintaining an
optimum ROP.

16"RSSBHA#2
OD(in)/ MaxOD Bottom/ Length Cum,Length
Item Name
ID(in) (in) TopConnection (m) (m)

1 PDCbit 16 75/8"RegPin 0,43 0,43

91/2 75/8"RegBox
2 AutoTrakV 15,65 2,53 2,96
2,48 T2Box

9.524 T2Pin
3 StabMod 157/8 3,63 6,59
3.118 T2Box
9 T2Pin
4 BCPM 9 3,87 10,46
3.118 75/8RegBox
9 75/8RegBox
5 BCPMNMSub 9 0,74 11,2
37/16 75/8RegBox
9 75/8RegPin
6 StabString 157/8 1,53 12,73
3 75/8RegBox

95/16 75/8RegPin
7 SubFloat 95/16 0,91 13,64
3 75/8RegBox

91/2 75/8"RegPin
8 NMSubFilter 95/16 1,87 15,51
3 75/8"RegBox
MultiActivating 9,5 7 5/8 Reg Pin
9 CirculationSub 9 5,5 21,01
3 1/16 7 5/8 Reg Box
(ifavailable)
91/2 75/8RegPin
10 3x91/2DC 09/01/2002 28,05 49,06
3 75/8RegBox

91/2 75/8"RegPin
11 XO 91/2 1,13 50,19
3 65/8"RegBox
81/4 65/8"RegPin
12 15x81/4"DC 81/4 137,24 187,43
213/16 65/8"RegBox
81/4 65/8"RegPin
13 JAR 81/4 10,22 197,65
3 65/8"RegBox

81/4 65/8"RegPin
14 2x81/4"DC 81/4 18,95 216,6
213/16 65/8"RegBox

81/4 65/8"RegPin
15 XO 81/4 1,4 218
3 NC50Box
5 NC50Pin
16 15x5"HWDP 5 140,4 358,4
3 NC50Box

5"DPS135, 5 NC50Pin
17 5 1941,6 2300
19,5lb/ft,Premium 4.276 NC50Box

Table 13 16 RSS BHA Assembly

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 41 of 41


PS-2100-0549-003-E-00

6.3.4. Recommended Rotary Packed BHA

16"PackedBHA#3
OD(in)/ MaxOD Bottom/ Length Cum,Length
Item Name
ID(in) (in) TopConnection (m) (m)

1 PDCbit 16 75/8"RegPin 0,43 0,43

9 75/8"RegBox
2 NBSw/float&TotcoRing 157/8 2,17 2,6
3 75/8"RegBox
9 75/8"RegPin
3 ShockSub 9 4,44 7,04
3 75/8"RegBox
9 75/8"RegBox
4 91/2ShortDC 9 4,57 11,61
3 75/8RegBox
9 75/8RegPin
5 StabString 157/8 1,53 13,14
3 75/8RegBox
9 75/8"RegBox
6 91/2DC 9 9,23 22,37
3 75/8RegBox
9 75/8RegPin
7 StabString 157/8 1,53 23,9
3 75/8RegBox
9 75/8"RegBox
8 91/2DC 9 9,23 33,13
3 75/8RegBox
91/2 75/8"RegPin
9 XOver 91/2 1,13 34,26
3 65/8"RegBox
81/4 65/8"RegPin
10 15x81/4"DC 81/4 137,24 171,5
213/16 65/8"RegBox
81/4 65/8"RegPin
11 JAR 81/4 10,22 181,72
3 65/8"RegBox
81/4 65/8"RegPin
12 2x81/4"DC 81/4 18,95 200,67
213/16 65/8"RegBox
81/4 65/8"RegPin
13 XO 81/4 1,4 202,07
3 NC50Box
5 NC50Pin
14 15x5"HWDP 5 140,4 342,47
3 NC50Box
5"DPS135, 5 NC50Pin
15 5 1957,53 2300
19,5lb/ft,Premium 4.276 NC50Box

Table 14 16 Rotary BHA Assembly


WBJ: 35 Ton
1
Note : Actual Hydraulic Simulation will be carried out during the operations.
2
Note : The dimensions of all tools and BHA components must be checked prior to RIH.


6.3.5. Recommended Drilling Procedure
1. Pick up enough 5 DP (+/-1700m.) to drill down to section TD.
2. P/U, M/U and RIH 16 NOV TUHI916S PDC Bit with 9 AutoTrak V.
Pay especial attention to BHA handling. Incident occurred in KL-27 when Rig tong
damaged Baker AutoTrak sub.
3. Perform surface function test on the AutoTrak V system. Record and report on DDR
parameters and weight below jar.
4. Continued to RIH to 18 float shoe.

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 42 of 42


PS-2100-0549-003-E-00

5. Drill out shoe with low parameters and clean out rat hole and drill 3 meters of new formation.
6. Circulate hole clean until MW in/out is equal and verify shakers are clean of any shoe track
debris.
Verify shakers are clean of any shoe track debris. Confirm MW in/out is equal.
Pull back into the Casing Shoe and conduct the FIT at 18- Casing shoe according to GRN
procedures using the previous MW of 1.10 sg. Do not excess the FIT gradient of 1.86 sg.

Openhole/ MudWeight Surfacepressure KickTolerance


ShoeDepth(m) FITvalue(sg)
Casingsize(in) (ppg) (psi) (bbls)

1618 450 1.86 1,1 +/490psi 93bbls

Table 15 16 Planned FIT

7. Record pressures versus pumped/returned volumes and inform Drilling Superintendent and
Senior Drilling Engineer. Report values on DDR.
8. Displace the hole with 1.35 sg (Avapolyoil mud) and condition mud to ensure consistent
density and properties.
9. Continue drilling ahead with AutoTrak BHA to section through Namurian, Visean D, Visean
C, and Visean B to +- 1200mMD, by this depth the maximum working hours of the drilling Jar
(see Annex XI) and AutoTrak will be exceeded. However in case of the +/- 150 circulation
hours on the drilling Jar reached before this depth, plan to perform the trip accordingly.
Limit drilling parameters (40-60rpm) until last stabilizer is below Casing Shoe.
Pump 5m3 of Supersweep pill every 2 stands. If needed pump every stand.
10. Pump +/- 6m3 of Supersweep Pill, circulated hole clean and POOH to change out the drilling
Jar & AutoTrak.
11. P/U, M/U and RIH re-runnable 16 NOV TUHI916S PDC Bit with 9 AutoTrak BHA.
Record weight below jar. Perform surface function test on the Auto Track system and report
the results on the DDR.
12. At TD, pump Super Sweep pill (+/- 10 m3) and circulate one bottoms up or until well is clean.
Flow check well.
13. Continue RIH to bottom and resume drilling 16 hole to section with AutoTrak BHA through
Visean B and Tournasian formations until reach the top of the first Dolerite layer (estimated
+/-138 m thick):
Monitor and control vibrations while drilling.
Optimize the drilling parameters between WOB and RPM to achieve reasonable
ROP.
Hi Vis Pills and SuperSweep Pills (+/- 5 m3 each) to be pumped whenever it is
necessary.

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 43 of 43


PS-2100-0549-003-E-00

Flow rate to be 2800-3200lpm.
Slow the drilling parameters while approaching the top of the dolerite to avoid
damaging the PDC Cutters and once the Top of Dolerite is confirmed optimize the
drilling parameters again.
In case of any indication of caving the mud weight will be increased accordingly and
to be advised by the office.
In case of losses; which might be come across +- 50 m above the dolerite; follow the
LCM decision Tree.
14. Once the dolerite is encountered, reduce bit RPM to 80-90 and continue drilling ahead.
Monitor parameters and minimize vibrations as much as possible. If very low ROP is
observed, consult with Drilling superintendent or the Operation drilling engineer for a
possible Bit trip.
15. If Bit trip is required at the Dolerite, POOH to surface, change out the Bit and RIH back to
bottom. New Bit to be used: NOV T52.
Alternative bit is MZ616BPX (Stingerblade). To be confirmed on due time from
the Operation Drilling Engineer. The intention of this bit is to drill thru +/-138 m
of the Dolerite and Strunian formation.
16. Continue drilling ahead to bottom of dolerite (1,896m TVDRT.). Confirm completely out of the
Dolerite with WSG. If necessary, drill ahead 10 to 20m below Dolerite.
Note: in RG-08; 124 m of Dolerite has been drilled with one Bit (T52) with an
average ROP on bottom of 1.56 m/hrs. However two TCI bits were required to drill
104 m of Dolerite in AZSE-21.
Losses has encountered in AZSE-21 started at 1,770 m.
17. POOH to surface, change out the Bit and RIH back to bottom. New Bit to be used: Smith
PDC MDSI619HBPX or Smith Si913 PDC, with the RSS BHA.
5. Continue drilling ahead thru Strunian and Famenian formation (+/- 30/40 m of Dolerite) to
section TD at +-2,300m. A criterion is to set the 13 3/8 casing below the overpressure
formation expected from 2200m to 2250m.
Note: If losses encountered while drilling this section. Refer to Annex VII Losses
decision Tree.
Try to optimize the trips to surface to test the BOPs every 21 days maximum.
18. If a Bit trip is required at the 2nd layer of Dolerite, POOH to change out the Bit and RIH back
to bottom. New Bit to be used is NOV T52, with Packed BHA.
Once confirm completely out of the Dolerite with WSG. If necessary, drill ahead 10
to 20m below Dolerite, POOH to Pick up a PDC bit and RSS BHA to drill across
Famenian, including a 3rd layer of Dolerite until section TD

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 44 of 44


PS-2100-0549-003-E-00

19. Detergent will be added if required for Bit / Stabilizers Balling.


20. At TD, pump high viscosity Pill, Supersweep pill and circulate one bottoms up or until well is
clean. Flow check well. Depending on hole conditions perform a wiper trip to shoe before
POOH to surface and rack back BHA.
21. If overpull/tight spots observed work out string first and then back reaming with low
parameters not more than 30rpm and minimum flow rate 1,000 to 1,500 lpm.
22. Rig up wire line equipment and perform Wireline logs run as per GRN well site geologist
indications
23. Rig down wire line equipment.
24. Prepare to run 13 3/8 Casing.

6.4. 16 Section Drilling Fluids


6.4.1. Recommended Drilling Fluids Rheology Parameters

Consider starting the section with a 1.35 sg mud weight (Avapolyoil system) based on fluid
formulation.
The centrifuges have to maintain the drilled solids below 5%.
Shall it become necessary to adjust the mud weight upwards due to hole problems, circulate the new
weightier mud around prior to drilling ahead.

Units 16HoleSection
IntervalDepth meters =+1850
AVAPOLYOIL/SOLTEX/
MudType
POLYMER
MudWeight sg 1.35
pH 9.510
PlasticViscosity cP ALAP
YieldPoint lb/100sqft 3035
Gels10sec/10min/30min 12/15/20
APIFluidLoss cc/30min 3cc
SectionTDStaticTemperature C 90

Table 16 16 Recommended Drilling Fluids Properties

6.5. 16 Cutting Sampling Mud Logging Program


Set of samples will be collected from the beginning of 16 drilling phase down to top section TD at
2300 m. Two sets of two types of samples will be collected every 10 meters.
Set-1 GRN: Washed and dried (Dry) / Unwashed (Wet)
Set-2 SONATRACH: Washed and dried (Dry) / Unwashed (Wet)

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 45 of 45


PS-2100-0549-003-E-00

Mud Sampling:

Refer to GEOLOGICAL OPS PROGRAM.

6.6. 16 Section Electric Logging Operations


Open Hole
The following log will be run after reaching 16 section TD.
Run 1A. SGT-DSLTBHC-EMS (Optional: GPIT)
Cased Hole
The following logs will be run in 18 casing:
Run 1B: CBL-VDL-CCL- SGT

6.7. 13 Casing Operations


6.7.1. 13 Casing String

Weight Centralization
Item Qty Description Size Grade Connection
(lb/ft) (Tobeconfirmed)
1 1 FloatShoe 13 72 Q125 VamTop
FloatShoe 2NWFlexible
2 1 13 72 Q125 VamTop
CasingJoint Centralizer
Casing
1NWFlexible
3 1 Intermediate 13 72 Q125 VamTop
Centralizer
Joint
4 1 FloatCollar 13 72 Q125 VamTop
FloatCollar 1NWFlexible
5 1 13 72 Q125 VamTop
CasingJoint Centralizer
1NWFlexible
6 +167 CasingJoint 13 72 Q125 VamTop Centralizerea.3
Joints

Table 17 13 Casing String

6.7.2. 13 Casing Preparations


1. All personnel and equipment for casing run is on location:
+/- 185 joints of 13 Vam Top casing to be sent to location (10% contingency).
Pre-assembled Float shoe & Float Collar joints.
Verify connection is Vam Top
Bow spring centralizers and stop collars.
Rigid centralizers and stop collars.
12 special drift bar (API 5CT) provided by Weatherford.
13 circulating head swedge with quick connection or Vam Top connection to NC50
(provided by Schlumberger COPS).

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 46 of 46


PS-2100-0549-003-E-00

The cementing head has a BTC connection on the bottom. Ensure the proper crossover
is on location (provided by Schlumberger). Min 5K psi is acceptable
Running compound (API Modified or BESTOLIFE dopes) and thread lock
All Casing running equipment: Power units, Power tongs 16K, Side door elevator 350 T,
JAM units, single joint elevator, Spider elevator 350T, 18 & 13 Casing cutters.
La Fleur circulating tool and required Bails (180 350 T).
Cement products availability. There should be enough cement/blend/additives on
location to pump a 50% excess over the theoretical hole volume.

2. All casing joints should be measured and tallied prior reaching section TD. The tally should
be approved by the Drilling Superintendent.
3. All casing joints must be drifted (special drift to be used).
4. Clean and visually inspect all casing threads. Confirm with Drilling Office if an inspection
company is required.
5. Make sure that the 18 wear bushing is retrieved. Install 2 centralizers in float shoe and
intermediate joints and 1 every three casing joints (Final Centralizer Program to be proposed
by Cementing Company, reviewed and approved by Company Man, Drilling Operation
Engineer and Drilling Superintendent).
Two stop collar per centralizer should be installed, above and below of the centralizer
and never one in the middle with enough space to allow the bow centralizer expand
with full compression. Company man should confirm the proper installation of the stop
collars and centralizers.
Centralization must be assured close to surface using rigid centralizers inside 18 5/8
casing. Stop collar to be installed just above and below rigid centralizer avoiding any
movement.

6.7.3. 13 Casing Running Procedure


1. Hold pre job safety meeting.
2. Rig up casing running equipment. Bails to be used: 132 350T rig bails.
3. P/U float shoe joint, 2 intermediate joints and collar joint (thread lock); fill-up with mud and
test that the floating device is working properly.
4. Continue RIH 13 casing and tag bottom (if it is feasible). Pick up +/- 1 m of bottom.
+/- 1 meters of rat hole to be considered.
Count number of casing joints remaining on the rack versus casing tally.
Space out the casing landing joint at rig floor level to have minimum stick up.
Make sure that coupling of the last joint to be placed below the Casing Head Housing (if
it is feasible). Otherwise the coupling should be above the cut level.

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 47 of 47


PS-2100-0549-003-E-00

If hole fill is observed, space out the 13 casing according to casing tally and
availability of pup joints at the site.
5. Condition mud to required properties as per Mud / Cementing Program.

6.7.4. 13 Casing Cementing Procedure

A detailed cement procedure will be prepared and issued prior to the casing operations based on
drilling conditions observed and according to the following guidelines.
Objectives:
Bring cement 100 m inside 18 casing to provide to ensure proper annulus isolation.
Avoid losses.
Note: 13 casing cement job will be logged (CBL-VDL-CCL) after drilling 12 section. If
losses are encountered, this log could be run immediately after cement job.
All the slurry properties have to be defined by Cementing Company and have to be included
in wellsite procedures.
All the properties should be confirmed through lab tests using Rig samples at least 3 days
before the job.

Procedure:
1. Hold a safety meeting prior to pressure test cementing lines and start the cement job.
2. Check cementing head connection, pressure rating and certification once it is received on
location.
3. Calculate cement volume requirement from caliper log with 25% excess in open hole (to be
confirmed). There should be enough cement on location to allow pumping 25% excess of the
open hole. Agree on final volume figures with HMD Drilling Office.
4. The 13 casing will be cemented in one stage with +/- 60m3 of 1.60sg Litecrete lead slurry
followed by +/- 42 m3 of 1.90 sg gas tight Flexstone tail slurry, Top of Tail: +/- 1,516m , 100m
above Tournasian formation, (25% excess included in OH over theoretical volume just as a
reference)
Spacer and slurries designed in plug flow pattern at 800 lpm. Continue to reciprocate
while pumping/displacement cement.
Highest ECD (estimated to be 1.74 sg) will be observed at end of displacement and
should be checked against the he FIT/LOT obtained.
Monitor returns during the job.
Critical periods of both slurries must be misaligned. To be verified by the cement lab
test.
In case of surface holding pressure is required while WOC; it will be officially conveyed
from HMD to the Rig site.

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 48 of 48


PS-2100-0549-003-E-00

5. Displace cement with mud and bump plug.
6. If plug is not bumped inform Superintendent immediately. Do not over displace more than
half shoe track volume. Compare total strokes versus calculated strokes after the efficiency
test.

Note that in case of a 3 joints shoe track the volume of the same is 20.40 bbl.
7. If plug was bumped, pressure test Casing (with green cement) with maximum pressure of
5000psi. (As per indicated in Annex III). If plug was not bumped the Casing will be tested at
a later stage.
Note: Pressure test is limited to 5000psi due to the limitation of 13 3/8 cement head of 5Kpsi
W.P..
8. Check for backflow by releasing pressure and observing volume of flow-back, allowing for
aeration.
9. Wait on cement 500 lbf/100 sq.ft SGS is achieved to compensate for hydrostatic loss and
prevent gas migration. Time to be confirmed from HMD. And Cement sample to be put in
oven at downhole temperature.
Note: Refer to Annex VI for more details about cementing job.

6.7.5. Wellhead Operation Sequence

1. Perform pre-job safety meeting for wellhead installation operation.


2. Drain the BOP and Well Head Housing through its side
outlet.
3. Lift 20 BOP.
4. Clean the Casing Head Housing. Make sure it is free from
cement.
5. Remove both latch screws, one on each side of hanger.
6. Remove one Screw on EACH handle.
7. Place hanger around casing. Set it on boards overhead.
8. Reposition handles and install screws. TIGHTEN
SECURELY (tapered screw heads installed in the handles
will pull the halves to proper position at top).
9. Replace both latch screws. Tighten until the gap is closed at the bottom. NEVER set this
hanger without BOTH LATCHES in place securely.
10. Verify that packing is not compressed (i.e., does not extend beyond O.D. of both top and
retainer rings).
Note: It is very important that the large caps crews that retain packoff assembly only be
tightened enough to remove the slack. PACKING MUST NOT be compressed prior to
slacking off casing weight onto hanger.

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 49 of 49


PS-2100-0549-003-E-00

11. Remove the four slip retainer screws on OD of slip bowl. These screws hold slips in
retracted position in bowl. Slips WILL NOT set unless screws are removed BEFORE hanger
is placed in head.
12. Pull tension on the casing to the desired hanging weight (minimum 15,000 lbs to energize
the pack-off).
13. Remove the support boards and install the hanger into the Casing Head/Spool bowl. A cat
line may be necessary to center casing with respect to bowl preparation.
14. Slack off on the casing. A sharp decrease on the weight indicator will signify that the Hanger
has taken weight and is supporting the casing.
15. Remove handles from hanger.
16. Check cap-screws in top of hanger and tighten if possible (100 ft/lb recommended).
17. Close well head housing side outlet.
18. Rough cut the 13 casing approximately 24" above the top of the casing head.
19. Move the excess casing and BOP out of the way.
20. Final cut the casing at 6.75" " [171.5 mm 3] above the top of the casing head. Place a
3/8" x 3/16" bevel on the Casing stub and remove all burrs and sharp edges.
21. Fill the void above the Casing Hanger with clean oil to the top of the Casing Head.

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 50 of 50


PS-2100-0549-003-E-00

Figure 15 13 Casing Cut and Casing Head Housing

22. Install BX-165 ring gasket into the ring groove of the casing head housing.
23. Lift and suspend the spool over the casing head housing, ensuring it is level.
24. Carefully lower the spool until it lands on the ring gasket. Install and tighten the studs and
nuts of the flange.
25. Injected Cameron seal packing and pressure test the P-seals to 500 / 2,300psi (80 % of the
13 collapse pressure).
26. Install a test pump to the port for testing the wellhead body/connection (test port #6 refer to
Cameron Manual) and inject test fluid to 2,300 psi (80 % of the 13 collapse pressure).

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 51 of 51


PS-2100-0549-003-E-00


Figure 16 13 Casing Spool
Note: For more detail the Cameron document included within the appendix available at Rig in hard
and soft copy.

6.7.6. 13 BOP Stack Installation and Testing Procedure

Note: Follow the pressure values presented in the table 31.

Refer to GRN BOPs testing procedures: PS-0000-0583-002-E-00

1. Held pre-job safety meeting.


2. Install spare BX-159 Ring gasket.
3. N/U 13 10k psi w.p BOP Stack (Single Rams, double Rams, and Annular Preventer) and
Bell Nipple. And perform fully function test.
4. M/U: 13 Cup Tester, 1x 5 DP joint with port, pup joint, side entry sub and safety valve.
5. RIH and Set 13 Test Cup below Well Head with test assy. Connect test pump to choke
manifold 2 outlet.

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 52 of 52


PS-2100-0549-003-E-00

6. Close upper Pipe Rams, open 9/16 AE autoclave tests port #5 and test wellhead body, p-
seals (from above) and wellhead SOV to 200 / 6700psi (5/10 min) against upper Pipe Rams.
Monitor for signs of leakage at port #5. Re-install fitting on port #5 after test.
7. Test Annular Preventer to 200 / 3500psi (5/10min).
8. Remove Test Cup
9. Run 13 BOP Combination Tool / Test plug (P/N 238875-17-01-01). Orientate the Tool
with the LS seal toward the bottom. Lower the Tool down through the BOP/Riser until it
lands on the load shoulder in the Casing Head Spool. Ensure test port of Tester Plug / drill
pipe is clear and open. Open the SOV to observe any potential leaks.
10. Connect test pump to side entry of test assy.
11. Pressure Test BOP (as per Annex III indications):
a. Test kill line check valve, choke hose connections, valve #1 of choke manifold and
upper Pipe Rams to 200 psi for 5 min, and at high pressure (6700psi) for 10 min.
Ensure kill line is disconnected from check valve, to verify any leaking. Downstream
valve from valve #1 of choke manifold should be open, so leaking can be verified.
b. With upper Pipe Rams closed. Test Outside kill line valve, outside choke line valve
to 200 psi for 5 min, and 6700psi for 10 min.
c. With upper Pipe Rams closed. Test Inside kill line valve, inside choke line valve to
200 psi for 5 min, and at high pressure (6700psi).
d. Test lower Pipe Rams to 200 psi for 5 min and 6700psi for 10 min.
e. Back out test assy from Test Plug. Remove test assy from BOP.
f. Connect test pump to choke manifold and pump through Drilling Spool. Test Blind
rams to 200 psi for 5 min, and 6700psi for 10 min.
*Record all tests on a chart recorder, Daily Drilling Report and IADC Report.
Note: 6700psi based on a displacement to gas scenario plus a kill margin)
12. Close annulus valve, release pressure and open the rams. Retrieve combination tool.
13. Install Wear bushing in section B as per Cameron procedure.

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 53 of 53


PS-2100-0549-003-E-00

6.7.7. 13 BOP Stack Up Diagram

Figure 17 12 Section BOP Stack Diagram

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 54 of 54


PS-2100-0549-003-E-00

7. 12 Hole Section Objectives & Overview
7.1. 12 Section Key Points
1. The objective of the 12 section is to drill through the Famenian, Frasnian, Givetian,
Couvinian, Emsian formation and to set the 9-5/8 Casing inside a competent formation in
Muraille de Chine formation. Planned Section TD is +/- 3,630 mMD.
2. Control shocks and vibrations.
3. TD section target tolerance is 50m
4. The Early Kick Detection system (EKD) must be rigged up/tested prior to drill out the 13-3/8
Shoe and to be activated by +/-3100 mMD.
5. Maintain the required MW to prevent hole instability.
6. Properly condition the hole for Wireline and Casing run.

7.2. 12 Section Hazards & Risks

1. Wellbore stability is an issue during the drilling of this interval, (up to 70-80% of cavings
reported on offset wells), and this could be aggravated by using insufficient mud weight.
2. Well control can be an issue, due to an abnormal the pore pressure gradient on the
Couvinian and Emsian. It is imperative to mention that a Kick has encountered in AZSE-3 in
Emsian formation.
3. Vibrations and bit bouncing.
4. Refer to Annex VIII Risk Assessment to see all the preventive and mitigation actions for this
phase.
5. Refer to Annex IX Offset wells information for more details about field experience.

7.3. 12 Section Drilling Operations


7.3.1. Recommended Bit & Hydraulics

The section will be drilled using a PDC Bit including the drill-out of the cement, Casing shoe and 3
meters of new formation to perform the FIT.

Bit 1strunPrimary Backup#1 Backup#2 Backup#3

SMITHPDC NOVPDC SmithPDC VarelPDC


12
MDSIZ619 SKH816M MDSiZ716LBPX R716PDGXU

Table 18 12 Recommended Bits

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 55 of 55


PS-2100-0549-003-E-00

7.3.2. Recommended Drilling Parameters

WOB FlowRate HSI


Section Mode Bit RPM SPP(psi) TFA(in2)
(Ton) (lpm) (HP/in2)

2,227
121/4" RSSBHA PDCMDSIZ619 1020 100170 21002700 37505300 0.5
(6x22/32")

Table 19 12 Recommended Drilling Parameters

7.3.3. Recommended BHA

121/4"RSSBHA#4
OD(in)/ MaxOD Bottom/ Length Cum,Length
Item Name
ID(in) (in) TopConnection (m) (m)

1 PDCbit 121/4 65/8"RegPin 0,28 0,28

91/2 65/8"RegBox
2 AutoTrakV 11.867 2,53 2,81
21/2 T2Box
91/2 T2Pin
3 MWDStabMod 121/8 1,81 4,62
31/8 T2Box
9 T2Pin
4 BCPM 9 3,67 8,29
3 T2Box
9 T2Pin
5 BCPMNMSub 9 0,75 9,04
37/16 T2Box
91/2 75/8"RegPin
7 StabString 121/8 1,77 10,81
3 75/8"RegBox
91/2 75/8"RegPin
8 SubFloat 95/16 0,91 11,72
3 75/8"RegBox
91/2 75/8"RegPin
9 NMSubFilter 95/16 1,87 13,59
3 75/8"RegBox
81/4 75/8"RegPin
11 XO 81/4 0,99 14,58
23/4 65/8"RegBox
81/4 65/8"RegPin
12 15x81/4"DC 81/4 137,24 151,82
27/8 65/8"RegBox
8 65/8"RegPin
13 JAR 8 10,2 162,02
27/8 65/8"RegBox
81/4 65/8"RegPin
14 2x81/4"DC 81/4 18,65 180,67
27/8 65/8"RegBox
81/4 65/8"RegPin
15 XO 81/4 1,1 181,77
27/8 NC50Box
5 NC50Pin
16 15x5"HWDP 5 141,3 323,07
3 NC50Box
5 NC50Pin
17 "DPS135,19,5lb/ft,Premium 5 3306,93 3630
41/4 NC50Box

Table 20 12 RSS BHA Assembly


WBJ: 31 Ton.
1
Note : Actual Hydraulic Simulation will be carried out during the operations with actual Mud properties/rheology.
2
Note : The dimensions of all tools and BHA components must be checked prior to RIH.

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 56 of 56


PS-2100-0549-003-E-00

7.3.4. Recommended Drilling Procedure

1. Pick up enough 5 DP to drill down to section TD (3630m TVDRT).


2. P/U, M/U and RIH NOV SKH816M PDC Bit with 9 AutoTrak V BHA. Record weight below
jar. Be extremely careful when handling smart tools at the Rig floor.
3. Perform surface function test on the Auto Track system and report the results on the DDR.
4. RIH w/ BHA and tag cement. Record the depth where cement was tagged on IADC report
and DDR
5. Drill out shoe track, clean rat hole and Circulated hole clean. (2 < WOB < 6 during drill out).
6. Performed Shoe Bond Test.
7. Drill 3 meters of new formation, circulated hole clean and until having homogeneous MW
1.40sg in/out.
8. Pull back into the Casing Shoe and conduct FIT to 2.0sg at 13-3/8 Casing shoe using 1.40 s
mud. according to GRN procedures.( Detailed procedure will be sent on due date)
9. Record pressures versus pumped/returned volume and inform Drilling Superintendent and
Senior Engineer. Report values on DDR.

Openhole/ ExpectedFIT MudWeight Surfacepressure KickTolerance


ShoeDepth(m)
Casingsize(in) value(sg) (ppg) (psi) (bbls)
110bblsusing
121/4133/8 2300 2.0 1,40 1970
1.8s.g

Table 21 12 FIT

Note1: Kick Tolerance has been calculated based on assumed FIT with EMW of 2.0 sg and MW of
1.80s.g. Therefore the KT will be re-calculated in case FIT of 2.0sg is not achieved.

Note2: In case the FIT of 2.0sg EMW is not achieved the contingency plan (set 9 5/8 Casing before
entering Emsian formation and finish the well in 6 hole) should be triggered and a separate program
or an amendment of this document should be issued and delivered.

10. Drill ahead with AutoTrak V BHA to +/- 2,800 mMD thru the Famenian formation.
a. By this depth +/- 2,800 mMD; the maximum working hours of the drilling Jar (+/- 200
hours) and AutoTrak will be exceeded. However in case of the +/- 200 circulation
hours on the drilling Jar reached before this depth. Plan to perform the trip
accordingly.
b. Mud weight at 2700m should be 1.45sg.

11. Pump +/- 6m of Supersweep Pill, circulated hole clean and POOH to change out the drilling
Jar & AutoTrak.

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 57 of 57


PS-2100-0549-003-E-00

12. P/U, M/U and Re-run 12 NOV SKH816M PDC Bit with 9 AutoTrak V BHA. Record
weight below jar. Perform surface function test on the AutoTrak system and report the
results on the DDR.
13. Continue RIH to bottom and resume drilling thru the Famenian and Frasnian formations
a. By this depth +/- 3,400 mMD; the maximum working hours of the drilling Jar (+/- 200
hours) and AutoTrak will be exceeded. However in case of the +/- 200 circulation
hours on the drilling Jar reached before this depth. Plan to perform the trip
accordingly.
b. Mud weight at 2900m should be 1.50sg.
c. Mud weight at 3000m should be 1.60sg.
d. Mud weight at 3200m should be 1.70sg.
e. Mud weight at 3450m should be 1.80sg.

14. Continue RIH to bottom and resume drilling 12. hole to section TD at +/-3,630m MD. This
depth is based on (+/-10 to 20m) into the Muraille de Chine formation (Competent Shale).
Geologist to immediately communicate to DSV once entered in M. de Chine.

Drilling notes:
Increase drilling parameters when the stabilizer is below Casing Shoe.
Monitor and control vibrations while drilling. The Drillers display must have the
proper alarms, and Mud Logger will communicate to Driller and Company Man if
vibration appears.
Optimize the drilling parameters between WOB and RPM to achieve reasonable
ROP.
When POOH: If more than 10t drag is observed for more than 10m, immediately
M/U the TDS and pump out of the hole the full stand, then try to test on elevators. If
back reaming is required low rpm to be used.
Flow rate to be used: between 2200-2700 lpm.
Try to optimize the trips to surface to test the BOPs every 21 days maximum.
In AZSE-21; had to pump out the hole in all the trips.
15. At TD, pump high viscosity Pill, SuperSweep Pill and circulate hole clean.
16. POOH and rack back BHA.

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 58 of 58


PS-2100-0549-003-E-00

7.4. 12 Section Drilling Fluids
7.4.1. Recommended Drilling Fluids Rheology Parameters

This section will be drilled with a range of MW from 1.4sg to 1.8sg MW to section T.D.
Shall it become necessary to adjust the mud weight due to hole problems, circulate the new
mud weight around prior to drilling ahead.

Units 121/4HoleSection
IntervalDepth meters +/1330
AVAPOLYOIL/SOLTEX/
MudType
POLYMER
MudWeight sg 1,401,80
pH 9.510
PlasticViscosity cP ALAP
YieldPoint lb/100sqft 2025
Gels10sec/10min/30min 15/20/30
APIFluidLoss cc/30min 3cc
SectionTDStaticTemperature C 135

Table 22 12 Recommended Drilling Fluids Parameters

7.5. 12 Cutting Sampling Mud Logging Program


Set of samples will be collected from the beginning of 12 drilling phase down to section TD.
Two sets of two types of samples will be collected every 10 meters.
Set-1 GRN: Washed and dried (Dry) / Unwashed (Wet)
Set-2 SONATRACH: Washed and dried (Dry) / Unwashed (Wet)
Mud Sampling:
REFER TO GEOLOGICAL OPS PROGRAM

7.6. 12 Section Wireline Logging Operations


Open Hole
The following logs will be run after reaching 12 section TD
Run 1A: SGT-DSLTBHC-EMS (Optional: GPIT)
Cased Hole
The following logs will be run in 13 Casing:
Run 2B: SGT-CBL-VDL-CCL

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 59 of 59


PS-2100-0549-003-E-00

7.7. 9 Casing Operations

Weight
Item Qty Description Size Grade Connection Centralization
(lb/ft)
1 1 FloatShoe 9 53.5 P110HC VamTop
FloatShoe 2NWFlexible
2 1 9 53.5 P110HC VamTop
CasingJoint Centralizer
Casing
1NWFlexible
3 1 Intermediate 9 53.5 P110HC VamTop
Centralizer
Joint
Casing
1NWFlexible
4 1 Intermediate 9 53.5 P110HC VamTop
Centralizer
Joint
5 1 FloatCollar 9 53.5 P110HC VamTop Madeuponpin
FloatCollar 1NWFlexible
6 1 9 53.5 P110HC VamTop
CasingJoint Centralizer
1NWFlexible
CasingJoint
7 +/50 9 53.5 P110HC VamTop Centralizerevery.3
HC
Joints.
1RigidPositive
8 +/215 CasingJoint 9 53.5 P110 VamTop Centralizerforthe
last2Joints

Table 23 9 Casing String

NB1:9-5/8 Casing High Collapse will be used from 3630 m to 2900 m.


NB2: The centralizing position shall be verified based on the caliper log.
NB3: 9 centralizer to be installed close to surface to enhance the casing centralization in line with
Wellhead and Rotary Table.
NB4: 9-5/8 ,53.5#, P-110, New Vam connection might be used subject to availability of Vam Top
connection in due date of the job

7.7.1. 9 Casing Preparation

Prior to run 9 casing; ensure all required equipment and accessories are available on site and
ready to be used:
+55 HC plus +-240 joints to be received at location (at least 10% contingency to be
received)
Different length of 9 Pup joints..
Float Collar, float shoe. Verify connection is Vam Top if not sent to the Rig pre-
assembled.
Bow spring Centralizers and stop collars.
9-5/8 Reamer Shoe & rotating Centralizers as back-up plan.
8 Drift provided by Weatherford.

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 60 of 60


PS-2100-0549-003-E-00

9 Circulating Head Swedge with Quick Connection or Vam top connection to
NC50 or 2 Weco (provided by Schlumberger).
The cementing head has a BTC connection on the bottom. Ensure the proper
crossover is on location (provided by Schlumberger).
Running compound and thread lock. Ensure running compound is compatible with
Vam Top connections (API modified as an example).
All Casing running equipment: Jam Unit, Power units, Power tongs 16K, Side door
elevator 350 T, single joint elevator, Spider elevator 350T, 13 & 9 Casing
cutter.
La Fleur circulating tool and required Bails (180 350 T).
All cementing products required. There should be enough cement/blend/additives on
location to pump a 25% excess over the theoretical hole volume.
1. Clean and visually inspect all Casing threads.
2. All Casing must be drifted, measured, tallied and approved by the drilling superintendent.
Note: Consider all the different possibilities available to reach a convenient stick up at the
rotary table (XOs, landing joints, pup joints and XOs landing joint).
3. Shoe track joints shall be thread locked.
4. Pump mud through Shoe track to make sure it is not plugged before continuing to run the
Casing.
5. Verify the Mud Pump efficiency and Cementing pumping unit need to be pressure tested
offline and ready for the cementing Job.
6. Make sure that the 13 5/8 Wear bushing is retrieved.
7. Install 9-5/8 Casing rams in BOP. Pressure test same as per GRN procedure.

7.7.2. 9 Casing Running Procedure

1. Hold pre job safety meeting


2. Rig up Casing running equipment, including 180 Bails and circulating tool.
3. P/U Float Shoe Joint, two intermediate joints, and Collar Joint (Thread lock), fill-up with mud
and test that the Floating device is working properly (Three joints between shoe and float
collar)
4. Centralization must be assured close to surface using Rigid Centralizers inside 13
Casing.
5. Continue RIH 9 casing with controlled speed, avoiding losses induction, and tag bottom
(if it is feasible).
+/- 1 meters of rat hole to be considered.
All connections to be recorded in JAM unit.

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 61 of 61


PS-2100-0549-003-E-00

Use fill up tool to fill up the casing while running in hole.
Count number of casing remaining on the rack versus casing tally.
Space out the casing landing joint at rig floor level to have minimum stick up.
Make sure that no casing coupling is across the casing head housing.
6. If hole fill is observed, space out 9 casing according to pipe tally and availability of pup
joints at the site will be considered.
7. Condition mud to required properties as per Cementing Program.

7.7.3. 9 Casing Cementing Preparation

A detailed cement procedure will be prepared and issued prior to the casing operations based on
drilling conditions observed and according to the following guidelines.
Objectives:
Bring cement to +/- 100 m above 13 shoe (estimated TOC: 2200m mMD) to ensure
proper annulus isolation.
Minimize wait on cement (WOC) time.
Avoid losses.
Note: 9 cement job will be logged (CBL-VDL-GR) after drilling 8 section. If losses are
encountered, this log could be run immediately after cement job.
All the slurry properties have to be defined by Cementing Company and to be included in
wellsite procedures.
Ensure that final batch tests have been received from Cementing Company confirming
thickening times and slurry properties by the assigned GRN representative.

7.7.4. 9 Casing Cementing Procedure

1. Hold a safety meeting prior to pressure test cementing lines and start the cement job.
2. Check Cementing head connection, pressure rating and certification once it is received on
location. 7.5Kpsi Cementing head is required.
3. Re-Calculate cement volume requirement from caliper (volume to be confirmed by the total
fluids engineer and/or operations engineer).
4. The Casing will be cemented with two slurries. Lead 1.95sg IsoBlok G+S slurry and 2.10sg
Flexstone Cement tail slurry. Tail slurry TOC: +/- 2900m.
+/- 12 m3 of 1.90sg Mudpush (spacer) to be pumped.
Estimated volume of Lead: 25 m3
Estimated volume of Tail: 28 m3.
25% excess included over theoretical OH volume only as a reference.
Spacer and slurries designed in plug flow pattern at 3 to 5 bpm. Continue to
reciprocate while pumping/displacement cement.

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 62 of 62


PS-2100-0549-003-E-00

Highest ECD will be observed at end of displacement and should be checked
against the FIT/LOT obtained.
Monitor returns during the job.

5. Displace cement and bump plug with 500psi over FCP.


If plug is not bumped inform Superintendent immediately. Do not over displace more
than half shoe track volume. Compare total strokes versus calculated strokes after the
efficiency test.

Note that in case of a 3 joints shoe track the volume of the same is 9.44 bbl.
6. Check for backflow by releasing pressure and observing volume of flow-back, allowing for
aeration.
7. Switch back to the cementing unit and perform green casing pressure test to 5200psi.
8. Wait on cement 500 lbf/100 sq.ft SGS is achieved to compensate for hydrostatic loss and
prevent gas migration. Time to be confirmed from HMD. Two cement samples to be put in
the oven at downhole temperature (WL log temp).

Note: Refer to Annex VI for more details about cementing job.

7.7.5. Wellhead Operations Sequence

1. Hold pre-job safety meeting for well head operations.


2. Drain flow line and BOP.
3. Remove flow line to enable picking up stack and
spacer spool.
4. Lift BOPs.
5. Clean the Casing head Housing. Make sure it is
free from cement.
6. Place hanger around Casing. Remove the four
slip retainer screws on the OD of slip bowl.
These screws hold slips in retracted position in
bowl. Align and install the Casing Hanger
according to Cameron procedures. Minimum set up
weight is 15 Klbs in order to energize the slips
Pack-off seal. Otherwise use the Cap Screws to
manually energize the Pack-off seal.
7. Slack off on the casing. Sharp decrease on
weight indicator must be seen.

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 63 of 63


PS-2100-0549-003-E-00

8. Rough cut the 9 Casing approximately 24" above the top of the Casing Head. Move the
excess Casing and BOP out of the way.
9. Final cut the Casing at 6.75" 1/8" [171.5mm 3] above the top of the Casing Head. Place a
3/8" x 3/16" bevel on the Casing stub and remove all burrs and sharp edges.
10. Install BX-159 ring gasket into the ring groove of the casing head spool.
11. Lift and suspend the 13 " 10K x 11" 10K tubing spool over the casing head spool, ensuring
it is level.

Figure 18 9 Casing Cut


12. Carefully lower the spool until it lands on the ring gasket. Install and tighten the studs and
nuts of the flange in alternating cross manner to the torque reference in the charts in the
back of this manual.

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 64 of 64


PS-2100-0549-003-E-00

Figure 19 Casing Head Spool, Section C


13. Inject Cameron seal packing. Energize and pressure test the two P seals to 500/5200 psi
(maximum section design pressure), refer to Annex III.
14. Test the connection at the ring gasket to 500/5200 psi as per Cameron procedures.

Note: For more details the Cameron document is included within the appendix available at Rig in
hard and soft copy.

7.7.6. 13 BOP Stack Installation and Testing Procedure


Refer to GRN BOPs testing procedures: PS-0000-0583-002-E-00

1. Held pre-job safety meeting.


2. Install13-5/8" 10k x 13-5/8" 10k DSA.
3. Nipple up B.O.P. stack on 11API 10K, BX-158 Ring gasket, Casing/Tubing Head Spool
flange.
4. Function test all BOP Rams
5. Make up and RIH following assembly: 9 tester cup, 1 x 5 DP joint, pup joint, side entry
valve and safety valve.
6. Set 9 test cup below well head with test assembly. Connect test pump to choke manifold
2 outlet. Align valves to pump through side outlet of drilling spool.
7. Close upper pipe rams and test wellhead and wellhead valve to 200 / 5200 psi (5/15 min)
against upper pipe rams.
8. Remove test cup.

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 65 of 65


PS-2100-0549-003-E-00

9. Run 11 BOP combination tool/test plug. Orientate the tool with the LS seal toward the
bottom. Lower the tool down through the BOP/Riser until it lands on the load shoulder in the
casing head spool. Ensure test port of tester plug is clear and open.
10. Connect test pump to side entry of test assembly.
11. Pressure test BOP (as per Annex III indications):
a. Test kill line check valve, choke hose connections, valve #1 of choke manifold and
upper pipe rams to 200 psi for 5 min and at high pressure (5200 psi) for 10 min.
Ensure kill line is disconnected from check valve and downstream valve from valve
#1 of choke manifold should be open, so leaking can be verified.
b. With upper pipe rams closed, test annular preventer to 200 / 3,500 psi (5/15min).
c. With upper pipe rams closed, test outside kill line valve, outside choke line valve to
200 psi for 5 min, and 5200 psi for 10 min.
d. With upper pipe rams closed, test inside kill line valve, inside choke line valve to 200
psi for 5 min, and at high pressure (5200 psi).
e. Test lower pipe rams to 200 psi for 5 min and 5200 psi for 15 min.
f. Back out test assembly from test plug. Remove test assembly from BOP.
g. Connect test pump to choke manifold and pump through drilling spool. Test blind
rams to 200 psi for 5 min, and 5200 psi for 15 min.
h. Record all tests on a chart recorder, the DDR and the IADC Report.
12. Close annulus valve, release pressure and open the rams. Retrieve combination tool.
13. Close blind rams and pressure test casing string to maximum pressure of 5200 psi (as per
indicated in Annex III).
14. Install wear bushing in section C as per Cameron procedures.

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 66 of 66


PS-2100-0549-003-E-00

7.7.7. 13 BOP Stack Up Diagram



Figure 20 8 Section BOP Stack Diagram

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 67 of 67


PS-2100-0549-003-E-00

8. 8 Hole Section Objectives & Overview
8.1. 8 Section Key points
1. Manage to have a stable and in gauge hole for wireline operations.
2. Keep the well within 50m radius at the geological targets: Sieg-C Ged-B and Ged-A.
3. Drill primary well targets down to planned TD at 3,914 mMD (70m below top of Silurian
formation).
4. Run and cement 7 Liner.

8.2. 8 Section hazards & Risks


1. The Siegenian and Gedinnian reservoirs are gas bearing and will present the risk associated
to the productive intervals.
2. Formation dips in the formations may lead to hole deviation.
3. Excessive bit wear while drilling very hard formations for the entire hole section.
4. Shocks and vibrations associated with hard formations
5. Tight hole and stuck pipe.

Refer to Annex VIII Risk Assessment to see all the preventive and mitigation actions for this phase.

Refer to Annex X Offset wells information for more details about field experience.

8.3. 8 Section Drilling Operations


8.3.1. Recommended Bit & Hydraulics

Rolling Cutter (ONYX360) R813 PDC with 13-16mm cutters will be used to drill out cement, shoe
track and continue drilling rathole for XLOT. The same PDC bit is planned to drill down to TD through
Siegenian, Gedinian and Silurian formations. No Dolerite expected in this section. In case of the 1st
bit got over before section TD; the 2nd bit will be advised on due time.
Drilling parameters have to be optimized maximizing a constant torque, adjusting RPM to avoid
vibration and with enough flow to proper cool the bit.

Bit Primary Backup#1 Backup#2 Utility

SmithPDC NOVPDC SMITHMT


81/2" SMITHPDC(ONYX360)R813
MSZI716LWUEBPX DSH813M SVH215

Table 24 8 Recommended Bits

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 68 of 68


PS-2100-0549-003-E-00

8.3.2. Recommended Drilling Parameters

WOB RPM FlowRate HSI


Section Mode Bit SPP(psi) TFA(in2)
(Ton) Rotary (lpm) (HP/in2)
0,893
81/2" RSSBHA PDCSMITHR813 916 120160 15002200 27004100 2.4
(3x14+4x12/32")

Table 25 8 Recommended Drilling Parameters

Note: the above values are based on 6 mud pump liners.

8.3.3. Recommended BHAs

The primary BHA will be Vertical RSS assembly. The possibility of using a rotary BHA or PDM BHA
for drilling part or the entire 8 hole section will be evaluated during operations. If decided to run a
rotary BHA it will be officially communicated by GRN team in Hassi-Messaoud (HMD).

81/2"RSSBHA#4
OD (in)/ Max OD Bottom/Top Length Cum. Length
Item Name
ID (in) (in) Connection (m) (m)
8 1//2
1 PDC bit 8 1//2 4 1/2" Reg Pin 0.29 0.29

6,75 4 1/2" Reg Box


2 AutoTrak V 8,5 2.17 2.46
2.31 T2 Box
7 T2 Pin
3 MWD-Stab-Mod 8 3/8 1.31 3.77
2,25 T2 Box
7 T2 Pin
4 BCPM 7 3.39 7.16
2,1666667 T2 Box
6,75 T2 Pin
5 BCPM NM Sub 6,75 0.8 7.96
3,25 NC-50 Box
6,375 NC-50 Pin
7 Stab String 8 1/4 1.61 9.57
2 3/4 NC-50 Box
6,75 NC-50 Pin
9 NM Sub - filter 6,75 1.8 11.37
2,8125 NC-50 Box
6,5 NC-50 Pin
10 Float Sub with Totco Ring 6 1/2 0.81 12.18
2,875 NC-50 Box
6,75 NC-50 Pin
11 18 x 6-3/4" DC 6,75 169.7 181.88
2,8125 NC-50 Box
6,75 NC-50 Pin
12 Jar 6,75 9.54 191.42
2,75 NC-50 Box
6,75 NC-50 Pin
13 2x 6-3/4 DC 6,75 18.48 209.9
2,8125 NC-50 Box
5 NC-50 Pin
14 12 x 5" HWDP 5 111.29 321.19
3 NC-50 Box
5 NC-50 Pin
15 5" DP S-135 19.5 lb/ft, Premium 5
4,2857143 NC-50 Box

Table 26 8 RSS BHA

WBJ: +/- 20 Ton.


1
Note : Actual Hydraulic Simulation will be carried out during the operations.
2
Note : The dimensions of all tools and BHA components must be checked prior to RIH.

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 69 of 69


PS-2100-0549-003-E-00

3
Note : Totco Ring to be installed in preparation for Gyro operation at TD.

81/2"PackedBHA#6
OD(in)/ MaxOD Length Cum,Length
Item Name Bottom/TopConnection
ID(in) (in) (m) (m)

1 PDCbit 81//2 81//2 41/2"RegPin 0,26 0,29

87/16 41/2"RegBox
2 NearbitStab 87/16 1,84 2,13
21/2 NC50Box
7 NC50Pin
3 1x63/4"DC 63/4 9,41 11,54
213/16 NC50Box
87/16 NC50Pin
4 StabString 87/16 1,71 13,25
21/2 NC50Box
63/4 NC50Pin
5 2x63/4"DC 63/4 18,82 32,07
213/16 NC50Box
87/16 NC50Pin
7 StabString 87/16 1,61 33,68
23/4 NC50Box
63/4 NC50Pin
11 18x63/4"DC 63/4 169,38 203,06
213/16 NC50Box
63/4 NC50Pin
12 Jar 63/4 9,54 212,6
23/4 NC50Box
63/4 NC50Pin
13 2x63/4DC 63/4 18,82 231,42
213/16 NC50Box
5 NC50Pin
14 12x5"HWDP 5 111,29 342,71
3 NC50Box

5"DPS135 5 NC50Pin
15 5 3571,4 3914,11
19,5lb/ft,Premium 42/7 NC50Box

Table 27 8 Packed BHA

8.3.4. Recommended Drilling Procedure

1. Pick up enough 5 DP to drill down to section TD (3,914 m MD).


2. P/U, M/U and RIH 8 SMITH PDC Bit R813 PDC with Autotrak V BHA. Record Weight
below jar. Be extremely careful when handling smart tools at the Rig floor.
3. RIH with 8 ATK BHA to float collar, tag the same and drill out and clean rat hole (2 <
WOB < 6)
4. Condition mud to ensure consistent density and properties. Verify shakers are clean of any
shoe track debris. Confirm MW in/out is 1.80sg equal.
Note: The previous hole sections mud will be recovered and transferred to the Mud
Treatment plant or other rig.
5. Performed Shoe Bond test.
6. Drill 3 meters of new formation, circulated hole clean and until having homogeneous MW
in/out.

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 70 of 70


PS-2100-0549-003-E-00

7. Pull back into the Casing Shoe and conduct Extended LOT & LOT respectively at 9-5/8
Casing shoe according to GRN procedures.
8. Record pressures versus pumped/returned volume and inform Drilling Superintendent and
Senior Engineer. Report values on DDR.

Openhole/ ExpectedLOT MudWeight Surfacepressure KickTolerance


ShoeDepth(m)
Casingsize(in) value(sg) (ppg) (psi) (bbls)
444bblsusing
81/295/8 3630 2.10to2.80 1.80 1,5505,200*
1.26s.g
Table 28 8-1/2 Expected ExLOT

*Note: The XLOT will be limited to 5,200psi surface pressure.

9. Displace hole from 1.80 sg to 1.26 sg Non Damage Avapolyoil Mud.


10. Drill ahead with ATK BHA.
Increase drilling parameters when the last stabilizer is below Casing Shoe.
Monitor and control vibrations while drilling. The Drillers display must have the
proper alarms, and Mud Logger will communicate to Driller and Company Man if
vibration appears.
Optimize the drilling parameters between WOB and RPM to achieve reasonable
ROP.
When POOH: If more than 10t drag is observed for more than 10m, immediately
M/U the TDS and pump out of the hole the full stand, then try to test on elevators. If
back reaming is required low rpm to be used.
11. If Bit change is required, circulated hole clean and pump his vis pill and Supersweep Pills.
12. POOH to shoe, perform flow check, circulate hole clean and resume POOH.
13. Make up & RIH with 8 new bit (7 or 8 blades to be confirmed by HMD depending on the
current depth). Continue drilling ahead with ATK or rotary BHA to well TD at +/-3,914m MD.
(+-70m below Base of Ged-A reservoir). TD to be agreed with Town based on G&G Ged-
A base definition.
14. Try to optimize the trips to surface to test the BOPs every 21 days (Max allowed period).
15. At TD; Pump 6m3 of SuperSweep Pill & circulate hole clean (2 bottoms up minimum).
16. Perform a wiper trip to the 9 shoe if considered necessary, and after agreement with the
office.
17. Drop Gyro, take survey while POOH and rack back BHA.
18. Run wireline logs.
19. Based upon the logs duration, control trips could be performed between wireline runs.

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 71 of 71


PS-2100-0549-003-E-00

8.4. 8 Section Drilling Fluids
8.4.1. Recommended Drilling Fluids Rheology Parameters

A Low Damage AVAPOLYOIL mud system will be run. Displace hole once the extended LOT is
done.

Refer to Annex VII for more information about mud system.

Units 81/2HoleSection
IntervalDepth meters +/284
AVAPOLYOIL/SOLTEX/
MudType
POLYMER
MudWeight sg 1,26
pH 9.510
PlasticViscosity cP ALAP
YieldPoint lb/100sqft 1820
Gels10sec/10min/30min 10/15/20
APIFluidLoss cc/30min 3cc
SectionTDStaticTemperature C 140

Table 29 8 Recommended Drilling Fluids Parameters

8.5. 8 Cutting Sampling Mud Logging Program


Set of samples will be collected from the beginning of 8 drilling phase down to TD.
Two types of samples will be collected as below.
From Muraille de Chine to top of Siegenian, every 5 meters.
Set-1: GRN: Washed and dried (Dry) / Unwashed (Wet)

Set-2 SONATRACH: Washed and dried (Dry) / Unwashed (Wet)


From Siegenian to TD, every 3 meters.
Set-1: GRN: Washed and dried (Dry) / Unwashed (Wet)

Set-2 SONATRACH: Washed and dried (Dry) / Unwashed (Wet)


Mud Sampling:
Refer to GEOLOGICAL OPS PROGRAM

8.6. 8 Section Electric Logging Operations


Open Hole
The following logs will be run after reaching 8 section TD:
Run 3A: SGT-EMS-DSI(P&S+Stoneley)
Run 3B: NGS-LDS/MCFL/APS-HRLA

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 72 of 72


PS-2100-0549-003-E-00

Run 3C: SGT-CMR200
Run 3D: MDT (SP-STD)-SGT) optional

Cased Hole

The following logs will be run in 9 casing:


SGT-CBL-VDL-CCL (USIT/IBC optional)

8.7. 7 Liner Operations


8.7.1. 7 Liner String

Weight
Item Qty Description Size Grade Connection Centralization
(lb/ft)
1 1 FloatShoe 7 32 13Cr110 VamTop
FloatShoe
2 1 7 32 13Cr110 VamTop TBA
CasingJoint
Casing
3 1 Intermediate 7 32 13Cr110 VamTop TBA
Joint
4 1 FloatCollar 7 32 13Cr110 VamTop TBA
FloatCollar
5 1 7 32 13Cr110 VamTop TBA
CasingJoint
Landing
6 1 7 32 13Cr110 VamTop TBA
Collar
7 +/36 CasingJoint 7 32 13Cr110 VamTop TBA
7X9
8 1 Weatherford 7 32 13Cr110 VamTop TBA
LinerHanger
Table 30 7 Liner Specifications

8.7.2. 7 Liner Running Procedure
A detailed Liner Running Program including Baker recommendations and best practices will be
issued as a separate document before the Liner Installation Job.

8.7.3. 7 Liner Cementing Procedure


Objective:
To cover and isolate reservoir main objectives.
Top of slurry 200 m inside 9 casing (50m above top of the liner).
The cement slurry design and the placement procedures will be detailed in the final cement proposal
to be issued by cementing company. The final recipe has to be on the rig at least 48 hours before the
cement job.

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 73 of 73


PS-2100-0549-003-E-00

1. Once the hanger has been set, set down 30 Klbs of DP weight on liner hanger to
compensate for pump out forces. Check rotation and condition mud before pumping cement.
2. Line up the cement unit and pressure test the surface cementing equipment to 6000 psi. Mix
the cement as per the program.

Note: Keep circulating and rotating (10-20 rpm) while mixing cement.

3. Pump the cement spacers and slurry (6m3 of mud push + 1.4m3 of intermediate spacer
1,45sg and 8m3 of 1.90sg Flexstone, 25% excess included).
4. After the cement has been pumped, close the main valve and release the drill pipe wiper
dart as required and displace with mud using cement unit pumps to accuracy displacement.
5. Displace drill pipe volume. For the last 5 bbls, slow pump rate to 2 bbl/min, since excessive
pump rate may interfere with the shear mechanism. A slight increase in pressure should be
noted as the wiper dart plug latches into the liner wiper plug. After the liner wiper plug shears
recalculate the actual displacement and increase pumping rate back.
6. The following guidelines should be used for the displacement.
a. If wiper plug shears early. Count from the shear
b. If wiper plug shear is < 1 bbl late. Count from the shear.
c. If wiper plug shear is > 1 bbl late. Use theoretical displacement only.

Note that in case of a 3 joints shoe track the volume of the same is 3.55 bbl.
7. Continue to displace the liner as per program, slowing the pump rate to 2 bbl/min on the last
5 bbls. As the liner wiper plug reaches the landing collar, pressure up to 1,000 psi over
displacement pressure and hold for 1 minute.
8. Bleed pressure back in to the pump truck tanks to ensure that the plugs and float equipment
are holding. If not holding, pressure up on the liner again increasing pressure slightly and
bleed back once again.
9. Proceed to set and test Weatherford packer (separate detailed program will be provided).

8.7.4. Inflow Test and Clean Out of Liner Top Packer

A detailed Liner Inflow Test Procedure including Horner Plot guidelines and interpretation will be
issued as a separate document before the Liner Inflow Test will be performed. Also a positive test
will be performed to confirm good seal of the liner top packer.

8.7.5.Preparing for Completion

Upon successful Inflow test of the Liner Top Packer the well will be displaced to brine. The clean-out
BHA will be POOH and Cased Logs will be run in order to evaluate the 7 liner cement job.
The well will be then handed over to Completion Department in order to carry out the planned
completion program.

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 74 of 74


PS-2100-0549-003-E-00

9. ANNEXES

9.1. ANNEX I Casing specifications

Tensile Torque (lb x ft)


Hole Casing Linear Yield
Hole Lenght Connecti ID Drift Burst Collapse Min
Depth Size Weight Grade Strength Remarks
Size (m) on (in) (in) (psi) (psi) Optimum
(m MDRT) (in) (lb/ft) (KLb)
(in) Max

24 +/- 450 18 +/- 450 87.5 K-55 BTC 17.755 17.567 2,248 627 1,366 To Triangle

20,850
16 +/- 2300 13 +/- 2300 72 Q-125 Vam Top 12.347 12.25 8,410 2,880 2,596 23,150 Special Drift
25,450
+/- 2900 P-110 7,950 20,850
12 +/- 3630 9 53.5 Vam Top 8.535 8.500 10,900 1,710 23,150 Special Drift
+/- 730 P-110HC 10,550 25,450
12,450
13Cr-110
8 +/- 3914 7 +/- 450 32 Vam Top 6.094 6.000 12,460 10,780 1,025 13,750 Special Drift
/ P-110
15,050
5,200
6 Contingency 4 - 13.5 13Cr-110 Vam Top 3.920 3.795 12,410 10,680 422 5,770
6,340

Table 31 Casing Specifications

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 75 of 75


PS-2100-0549-003-E-00

9.2. ANNEX II 10K psi W.P. Wellhead Specifications


Figure 21 Cameron Wellhead System 10K

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 76 of 76


PS-2100-0549-003-E-00

9.3. ANNEX III BOP, Wellhead and Casing Pressure Test

We llhe a d T e s t ing B O P ( ps i)
E v e nt in whic h We llhe a d S e c t io n We llhe a d S e c t io n
C a s ing P re s s ure T e s t ( ps i) t he C a s ing is S e c t io n S e a ls / C o nne c t io n B o dy P re s s ure T e s t The BOP shall be tested prior to each new hole section or every 14 days (21 days maximum).
P re s s ure T e s t e d P re s s ure T e s t ( ps i) wit h C up T e s t e r ( ps i)
Choke manifold, surface lines and valves to be tested at low pressure for 5 min and at high pressure for 10 min.

Casing Head
18- 500 psi 1,100 psi w/ 1.05 sg M W 20-3/4" 3K B OP rams 21-1/4 2K annular
Ho using
B efo re drilling o ut (Limited to 80% o f (gas to surface limited by
87.5 ppf 1,100 psi w/ 1.05 sg M W 21-1/4 5K RA M preventer: 200 / 2,400 psi w/ 1.05 sg M W (80% o f wo rking pressure)
the sho e track co llapse pressure o f K- sho e strength + SF)
K55 A nnular preventer: 200 / 1,400 psi w/ 1.05 sg M W (70% o f wo rking pressure o f annular preventer)

18- , K-55 Rating: B urst Yield P ressure = 2,248 psi / 80 % o f B urst Yield P ressure = 1,798 psi Co llapse P ressure = 627 psi / 80% o f Co llapse P ressure = 501psi

13- Casing Spo o l 2,300 psi 6,700 psi w/ 1.30 sg M W 13-5/8" 10K B OP
5000* psi w/ 1.35 sg M W Immediately after
(Limited 80% o f Casing (Limited to 80% o f Casing
72 ppf (Limited to 80% o f B urst bumping to p cement 21 5K 13-5/8 10K RA M preventer: 200 / 6,700 psi w/ 1.35 sg M W (Limited to 80% o f Casing B urst P ressure)
Co llapse P ressure) B urst P ressure)
P ressure) plug
Q125 A nnular preventer: 200 / 3,500 psi w/ 1.35 sg M W (70% o f wo rking pressure o f annular preventer)

- 13- , Q-125 Rating: B urst Yield P ressure = 8,410 psi / 80 % o f B urst Yield P ressure = 6,728 psi Co llapse P ressure = 2,880 psi / 80% o f Co llapse P ressure = 2,304 psi
* Green casing pressure test is limited to 5000psi due to the maximum W.P . o f 5kpsi o f the 13 3/8" cementing head. In case is available o nsite a cement head with W.P . = 7,5kpsi, the casing sho uld be tested up to 6700psi.

9-5/8 Tubing Head 5,200 psi 5,200 psi w/ 1.80 sg M W 13-5/8" 10K B OP
5,200 psi w/ 1.80 sg M W Immediately after
53.5 ppf (Limited to displacement bumping to p cement 13-5/8 10K (Design pressure) (Design pressure) RA M preventer: 200 / 5,200 psi w/ 1.80 sg M W (Design pressure)
to gas) plug
P -110 to 2900m x 11 10K A nnular preventer: 200 / 3,500 psi w/ 1.80 sg M W (70% o f wo rking pressure o f annular preventer)

HC P -110 fro m 9-5/8 , P -110 Rating: B urst Yield P ressure = 10,900 psi / 80 % o f B urst Yield P ressure = 8,720 psi. Co llapse P ressure = 7,950 psi / 80% o f Co llapse P ressure = 6,360 psi
2900 to 3630m 9-5/8 , P -110 H C Rating: B urst Yield P ressure = 10,900 psi / 80 % o f B urst Yield P ressure = 8,720 psi. Co llapse P ressure = 10,520 psi / 80% o f Co llapse P ressure = 8,410 psi

7 Liner 13-5/8" 10K B OP


Immediately after
32 ppf 5,200 psi w/ 1.26 sg M W bumping Liner Wiper N/A N/A N/A RA M preventer: 200 / 5,200 psi w/ 1.26 sg (Design pressure)
P lug
13Cr-110 A nnular preventer: 200 / 3,500 psi w/ 1.26 sg M W (70% o f wo rking pressure o f annular preventer)

A fter liner po sitive pressure test; the TOL has to be po sitive and negative tested. Separate pro cedure will be issued.
7 , 13Cr-110 B urst Yield P ressure = 12,460 psi / 80 % o f B urst Yield P ressure = 9,968 psi. Co llapse P ressure = 10,780 psi / 80% o f Co llapse P ressure = 8,624 psi

Table 32 - BOP, Wellhead and Casing Pressure Test Activity Outline.

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 77 of 77


PS-2100-0549-003-E-00

9.4. ANNEX IV Drilling Bits Specification.

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 78 of 78


PS-2100-0549-003-E-00

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 79 of 79


PS-2100-0549-003-E-00

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 80 of 80


PS-2100-0549-003-E-00

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 81 of 81


PS-2100-0549-003-E-00

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 82 of 82


PS-2100-0549-003-E-00

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 83 of 83


PS-2100-0549-003-E-00

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 84 of 84


PS-2100-0549-003-E-00

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 85 of 85


PS-2100-0549-003-E-00

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 86 of 86


PS-2100-0549-003-E-00

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 87 of 87


PS-2100-0549-003-E-00

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 88 of 88


PS-2100-0549-003-E-00

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 89 of 89


PS-2100-0549-003-E-00

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 90 of 90


PS-2100-0549-003-E-00

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 91 of 91


PS-2100-0549-003-E-00

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 92 of 92


PS-2100-0549-003-E-00

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 93 of 93


PS-2100-0549-003-E-00

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 94 of 94


PS-2100-0549-003-E-00

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 95 of 95


PS-2100-0549-003-E-00

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 96 of 96


PS-2100-0549-003-E-00

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 97 of 97


PS-2100-0549-003-E-00

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 98 of 98


PS-2100-0549-003-E-00

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 99 of 99


PS-2100-0549-003-E-00

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 100 of 100
PS-2100-0549-003-E-00

9.5. ANNEX V Mud program summary


Properties Units 24"Section 16"Section 121/4"Section 81/2"section Completion/DST
From: 15m From: 450m From: 2.300m From: 3.630m SiegenianD@3644m
SectionDrilled meters To: 450m To: 2.300m To: 3.630m To: 3.914m SiegenianD@3668m
Totaldrilled 435m Totaldrilled 1.850m Totaldrilled 1.330m Totaldrilled 284m GedinianB@3727m
MudWeight SG 1,05sgto1,10sg 1,35sg 1,80sg 1,26sg CaCl2Brine@1,28sg
0,98sgemwat450mTVD 1,29sgemwat2200m 1,35sgemwat2750m 1,19SGemwat3650m 1,19SGemwat3650m
PoreGradient SGEMW 1,46sgemwat3350m 1,17sgemwat3750m 1,17sgemwat3750m
1,67sgemwat3536m 1,13sgemwat3900m 1,13sgemwat3900m
FracGradient SGEMW 1,85sgemwat450mTVD 2,02sgemwat2300m 2,11sgemwatTD 2,08sgemwatTD 2,08sgemwatTD
MudType AMINEPOLYMER AVAPOLYOIL/SOLTEX/POLYMER AVAPOLYOIL/SOLTEX/POLYMER NONDAMAGINGAVAPOLYOIL
PV@50C cp ALAP ALAP ALAP ALAP
YV@50C lbs/100ft2 35/40lbs/100ft2 30/35lbs/100ft2 20/25lbs/100ft2 18/20lbs/100ft2
APIFluidloss cc 10ccallNamurianinterval 3cc 3cc 3cc
Gels10",10',30' lbs/100ft2 18/20/25 12/15/20 15/20/30 10/15/20
pH 9,510 9,510(highlevelofHardness>0,8) 9,510 9,510
BHSTC Celsius 45C 90C 135C 140C 140C
DRILLWATER 919lts DRILLWATER 695lts DRILLWATER 540lts DRILLWATER 710lts 1CaCl2BrineFormulation@1,28sg
SODAASH 1kg NaCL 225kgs NaCL 175kgs NaCL 230kgs WATER 890lts
CAUSTICSODA 1kg SODAASH 1kg SODAASH 1kg SODAASH 1kg CaCl2 380kgs
AVAPERM 30lts CAUSTICSODA 1kg CAUSTICSODA 1kg CAUSTICSODA 1kg AVACIDE 1lts
AVAPOLYMER50/50 8kgs AVAPERM 15lts AVABUFFER asrequired AVABUFFER asrequired INCORR 3lts
POLICELSL 8kgs AVAPOLYMER50/50 8kgs AVAPERM 15lts AVAEXTEMP 10kgs DEOXY 2lts
POLICELLRG 4kgs POLICELLSL 8kgs AVAPOLYMER50/50 8kgs AVAPERM 15lts 2CleanUPpills:
SOLTEX 15kgs POLICELRG 4kgs VISCO83SL 5kgs AVAPOLYMER50/50 8kgs Viscouspills: 20m3
INTASOLF 10kgs AVAPOLYOIL 100lts VISCOXC84 2kgs AVAPOLYOIL 100lts CaCl2Brineat1,28sg 1m3
SANDSEAL 10kgs SOLTEX 25kgs AVAPOLYOIL 100lts SOLTEX 20kgs AVAHEC 12kgs
MUDDESIGN/FORMULATION AVACARB 30kgs INTASOLF 20kgs VICTOSAL 1215kgs VISCO83SL 8kgs CAUSTICSODA 1kg
SANDSEAL 10kgs SOLTEX 2025kgs VISCOXC84 1kg
AVACARB 30kgs INTASOLF 20kgs AVAFULFLOW 40kgs WashPills: 10m3
BARITE 175kgs SANDSEAL 10kgs DEFOAMER asrequired CaCl2Brine 850lts
DEFOAMER asrequired AVACARB 30kgs AVACARB 70kgs AVAWASH 150lts
AVALIGNE asrequired BARITE 810kgs
SODAASH asrequired DEFOAMER asrequired
AVALIGNE asrequired
50m3ofKillmud@1,50sg 50m3ofKillmud@1,50sg 50m3ofKillmud@1,90sg 50m3ofKillmud@1,90sg 50m3ofHeavybrine@1,35sg
10m3LCMpill@150kg/m3 10m3LCMpill@300kg/m3 10m3LCMpill@300kg/m3 10m3LCMpill@300kg/m3 availableinAdrarLMP
ReadybeforetheSpud ReadybeforetoStartthesection ReadybeforetoStartthesection ReadybeforetoStartthesection
110m3
EstimatedMudvolumerequired 500m3 1.000m3 550m3 280m3
(200m3reusedfrompreviouswells)
EstimatedCostoftheSection 170.000us$ 600.000us$ 360.000us$ 80.000us$ 60.000us$
HoleCleaning: 1RiskofLossesattheTOPofDolerites: Mudweightmanagement: HoleCleaning: CaCl2BrinewillbefilteredandInhibited
Sweeppillswhenrequired Tournaisian&FamenianDolerites70m3/hr Startthesectionwith1,35sgmud Sweeppillswhenrequired
10m3Activemud HoleCleaning: 1,40sg@2500m 6m3Activemud Filtrationthrough5and10microns
5kgsSuperSweep(0,5kgs/m3) Sweeppillswhenrequired 1,45sg@2700m 3kgsSuperSweep(0,5kgs/m3) cartridgestoachieveasolidscontent
10m3Activemud 1,50sg@2900m <0,5%
BitBalling: 5kgsSuperSweep(0,5kgs/m3) 1,60sg@3000m BoreHoleInstability: NTUwillbereportedasreferenceONLY
Detergent/NutPlugPill; 2BoreHoleInstability: 1,70sg@3200m SensitiveClaysinSilurian
Activemud 8m3 HoleinstabilityinTournaisianand 1,80sg@3450m Closeobservationofcavingsatshakers
COMMENTS
AVADETER25lts/m3 200lts FamenianatTopandBaseofDolerite BoreHoleInstability: Mudweightcouldbeincreased
NutPlugF80kg/m3 640kgs Closecontrolofchemicalsconcentration SensitiveClaysinFamenian upto1,35sgforholestability
NutPlugM80kg/m3 640kgs Observationforpresenceofcavings HoleCleaning: Closemonitoringofchemicalsconcentration
atshakersandMudloggersamples Sweeppillswhenrequired
Anhydriteat+/350m ClosemonitoringofMudweight 10m3Activemud
TreataccordinglywithSodaAsh 3ImportantLayersofAnhydriteinViseanD:
Harnesscontrolled<0,4gr/m3
5kgsSuperSweep(0,5kgs/m3)

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 101 of 101
PS-2100-0549-003-E-00

9.6. ANNEX VI Cement program summary

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 102 of 102
PS-2100-0549-003-E-00

9.7. ANNEX VII LCM Decision Tree


Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 103 of 103
PS-2100-0549-003-E-00

9.8. ANNEX VIII - Risk Assessment
Prior to each non-routine or routine operation commencing a Risk Assessment process must be
performed. This process should be well structured and with a logical sequence. It is recommended to
carry out the assessments in two stages. Stage one covers the identification of hazards (task analysis);
stage two covers the assessment of risk and selection of control measures in order to reduce the risk to
an acceptable level (risk assessment) and the subsequent communication of this in the form of
information and instruction to the workforce involved in the task.
EXPOSURE ( E )
Accident Scenario Frequency (1/year) < 10 -6 10 -6 to 10-5 10 -5 to 10-4 10 -4 to 10 -3 10 -3 to 10 -2 10 -2 to 10 -1 10 -1 to 1 1 to 100
Value 0.4 0.8 1.6 3.1 6.3 12.5 25 100
It has happend
It has not It has happend It happens on It happens on a
Specific sector of activity at global level Unheard of in the last five
Area of assessment

happend before an annual basis monthly basis


years
It has happend
It has happend It happens on It happens on a
Specific sector of activity in GRN in the last five
before an annual basis monthly basis
years
It has happend
It has happend It happens on
According to the area of the business/activity in the last five
before an annual basis
years

CONSEQUENCES ( C )
Dam age to property
and loss of profits Level of
Level of Personal
Environm ent dam age difussion; Value
consequences Injuries
Enviromental reputation
rem ediation costs ()
Non-significant enviromental incident in an
Incident w ithout area w ithout guaranteed containment, No
Low 5 k - 100 k 1.7
lost time causing local environmental damage w ithin dissemination
the limits of the property
Relevant environmental damage that
Up to 30 days of
exceeds the levels of reference for
lost time. Green level
Moderate 100 k - 1 M environmental quality or is capable of 3
<1% probability of crisis
generating legal action and does not have
1 death
permanent effects
Serious environmental damage that could
Over 30 days of
affect the property's environment, w hich
lost time. Yellow level
Serious 1 M - 10 M exceeds in large areas the reference 7
<10% probability crisis
levels for environmental quality and could
of 1 death
affect third parties
Very serious environmental damage. The
company is required to provide correction
Could cause a and/or significant compensation
Very Serious death or 10 M - 100 M measures, in large areas it esceeds the Red level crisis 16
permanent injuries reference levels for environmental quality;
high probability of permanent residual
damage
Could cause Catastrophic environmental damage; loss Temporary
Disastrous betw een 2 and 9 100 M - 1000 M of environmental resources and services. international 40
deaths Permanent damage affectation
Catastrophic and w idespread
Permanent
Could cause 10 environmental damage; extensive loss of
Catastrophic > 1000 M international 100
deaths or more environmental resources and services.
affectation
Permanent damage

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 104 of 104
PS-2100-0549-003-E-00


24" SECTION
Scores
Success Residual
Operation Risk / Hazard Consequences Preventive Actions Mitigation Actions
Cons Expo Like Risk (%) Risk ( R )
(C) ( E) (L) ( R)
Drilling to TD (450 mMDBRT) Washouts below 30" conductor Hole collapse and stuck pipe Ensure good cement behind conductor pipe At any sign stop drilling operations and
pipe Loss of location Drill w ith controlled parameters (flow rate, WOB and RPM; control ROP < 5 m/h) assess to spot a cement plug across (keep
Ensure adequate Rig pad terrain compression/ circulation and rotation)
Instruct crew s on w atching for any sign of mud at surface Spot Hi-vis pill
7 1,6 2,5 28,0 Moderate POOH drill string 90% 2,8 Minor
Assess possible Rig dow n
After a possible Rig dow n starting to build a
new cellar

Drilling to TD (450 mMDBRT) Bit balling w hile drilling claystones Extra trip Use of Center Jet to enhance Bit cleaning Sw eep Low -vis pill + LCM
Lost time (NPT) Monitor torque trend POOH slow ly to avoid sw abbing effect
1,7 12,5 2,5 53,1 High Control WOB and enhance hydraulic Clean and re-run or change Bit 75% 13,3 Minor
Incorporate detergent in the mud system

Drilling to TD (450 mMDBRT) Build angle Correct the w ell trajectory further To use a packed BHA Prepare correction plan for the next section
dow n the hole 3 6,3 2,5 47,3 High Control WOB 85% 7,1 Minor

Drilling to TD (450 mMDBRT) Mud losses (losses experienced in Hole collapse and stuck pipe Being ready to pump LCM pill (already prepared) Stop drilling and keep circulating at low er
RG-6) Lose the hole Keep enough LCM material on location flow rate. Keep moving drill string
Loss of hydrostatic column Prepare a cement plug recepy before spudding (thixotropic) Keep fluid level in the w ell
inducing a shallow gas kick Minimize circulating time at connections Try to cure losses w ith LCM pills
3 6,3 5 94,5 Urgent Close monitoring of Stand pipe pressure and flow returns to identify any sign of If it is not possible to cure losses w ith LCM 70% 28,4 Moderate
losses (Mud Logging unit to help) material, prepare and pump cement plug
Maintain the mudw eight and conditions as per program Work string if stuck pipe
Ensure to have enough w ater (w ater pit full and trucks ready to transport)

Drilling to TD (450 mMDBRT) Bit bouncing and vibrations Reduce bit life Optimize drilling parameters to reduce vibrations (WOB and RPM) Vary drilling parameters (WOB, RPM) to
Cause damage on drill string Use Shock Sub mitigate vibrations and Bit bouncing
components 3 6,3 1,2 22,7 Moderate Have shock sub at location 60% 9,1 Minor
Cause damage to Top Drive
Loss of bit cones
Drilling to TD (450 mMDBRT) Erratic casing point Weak shoe if it is placed in front of Proper sampling correlation w hile drilling. Assess the situation to evaluate the
a sandstone instead of a claystone / Mud Logging and Geologist to advice competent formation for shoe depth necessity of reinforcing the shoe w ith
shale 3 6,3 2,5 47,3 High cement plug 70% 14,2 Moderate
Entering in Visean formation w ith
probability of gas
Drilling Namurian claystones Tight hole Lost time (NPT) To use proper MW Pump out of hole at reduced flow rate
Observed in KL-2 To perform proper hole conditioning To ream / backream hole if necessary to
1,7 12,5 2,5 53,1 High Reduce mud filtrate w ork tight spots 75% 13,3 Minor
Progress in new mud formulations

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 105 of 105
PS-2100-0549-003-E-00

24" SECTION
Scores
Success Residual
Operation Risk / Hazard Consequences Preventive Actions Mitigation Actions
Cons Expo Like Risk (%) Risk ( R )
(C) ( E) (L) ( R)
Running Casing Casing running equipment failure Lost time (NPT) due to Casing To have Casing running equipment back-up on site Sw itch to use back-up equipment
running equipment repairs 1,7 6,3 1,2 12,9 Minor Crosscheck equipment on site since w ill be firs 18 5/8" job in the project immediately or perform equipment repairs as 90% 1,3 Minor
fast as possible
Running Casing Induce losses due to surge Stuck casing due to hole collapse Control running speed (run surge simulation prior to start RIH) Reduce running speed if losses are
pressure Critical zone not covered by Perform w iper trip prior to run casing detected
Unable to reach bottom casing Pump and displace Hi-vis pill after last w iper trip Keep w ell fluid level if losses are detected
Cement job operation seriously 3 6,3 1,2 22,7 Moderate * Prepare to incorporate fibers in your cementation POOH casing to condition the hole 70% 6,8 Minor
compromised

Cementing Job Losses w hile cementing Level drops once cement job has To use considerable excess of cement in volume (50-100 %) Reduce pumping rate
finished To add some fibers to cement slurry in case of losses w hile running casing or Perform Top job
No good isolation achieved w hile circulating prior to perform cement job
1,7 6,3 1,2 12,9 Minor To re-design pumping schedule w ith low er pumping rate in case of having 70% 3,9 Minor
losses prior to start cement job

Cementing Job Casing Float Equipment failure Lost time (NPT) due to additional Function test float valves from float equipment (Shoe) prior to RIH Sting back in, Re-pump return volume,
WOC 1,7 6,3 1,2 12,9 Minor maintain pressure until surface samples are 70% 3,9 Minor
hard







Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 106 of 106
PS-2100-0549-003-E-00

16" SECTION
Scores
Success Residual
Operation Risk / Hazard Consequences Preventive Actions Mitigation Actions
Cons Expo Like Risk (%) Risk ( R )
(C) ( E) (L) ( R)
Drill out shoe track Premature bit damage Extra trip To drill out shoe track w ith proper parameters Replace damaged bit
Casing damage Casing and w ell integrity To drill 16" hole w ith reduced parameters until last stabilizer from
compromised BHA is out of the casing

7 3,1 1,2 26,0 Moderate 90% 2,6 Minor

Perform FIT To induce losses Difficulties to drill ahead 16" Ensure previous casing point is set at competent formation Evaluate option to drill ahead w ith low er
Low er Fracture Gradient than section Use best practices to perform FIT LOT value (low er KT)
expected 3 6,3 1,2 22,7 Moderate Ensure pumping unit is in perfect conditions Evaluate remedial actions (LCM, cement 70% 6,8 Minor
To lose one diameter Use fresh and light mud plug)
Drilling to TD (+/- 2,300 mRT) Hole collapse and stuck pipe Maintain good mud properties Stop drilling and keep circulating at low er
Mud losses may occur w hile Differential sticking 3 6,3 1,2 22,7 Moderate Keep enough LCM material on location flow rate. 70% 6,8 Minor
drilling the Dolerite ( encountered Loss of the hole Ready to pump cement plug Keep moving drill string
Drilling to TD (+/- 2,300 mRT) Wellbore stability (above and Hole collapse and stuck pipe Drill the section w ith min mud w eight of 1.35 to 1.4 sg Mud Be ready to raise the mud w eight in case of
below the Doletrite formation) Differential sticking Maintain a good mud rheology unstable formation situation
Loss of the hole Monitor the hole condition and sw eep Hi-vis pills Minimize the lateral and vibrational shock to
w ellbore
7 6,3 1,2 52,9 High 70% 15,9 Moderate

Open Hole Logging Stuck Logging Tools Lost time (NPT) Ensure good QA-QC is applied to logging tools Perform fishing operations (normal or
Undesirable fishing operations Ensure good hole condition prior to logging operations reverse cut & thread)
3 3,1 1,2 11,2 Minor Apply best logging practices 70% 3,3 Minor

Running Casing Casing running equipment failure Lost time (NPT) due to Casing To have Casing running equipment back-up on site Sw itch to use back-up equipment
running equipment repairs 1,7 6,3 5 53,6 High immediately or perform equipment repairs as 90% 5,4 Minor
fast as possible
Running Casing Induce losses due to surge Stuck casing due to hole collapse Control running speed (run sw ab & surge simulation prior to start Reduce running speed if losses are
pressure Critical zone not covered by RIH), important in this long section. detected
Unable to reach bottom casing Perform w iper trip prior to run casing Keep w ell fluid level if losses are detected
Possible gas kick due to lost of Pump and displace Hi-vis pill after last w iper trip POOH casing to condition the hole
hydrostatic column 3 6,3 2,5 47,3 High Include fibers in Cement recepy 70% 14,2 Moderate
Cement job operation seriously
compromised

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 107 of 107
PS-2100-0549-003-E-00

16" SECTION
Scores
Success Residual
Operation Risk / Hazard Consequences Preventive Actions Mitigation Actions
Cons Expo Like Risk (%) Risk ( R )
(C) ( E) (L) ( R)
Cementing Job Losses w hile cement Level drops once cement job has To use gas tight slurry Reduce pumping rate
finished To use excess of cement according to caliper Perform Remedial Job
No good isolation achieved To add some fibers to cement slurry in case of losses w hile
Possible gas coming into the w ell running casing or w hile circulating prior to perform cement job
due to lost of hydrostatic column To re-design pumping schedule w ith low er pumping rate in case
1,7 6,3 1,2 12,9 Minor of having losses prior to start cement job 70% 3,9 Minor
To use bottom and top cement plugs method
Appling Surface Pressure if required w hile WOC.

Cementing Job Casing Float Equipment failure Lost time (NPT) due to additional Function test float valves from float equipment (Shoe and Collar) Close w ell to prevent cement flow back
WOC 1,7 6,3 1,2 12,9 Minor prior to RIH and WOC 70% 3,9 Minor
Do not overdisplace more than 50% of shoe track volume




Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 108 of 108
PS-2100-0549-003-E-00

12 1/4" SECTION
Scores
Success Residual
Operation Risk / Hazard Consequences Preventive Actions Mitigation Actions
Cons Expo Like Risk (%) Risk ( R )
(C) ( E) (L) ( R)
Drill out shoe track Premature bit damage Extra trip To drill out shoe track w ith proper parameters Replace damaged bit
Casing damage Casing and w ell integrity To drill 12 1/4" hole w ith reduced parameters until last stabilizer
7 3,1 1,2 26,0 Moderate 90% 2,6 Minor
compromised from BHA is out of the casing

Perform XLOT To induce losses Difficulties to drill ahead 12 1/4" Ensure previous casing point is set at competent formation Evaluate option to drill ahead w ith low er
Low er KT than previously section 3 6,3 5 94,5 Urgent Use best practices to perform XLOT LOT value (low er KT) 70% 28,4 Moderate
expected. Ensure pumping unit is in perfect conditions Evaluate remedial actions (LCM, cement
To loose one diameter Use fresh and light mud plug)
Drilling to TD (+/- 3,630mRT) Gas kick from Couvinan formations Well Control situation Reservoir data available (Pore Pressure / Fracture Gradient) Apply Well Control procedures
(Kick happened in AZSE-3) Lost time (NPT) Mud w eight above Pore Pressure (overbalance)
Apply best drilling and tripping practices
40 3,1 2,5 310,0 Urgent Full BOP arrangement has been placed before start drilling the 90% 31,0 Moderate
hole section.
Use of EKD System.

Drilling to TD (+/- 3,630mRT) Wellbore stability Hole collapse and stuck pipe Drill the section w ith min mud w eight of 1.60 to 1.65sg Mud To ream / backream hole if necessary to
Differential sticking Maintain a good mud rheology w ork the tight spots
Loss of the hole / diameter 7 6,3 2,5 110,3 Urgent Reduce mud filtrate Be ready to raise the mud w eight in case of 50% 55,1 High
Optimize BHA unstable formation situation
Monitor the hole condition and sw eep Hi-vis pills

Drilling to TD (+/- 3,630mRT) Build angle Correction runs The Reggane w ells w ill be drilled w ith RSS in order to maintain the Correction plan
Additional trips verticallity
Extra cost 3 6,3 2,5 47,3 High To use a locked BHA 85% 7,1 Minor
Undesirable DLS To take inclination survey at middle of the section
Apply best drilling practices

Drilling to TD (+/- 3,630mRT) Vibrations (stick & slip, lateral, Reduce Bit life Use of stiffer 9 1/2 " DC to drill the section Vary drilling parameters (WOB, RPM) to
axial) Cause damage on drill string Optimize drilling parameters to reduce vibrations (WOB and RPM) mitigate vibrations
components Motor to be considered. Trip out of hole to change out damage bit
Cause damage to Top Drive 3 6,3 2,5 47,3 High To have backup Bits on site (TCI) 60% 18,9 Moderate
Additional trips
Extra cost

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 109 of 109
PS-2100-0549-003-E-00

12 1/4" SECTION
Scores
Success Residual
Operation Risk / Hazard Consequences Preventive Actions Mitigation Actions
Cons Expo Like Risk (%) Risk ( R )
(C) ( E) (L) ( R)
Open Hole Logging Logging Tools premature failures Lost time (NPT) Ensure good QA-QC is applied to logging tools Perform fishing operations (normal or
Stuck Logging Tools Undesirable fishing operations Ensure good hole condition prior to logging operations reverse cut & thread)
LIH Logging Tools Apply best logging practices
3 6,3 2,5 47,3 High 70% 14,2 Moderate
Intermediate w iper trips to be considered
Access the possiblity of using LWD tools.

Running Casing Induce losses due to surge Stuck casing due to hole collapse Control running speed (run sw ab & surge simulation prior to start Reduce running speed if losses are
pressure Critical zone not covered by RIH), important in this long section. detected
Unable to reach bottom casing Perform w iper trip prior to run casing Keep w ell fluid level if losses are detected
Possible gas kick due to lost of 3 6,3 2,5 47,3 High Pump and displace Hi-vis pill after last w iper trip POOH casing to condition the hole. 70% 14,2 Moderate
hydrostatic column Use of Overdrive & reamer Shoe
Cement job operation seriously
compromised
Cementing Job Losses w hile cement Level drops once cement job has To use gas tight slurry Reduce pumping rate
finished To use excess of cement according to caliper Perform remedial Job
No good isolation achieved To add some fibers to cement slurry in case of losses w hile
Possible gas coming into the w ell running casing or w hile circulating prior to perform cement job
1,7 6,3 5 53,6 High 70% 16,1 Moderate
due to lost of hydrostatic column To re-design pumping schedule w ith low er pumping rate in case
of having losses prior to start cement job
Appling Surface Pressure if required w hile WOC.

Cementing Job Casing Float Equipment failure Lost time (NPT) due to additional Function test float valves from float equipment (Shoe and Collar) Close w ell to prevent cement flow back
WOC 1,7 6,3 1,2 12,9 Minor prior to RIH and WOC 70% 3,9 Minor
Do not overdisplace more than 50% of shoe track volume

Cased Hole Logging Logging Tool premature failure Lost time (NPT) Ensure good QA-QC is applied to logging tools Additional WOC to improve tool response
Accuracy of Cement Bond log Impact on the future depth Establish proper WOC period to ensure adequate tool response
Difficulties to make proper correlation for critical jobs To include PIP Tags or Pup Joints in the casing string to facilitate
3 6,3 2,5 47,3 High 70% 14,2 Moderate
correlations correlation
Run a scraper before perform IBC log.

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 110 of 110
PS-2100-0549-003-E-00

8 1/2" SECTION
Scores
Success Residual
Operation Risk / Hazard Consequences Preventive Actions Mitigation Actions
Cons Expo Like Risk (%) Risk ( R )
(C) ( E) (L) ( R)
Open Hole Logging Logging Tools premature failures Lost time (NPT) Ensure good QA-QC is applied to logging tools Perform fishing operations (normal or
Stuck Logging Tools Undesirable fishing operations Ensure good hole condition prior to logging operations reverse cut & thread)
LIH Logging Tools Apply best logging practices
3 6,3 2,5 47,3 High 70% 14,2 Moderate
Intermediate w iper trips to be considered
Access the possiblity of using LWD tools.

Running Liner Casing running equipment failure Lost time (NPT) due to casing To have Casing running equipment back-up on site Sw itch to use back-up equipment
running equipment repairs immediately or perform equipment repairs as
1,7 6,3 5 53,6 High fast as possible 90% 5,4 Minor

Running Liner Liner hanger prematurely sets Lost time (NPT) Control running speed (run sw ab & surge simulation prior to start Evaluate depth of the set against objective
inside the 9 5/8" Sidetrack the w ell RIH) depth, versus attempting to pull liner out of
Liner top packer prematurely sets Well Integrity compromised on 7 3,1 2,5 54,3 High Do not pump at higher rates than the programmed pumping rates hole 70% 16,3 Moderate
inside the 9 5/8" zonal isolation Avoid abrupt brake application w hile connecting joints Mill the hanger packer and retrieve the liner

Running Liner Induce losses due to surge Stuck casing due to hole collapse Control running speed (run sw ab & surge simulation prior to start Reduce running speed if losses are
pressure Critical zone not covered by RIH) detected
Unable to reach bottom casing Perform w iper trip prior to run casing Keep w ell fluid level if losses are detected
Possible shallow gas kick due to 3 6,3 2,5 47,3 High Pump and displace Hi-vis pill after last w iper trip POOH casing to condition the hole 70% 14,2 Moderate
lost of hydrostatic column
Cement job operation seriously
compromised
Running Liner Liner stuck (hangs-up) off bottom Sidetrack the w ell Perform w iper trip prior to run casing Rotate liner in open hole at programmed
in open hole Limited DST capacity Pump and displace Hi-Vis pill after last w iper trip scheduled rotation rates and ream if liner
reamer shoe
3 6,3 2,5 47,3 High 90% 4,7 Minor
Evaluate depth of set against objective
depth, versus attempting to pull liner out of
hole
Setting Liner Can not set the liner Lost time (NPT) Check and inspect LH hydraulic system Increase circulating rate to attempt to seat
Drift liner prior to running liner ball
Drift DP prior to POOH on last w iper trip Set liner on bottom at w ell TD
1,7 6,3 2,5 26,8 Moderate 70% 8,0 Minor
Check ball size If circulation is OK, check release of liner
Make sure that the Ball is properly install on the cement head hanger running tool and continue to
cementation
Cementing Job Losses w hile cement Level drops once cement job has To use gas tight slurry Reduce pumping rate
finished To use excess of cement according to caliper Cement Remedial Job
No good isolation achieved To add some fibers to cement slurry in case of losses w hile
Possible gas coming into the w ell 1,7 6,3 5 53,6 High running casing or w hile circulating prior to perform cement job 70% 16,1 Moderate
due to lost of hydrostatic column To re-design pumping schedule w ith low er pumping rate in case
of having losses prior to start cement job

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 111 of 111
PS-2100-0549-003-E-00

9.9. ANNEX IX Well Diagram (A3 Format)

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 112 of 112
PS-2100-0549-003-E-00

9.10. ANNEX X Offset wells
9.10.1. 24 Section Offset Experience and Information

AZSE-21
No hole Problems were reported. Apart of slow ROP observed from 320m down to section TD.
AZSE-1
No Problems were reported.
AZSE-2
Washout until 85 m due to unconsolidated sand.
Severe Bit balling.
AZSE-3ST
High Vibration during drilling this section.
Bit & Stabilizers got completely balled up.
Very Low ROP from 364 m to 398 in Namurian Formation.

Reggane-1

Shallow HC occurrence was reported.

Reggane-5
The upper section of the well was drilled with a 24 bit to a MD of 267m MDRT.
No Problems were reported.

Reggane-6
The upper section of the well was drilled with a 24 bit to 393m MDRT.
Bit and stabilizers balled up. Also losses were experienced. Not reported severity.
The 24 section was then cased (18-" Casing) without any problems.
No shallow gas encountered.
Reggane-7
The 24 hole 18 Casing section was drilled to a section TD of 281 m MDRT
No Operational problems were reported.
Reggane-8
The 24 hole 18 Casing section was drilled to a section TD of 245 m MDRT
No Operational problems were reported.
Reggane-16
The 24 hole 18 Casing section was drilled to a section TD of 345 m MDRT

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 113 of 113
PS-2100-0549-003-E-00

No Operational problems were reported.

9.10.2. 16 Section Offset Experience and Information


The main difference versus the offset wells the Dolerite will be drilled in the 16 hole section and the TD
of this section is most deepest well among the other offset wells. Other than that, tight hole and
deviation issues were predominant in all the offset wells.
AZSE-21
High Torque & Vibration during drilling this section.
Partial & total losses encountered in AZSE-21 where LCM Pills and Thixotropic Cement plug were
required to cure losses.

Very low ROP in Dolerite & Strunian formation (Quartzitic Sandstone).

7 bits (TCI & PDC) were required to drill the 16 section.

AZSE-1
Fluid losses from 599 to 770m (150-600 l/hrs).
AZSE-2
Formation Breakout and having ledges in many interval which leaded to difficult Tubular running..
Tight Spots in many intervals.
Seepages losses were associated to fractured limestone.
AZSE-3ST
High Torque & Vibration during drilling this section.
At 619m a 6.5 % gas peak with some traces of CO2 was observed.
Losses have encountered in this section: Avagraph seal was used from +/- 1000 m to tackle the losses
Reggane-5
17-1/2 hole section was drilled from 267 to 1175 m through Carboniferous formations. Shoe was set in
Visean A. Several tight hole, overpull and stuck pipe incidents were reported. Necessary to back ream
several times and increase the MW to 1.18sg.
No dolerite was found in this section. Av ROP 7 m/hr. 1 bit run. See 12.25 section for more
information about dolerites.
Reggane-6
16 hole section was drilled from 470 to 1540 m through Carboniferous formations. Shoe was set in
Visean A. No operational issues reported.
No dolerite was found in this section. Av ROP 5.5 m/hr. 2 bit runs.
Reggane-7
16 hole section was drilled from 282 m to 1182 m through Carboniferous formations. Shoe was set in
Tournasian. No operational issues reported.
No dolerite was found in this section. Av ROP 15 m/hr. 1 bit run.

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 114 of 114
PS-2100-0549-003-E-00

Reggane-8
16 hole section was drilled from 245 m to 1251 m through Carboniferous formations. Shoe was set in
Famennian. No operational issues reported.
Two main layers of Dolerite were found in RG-8. Both in 16 section
Dolerite #1 (735 863 m) A PDC with 6 blades 19 mm was used to drill the top part of the
section, once dolerite was identified the bit was pulled to preserve bit life as this bit was too
aggressive to drill any kind of dolerite.2 runs were required to drill it. Both using same TCI, NOV
T52 (IADC 525). 1st run 1.6 m/hr and 2nd run 1.47m
Dolerite #2(1185-1251m). Drilled with same bit as previous formation, Varel R716 DGHX PDC 7
blades 16 mm cutters. Cuttings comparison showed 1st dolerite much harder than 2nd dolerite.
ROP in dolerites: 5m/h
Reggane-16
16 hole section was drilled from 345 to 1843 m through Carboniferous formations.
A long section of Visean formations was drilled with PDC 7 blades 16 mm cutters with average ROP of
15 m/hr,( excluding controlled ROP). Caving has encountered around the dolerite formation.

9.10.3. 12 Section Offset Experience and Information

AZSE-21
Encountered tight spots, overpull and had to back reaming many intervals.

Traces of caving while drilling 12.25 section started 2475 m to section TD.
Had to pull out of the hole in most of the trips.
AZSE-1
No Problems were reported.
AZSE-2
Formation Breakout and caving have encountered around the Dolerite layers.
AZSE-3ST
High Torque & Vibration during drilling this section.
Losses have encountered in Tournsian FM at 20m3/hr and then reduced to 10m3/hr by reducing the
flow rate pumping 7m3 of 200kg/m3 LCM Pill.
A kick was occurred from Emsian. Gained 23m3, followed by lost circulation and underground blow out.
Plugged back and ten sidetrack was carried out. More details will be delivered from AZSE-3 Well
Control Report.
Reggane-5
12- hole section was drilled from 1175 m to 3183 m Devonian formations. Shoe was set inside
Givetian formation. Several tight hole incidents observed. Had to ream/back ream several intervals.
Two main dolerite layers were found in this section:
1305-1390m with and av ROP of 2.3 m/h 2 bits

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 115 of 115
PS-2100-0549-003-E-00

1743-1790m. with and av ROP of 1.0 m/h - 2 bits
Total of 12 bits were required. For non-dolerite formations the average ROP was 2.9m/h
Reggane-6
12- hole section was drilled from 1540 m to 3665m through Devonian formations. Shoe was set in
Couvinian. Several tight hole incidents observed. Had to ream/back ream several intervals, especially
experienced in dolerites.
Two main dolerite layers were found in this section:
1780-1890m with and av ROP of 1.35 m/h 3 bits
2285-2335m. with and av ROP of 0.94 m/h - 2 bits
Total of 8 bits were required for the section. For non-dolerite formations the average ROP was 8.6m/h
Reggane-7
12- hole section was drilled from 1182m to 3162m through Devonian formations. Shoe was set in
Couvinian.. The biggest issue was the deviation of the well trajectory.
Two main dolerite layers were found in this section:
1255-1340m with and av ROP of 1.77 m/h 4 bits
1755-1800m. with and av ROP of 4.12 m/h - 2 bits
Total of 7 bits were required for the section. For non-dolerite formations the average ROP was 9.6m/h
Reggane-8
12- hole section was drilled from 1251m to 2758m drilling the same formations as the ones to be
drilled in RG-16. No major issues were reported with neither inclination nor ROP performance. No
dolerite was found though whereas in RG-16 27m are expected.
The section was drilled with a PDC 7 blades 16mm. 2 bits were required. In Famenian the average ROP
was 15m/hr. In frasnian formation the ROP dropped to 6m/h at the top and 1.8m at the bottom. In
Givetian, Couvinian and Emsian, the ROP was around 1.7m/hr.
Reggane-16
12- hole section was drilled from 1840 m to 2516 m through Famenian formation. One layer of
dolerites was drilled from 2065 m to 2119 m. This section could be finished to the planned TD due to
hole instability. Consequently 9 5/8 casing was run prematurely and also not to the drilled TD. Total
almost 15.5 days as NPT for hole instability.
The main lesson learnt is to take into the formation collapse pressure refer to Geo-mechanical study,
wiper trips is recommended to anticipate any potential hole instability and ledges above Dolerite
formation. It was related to a geomechanical issue by not having the required minimum mud weight.

9.10.4. 8 Section Offset Experience and Information


AZSE-21
Very slow ROP especially in GED A.

Encountered hole instability prior/during the 7 CSG cementing Job

AZSE-1

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 116 of 116
PS-2100-0549-003-E-00

Fluid losses while cutting cores.
AZSE-2
This interval was drilled in 6 hole in AZSE-2 and no major issue reported apart of low ROP.
AZSE-3ST
This interval was drilled in 6 hole in AZSE-3ST and no major issue reported.
Hoe deviation of 13.5 at 3,875m.
Reggane-5
8 hole section was drilled from 3183 to 4202 m through Devonian and Silurian formations. Shoe was
set in Ordovicean. No dolerite encountered.
Very low ROP experienced (Av section ROP: 3.1 m/h). 12 bits were required to drill the section. One of
them lost a cone.
Note RG-5 well was finished in 6 hole but RG-16 will not drill those formations
Reggane-6
8 hole section was drilled from 3665 to 4633 m through Devonian and Silurian formations. Shoe was
set in Ordovicean. No dolerite encountered.
Problems trying to keep verticality.
Cavings reported in Emsian. Special caution to be taken in Emsian formation, during the exploration
phase 2x kicks were taken in this formation.
Very low ROP experienced (average section ROP: 3.4 m/h). 10 bits were required to drill the section.
Covinian formations seemed to be a bit softer but Emsian, Siegenian and Gedinnian are extremely
hard.
Note RG-6 well was finished in 6 hole but RG-16 will not drill those formations (Hamra Quartzites).
Reggane-7
8- hole section was drilled from 3162m to 3552m through Devonian and Silurian formations. Shoe
was set in Gothlandian. The biggest issue was the difficulties trying to keep the well vertical.
Very low ROP experienced (average section ROP: 1.9 m/h). 9 bits were required to drill the section.
Reggane-8
8- hole section was drilled from 2758m to 3040m through Devonian and Silurian formations. Not
extreme issues observed. Hard formation in reservoirs (silicified sandstones). The ROP throughout the
reservoirs was controlled max to 5m/h.
2x bits were required. First was a 7 blade 13mm which drilled 148 at 2.4 m/h and then a new PDC 8
blades 13 mm was run to complete the section. The Gedinnian formations were dilled at around 5m/hr
and the Silurian at +6 m/hr.
Reggane-16
This section is being drilled in 6 hole without any issue. However it is building angle up to 24 due to
formation dip and not using ATK.

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 117 of 117
PS-2100-0549-003-E-00

9.11. ANNEX XI Drilling Jar Change out recommendations

Groupement Reggane

Reggane Nord Development Project Confidential

Document Number Drilling Program Azrafil South East-4 Well Page 118 of 118
PS-2100-0549-003-E-00














Thispagehasbeenleftblankintentionally