DAILY ACTIVITY REPORT (MECHANICAL- C

SL NO. PACKAGE EQUIPMENT CENTRE

PRIMARY CRUSHER/COAL SHED

TRANSFER HOUSE 1

TRANSFER TOWER 2

CONVEYOR 1A & 1B

1 CHP
CONVEYOR 2A &2B
CONVEYOR 3A &3B

CONVEYOR 4A & 4B

CONVEYOR 5A & 5B

SECONDARY CRUSHER HOUSE

BOILER -I

STRUCTURAL

PRESSURE PART
ROTATING EQUIPMENTS

HOT AIR PATH

COLD AIR PATH


FLUE GAS PATH

FUEL PATH

INSULATION

ESP

BOILER -II

STRUCTURAL

PRESSURE PART

2 BOILER & ESP

ROTATING EQUIPMENTS
HOT AIR DUCTING

COLD AIR DUCTING

FLUE GAS DUCTING

FUEL PATH

INSULATION

ESP
RAW WATER PUMP HOUSE

CLARIFIED WATER PUMP HOUSE

CW AND ACW PUMP HOUSE

UTILITY WATER PUMP HOUSE

COMPRESSOR HOUSE

3 LP PIPING
FIRE FIGHTING SYSTEM

LDO SYSTEM
PIPE RACK

FABRICATION &ERECTION OF
PIPING

FANS ,GEAR BOXES,PROPELLER


SHAFT & STRUCTURALS

COOLING
4 DISTRIBUTION PIPE LINES
TOWER
DRIFT ELIMINATORS & SPLASH
GUARDS

DECK RAILING WORK.

STRUCTURAL

TURBINE

TURBOGENERATOR
CONDENSER

AUXILLARIES
5 TG BUILDING

FABRICATION &ERECTION OF
PIPING

LUBE OIL SYSTEM

AC DUCTING WORK

STRUCTURAL

ERECTION OF EMBEDED PLATES &


OPENING
6 ASH SILO
ASH HANDLING EQUIPMENT

ASH TRANFER PIPE LINE


STRUCTURAL

EQUIPMENT ERECTION
WATER
7 TREATMENT
PLANT
FABRICATION &ERECTION OF
PIPING

CHEMICAL HOUSE

WATER RESERVOIR
MANPOWER DETAILS
SL NO CONTRACTOR MANPOWER
GIRI
1 CONSTRUCTIONS 26
(HAZEMAG)
2 THERMAX 262
3 GPR 20
4 APT 15
5 SUVENDU SAHU 6
JOSEPH
6 6
CONSTRUCTIONS
EPORT (MECHANICAL- CPP) DATE-02.09.13
PLANNED FOR
ACTIVITY AT SITE TOMORROW

Vertical bracing erection & welding in


progress.Balance rafter bracings which Same to continue
reached site on29/8/13 are being fitted in
position.

Side Sheeting work & final welding in


progress Same to continue

Materials from harimachines received at


site & materials to be unloaded.

No activity

Alignment & Welding of walkway is in


progress. Erection of gallery completed. Same to continue
Alignment of Gallery is in progress.
No activity

Levelling of ramp for trussel erection


completed. Final welding of trussel TR-6 is shifting ofposition.
trussel TR-6 to its
under progress.

Materials from harimachines received at


site & unloading is in progress.

No activity

All fabrication scraps being


cut for use &house keeping
Final painting work in progress. work to continue. Painting
work to continue.

No activity Same to continue


Completed

Completed

Completed
No activity

Completed

Insulation work of outlet nozzle of ESP- Same to continue


1 ,Economiser duct & MDC is in progress.

No activity

Final painting work in progress. Final


welding of connecting beams between Same to continue
Boiler-1 & Boiler-2 is in progress.

Internal Hydro test completed


succesfully.External hydrotest to Same to continue
start.Erection & final welding of non
integral piping support in progress.

Erection of ID Fan completed & alignment


is in progress. ID fan foundation Same to continue
modification in progress & foundation
work for PA & SA FAN in progress.
Bed ash cooler outlet duct pre assembly is
in progress. Fabrication work of SA fan Same to continue
delivery line in progress

Erection & welding of secondary air duct Same to continue


fitting work in progress .

Welding work at ID FAN ducting in


progress. Welding & Erection of
economiser casing in progress.Connecting Same to continue
duct from boiler to economiser work in
progress.

MDC welding in progress. Erection &


welding of MDC Bypass to ash seperator Same to continue
is in progress.

No activity

Emitting electrode erection in progress.


Pre assembly & welding of 1st,3rd fields Same to continue
Hopper taken up.
clearing of raw water pump
Pipe assembly & welding is in progress. house area for starting of
vertical pump erection.

Erection of purlin & sag rods completed. Same to continue


Side sheeting work continuing.

Erection of side runner completed & Roof Same to continue


sheeting work is in progress.

No activity as monitoring basin work yet


to start.

No activity

Fire fighting pumps have reached


transporters Godown.GPR informed and
freight clearance by GPR is awaited

Clearing of the Cooling


No activity Tower materials for
foundation layout to start.
Fabrication of remaining pipe racks Erection of pipe rack.
completed & painting work is in progress.

Fabrication of pipe supports for CW


Pump inlet is in progress. Erection of Same to continue
1400mm cooling water pipe near TG
building is in progress

No activity No activity

No activity No activity

No activity No activity

No activity

Final welding is in progress.Fixing of Same to continue


chequered plates for steps is in progress .

No activity

No activity
Expansion work of tube end is in progress
& welding of vaccume pipes to condenser Same to continue
is in progress.

Positioning & alignment of condensate Same to continue


float tank is under process.

Fabrication of boiler feed pump delivery No activity


line in progress.

Fabrication & erection of lube oil pipe line


is in progress. Same to continue

Insulation work of 10.5 M control room


roof completed.Erection of AC duct & Same to continue
rapping of insulation is in progress.

Final welding & fixing of gratings work is Same to continue


in progress.

No activity No activity

No activity

No activity
Completed

No activity No activity

DM Water production for Boiler -2


external hydro test.

Erection of purlins taken up & is in Same to continue


progress.
No activity
02.09.13
REMARK

Hoppers, railings & chutes for


feeder breaker awaited at site.
Party has been followed up.

All materials received at site

Follow up on for Short Post and


stringers for inclined ramp.
Civil foundation work yet to be
completed

Trussel fabrication completed &


gallery to be received.party not
despatching further materials
despite of repeated reminders.
Rigorous followup required as
party is not able to provide any
evidence of work in progress.

Civil work yet to be completed


Balance Erection work awaiting
completion of fan foundation.

Insulation work to start after


hydro test.
Plastering work of Raw water
pump house is in progress which
will be completed by 5/9/13,and
pump erection work shall start.

Follow up on for cables & conduits


of fire sensors at TG Building
10.5M control room roof.

Civil foundation work to


start.fabricated tank awaited at
site
1400 dia. Pipes awaited at site.
Follow up is on.

Civil work yet to be completed &


mobilisation to be started by
Paltech

same as above

same as above
All other available equipments
have been placed in position.

IBR Approval awaited

Materials indented for supply of


cooling water to A.C.Units
Erection of remaining small pumps
to be taken up during erection of
panels