EPS ID: LEC EPS Name: Libyan Engineers Company

EPS ID: LEC 2 EPS Name:Tripoli

Currency used: Libyan Dinar Currency Id: LYD Conversion Rate: 0.75USD

Units of Measure: Kg Kilogram

Bag Number of Bags

Items Numbet of Items

M Meter

Project name: Complete Infrastructure Project

1. Project start date: 09-03-2010


2. Project finish date:

Calendars:

1) Libyan calender with 6 workday’s week, holidays inclusive.

Budget:

1) Original Budget: LYD. 10,00,000


2) Estimated Budget: LYD. 8,00,000

Work Breakdown Structure (WBS):

1.1 Master Plaaning

1.2 Design

1.3 Mobilised Design team

1.4 Final Design

1.5 Design support during Construction

1.6 Construction of complete infrastructure


1.7 Quality control plan

1.8 Mobilization Plan

1.9 Staffing Plan

1.10Procurement Plan

WBS ID Activities Predecessor Activities name Number of Days


ID

1.1 A3410 (A) ------- Surveying network correction 00


1.2 A1200(B) A3410(A) Intial Design 25
1.2 A1210(C) A1200(B) Design observation 12
1.2 A1211(D) A1210(C) Redesign for sewer drainage 09
Drawings
1.2 A1212(E) A1211(D) Redesign for water Drawings 09
1.2 A1213(F) A1212(E) Redesign for Road Drawings 09
1.2 A1214(G) A3140 (A) Approval for sewer Drawings 04
1.2 A1224(H) A3410(A) Approval for Water Drawings 04
1.2 A1234(I) A3410(A) Approval for Road Drawings 05
1.2 A1830(J) A1234 (I) Design for Pump station 07
1.3 A1020(K) A1830(J) Start Design work 00
1.4 A1060(L) A1830(J) Complete Design Work 00
1.5 A1220(M) A1210(C) Preparation of Shop drawings and 11
sample submission
1.5 A1230(N) A1220 (M) Review of Shop Drawiings & 07
Samples
1.6 A1070(O) A1060 (L) Construction start date 00
1.6 A1320(P) A1070(O) Quality Plan 17
1.7 A1310(Q) A1070 (O) Safety Plan 17
1.7 A1330(R) A1070 (O) Night Lighting 17
1.8 A1250(S) A1330 (R) Environmental 14
1.8 A1260(T) A1070 (O) Cutting Tree 14
1.8 A1270(U) A1250(S) Expropriation, Compensatuon and 14
Attorney
1.8 A1280(V) A1270(U) Dewatering 14
1.8 A1300(W) A1280(V) Methods of Construction 16
1.9 A1290(X) A1300(W) List of Subcontractors 16
1.10 A1360(Y) A1070(O) Concrete 16
1.10 A1370(Z) A1070(O) Structural steel 16
1.10 A1380(1) A1070(O) Asphalt, Bitumin and Additives 16
1.10 A1385(2) A1070(O) Horizontal Marking and Road 16
Signs
1.10 A1390(3) A1385(2) Pipes And Valves 16
1.10 A1400(4) A1390 Electical 16
1.10 A1410(5) A1400 Telecommunication 16
1.10 A1420(6) A1410 Precast Concrete Cubes- 35
Production

Resources:

Resource Id Resource Name Price/unit


1 Mason Lyd. 20/d
2 Engineer Lyd.1500/m
3 Administrator Lyd.2000/m
4 Accountants Lyd.700/m
5 Secretaries Lyd.350/m
6 Technicians Lyd.600/m
7 Drivers Lyd.500/m
8 Cook Lyd.400/m
9 Cleaners Lyd.200/m
10 Rent Lyd.1200/m
11 Fuel Lyd.300/m
12 Office Equipment Lyd.3000/m
13 Foodstuff Lyd.1000/m
14 Insurance Lyd.500/m
15 Spareparts Lyd.80/m
16 Miscellaneous Lyd.300/m
17 Taxes Lyd.500/m
18 Helper Lyd.10/d
19 Plumber Lyd.20/d
20 Electrician Lyd.50/d
21 Cement Lyd.9.5/bag
22 Steel Lyd.1/Kg
23 Sanitary items Lyd.70/item

1) Determine the Critical Path Method (CPM)?


2) Determine the Total Budgeted Cost?
3) Prepare the Gantt chart.
4) Estimate Project Finish Date?

AB C IGH DA E F