Existing Structure Proposed For Proposing Structure

Page no of Chainage as Chainage as Design


S.no
Schdule B per old Dpr per Site Chainage
Type Size Type

KM 12+000 - 13+000

1 Span of 8.00 C/C


B-19 12+538 12+491 12+450 Slab Culvert Widening Slab Culvert
(Skew)

B-17 12+705 12+667 12+618 HPC 2X900mm Reconstruction Box Culvert

B-18 12+934 12+887 12+845 HPC 2X900mm Reconstruction HPC

KM 13+000 - 14+000

13+270 13+270 13+252 HPC 1x1000mm Widening HPC

1 span of 6.00
B-17 13+351 13+310 13+262 Slab Culvert Reconstruction Box Culvert
C/C(Skew)

2 Spans of 5.50m
B-22 13+537 13+584 13+626 Minor Bridge Widening Minor Bridge
C/C (Skew)

KM 14+000 - 15+000

B-20 New New 14+210 New New New Box Culvert

B-17 14+927 14+870 14+827 HPC 2x1100mm Reconstruction Box Culvert

KM 15+000 - 16+000

B-17 15+930 15+878 15+830 HPC 1x1200mm Reconstruction Box Culvert

KM 16+000 - 17+000
Proposed structure as
B-19 16+230 16+138 No Structure Identified HPC
per Schedule B

B-18 16+626 16+575 16+525 Slab Culvert 4x3x2m Reconstruction Box Culvert

B-19 16+880 16+825 16+778 HPC 1x900mm Widening HPC

KM 17+000 - 18+000

T-Beam
B21 17+695 17+645 17+597 Minor Bridge 3x7.5m Reconstruction Bridge

KM 18+000 - 19+000

B-20 New New 18+140 New New New Box Culvert

1 Span of 10.00m T-Beam


B-21 18+374 18+325 18+275 Minor Bridge Reconstruction
C/C Bridge

B-18 18+847 18+800 18+745 HPC 1x900mm Reconstruction HPC

B-18 18+940 18+890 18+838 HPC 2x900mm Reconstruction Box Culvert

KM 19+000 - 20+000

B-18 19+180 19+125 19+080 HPC 1x900mm Reconstruction HPC

B-19 19+330 19+280 19+230 HPC 1x900mm Widening HPC

B-18 19+461 19+410 19+360 HPC 1x900mm Reconstruction HPC

B-18 19+599 19+545 19+497 HPC 1x900mm Reconstruction HPC

B-18 19+731 19+680 19+629 HPC 1x900mm Reconstruction Box Culvert

B-20 New New 19+810 New New New HPC


Proposed structure as
B-19 20+069 19+975 No Structure Identified HPC
per Schedule B

KM 20+000 - 21+000

B-18 20+380 20+335 20+273 HPC 2x1000mm Reconstruction Box Culvert

Single Cell 4 Spans


B-19 20+825 20+785 20+721 Box Culvert Widening Box Culvert
3.00x2.00m

Proposed structure as
B-19 20+835 20+795 20+731 No Structure Identified HPC
per Schedule B

KM 21+000 - 22+000

B-20 New New 21+520 New New New Box Culvert


Proposing Structure

Size

Single Span 5m
(effective)

Single cell 3x2m

2x1200mm

1x1000mm

Single cell 4x3m

2 span of 5.5m

Single cell 3x2.25m

Single cell 3x3m

Single cell 3x2.5


2x1100mm

Single cell 3.7x3m

1x1000mm

Single Span of 21m

Single cell 3x2.25m

Single span of 8.00

1x1200mm

Single cell 3x2.5m

1x1200mm

2x1200mm

1x1200mm

1x1200mm

Single cell 3x2.5m

1x1200mm
1x1000mm

Single cell 3x2.5m

Single cell 4x3m

2x1000mm

Single cell 3x2.5m