Documente Academic
Documente Profesional
Documente Cultură
Black cotton soil has a tendency to shrink and swell excessively. When these type of soil come in
contact with water, they swell and when becomes dry, it shrinks. This alternate process of swelling
and shrinking results in the differential settlement of foundation which in turn causes cracks in
building. The cracks thus formed are sometimes 15 to 20 cm wide and 2.5 to 4.5 m deep.
Therefore necessary precautions need to be taken during construction to avoid any damage to
building foundation.
Following precaution should be employed during construction on black cotton soil.
In designing footings on these solis, the following points should be keept in mind:
1. The safe bearing capacity should be properly determined, taking into account Ihe effect of
susained loading. The long term effect of loading results in slow consolidation. In absence of tests,
the bearing capacity of these soils may be limited to 5 to 10 t/m2.
2. The foundation should be taken at Ieast 50 cm lower than the depth of moisture movement. This
depth should also be much more than depth of tension cracks.
3. Where this soil occurs only in top layer, and where the thickness of this layer does fol exceed 1 to
1.5 m, the entire layer of black cotton soil (or other expansive soil) should be removed, and the
foundation should be laid on non-shrinkable non- expansive soil.
4. Where the depth of clay layer is large, the foundation or footing should be prevented from
coming in contact with the soil. This can be done by excavating wider and deeper foundation trench
and interposing layer of sand/mooram around and beneath the footing.
5. Where the soil is highly expansive, it is very essential to have minimum contact between the soil
and the footing. This can be best achieved by transmitting the loads through deep piles or piers and
by supporting wall loads on capping beams which are kept some distance (5 to 15 cm) above the
ground surface, to permit free expansion of the soil.
6. Where the bearing capacity of soil is poor, or soil is very soft, the bed of the foundation trench
should be made firm or hard by ramming mooram and ballast mio it.
7. The foundations should be constructed during dry season. Also suilable plinth protection around
the external wall should be made on the ground surface, with its slope away from the wall, so that
moisture does not penetrate the foundation during rainy season.
2. Pier foundation :- Pier foundation used in black coton soil for a wall carrying heavy loads. Piers
are dug at regular interval and filled with cement concrete. The piers may rest on good bearing
strata.
3. Under-reamed pile foundation. An under-reamed pile is a pile of shallow depth (1 to 6 m)
having one bulb a its lower end. If this bulb is taken or provided at a level lower than the critical
depth of moisture movement in expansive solis.
Precautions to be Taken
1. The maximum load on black cotton soil should be limited to 5 tonnes/m2. If there is a
chance for water to come in contact with foundation, then the load should be limited to 4.9
tonnes/m2.
2. Foundation should be placed at a depth where the cracks cease to extend. The minimum
depth of foundation should be at least 1.5 m.
3. The main wall of the building must be provided with all round reinforced concrete ties or
bands.
4. Reinforced concrete ties or bands having 10 to 15 cm deep should be placed at plinth
level, lintel level and eaves level.
5. In case the depth of black cotton soil is only 1 m to 1.5 m, then completely remove the entire
black cotton soil and place the foundation below that depth.
6. Try to avoid direct contact of black cotton soil with foundation material. This can be
achieved by making wider trenches for foundation and filling spaces on either side of the
foundation masonry with sand or morroum.
7. Ram the bed of the foundation trench to make it farm and hard. On this rammed bed, spread
a thick layer of morroum (i.e. 30 cm) in two layers, each layer being 15 cm. each layer
should be water and rammed properly to get highest possible density. On this compacted
layer of morroum, place either sand or stone upto desired height where concrete foundation
bed has to be made.
8. In case of important structures, raft foundation should be provided.
9. For less important structures (such as boundary wall construction), the foundation should
preferably taken at least 15 cm below the depth at which cracks in soil cease to occur.
10.Construction should be done in dry season.
11.For main walls or for load bearing walls, the width of the trench should be dug 40 cm wider
than width of foundation. Then fill the space on either side of the trench (i.e. 20 cm in each
side) with coarse sand. This is done to separate the foundation masonry from direct contact
with black cotton soil. In case of compound wall this width of sand filling can be reduced to
15 cm on each side.
12.Under reamed pile foundation is also a good choice of foundation in black cotton soil.