Documente Academic
Documente Profesional
Documente Cultură
• The implications of routes located on ridge tops, valley floors (including flood
plain routes), valley sides and flat to rolling terrain (see discussion in Chapter 5)
• The location of major bridges as potential fixed points in route selection
• Anticipated levels of flooding, scour and sediment accretion where these factors
control feasibility and significantly influence route option cost comparisons.
The ERA Drainage Design and Bridge Design Manuals both contain relevant information
and should be consulted as appropriate.
Figure 7-1 V-Shaped Valley Without Figure 7-2 River Terraces Permit Route
Flood Plain Terraces Location in the Foreground
• the extreme flood level and the level of the road needed to avoid being flooded
• the migration of meanders which can outflank bridges or erode embankments and
side slopes (Figure 7-4)
• the potential for tributary fans to:
o impact river crossings and embankments
o divert floodwaters in the main river against the opposite valley side, causing
scour (Figure 7-5)
o temporarily block or partially block flood plains, thus causing upstream
flooding
• the potential for loss of flood plain storage or conveyance, due to:
o the effect of tributary fans (above)
o the volume loss caused by the presence of an embankment ‘footprint’, or
o the ‘sterilisation’ of flood plain storage that has become cut off from the
river by an embankment.
The route will need to be located at a level that avoids flooding, typically above the flood
event with an annual exceedance probability of 1%, the 1 in 100 year return period flood.
The height and size of embankment required to achieve this will need to be included in the
cost comparisons between route options, as will the requirements for scour protection of
road embankments and associated drainage structures. It is recommended that, wherever
possible, flood plains are avoided when identifying and selecting route options as they can
pose significant risk to engineering structures. Figure 7-6 illustrates a fairly extreme
example where the entire valley floor is occupied by active flood plains and associated
potential flood and scour effects.
Figure 7-5 Tributary Fan Pushes the Blue Nile against its Opposite Bank
channel is now eroding the toe of the approach embankment and failure can be seen on the
embankment slope.
If maps or images are available from different dates it may
may be possible to see how rapidly
the meanders are moving. Meander progression can require extensive river training at
bridges or erosion protection at the toe of embankments or both, and is thus an important
consideration for route selection.
Figure 7-9
9 Meander Migration and Cut-Off
Accretion can also be a problem for bridges and embankments located on flood plains.
Figure 7-10
10 shows a bridge in Ethiopia where accretion has almost filled the waterway
opening in the intervening 60 to 70 years.
channel protection works for considerable distances above, and particularly below, a road
in order to ensure long-term
term stability.
The preferred location for a bridge is over a straight, stable reach of the river with a single
channel and erosion resistant materials on which to found the abutments. However, such
combined conditions are rarely encountered and the best available site is selected based on
the following factors:
• channel stability
• channel width
• potential for scour.
A stable channel will require less training works to ensure the watercourse flows through
the waterway efficiently. Within an otherwise unstable channel there may be locations that
are more stable. The reason may be obvious, for example where a rock outcrop provides
natural river training, or less obvious, for example where underlying changes in geology
control the channel geometry. Such locations are likely to be preferred if they can be
found. Alternatively, locations where the channel is situated against a stable valley side
may be more suitable than where the channel is free to shift.
Usually the most significant factor in the cost of a bridge is its span. For that reason a
single narrow channel is preferred as a crossing location to either a broader channel or a
reach where there are multiple channels. Training the river to reduce the width or number
of channels is possible but is likely to be costly and probably ineffective in the long-term.
Similarly, a location where the route crosses a river at right angles will minimise the skew
and hence the length and cost of the bridge. Realigning the river to suit the road alignment
may be possible, but again it is likely to need costly river training works.
Scour at bridges may be exacerbated by a variety of factors, and these should be avoided
where possible:
• Severe scour can occur at the confluence of two streams. It can also be difficult to
estimate extreme flood flows and hence flood levels at such locations. The reaches
upstream and downstream of any confluence should be avoided if possible.
• Scour and bank erosion will occur at bends. They should be avoided unless the
outside of the bend is an erosion resistant valley side.
• Bridge piers cause local scour, so a location that does not need any piers in the river
channel is preferred over a location where piers are required.
• Existing structures, such as an earlier bridge, will alter the channel hydraulics. If
two bridges have to be located close together, their effects on each other will need
to be considered and may require uneconomic spans to be selected to minimise the
interaction of scour effects.
For larger bridges, a preliminary estimate of flood flows will usually be needed at route
selection stage to improve the accuracy of estimation of both the waterway required and
potential for scour, particularly if these factors are considered likely to have a significant
effect on the overall cost estimate for each route option. This preliminary estimate should
be based on readily available information such as catchment characteristics and design
rainfall. Any flow estimate should be compared with data from a physical inspection of
the potential bridge location, to check that the estimate looks reasonable.
Further information on the location of bridges, including requirements for minimum
freeboard above design flood level, can be found in the ERA Bridge Design Manual.
River flow data can be obtained from the Ministry of Water and Energy Resources. The
usefulness of rainfall and flow data at route selection stage will vary according to each
project. As a minimum it is recommended that this data is reviewed to identify any
hydrological constraints on route selection and any requirements for major investments to
accommodate drainage patterns and anticipated flood events.