20171228-5223 FERC PDF (Unofficial) 12/28/2017 3:04:31 PM

One Blue Hill Plaza, 7th Floor


Post Office Box 1565
Pearl River, NY 10965
845.620.1300 Voice | 845.620.1320 Fax

December 28, 2017

Ms. Kimberly D. Bose, Secretary


Federal Energy Regulatory Commission
888 First Street, N.E.
Washington, D.C. 20426

Re: Millennium Pipeline Company, L.L.C., Docket No. CP16-17-000


Valley Lateral Project
Supplement #1 to the Bi-Weekly Status Report #26
Period Ending December 27, 2017

Dear Ms. Bose:

On November 9, 2016 the Federal Energy Regulatory Commission (“Commission” or


“FERC”) issued an Order Denying Motion to Dismiss and Issuing Certificate (“Order”) for
Millennium Pipeline Company, L.L.C.’s (“Millennium”) Valley Lateral Project (“Project”).1
Pursuant to Environmental Condition No. 8 in Appendix B of the Order, Millennium hereby
submits for filing supplement #1 to the bi-weekly construction progress report for the reporting
period ending December 27, 2017.

If you have any questions regarding this filing, please contact me at 845-620-1300.

Respectfully submitted,

/s/ Bruce Page

Bruce Page
Director–Operations, Engineering, Project Management
Millennium Pipeline Company, L.L.C.

cc: Anthony Rana, FERC

Enclosure

1
Millennium Pipeline Co., L.L.C., 157 FERC ¶ 61,096 (2016).

www.millenniumpipeline.com
20171228-5223 FERC PDF (Unofficial) 12/28/2017 3:04:31 PM

VALLEY LATERAL PROJECT


STATUS REPORT
Period Ending: December 27, 2017 Report #26—Supplement 1

For the Period of December 20, 2017 through December 27, 2017

PROJECT SUMMARY:
Construction Activities During Reporting Period
 Tree Felling: Entire ROW tree felling by hand is 99.5% complete except at MP 0.69

 Access roads and access pads: Access Road TRO-007 is top soiled

 Grubbing: Is complete from MP 5 to MP 5.66

 Eagle Nest Monitoring:


Millennium has completed pipeline construction activities in the vicinity of the unoccupied
bald eagle’s nest located near MP 5.3 of the Project right of way. Prior to construction,
Millennium’s bald eagle biologist periodically inspected the nest. During the time period in
which construction activities occur in this area, Millennium has had and will continue to have
a bald eagle biologist on site. No nesting or breeding activities were observed by the bald
eagle biologist during this reporting period. Daily bald eagle monitoring reports for this
reporting period are attached.
 Grading: ROW grading is complete from MP 5.32 to MP 5.66
 Stringing: Pipe is strung from MP 5.32 to MP 5.58
 Welding: Welding is complete from MP 5.32 to MP 5.58
 Trenching: Trenching is complete from MP 5.32 to MP 5.58
 Backfill: Backfilling is complete from MP 5.32 to MP-5.58
 Restoration: complete from MP 5.32 to MP 5.46
 Bore of wetland W-V at MP 5.3 is 100% Complete.

Notices to Proceed and Variances


 On October 27, 2017 the Commission granted Millennium’s Request to proceed with
construction for all portions of the Project.
 Millennium filed a Request for Variance to add the Milford Yard as an additional Project
pipe/contractor yard during construction with the Commission on December 11, 2017, which
was granted on December 20, 2017.

Environmental Training
 Construction Environmental Training was completed on 11/28/2017.

www.millenniumpipeline.com

1
20171228-5223 FERC PDF (Unofficial) 12/28/2017 3:04:31 PM

VALLEY LATERAL PROJECT


STATUS REPORT
Period Ending: December 27, 2017 Report #26—Supplement 1

For the Period of December 20, 2017 through December 27, 2017

Update on Federal Authorizations


 Millennium has received all authorizations required under federal law.
 On December 7, 2017, the U.S. Court of Appeals for the Second Circuit denied a request
from the New York State Department of Environmental Conservation to stay construction of
the Project and dissolved the administrative stay it had put in place allowing construction to
proceed.
 On December 15, 2017, the Second Circuit denied a separate request by Sarah E. Burns,
Amanda King, Melody Brunn and Brunn Living Trust, Pramilla Malick, and Protect Orange
County for an emergency stay to stop construction activity in the vicinity of the bald eagle
nest.

Planned Construction Activities During Next Reporting Period


 Complete restoration from MP 5.46 to MP 5.56. Install safety fencing in Bald eagle effected
zone with signage of no access. After 12/31/2017 there will be no access between MP 5.34
to MP 5.56.
 Start grading from MP 5.29 back towards MP 5

www.millenniumpipeline.com

2
20171228-5223 FERC PDF (Unofficial) 12/28/2017 3:04:31 PM

VALLEY LATERAL PROJECT


STATUS REPORT
Period Ending: December 27, 2017 Report #26—Supplement 1

For the Period of December 20, 2017 through December 27, 2017

2017-2018 Pipeline Construction Summary.

Construction Status: Pipeline Facilities


Activity % Complete Comments
Clearing 99% All tree felling is complete, except at MP-.69

Grading 4%
Ditching 4%
Stringing 4%
Bending 4%
Welding 4%
Coating 4%
Lower-in/Tie-in 4%
Backfill 4%
Winterization 2%
Final Clean Up 2%
Hydro-Test 0

Horizontal Directional Drill Operations


Drill Location Noise Level at the start of Date Noise Mitigation Implemented
Drilling

None – Horizontal Directional Drilling has not commenced.




Noise mitigation measures that Millennium would implement if the initial noise measurements
exceeded a day-night sound level (Ldn) of 55 decibels on the A-weighted scale (dBA) at the
nearest NSA and/or increased noise is over ambient conditions greater than 10 decibels – [No
Horizontal Directional is taking place at this time.]

www.millenniumpipeline.com

3
20171228-5223 FERC PDF (Unofficial) 12/28/2017 3:04:31 PM

VALLEY LATERAL PROJECT


STATUS REPORT
Period Ending: December 27, 2017 Report #26—Supplement 1

For the Period of December 20, 2017 through December 27, 2017

Summary of Issues and Corrective Action


Mile Post Compliance Level/Issued Date Description of Issue and
By Corrective Action


None

Agency On-site Inspections


Mile Post Name/Agency Represented Date Environmental Compliance
Concerns
Entire Tetra Tech 12/14/17 None
project
MP-5.3-5.66 Wawayanda Town SWPPP 12/18/17 None
Inspection
None – There were no new Agency On-site Inspections this period.


Landowner Complaints
Landowner Tract # Date Issue/Resolution
Property Milepost


There were no new Landowner complaints this week.

www.millenniumpipeline.com

4
20171228-5223 FERC PDF (Unofficial) 12/28/2017 3:04:31 PM

VALLEY LATERAL PROJECT


STATUS REPORT
Period Ending: December 27, 2017 Report #26—Supplement 1

For the Period of December 20, 2017 through December 27, 2017

Construction Status: Aboveground Facilities


Aboveground Activity % Complete Comments
Facilities

Summary of Issues and Corrective Action


Spread Compliance Level/Issued Date Description of Issue and
By Corrective Action

None – Construction has not commenced




Agency On-site Inspections


Spread Name/ Agency Represented Date Environmental Compliance
Concerns

None – There were no new Agency On-site Inspections this period.




Landowner Complaints
Spread Landowner Property Tract # Date Issue / Resolution
Milepost

None – There were no Landowner complaints this week.




www.millenniumpipeline.com

5
20171228-5223 FERC PDF (Unofficial) 12/28/2017 3:04:31 PM

VALLEY LATERAL PROJECT


STATUS REPORT
Period Ending: December 27, 2017 Report #26—Supplement 1

For the Period of December 20, 2017 through December 27, 2017

Miscellaneous Comments (i.e. Notification, meetings):

Notifications: Millennium will resume bi-weekly construction reports starting next reporting period.
Site-Specific Plans: None
Workspace Revisions: None

www.millenniumpipeline.com

6
20171228-5223 FERC PDF (Unofficial) 12/28/2017 3:04:31 PM
20171228-5223 FERC PDF (Unofficial) 12/28/2017 3:04:31 PM
20171228-5223 FERC PDF (Unofficial) 12/28/2017 3:04:31 PM
Document Content(s)

Valley Lateral Bi-Weekly Report 26_Supp1.PDF..........................1-9