Sunteți pe pagina 1din 136

Power Plant Optimization

Guidelines

TR-110718

Final Report, December 1998

Effective December 6, 2006, this report has been made publicly available in accordance
with Section 734.3(b)(3) and published in accordance with Section 734.7 of the U.S. Export
Administration Regulations. As a result of this publication, this report is subject to only
copyright protection and does not require any license agreement from EPRI. This notice
supersedes the export control restrictions and any proprietary licensed material notices
embedded in the document prior to publication

EPRI Project Manager


J. Stallings

EPRI • 3412 Hillview Avenue, Palo Alto, California 94304 • PO Box 10412, Palo Alto, California 94303 • USA
800.313.3774 • 650.855.2121 • askepri@epri.com • www.epri.com
DISCLAIMER OF WARRANTIES AND LIMITATION OF LIABILITIES
THIS REPORT WAS PREPARED BY THE ORGANIZATION(S) NAMED BELOW AS AN ACCOUNT OF WORK
SPONSORED OR COSPONSORED BY THE ELECTRIC POWER RESEARCH INSTITUTE, INC. (EPRI).
NEITHER EPRI, ANY MEMBER OF EPRI, ANY COSPONSOR, THE ORGANIZATION(S) NAMED BELOW,
NOR ANY PERSON ACTING ON BEHALF OF ANY OF THEM:

(A) MAKES ANY WARRANTY OR REPRESENTATION WHATSOEVER, EXPRESS OR IMPLIED, (I) WITH
RESPECT TO THE USE OF ANY INFORMATION, APPARATUS, METHOD, PROCESS, OR SIMILAR ITEM
DISCLOSED IN THIS REPORT, INCLUDING MERCHANTABILITY AND FITNESS FOR A PARTICULAR
PURPOSE, OR (II) THAT SUCH USE DOES NOT INFRINGE ON OR INTERFERE WITH PRIVATELY OWNED
RIGHTS, INCLUDING ANY PARTY'S INTELLECTUAL PROPERTY, OR (III) THAT THIS REPORT IS
SUITABLE TO ANY PARTICULAR USER'S CIRCUMSTANCE; OR

(B) ASSUMES RESPONSIBILITY FOR ANY DAMAGES OR OTHER LIABILITY WHATSOEVER (INCLUDING
ANY CONSEQUENTIAL DAMAGES, EVEN IF EPRI OR ANY EPRI REPRESENTATIVE HAS BEEN ADVISED
OF THE POSSIBILITY OF SUCH DAMAGES) RESULTING FROM YOUR SELECTION OR USE OF THIS
REPORT OR ANY INFORMATION, APPARATUS, METHOD, PROCESS, OR SIMILAR ITEM DISCLOSED IN
THIS REPORT.

ORGANIZATION(S) THAT PREPARED THIS REPORT

Energy Technologies Enterprises Corporation

ORDERING INFORMATION
Requests for copies of this report should be directed to the EPRI Distribution Center, 207 Coggins Drive, P.O. Box
23205, Pleasant Hill, CA 94523, (925) 934-4212.

Electric Power Research Institute and EPRI are registered service marks of the Electric Power Research Institute, Inc.
EPRI. POWERING PROGRESS is a service mark of the Electric Power Research Institute, Inc.

Copyright © 1998 Electric Power Research Institute, Inc. All rights reserved.
CITATIONS

This report was prepared by

Energy Technologies Enterprises Corp.


7722 Desdemona Court
McLean, Virginia 22102

Principal Investigator
S. Tavoulareas

This report describes research sponsored by EPRI.

The report is a corporate document that should be cited in the literature in the
following manner:

Power Plant Optimization Guidelines, EPRI, Palo Alto, CA: 1998. TR-110718.

iii
REPORT SUMMARY

During the last five years, new software products have become available that use
statistical analysis or neural network techniques to optimize power plant performance
based on multiple objectives. The growing impetus to reduce costs of NOx compliance
and electricity production has accelerated deployment of these applications in the
utility industry.

Background
Optimization software was being implemented in approximately 130 boilers as of
September 1998 (of these applications, more than half were one-time efforts; after an
optimized list of set points had been given to the plant, the optimization software was
removed). Reported NOx emission reduction has ranged from 5 to 40% and heat rate
reduction from 0.5 to 3%. In the combustion area, key objectives are reduction of NOx
emissions, heat rate, and unburned carbon. While some U.S. utilities have gained
experience with software tools, the majority of utilities need more information on how
to select the most appropriate software for their plant optimization programs.

Objectives
• To determine the potential improvement in plant performance and emission
reduction through use of power plant optimization software.
• To select the most appropriate optimization type among stand-alone, on-
line/advisory, and closed-loop.
• To evaluate various options by carrying out a cost-benefit analysis.

Approach
The Power Plant Optimization (PPO) Guidelines were developed with the expertise of
the contractor and EPRI, as well as advice from the Power Plant Optimization Interest
Group (consisting of EPRI members interested and involved in plant optimization). The
project team’s approach was to lead utility planners through a five-step process, which
methodically would set appropriate optimization objectives, identify projected
performance improvements, and estimate costs and benefits of various optimization
types. To facilitate this analysis, the team included two Excel™ spreadsheets with the
program. A beta version of these Guidelines was distributed to 40 utility engineers,
many of whom provided feedback on how to improve them further. Version 1.0, which
accompanies this report, incorporates the comments of these utility users.

v
Results
Forty utility engineers have already used the beta version of these Guidelines. Many of
these engineers have used them to make decisions on how to structure optimization
programs and how to improve efficiency and cost-effectiveness of plant operations. Use
of optimization software is expected to grow significantly, and these Guidelines will
play a critical role in this growth. Two case studies carried out by Allegheny Power and
Northern State Power are included in this document and provide a good example of
how the Guidelines can be used.

EPRI Perspective
Power plant optimization software has become more widespread as a result of the
industry’s attempt to find less expensive ways to comply with NOx emission
regulations. Optimization products are of strategic importance to the utility industry,
which soon will operate in a deregulated market in which key economic parameters
and operating objectives change continuously. Optimization tools will allow utilities to
adjust to such dynamic environments. EPRI has played and will continue to play a
leading role in this technical area by supporting utility demonstration of all
optimization tools, disseminating relevant information, and developing software
evaluation guidelines.

AP-110718
Interest Categories
Fossil steam plant performance optimization
Air emissions control
Emissions monitoring
Fossil steam plant O&M cost reduction

Keywords
Heat rate
Nitrogen oxides
Emission control
Performance testing
Computer applications
Computer applications
Cost Reduction

vi
EPRI Licensed Material

INTRODUCTION/ HOW TO USE THIS DOCUMENT

As of September 1998, approximately 50 utilities in the U.S. have utilized optimization


software in 92 units, mainly to reduce NOx emissions and heat rate. Approximately 40
more optimization projects are planned to be completed by the end of 1998. Industry
experience to date suggests that moderate NOx reduction (5-40%) and heat rate
improvement (0.5-1.5 percentage points) can be achieved with optimization software.

Detailed description of the various software available and the industry experience are
provided in EPRI’s Power Plant Optimization Web Site (http://www.epriweb.com/
gg/98funders/ppo/index.html) and the proceedings from EPRI’s Workshops on
Power Plant Optimization in 1997 and 1998 (TR-108687 and TR-111316, respectively).
The web site is updated monthly and is a good source of information on ongoing
projects and key industry developments. Key definitions associated with power plant
optimization are provided in Box I.

The purpose of this document is to build upon these sources of information and
provide utilities with a step-by-step guide on how to:

x determine the potential power plant performance improvement if an optimization


package were used,

x select the most cost effective optimization type among: stand-alone1, on-line/
advisory, and closed-loop, and

x evaluate alternative optimization software packages.

The approach followed in this document emphasizes:

x low-cost options; it starts from a simple (“quick”) tuning and moves to more
expensive optimization and potential hardware changes (e.g. NOx control retrofit
options) only as needed or supported by sound economic justification;

1
“Stand-alone” type optimization projects were referred to as “Off-line/One-time” type projects during
the EPRI/ESEERCO Conference and in the conference proceedings (EPRI TR-108687).

vii
EPRI Licensed Material

x setting baseline performance after quick tuning to assess the real potential of
optimization; tuning and baseline performance are described in detail in EPRI’s
“NOx Emissions Testing and Optimization for Coal-fired Utility Boilers” (TR-
105109) to which the reader is referred frequently;

x establishing clear objectives for the optimization project; and

x identifying the type of optimization and the specific software package which is most
appropriate and cost-effective.

Box I Definitions

Power plant optimization is a process which involves changes in operating variables


and equipment settings to achieve a set of objectives. Optimization software may be
used in the following three modes:

x Stand-alone: while the optimization system may obtain data electronically


from the DCS or other data sources, one or more variables are often provided
manually for each iteration; in most cases, this optimization is performed
once and then the system is maintained at the same operating conditions.
Optimization may be repeated periodically

x On-line/advisory: all the data required for optimization (variables which


change with operation) are obtained electronically; the system provides
advice to the plant operator who makes the final decision whether or not the
proposed optimum should be implemented

x Closed-loop: fully integrated into the power plant controls; the optimization
system feeds control biases directly into the control system causing the field
equipment to change without human intervention.

More information on typical optimization systems, as well as specific software available


in the market, is provided in EPRI publications TR-108687 and TR-111316.

While this document uses the terms “power plant optimization”, most experience so far
is with “boiler optimization.” However, the same software may be used for power
plant optimization.

viii
EPRI Licensed Material

These guidelines consist of 5 basic steps (see the figure on the following page) which
are described in the first five sections of the report (one section devoted to each step).

x Step 1: Tune unit and establish baseline performance,

x Step 2: Establish clear needs and objectives,

x Step 3: Determine optimization potential/Can optimization alone meet established


objectives?

x Step 4: Identify the most cost-effective type of optimization, and

x Step 5: Select the best optimization product for your application.

Quick tuning and establishment of baseline performance is recommended as the first


step, before establishing objectives for the power plant optimization project.
Alternatively, objectives may be set first (especially when the boiler is tuned recently),
but they should be re-assessed after the quick tuning is done and baseline performance
is established.

There are three appendices:

x Appendix A: Software User’s Guide provides guidance on how to use the spreadsheets
which accompany this report on a floppy disk. Guidance is also included for the
applicable sections (Steps 3, 4, and the case studies in Appendix B).

x Appendix B: Case Studies provides two examples which illustrate how the guidelines
may be applied to specific power plants.

x Appendix C: Formulas provides all the formulas used for estimating the costs and
benefits of power plant optimization in the guidelines and spreadsheets.

The material provided in this report includes both general guidance and step-by-step
instructions to evaluate the various options for a specific power plant under
consideration. In steps 3 and 4, detailed instructions (highlighted in shaded boxes)
provide for using these spreadsheet tools (Tables 3-1 and 4-1).

ix
EPRI Licensed Material

Guidelines Process to Evaluate Power Plant Optimization Options

Step 1
Tune unit &
Establish baseline performance

Step 2
Establish clear needs
& objectives

Consider optimization in
combination with other
options such as:
Step 3
Determine optimization potential/ NO
z NOx controls (Low NOx
Can optimization alone meet
burners, SNCR, reburning,
established objectives?
and SCR)

z Hardware modifications
YES for heat rate improvements

Step 4
Identify the most cost-effective
type of optimization

Step 5
Select the best optimization
product for your application

x
EPRI Licensed Material

ABBREVIATIONS AND ACRONYMNS

ABB/CE Asea Brown Boveri/Combustion Engineering


BOOS Burner out of service
CAAA Clean Air Act Amendment of 1990
CO2 Carbon dioxide
CO Carbon monoxide
DAS Data acquisition system
DCS Digital control system
EPA U.S. Environmental Protection Agency
ESP Electrostatic precipitator
I/O Input/output
I&C Instrumentation and controls
kWh Kilowatts per hour
Lbs/MBtu Pounds per million British thermal units
LNCFS-III ABB/CE Low NOx Concentric Firing Systems-III
LOI Loss on ignition
MOOS Mills-out-of-service
MW Megawatt
NOx Nitrogen oxides
NPV Net present value
NSP Northern States Power
O&M Operating and maintenance
O2 Oxygen
OEM Original equipment manufacturer
OFA Overfire air
PA Primary air
PEPCO Potomac Electric Power Company
ppm Parts per million
PPO Power plant optimization
PV Present value
SNCR Selective non-catalytic reduction
SCR Selective catalytic reduction
SO2 Sulfur dioxide
TVA Tennessee Valley Authority
UBC Unburned carbon

xi
EPRI Licensed Material

CONTENTS

1 STEP ONE: TUNE UNIT AND ESTABLISH BASELINE PERFORMANCE ........................ 1-1
A. Perform Diagnostic Testing ............................................................................................ 1-2
B. Perform Quick Tuning..................................................................................................... 1-5
What is Quick Tuning? .................................................................................................... 1-5
C. Establish Baseline Performance..................................................................................... 1-7

2 STEP TWO: ESTABLISH CLEAR NEEDS AND OBJECTIVES ......................................... 2-1


B. Differentiate between “firm requirements” and “desirable outcomes” ............................. 2-3
C. Articulate project objectives............................................................................................ 2-4

3 STEP THREE: DETERMINE OPTIMIZATION POTENTIAL/CAN OPTIMIZATION


ALONE MEET ESTABLISHED OBJECTIVES?..................................................................... 3-1
Can Optimization Alone Meet Established Objectives? ...................................................... 3-2
Background and Instructions for Completing Table 3-1 ...................................................... 3-4
Information on the Last Unit Tune Up ............................................................................. 3-4
Unit Operating Flexibility (at full load).............................................................................. 3-5
Fuel Flow Biasing ........................................................................................................ 3-5
Air Flow Biasing........................................................................................................... 3-7
Excess O2 (baseline vs. minimum O2 level) ................................................................. 3-8
Operating Flexibility of Burner Tilts (only in the case of T-fired boilers)..................... 3-10
Operating Range of Air and Gas Dampers................................................................ 3-12
Primary Air to Fuel Ratio (PA/Fuel) ........................................................................... 3-12
Other Control Variables............................................................................................. 3-13
Ability to Change Equipment Settings ........................................................................... 3-14
Burner Settings ......................................................................................................... 3-14
Pulverizer Settings (in case of coal-fired power plants)............................................. 3-16
Other Equipment Settings ......................................................................................... 3-16

xiii
EPRI Licensed Material

Air Distribution Modifications ..................................................................................... 3-17


Coal Pipe Orificing..................................................................................................... 3-18
Mill Modifications ....................................................................................................... 3-21
Expected Performance Improvements .......................................................................... 3-23
Project Classification.............................................................................................. 3-24

4 STEP FOUR: IDENTIFY THE MOST COST-EFFECTIVE TYPE OF OPTIMIZATION ........ 4-1
Types of Optimizations: ...................................................................................................... 4-2
A. Availability of DCS and DAS ....................................................................................... 4-2
B. Continuous vs. One-time or Periodic Optimization...................................................... 4-2
C. Performance Improvement Objectives........................................................................ 4-3
D. Cost-Benefit of Alternative Optimization Types .......................................................... 4-3
Background and Instructions for Completing Table 4-1 ...................................................... 4-7
COSTS ............................................................................................................................... 4-7
UP FRONT COSTS......................................................................................................... 4-7
Up Front License Fees ................................................................................................ 4-7
Additional Computer Software and Hardware ............................................................. 4-8
Installation and Calibration .......................................................................................... 4-8
Training ..................................................................................................................... 4-11
Power Plant Hardware Modifications......................................................................... 4-11
ANNUAL COSTS (O&M Including Recalibration).......................................................... 4-11
Annual Software License and Maintenance Fees ..................................................... 4-12
Technical Support ..................................................................................................... 4-12
OPTIMIZATION BENEFITS .............................................................................................. 4-14
UP FRONT (ONE TIME) BENEFITS ............................................................................. 4-14
NPV of Deferred Costs.............................................................................................. 4-14
NPV of Avoided Costs............................................................................................... 4-14
ANNUAL BENEFITS ..................................................................................................... 4-15
Annual Avoided Costs............................................................................................... 4-15
Fuel Cost Savings ..................................................................................................... 4-16
O&M Impacts ............................................................................................................ 4-17
Value of Change in Unit Availability .......................................................................... 4-18
Value of Change in Unit Output ................................................................................ 4-18
Benefits Due to Emission Reductions ....................................................................... 4-19

xiv
EPRI Licensed Material

Cost-Benefit Analysis Results ........................................................................................... 4-22

5 STEP FIVE: SELECT THE BEST OPTIMIZATION PRODUCT FOR YOUR


APPLICATION........................................................................................................................ 5-1
Selecting an Optimization Package .................................................................................... 5-2
Key Factors......................................................................................................................... 5-2
Comments on the Key Factors for Evaluating Optimization Software................................. 5-3
A. Demonstrated track record of the optimization product in similar applications............ 5-3
B. Experience of the software vendor in supporting product deployment ....................... 5-6
C. Total cost of applying the optimization product........................................................... 5-7
D. Benefits from the utilization of the optimization product.............................................. 5-9

A SOFTWARE USER’S GUIDE .............................................................................................A-1


System Requirements......................................................................................................... A-1
Hardware Requirements ................................................................................................. A-1
Software Requirements................................................................................................... A-1
Installation........................................................................................................................... A-1
Using the Software .............................................................................................................A-2
Table 3-1......................................................................................................................... A-3
Table 4-1......................................................................................................................... A-3
Tables B-3, B-5, B-7, B-8, B-9, and B-11 ........................................................................ A-4
User Tutorial ....................................................................................................................... A-4

B CASE STUDIES..................................................................................................................B-1
Case Study 1: Allegheny Power’s Armstrong 1 Unit ........................................................... B-1
Background.....................................................................................................................B-1
Armstrong Unit 1 ............................................................................................................. B-2
Evaluation of Alternative Power Plant Optimization Options ........................................... B-7
Case Study 2: Northern States Power Riverside 7 Unit .................................................... B-17
Background................................................................................................................... B-17
NSP’s NOx Compliance Plans and Future Needs..................................................... B-17
Description of Riverside 7 ............................................................................................. B-18
Evaluation of Power Plant Optimization Software ......................................................... B-18

C FORMULAS ........................................................................................................................C-1

xv
EPRI Licensed Material

LIST OF FIGURES

Figure 1-1 Impact of Auxiliary Air Register Settings on NOx Emissions and Heat Rate
at PEPCO’s Potomac River Power Plant ........................................................................ 1-6
Figure 3-1 Effect of air biasing on NOx emissions--400 MW tangential-fired Boiler............... 3-5
Figure 3-2 BOOS results for a 365 MW single-wall-fired boiler.............................................. 3-6
Figure 3-3 Effect of Coal Quality on NOx Emissions Typical Uncontrolled ............................ 3-9
Figure 3-4 Hypothetical NOx Reduction with Balanced Combustion .................................... 3-9
Figure 3-5 Effect of Burner Tilt Position on NOx Emissions for Baseline (Uncontrolled)
and Low-NOx (Controlled) Operation--400 MW Tangential-Fired Boiler ....................... 3-11
Figure 3-6 Effect of Burner Tilt Position on NOx--105 MNW Tangential-Fired Boiler ........... 3-11
Figure 3-7 Effect of Varying the Ratio of Primary Air to Coal on NOx Emissions--105
MW Tangential-Fired Boiler........................................................................................... 3-13
Figure 3-8 Union Electric/Meramec Unit 4: Unburned Carbon vs. Coal Fineness, Coal
Flow Imbalance and Coal Blend.................................................................................... 3-20
Figure 3-9 PEPCo’s Potomac River 4/Effect of Mill Maintenance on LOI ........................... 3-21
Figure 3-10 Smith 2/Relationship Between LOI, NOx and Coal Fineness ........................... 3-22
Figure 3-11 Typical Particle Size Distribution with Static and Dynamic Classifiers .............. 3-23
Figure 3-12 Utility Experience with Combustion Tuning & Optimization NOx Reduction
Achieved ....................................................................................................................... 3-24
Figure 4-1 Optimization Cost Effectiveness ........................................................................... 4-3
Figure A-1 A Portion of Table 3-1 Before and After a Change is entered.............................. A-6
Figure A-2 A Portion of Table 3-1 Before and After a Second Input is Entered..................... A-7
Figure A-3 A Portion of Table 4-1 Applied to Boiler XYZ; Before Use and After a
Change is Entered .......................................................................................................... A-9
Figure A-4 A Portion of Table 4-1 Applied to Boiler XYZ; After a Second Group of
Changes is Entered....................................................................................................... A-11
Figure B-1 Armstrong Units 1 & 2 Boiler Arrangement .......................................................... B-4
Figure B-2 Burner and Mill Arrangement ............................................................................... B-5
Figure B-3 Armstrong Unit 1 NOx Emissions After IFS Burner Installation ............................ B-6
Figure B-4 Armstrong Unit 1 Boiler Efficiency After IFS Burner Installation ........................... B-6
Figure B-5 Alternative Coal Pipe Arrangements for Improved NOx Control......................... B-20

xvii
EPRI Licensed Material

LIST OF TABLES

Table 1-1 References and Guidance Documents .................................................................. 1-2


Table 1-2 Comparison of Three Measurement Approaches .................................................. 1-3
Table 1-3 Suitability of Measurement Approaches for NOx Test Elements (Phases) ............ 1-4
Table 3-1 Project Classification to Determine Potential Performance Improvements
Due to Optimization......................................................................................................... 3-3
Table 3-2 Expected Performance Improvements................................................................. 3-23
Table 3-3 Previous Tuning Objective – Safe Operation....................................................... 3-24
Table 3-4 Previous Tuning Objective – Heat Rate Improvement ......................................... 3-24
Table 3-5 Previous Tuning Objective – NOx Reduction...................................................... 3-25
Table 3-6 Previous Tuning Objective – NOx Reduction & Heat Rate Improvement ............ 3-25
Table 4-1 Power Plant Optimization Cost-Benefit Analysis.................................................... 4-5
Table B-1 Allegheny's Experience with Power Plant Optimization........................................ B-2
Table B-2 Characteristics of Eastern Bituminous Coal Burned in Armstrong 1...................... B-3
Table B-3 Project Classification to Determine Potential Performance Improvements
Due to Optimization Armstrong 1/Advanced Control for Coal Flow Distribution .............. B-9
Table B-4 Expected Performance Improvements with Optimization (Case 1)...................... B-10
Table B-5 Project Classification to Determine Potential Performance Improvements
due to Optimization Armstrong 1/ No Coal Flow Distribution Control ............................ B-11
Table B-6 Expected Performance Improvements with Optimization (Case 2)...................... B-12
Table B-7 Power Plant Optimization Cost-Benefit Analysis--Armstrong 1 Advanced
Control for Coal Flow Distribution.................................................................................. B-13
Table B-8 Power Plant Optimization Cost-Benefit Analysis--Armstrong 1 Without Coal
Distribution Control........................................................................................................ B-15
Table B-9 Project Classification to Determine Potential Performance Improvements
Due to Optimization—Riverside 7 ................................................................................. B-23
Table B-10 Expected Performance Improvements with Optimization (Case 1).................... B-24
Table B-11 Power Plant Optimization Cost-Benefit Analysis—Riverside 7 .......................... B-25

xix
EPRI Licensed Material

1
STEP ONE: TUNE UNIT AND ESTABLISH BASELINE

PERFORMANCE

Step 1
Tune unit &
Establish baseline performance

Step 2
Establish clear needs
& objectives
Consider optimization in
combination with other
options such as:
Step 3
Determine optimization potential/ z NOx controls (Low NOx
Can optimization alone meet burners, SNCR, reburning,
established objectives? NO and SCR)

z Hardware modifications
YES for heat rate improvements
Step 4
Identify the most cost-effective
type of optimization

Step 5
Select the best optimization
product for your application

1-1
EPRI Licensed Material
Step One: Tune Unit and Establish Baseline Performance

Unit performance deteriorates with time and requires periodic retuning and
optimization. Before optimization is carried out, tuning is recommended because:
x it may be adequate to satisfy low-to-moderate performance improvement
requirements (e.g., NOx emission reduction less than 15%),

x it is important even if other performance improvement options are implemented,


because it reduces the magnitude of improvement needed and costs associated with
it. For example, if a 15% NOx reduction improvement is achieved through tuning,
low NOx burners may be adequate to meet NOx regulations instead of low NOx
burners with overfire air, potentially saving $5-10 per kW.

Before tuning is performed, diagnostic testing is recommended. After tuning, baseline


performance should be established to serve as the reference point for evaluating
performance improvement alternatives. The following table provides references to
guidance documents which will prove helpful in planning and implementing such
programs.

Table 1-1
References and Guidance Documents

Key Actions Sources/Support Material

Perform diagnostic testing to identify problems Section 5 of EPRI’s “NOx Emissions Testing
and areas of potential performance and Optimization for Coal-fired Utility Boilers”
improvement (TR-105109)

Perform Quick Tuning; in most cases, quick Section 7 of EPRI’s “NOx Emissions Testing
tuning improves performance without any out- and Optimization for Coal-fired Utility Boilers”
of-pocket costs (TR-105109)

Establish Baseline Performance Section 4 of EPRI’s “NOx Emissions Testing


and Optimization for Coal-fired Utility Boilers”
(TR-105109)

A. Perform Diagnostic Testing

Diagnostic testing is beneficial because it helps to:

x verify proper functioning of plant components,

x identify off-design operating conditions and problem areas,

x identify site-specific constraints and practices which may preclude the unit from
achieving better performance, and

1-2
EPRI Licensed Material
Step One: Tune Unit and Establish Baseline Performance

x identify potential improvements which can be achieved with minimum effort and
budget.

Detailed guidance on how to carry out a diagnostic program is provided in Section 5,


Table 3-1 of EPRI’s “NOx Emissions Testing and Optimization for Coal-fired Utility
Boilers” (TR-105109). In most cases, Type 1 testing (types of testing are shown in
Tables 1-2 and 1-3) is sufficient. Type 2 or 3 testing should be performed only in case
one or more of the following conditions exist:

x relatively high performance improvement is being sought; for example, NOx


emission reduction in the 20-35% range with simultaneous improvement in one or
more of the following: heat rate, unburned carbon, outlet steam temperatures,
and/or opacity,

x there are indications of non-uniform air and coal flow distribution in the coal pipes
and flue gas in backpass ducts, which may require multiple gas sampling and coal
pipe measurements, and/or

x past operating experience and maintenance records suggest high corrosion rate
and/or malfunctioning equipment.

Table 1-2
Comparison of Three Measurement Approaches

Measurement Approach
Element Type 1 Type 2 Type 3
Scope Quick NOx Emissions Emissions characterization with Emissions characterization
assessment with minimal appropriate combustion with comprehensive
performance data diagnostics combustion diagnostic and
performance testing

Instrumentation See Table 1-2 of See Table 1-2 of See Table 2 of


and sampling and TR-105109 TR-105109 TR-105109
analytical
procedures

Applicability of Provides quick, inexpensive Provides sufficient data to Provides instrumentation and
Results assessment of NOx emissions; identify emissions range and measurements suitable for
potentially inadequate for NOx dominant parameters and to combustion tuning and
retrofit assessment assess NOx retrofit options optimization of combustion
system for reduced NOx
emissions
Emissions r25% r10-15% r5-10%
measurement
precision
Relative Cost Low Moderate High
Source: TR-105109

1-3
EPRI Licensed Material
Step One: Tune Unit and Establish Baseline Performance

Table 1-3
Suitability of Measurement Approaches for NOx Test Elements (Phases)

Measurement Approach
Element Type 1 Type 2 Type 3
Baseline Testing X X X
Combustion Equipment X X
diagnostic testing

Parametric Testing X X
(preliminary and detailed)

Combustion Tuning X
Source: TR-105109

Diagnostic testing may include the following inspections and measurements:

x visual inspection of combustion equipment,

x measurement of gas composition uniformity at economizer exit,

x measurement of excess O2 before and after the air heater to estimate air in-leakage
through the boiler casing and the air heater,

x measurement of unburned carbon in the flyash and combustion efficiency,

x measurement of coal fineness,

x determination of uniformity of air and fuel distribution to the burners,

x inspection of air heaters for potential plugging, and

x inspection of plant instrumentation to ensure proper calibration.

All components which may affect measurements used for performance assessment
should be checked. Examples of components to check include:

x Instrumentation and controls: Make sure that the existing instrumentation is


calibrated and in good working condition. In particular, accurate measurement of
excess O2, NOx and CO are essential. Also, the controls should be able to achieve
repeatable operating conditions (same control settings should result in
approximately the same plant performance).

x Air registers: Make sure that they are in good operating condition and set properly
(based on operating guidelines).

1-4
EPRI Licensed Material
Step One: Tune Unit and Establish Baseline Performance

x Dampers: Air and gas dampers (the latter in case of split backpass) and associated
drives may not be in good operating condition, adversely affecting combustion,
NOx generation, and general unit performance. Tempering air and overfire air
dampers may have similar effects.

x Burner and overfire air adjustment mechanisms: Burner tilts and yaws in T-fired boilers
may not be in good operating condition or may require tuning. Similarly, overfire
air adjustment mechanisms in wall-fired boilers may not be operating properly.

Certain measurements are inherently variable (e.g., feeder speed of pulverizers) and
the appropriate average should be used. However, there may be cases in which key
measurements are not repeatable and plant optimization may not be feasible or
practical. Such case has been observed in a couple of power plants which did not have
well-calibrated instrumentation.

B. Perform Quick Tuning

A power plant may not have been tuned recently or may have been tuned for an
operating objective different from present operating requirements. For example, the
objectives of the previous tuning could have been safe operation and heat rate
improvement, but future operation may need to focus on balancing NOx emissions
requirements and heat rate improvement. Knowledge of the operating condition and
limitations of the specific plant equipment, NOx formation mechanisms, and power
plant engineering principles can be applied in a systematic but quick way (Quick
Tuning) to improve plant performance.

What is Quick Tuning?

Tuning, as defined in TR-105109, involves Type 3 testing (see Tables 1-2 and 1-3) in
which operational modifications are made to the combustion process to achieve specific
operating objectives such as NOx emissions reduction or heat rate improvement. A key
component of this type of tuning is parametric testing which involves the use of
specialized instrumentation such as multiple-point sampling system to analyze gas and
unburned carbon.

Quick tuning is a simplified tuning (Type 1 instead of Type 3 testing) which can be
carried out by a plant performance engineer (either from the utility staff or an outside
consultant) in a period of 3-5 working days. The general approach followed is to check
the operating condition of key components based on visual observation, evaluate
whatever data are already available at the plant, and attempt to improve performance
through adjustments of control variables and changes in equipment set-points. The
available instrumentation is usually adequate, provided that there are O2, NOx, and CO
monitors available.

1-5
EPRI Licensed Material
Step One: Tune Unit and Establish Baseline Performance

Examples of components which may be tuned include:

x Adjust air registers: Very often the registers are set-up to maximize combustion
efficiency (reduce unburned carbon). Sometimes they are in a sub-optimum setting
either because there is a problem with their controls (such as: broken drives and not
properly operating position sensor) or because they have not been tuned recently.
Resetting of the air registers is simple and can improve both combustion efficiency
and NOx emissions. The latter can be achieved if the air register settings contribute
to “air staging” (creating air-lean flame by distributing more air to the outside of the
flame and towards the top burner elevations). Tuning of Potomac Electric Power
Co.’s (PEPCO) Potomac River power plant (see Figure 1-1) is a good example of
how the auxiliary air register settings affect NOx emissions and heat rate. If NOx
reduction is a key operating objective, setting the air registers as shown in Figure 1-
1 could be a good starting point.

Burner Elevation 5 1 1
Original
Setting
(Baseline)

Aux Air
Fuel Air 0 0 0
Air Flow O2 (%) NOx (lb/MBtu) ' Heat Rate (%)
Burner Elevation 5 1 1
Tuned for
NOx
Minimization

0 0 0
Air Flow O2 (%) NOx (lb/MBtu) ' Heat Rate (%)
Source: PEPCo

Figure 1-1
Impact of Auxiliary Air Register Settings on NOx Emissions and Heat Rate at
PEPCO’s Potomac River Power Plant

x Adjust damper set-points: Changes in damper settings may improve air or gas non-
uniformities and enhance combustion.

1-6
EPRI Licensed Material
Step One: Tune Unit and Establish Baseline Performance

x Assess low excess air operation: Lowering excess air is desirable because it reduces
NOx emissions and improves boiler efficiency. However, below a certain excess air
level, unburned carbon and CO emissions start increasing and counter-balance the
benefits of low excess air operation. It is therefore desirable to identify the optimum
excess air level and operate as close to this level as possible. The optimum excess
air level can be identified by reducing the excess air and monitoring CO emissions
and unburned carbon.

x Assess combustion staging: Creating fuel-rich and fuel-lean combustion zones in the
boiler has been proven to reduce NOx emissions. Within certain limits, such
changes do not adversely affect combustion efficiency. Techniques which have been
well documented in the literature (EPRI’s TR-105109 provides good guidance on
combustion staging) include:

¡ fuel staging (biasing fuel distribution among the burner elevations),

¡ air staging (see above example from PEPCo’s Potomac River plant),

¡ burners out of service (BOOS), sometimes called mills out of service


(MOOS), and

¡ simulated overfire air (OFA).

x Improve pulverizer performance: Air-to-fuel ratio and quick tuning of the pulverizer
(e.g., adjustment of spring tension and outlet temperature) can improve coal
fineness, combustion efficiency, and general plant performance. Balancing of air
and coal flows is very important, especially for wall-fired boilers, but it may not be
part of quick tuning because it requires more extensive effort to assess the level of
balancing needed and to implement the necessary modifications (e.g., coal pipe
orificing).

Changes made under quick tuning may have adverse impacts on unburned carbon, CO
emissions, slagging, fouling corrosion, unit generating capacity, rate of load change and
unit heat rate. More information regarding assessment of adverse impacts of tuning
(combustion tuning trade-offs) is provided in Section 7 of TR-105109.

C. Establish Baseline Performance

It is essential to establish baseline performance which reflect what can be achieved by a


well-tuned unit with reasonable effort of the plant staff. Baseline performance then can
be used as a reference point to decide what improvements need to be made and how
well the performance improvements will perform.

1-7
EPRI Licensed Material
Step One: Tune Unit and Establish Baseline Performance

Depending on the dispatch profile (cycling duty) of the unit, baseline tests may involve
testing only at full load or at various loads. Detailed guidance on how to plan and
implement baseline testing is provided in Section 4 of EPRI’s “NOx Emissions Testing
and Optimization for Coal-fired Utility Boilers” (TR-105109)..

1-8
EPRI Licensed Material

2
STEP TWO: ESTABLISH CLEAR NEEDS AND

OBJECTIVES

Step 1
Tune unit &
Establish baseline performance

Step 2
Establish clear needs
& objectives
Consider optimization in
combination with other
options such as:
Step 3
Determine optimization potential/ z NOx controls (Low NOx
Can optimization alone meet burners, SNCR, reburning,
established objectives? NO and SCR)

z Hardware modifications
YES for heat rate improvements
Step 4
Identify the most cost-effective
type of optimization

Step 5
Select the best optimization
product for your application

2-1
EPRI Licensed Material
Step Two: Establish Clear Needs and Objectives

A. Identify desired performance improvements relative to baseline performance

Performance improvements are usually dictated by regulatory requirements (e.g.,


reduction of NOx emissions or opacity) and/or driven by economics (e.g., need to
reduce heat rate or unburned carbon to make it easier to sell the flyash). In
determining the unit’s performance improvement needs, the following options should
be investigated:

x Reduce NOx emissions:

¡ What are the unit, plant, and system NOx reduction requirements?

¡ Are these requirements clear or might future regulations demand


additional NOx reductions? Is there adequate information to identify
how NOx requirements may change over time (covering the life of the
unit under consideration)?

¡ Is there flexibility in terms of NOx averaging?

¡ Is NOx emission banking an option in case the unit overcomplies?

¡ Is buying NOx emission allowances an option? If yes, at what cost?

x Lower heat rate: This objective is usually driven by economics; there are no specific
requirements, but targets may be set based on the historical records and the
assessment of potential heat rate improvement. Depending on how well the unit is
tuned, heat rate improvements due to optimization may range from 0.5 to 1.5
percentage points at full load or up to 5 percentage points at low loads.

x Reduce unburned carbon (UBC):

¡ Are there any unburned carbon requirements, such as maximum UBC (or
LOI), to sell the flyash?

¡ Are there any other adverse impacts from high UBC such as reduced
collection efficiency of the ESP?

If there are no specific requirements to reduce or keep UBC to below a certain level,
economics should dictate the optimum level.

x Lower opacity

x Lower CO emissions:

2-2
EPRI Licensed Material
Step Two: Establish Clear Needs and Objectives

¡ What is the maximum level of CO emissions set by the manufacturer or


the plant operator?

¡ Is the unit exceeding it on the average? occasionally?

x Requirements and constraints associated with outlet steam temperatures: Are boiler outlet
steam temperatures below design levels? If yes, is it required to increase these
temperature for safe operation? If operating safety is not jeopardized, determine the
relationship between steam temperature (both superheat and reheat) and improved
heat rate (% improvement in heat rate per degree steam temperature increase).

x Other requirements: While not easy to quantify, other unit performance


improvements are not uncommon, for example:

¡ improve operating safety; this may suggest increasing the excess O2


(keeping it above a lower limit) or reducing UBC,

¡ reduce potential for waterwall corrosion by increasing excess O2 above a


certain level, or

¡ reduce maintenance requirements and improve equipment reliability.

B. Differentiate between “firm requirements” and “desirable outcomes”

As already indicated in the above questions, it is very important to differentiate


between “firm requirements” and “desirable outcomes.” Firm requirements may
include:

x Annual average NOx of the unit to comply with CAAA requirements; for example:
340 ppm (0.45 lbs/MBtu) for T-fired and 375 ppm (0.50 lbs/MBtu) for wall-fired
boilers burning coal,

x NOx cap at plant and/or system level; for example: specified numbers of tons per
year from a multi-unit power plant or a power system,

x UBC (or LOI) below a certain level for selling the flyash, if flyash disposal is an
available option, keeping UBC below a certain level may not be a firm requirement,

x Maximum opacity as specified by local or federal regulations, for example, 15%


opacity may be set as a maximum,

x Maximum CO emissions; maximum daily average and/or instantaneous values


may be specified, and

2-3
EPRI Licensed Material
Step Two: Establish Clear Needs and Objectives

x Also, minimum steam temperature level or maximum superheat-reheat temperature


differential may be specified.

“Desirable outcomes” may include:

x Lower NOx emissions than required by regulations to allow more expensive units
in the system to operate at higher NOx levels (NOx averaging or trading); therefore,
reducing system compliance costs,

x Lower heat rate, and

x Higher steam temperatures.

To the extent possible, firm requirements should be minimized, so that optimization


may determine the best operating conditions. The fewer firm requirements, the greater
the operating efficiency that can be achieved through optimization.

C. Articulate project objectives

It is important that clear objectives are articulated which reflect:

x firm requirements,

x desirable outcomes, and

x references to important factors and key assumptions.

Examples of project objectives:

x “Reduce annual average NOx emissions from the present baseline level of 390 ppm
(0.52 lbs/MBtu) to 320 ppm (0.43 lbs/MBtu) without adverse operating impacts on
heat rate, LOI, CO, and opacity. NOx reductions beyond this target are not of any
value to the utility at this point in time.”

x “Reduce annual average NOx emissions from the present baseline level of 390 ppm
(0.52 lbs/MBtu) to 320 ppm (0.43 lbs/MBtu). Further NOx reduction and heat rate
improvement are desirable to the extent that these improvements are economic.
Also, adverse O&M impacts are acceptable provided that they result in lower
overall production cost and do not jeopardized plant safety.” (Notes: value of
additional NOx reduction to
the system is worth 400-500 $/ton of NOx removed; marginal cost of power is 8
cents/kWh).

2-4
EPRI Licensed Material
Step Two: Establish Clear Needs and Objectives

x “Reduce heat rate while keeping annual average NOx emissions below 360 ppm
(0.48 lbs/MBtu). Additional NOx reductions are not of any value to the utility at
this point in time.”

2-5
EPRI Licensed Material

3
STEP THREE: DETERMINE OPTIMIZATION

POTENTIAL/CAN OPTIMIZATION ALONE MEET

ESTABLISHED OBJECTIVES?

Step 1
Tune unit &
Establish baseline performance

Step 2
Establish clear needs
& objectives Consider optimization in
combination with other
options such as:

Step 3 z NOx controls (Low NOx


Determine optimization potential/ burners, SNCR, reburning,
Can optimization alone meet NO and SCR)
established objectives?
z Hardware modifications
YES for heat rate improvements
Step 4
Identify the most cost-effective
type of optimization

Step 5
Select the best optimization
product for your application

3-1
EPRI Licensed Material
Step Three: Determine Optimization Potential/Can Optimization Alone Meet Established Objectives?

Can Optimization Alone Meet Established Objectives?

Deciding whether optimization alone can meet the established objectives involves:

x estimating the level of performance improvement to be expected through


optimization, and

x comparing this level to the desirable level of performance improvement established


in Step 2; optimization is adequate if it meets the “firm requirements.

If optimization is not adequate to meet the established objectives, it is still a very cost-
effective option and should be evaluated in combination with other options such as low
NOx burners, SNCR, or SCR.

Estimating the potential performance improvement requires consideration of site-


specific factors and requirements, as well as the performance improvement potential of
the various types of optimization software. Table 3-1 provides a structure through
which the user may determine the potential performance improvement achieved
through optimization by considering site-specific factors (see printout of Table 3-1 on
the next page and the text Box 3-1 which describes the software version of Table 3-1.

Box 3-1 Software Guidance on Table 3-1

For system requirements, installation and loading of the Excel files included on
the floppy disk, see Appendix A. The Excel file “Table 3-1.xls” provided on the
floppy disk should be used to carry out Step 3 of the guidelines. A print out of
the table appears in these guidelines on page 3-3. The user should answer the
questions about the technical circumstances of the boiler in question by entering
the appropriate score from 1 to 3 based on the instructions given in this section.
The table then automatically calculates a Total Score between 100 and 300
which indicates the degree to which optimization can improve boiler
performance. Tables 3-2 and 3-2a to 3-2d on pages 37-39 of the guidelines (they
are not included on the disk) provide the performance improvements that can
be expected based on the score generated in Table 3-1.

The main criteria for estimating the level of performance improvement are grouped
into the following four categories:

1. time since last tuning and its objective (weighting: 30%),

3-2
EPRI Licensed Material
Step Three: Determine Optimization Potential/Can Optimization Alone Meet Established Objectives?

Table 3-1
Project Classification to Determine Potential Performance Improvements Due to Optimization

3-3
EPRI Licensed Material
Step Three: Determine Optimization Potential/Can Optimization Alone Meet Established Objectives?

2. unit operating flexibility (weighting: 20%),

3. ability to change equipment settings (weighting: 20%), and

4. ability to modify hardware (weighting: 30%).

As shown in parentheses (above), a weighting factor is applied to each category


reflecting its importance relative to potential performance improvement. While some
of the weighting factors for these categories may seem arbitrary, they reflect actual
industry experience (the authors have participated in 10-12 optimization projects) and
provide an effective way to categorize each project. As such, Table 3-1 could be used
either as an analytical tool or as a general guideline.

In each category, a number of questions are presented. By responding to these


questions (in shaded boxes), the spreadsheet automatically provides a Total Score
which classifies the project into one of three categories (A, B or C). The expected
performance improvements (mainly NOx reduction and heat rate improvement) are
shown in Tables 3-2 and 3-2a through 3-2d. Table 3-2 shows performance
improvement for each of the three project classifications. Tables 3-2a through 3-2d
further narrow down the expected performance improvement based on the objectives
of the last tuning.

Background and Instructions for Completing Table 3-1

Information on the Last Unit Tune Up

Combustion system tuning here refers to systematic checking and adjustment of control
variables and equipment settings to ensure that unit operating objective are met. Such
tuning may be done by the boiler manufacturer, a service company (engineering
consultant), or plant personnel. The longer the time since the last tuning, the higher the
possibility and potential for performance improvement.

When was the unit last tuned?

x Enter 1 if less than a year,

x Enter 2 if between 1-2 years, or

x Enter 3 if more than 2 years,

3-4
EPRI Licensed Material
Step Three: Determine Optimization Potential/Can Optimization Alone Meet Established Objectives?

Tuning Objective?

x Enter 1 if the goal was to ensure safe operation (stable flame and
complete combustion),

x Enter 2 if the goal was to improve heat rate,

x Enter 3 if the goal was to reduce NOx emissions, or

x Enter 4 if the goal was to reduce both heat rate and NOx emissions.

Unit Operating Flexibility (at full load)

Fuel Flow Biasing

The capability to bias fuel flow relative to the baseline setting presents the potential to
reduce NOx emissions by up to 20-25%. More fuel is typically directed to the lower
burner elevations than the upper elevations with the possibility of no fuel in the top
burner. Figure 3-1 shows the NOx reduction achieved at Kansas Power & Light’s
Lawrence #5 unit due to biased firing

0.6 450
N O x E m issions (Lb /M B tu)

N O x E m issions (pp m )

Baseline

0.4 300

Biased Firing
0.2 (m inim um fuel air, 150
m axim um auxiliary
air to top elevations)

0.0 0
0 1 2 3 4 5 6 7
E xcess O 2 (% )

Source: Kansas P ower & Light Co, Law rence U nit 5; E PR I Report TR -102906

Figure 3-1
Effect of air biasing on NOx emissions--400 MW tangential-fired Boiler

3-5
EPRI Licensed Material
Step Three: Determine Optimization Potential/Can Optimization Alone Meet Established Objectives?

When there is adequate fuel supply system capacity, burners out of service (BOOS)
may be used to reduce NOx emissions. Figure 3-2 shows the impact of BOOS on NOx
emissions in a 365 MW front wall-fired boiler.

1.0 750
Range in NOx emissions for each pattern
reflects differences in excess O2 levels
NOx Emissions (Lb/MBtu)

NOx Emissions (ppm)


0.8 600

0.6 450

0.0 0.0
Top pulverizer

Bottom pulverizer

Burner Firing Pattern


Burner in Service Burner Out Of Service
Source: Energy Technology Consultants, Inc.

Figure 3-2
BOOS results for a 365 MW single-wall-fired boiler

Fuel biasing may have an impact on combustion efficiency, because it affects the fuel
distribution along the height of the combustion zone and the residence time of the fuel
particles in the furnace.

3-6
EPRI Licensed Material
Step Three: Determine Optimization Potential/Can Optimization Alone Meet Established Objectives?

Fuel Flow Biasing

Specify the level of fuel flow biasing capability at full load as follows:

x Enter 1 for no biasing; i.e. if the fuel feed system (or mills in the case of
coal-fired power plants) are operating at or near maximum capacity,

x Enter 2 if some fuel biasing is available, but not enough to have one
mill or row of burners out of service, or

x Enter 3 if there is enough fuel feed system capacity to have one mill or
row of burners out of service at full load.

Air Flow Biasing

Air flow biasing is similar to fuel biasing in that the air distribution along the height of
the combustion zone can be altered relative to baseline conditions. Introducing more
air through the top burner elevations and less through the lower elevations delays
combustion and reduces NOx emissions. Examples of air flow biasing are shown in
Figure 1-1 and 3-1.

Air flow biasing can be used independently from other control changes or may be
combined with fuel biasing. The highest level of biasing is achieved when the top
burner elevation is out of service and more air flow is biased towards the upper burner
elevations. This type of operation very often is referred to as “simulated overfire air”
and achieves the highest NOx reduction.

Non-uniform air flow distribution is usually indicated by different excess O2


measurements from one side of the boiler backpass (flue gas duct) to the other. 1-3
percentage points difference is not unusual in many boilers. Reducing this difference
allows the total excess air to be reduced as well.

3-7
EPRI Licensed Material
Step Three: Determine Optimization Potential/Can Optimization Alone Meet Established Objectives?

Air Flow Biasing

Specify the level of air flow biasing capability at full load as follows:

x Enter 1 for no biasing; this is the case in which the air supply system
(fans) are operating at or near maximum capacity,

x Enter 2 if air biasing is possible and can increase or decrease air flow
rate through each air compartment by up to 20% relative to baseline
conditions, or

x Enter 3 if more than 20% air flow biasing can be achieved.

Excess O2 (baseline vs. minimum O2 level)

The impact of excess O2 (excess air) on NOx emissions and combustion efficiency has
been well documented: Figure 3-3 shows how excess O2 impacts NOx for various types
of coals. Lower excess O2 results in lower NOx and higher boiler efficiency. However,
below a certain level of excess O2, the combustion efficiency (more specifically, the
unburned carbon and CO emissions) is adversely affected. Figure 3-4 illustrates the
relationship between excess O2, NOx, and unburned carbon. Maximum O2 is also
limited by equipment capacity constraints.

1 .6 1 2 00
N O x E m is s io ns (L b /M B tu )

B itu m in o u s
N O x E m is s io ns (p p m )

1 .4 1 0 50

1 .2 900
S u bb itu m in o u s
1 .0 750

0 .8 600
L ig nite
0 .6 450

0 .4 300

0 .0 0
0 1 2 3 4 5 6 7
E xc e s s O 2 (% )
S o urc e: E E R

Figure 3-3
Effect of Coal Quality on NOx Emissions Typical Uncontrolled

3-8
EPRI Licensed Material
Step Three: Determine Optimization Potential/Can Optimization Alone Meet Established Objectives?

NOx

NOx Reduction
with Bal. Comb.

UBC

Avg. O2-Unbal.
Avg. O2-Bal.
Unbalanced
Balanced

Avg. UBC (b oth cases)

Excess O 2

Note: Points on curves represent average operating conditions for each burner mill group (assumes 3 mills total).
Source: EPRI/TR-105109

Figure 3-4
Hypothetical NOx Reduction with Balanced Combustion

The maximum excess O2 and the level of excess O2 at which combustion efficiency
starts decreasing define an operating range. The wider this range, the higher the
potential for performance improvements.

The excess O2 operating range changes with load and operating conditions. If this
operating range has not been established, it is recommended that it be established, at
least at full load, by reducing the excess O 2 until CO emissions and/or unburned carbon
start increasing significantly. For such measurements, a CO monitor and LOI analysis
are required.

3-9
EPRI Licensed Material
Step Three: Determine Optimization Potential/Can Optimization Alone Meet Established Objectives?

Excess O2 (baseline vs. Minimum O2 level)

Indicate the excess O2 operating range at full load as follows:

x Enter 1 if the baseline excess O2 is within 0.5 percentage point from the
minimum excess O2,

x Enter 2 if the baseline excess O2 is within 0.5 and 1.5 percentage point
from the minimum excess O2, or

x Enter 3 if the baseline excess O2 is at least 1.5 percentage points higher


than the minimum excess O2.

Operating Flexibility of Burner Tilts (only in the case of T-fired boilers)

Burner tilt has an impact on NOx emissions. While in most cases increasing tilt
increases NOx (see Figure 3-5), under certain circumstances, (see Figure 3-6), the
opposite may be true. Also, tilt affects combustion efficiency (up tilt reduces the coal
particle residence time) and boiler outlet steam temperatures. The higher the flexibility
to change burner tilt the higher the potential for performance impacts.

0 .8 0 600
N O x E m is s io n s (L b /M B tu )

N O x E m is s io n s (p p m )

U n co n tro lled
0 .6 0 450

0 .4 0 300

C o n tro lled

0 .0 0 0
-1 5 -1 0 -5 0 +5 +10 +15 +20 +25

B u r n e r T ilt A n g le (d e g )

S o u r c e : U ta h P o w e r & L ig h t C o m p a n y , H u n te r U n it 2

3-10
EPRI Licensed Material
Step Three: Determine Optimization Potential/Can Optimization Alone Meet Established Objectives?

Figure 3-5
Effect of Burner Tilt Position on NOx Emissions for Baseline (Uncontrolled) and
Low-NOx (Controlled) Operation--400 MW Tangential-Fired Boiler

Operating Flexibility of Burner Tilts (only in the case of T-fired boilers)

Indicate the burner tilt operating range at full load as follows:

x Enter 1 if the burner tilts are not operational (e.g., stuck),

x Enter 2 if the burner tilts are operational, but over a limited range
(e.g., -15 to +10 degrees), or

x Enter 3 if the burner tilts are operational over the full operating range,
typically -30 to +30 degrees.

0.70 525
NOx Emissions (Lb/MBtu)

0.68 510

NOx Emissions (ppm)


0.66 495

0.64 480

0.62 465

0.60 455
-20 -10 0 +10 +20

Burner Tilt Angle (deg)

Source: Potom ac Electric Power Company, Potom ac River Station

Figure 3-6
Effect of Burner Tilt Position on NOx--105 MNW Tangential-Fired Boiler

3-11
EPRI Licensed Material
Step Three: Determine Optimization Potential/Can Optimization Alone Meet Established Objectives?

Operating Range of Air and Gas Dampers

The more flexibility to adjust gas and air dampers, the higher the potential for
performance improvements, for example:

x Air dampers which control the air flow rate to the four corners of T-fired boilers or
to front versus rear wall of opposed wall-fired boilers,

x Air dampers which control the air flow to individual burners, or

x Gas dampers in split backpass boilers.

Operating Range of Air and Gas Dampers

Indicate the level of flexibility of air and/or gas dampers as follows:

x Enter 1 if adjustable dampers do not exist or the dampers can not be


adjusted, either because they are not operational (e.g., stuck) or
because they can not be controlled remotely,
x Enter 2 if the dampers can be adjusted, but to a limited extent (e.g.,
half operating range), or
x Enter 3 if the dampers can be adjusted over the full operating range.

Primary Air to Fuel Ratio (PA/Fuel)

PA/Fuel ratio has an impact on both NOx emissions and combustion efficiency. The
relationship between NOx and primary air velocity (an indicator of PA/Fuel ratio) for
an 105 MW T-fired boiler is shown in Figure 3-7 (see next page). The more flexibility
the boiler has to adjust PA/Fuel ratio, the higher the probability of performance
improvements. However, this flexibility is typically limited by available primary air
fan capacity and pulverizer (in the case of coal-fired power plants) operating
constraints.

3-12
EPRI Licensed Material
Step Three: Determine Optimization Potential/Can Optimization Alone Meet Established Objectives?

Primary Air to Fuel Ratio (PA/Fuel)

Indicate the level of flexibility of PA/Fuel ratio as follows:

x Enter 1 if there is no operating flexibility; PA/Fuel ratio has to comply


with predetermined settings,
x Enter 2 if some operating flexibility exists, for example, PA/Fuel ratio
may change within the range 1.8 to 2.0, or
x Enter 3 if there is more flexibility with the PA/fuel ratio, for example
PA fuel ratio may change within the range of 1.5 to 2.5.

0.45 337.5
NOx Emissions (Lb/MBtu)

NOx Emissions (ppm )


0.40 300

0.35 262.5

0.30 225
70 80 90 100 110

Average Primary Air Velocity (ft/sec)


Note: Tests conducted at reduced load of 35 MW
Source: Potomac Electric Power Company, Potomac River Station

Figure 3-7
Effect of Varying the Ratio of Primary Air to Coal on NOx Emissions--105 MW
Tangential-Fired Boiler

Other Control Variables

Control variables other than those discussed above may be available, depending on the
configuration of the boiler. “Control variables” are defined as all the operating
parameters which can be changed remotely (from the control room). Such variables
may include tempering air dampers and exit temperature control of the pulverizers or
the ability to mix different coals.

3-13
EPRI Licensed Material
Step Three: Determine Optimization Potential/Can Optimization Alone Meet Established Objectives?

Other Control Variables

Indicate the level of flexibility provided by these categories of control variables


as follows:

x Enter 1 if there is no operating flexibility,

x Enter 2 if some operating flexibility exists, for example, air registers


may change by up to 30% of the original setting, or

x Enter 3 if the control variables can change throughout their “design”


operating range.

Ability to Change Equipment Settings

This category includes changes which cannot be made from the control room, but
require manual adjustment of equipment. In most cases, these changes can be made
while the boiler is operating. For example, adjustments of burner settings can be done
while the burner is operating. Some of the pulverizer changes may require the
pulverizer to be off-line, but this does not mean that the boiler must be off-line as well;
adjustments could be made to one pulverizer at a time, while the boiler is operating at
or near full load.

Burner Settings

Changing the original burner settings may improve boiler performance. Burner
settings which should be considered include:

x air registers,

x air sleeve dampers and coal nozzle axial position (in some wall-fired boilers),

x yaw of burners and/or overfire air ports (in the case of T-fired boilers), and

x relationship between burner tilt and overfire air tilt (in the case of T-fired boilers); in
most cases, the overfire air tilt angle is set based on the burner tilt angle; the original
setting could be changed or the overfire air tilt may be decoupled from the burner
tilt.

These parameters are usually set during combustion system tuning which is carried out
by the burner vendor. While readjustment of these parameters may yield performance
improvements, it is not always easy to do so. Constraints may relate to:

3-14
EPRI Licensed Material
Step Three: Determine Optimization Potential/Can Optimization Alone Meet Established Objectives?

x contractual requirements specified by the burner vendor regarding operation and


maintenance of the combustion system,

x physical layout of the combustion system which makes it difficult to adjust burner
settings, and

x limited personnel with experience to make the necessary adjustments.

3-15
EPRI Licensed Material
Step Three: Determine Optimization Potential/Can Optimization Alone Meet Established Objectives?

Burner Settings

Indicate the level of flexibility to adjust the burner settings:

x Enter 1 if there is no or very limited flexibility to adjust the burner


settings as part of an optimization program,
x Enter 2 if there is some flexibility, for example, half of the burner
settings can be adjusted, or
x Enter 3 if most of the burner settings can be adjusted.

Pulverizer Settings (in case of coal-fired power plants)

Very often pulverizer performance can be improved through changes such as:

x journal spring pressure,

x adjustment of classifier blades and clearances,

x adjustment of flow straighteners, and

x changes in outlet temperature set-point.

Pulverizer Settings (in case of coal-fired power plants)

Depending on the flexibility to adjust pulverizer settings:

x Enter 1 if there is no or very limited flexibility to adjust the pulverizer


settings as part of an optimization program,
x Enter 2 if there is some flexibility, for example, half of the pulverizer
settings can be adjusted, or
x Enter 3 if most of the pulverizer settings can be adjusted.

Other Equipment Settings

Changes in the settings of other equipment may help improve overall plant
performance, for example, in some wall-fired boilers with low NOx burners, the burner
coal nozzle is adjustable. Changing the position of the nozzle affects NOx emissions,
LOI, and boiler efficiency.

3-16
EPRI Licensed Material
Step Three: Determine Optimization Potential/Can Optimization Alone Meet Established Objectives?

Other Equipment Settings

Depending on the flexibility to adjust the settings of other equipment:

x Enter 1 if there is no other equipment,


x Enter 2 if there is one other piece of equipment that can be adjusted, or
x Enter 3 if there are more than one piece of equipment that can be
adjusted.

Hardware Modifications

This category includes hardware modifications which are not considered major in
terms of amount of investment, but can improve plant performance significantly.
Examples of such modifications include:

x modifications of the air distribution system,

x coal pipe orificing, and

x installation of dynamic classifiers.

In most cases, hardware modifications require the equipment to be off-line. In some


cases, boiler shut-down may be avoided, for example, dynamic classifiers and coal pipe
orificing may be done one pulverizer at a time while the boiler is operating.

Air Distribution Modifications

Better control of air flow distribution along the height of the combustion zone and the
individual burners usually results in better performance. In many cases, the air flow
distribution can be improved through:

x addition of dampers,

x addition of turning vanes, and

x adjustment of existing directional plates/vanes.

An example of a successful application of such modifications is Potomac Electric Power


Co.’s (PEPCo) Potomac River #4 optimization which is described in Box 3-2 (see next
page).

3-17
EPRI Licensed Material
Step Three: Determine Optimization Potential/Can Optimization Alone Meet Established Objectives?

Air Distribution Modifications


x Enter 1 if air distribution modifications will not be included in the
optimization program, or
x Enter 3 air distribution modifications will be included in the
optimization program.

Note: there is no “Enter 2” option in this and several of the following boxes

Coal Pipe Orificing

In case of significant coal pipe-to-pipe flow imbalance (more than 5% from uniform
flow distribution), orificing may improve the coal flow distribution, combustion
efficiency, and overall plant performance. Figure 3-8 provides an example of the

3-18
EPRI Licensed Material
Step Three: Determine Optimization Potential/Can Optimization Alone Meet Established Objectives?

Box 3-2 PEPCo Modifies the Air Distribution System for NOx Optimization

Installation of splitter dampers, tuning vanes and windbox compartmentalization at PEPCo’s Potomac
River 4 balanced the air distribution from the front to the rear corners and resulted in a more uniform
air distribution in each burner. While it was not possible to assess the NOx reduction achieved with
these modifications (because other modifications were made at the same time followed by optimization),
they were a contributing factor to the overall NOx reduction achieved which reached 30-35%.

Hot Air from


Before Modifications Air Heater

PEPCO’s Potomac River 4


To Front To Rear
Corners Corners Combustion Air System

Furnace
Hot Air from
Air Heater

After Modifications Splitter Damper

To Front To Rear
Corners Corners

Turning Vane

Windbox Compartmentalization
Furnace

Source: PEPCO

3-19
EPRI Licensed Material
Step Three: Determine Optimization Potential/Can Optimization Alone Meet Established Objectives?

beneficial impacts of improved fuel balancing, as well as higher coal fineness at Union
Electric’s Meramec #4 unit (a front wall-fired 360 MW boiler retrofitted with B&W’s
XCL burners). Improving the coal balance from ± 10% to ± 5% from the uniform flow
distribution reduces unburned carbon in the flyash by 2-3 percentage points.

25

+/- 10% Fuel Balance


99.0% 50 Mesh
20 70% 200 Mesh
% Carbon in Flysash

15
+/- 5% Fuel Balance

10
+/- 10% Fuel Balance
99.9% 50 Mesh
80% 200 Mesh
5
+/- 5% Fuel Balance

0
0 25 50 75 100

% of Coal A (Kerr McGee mine)


Remaining is Coal B (Rend Lake mine)

Source: Union Electric

Figure 3-8
Union Electric/Meramec Unit 4: Unburned Carbon vs. Coal Fineness, Coal Flow
Imbalance and Coal Blend

Coal Pipe Orificing

x Enter 1 if coal pipe orificing will not be included in the optimization


program, or

x Enter 3 if coal pipe orificing will be included in the optimization


program.

3-20
EPRI Licensed Material
Step Three: Determine Optimization Potential/Can Optimization Alone Meet Established Objectives?

Mill Modifications

Mill modifications, including installation of exhausters, riffle distributors, and dynamic


classifiers, may result in better coal fineness and coal size distribution control, which in
turn improves combustion efficiency and plant performance.

Coal fineness and size distribution have a significant effect on the combustion process,
and control of size distribution can be used to reduce LOI. Generally, higher coal
fineness results in better coal combustion. Coarse coal particles (usually defined to be
larger than 150 microns [remaining on 100 mesh]) have been shown to be the primary
source of unburned carbon. The percentage of coal remaining on 50 mesh (300 micron)
is increasingly used as the key indicator of adequate coal size distribution.

Figure 3-9 shows the effect of improved size distribution on LOI at PEPCo’s Potomac
River #4, a 100 MW T-fired boiler without combustion NOx controls. This
improvement was the result of pulverizer maintenance and tuning. As this figure
shows, the reduction of larger particles (percentage remaining on 50 mesh [300 micron]
was reduced from 3% to 0.5%, resulting in lower LOI even though the percentage
through 200 mesh (75 micron) did not change significantly. Furthermore, improved
coal size distribution allows operation at lower excess O2, which reduces NOx
emissions.

20 Before After
18 Plus 50 mesh 2 to 3% 0.5%
16 Minus 200 mesh 74% 73%
14
LOI (%)

12
10 Before mill maintenance
8
6 After mill
4 maintenance
2
0
0 1 2 3 4 5 6
Economizer O2 (%)
Source: PEPCo

Figure 3-9
PEPCo’s Potomac River 4/Effect of Mill Maintenance on LOI

The beneficial effect of higher coal fineness and improved size distribution on both LOI
and NOx emissions is also demonstrated by Figure 3-10 which shows the test results

3-21
EPRI Licensed Material
Step Three: Determine Optimization Potential/Can Optimization Alone Meet Established Objectives?

from Gulf Power’s Smith #2 (a 180 MW T-fired boiler) retrofitted with ABB/CE’s
LNCFS III.

0.4 300
increa
sing e
xce
NOx emissions (lbs/Mbtu) ss oxy
gen

NOx emissions (ppm)


0.3 225

0.2 150
low fineness
0.1 medium fineness 75
high fineness

0 0
0.0 2.0 4.0 6.0 8.0 10.0 12.0 14.0
LOI (%)
Source: Southern Company Services

Figure 3-10
Smith 2/Relationship Between LOI, NOx and Coal Fineness

As coal fineness improves, the same NOx emission level can be achieved with lower
LOI and excess O2. For example, 225 ppm (0.30 lbs/MBtu) NOx level can be achieved
with low fineness2 coal resulting in 10-11% LOI or with high fineness coal resulting in
3% LOI. Such relationships are useful in optimizing unit performance to satisfy its
operating objectives (e.g., NOx requirements and LOI constraints).

One of the options used to improve and control coal size distribution is dynamic
classifiers which achieve a better particle size distribution than static classifiers, (see
Figure 3-11). Additional advantages of dynamic classifiers include:

x better control of particle size distribution,

x improved flexibility which is particularly important when the coal quality varies,
and

x better load response and unit turndown.

2
The low and high fineness represent the minimum and maximum fineness achievable with the
pulverizers available at Smith 2; different pulverizers may achieve wider range of finenesses.

3-22
EPRI Licensed Material
Step Three: Determine Optimization Potential/Can Optimization Alone Meet Established Objectives?

100

90

% Passing
80
Static
Dynamic
70

60
60 100 140 180 220 260 300

Sieve (micron)
Source: EnTEC

Figure 3-11
Typical Particle Size Distribution with Static and Dynamic Classifiers

Mill Modifications

x Enter 1 if mill modifications will not be included in the optimization


program, or

x Enter 3 if mill modifications will be included in the optimization


program.

Expected Performance Improvements

Based on the Total Score in Table 3-1, the user’s project falls in one of the classifications
shown in Table 3-2.

Table 3-2
Expected Performance Improvements

Project Classification Total Score % NOx Reduction Heat Rate


Improvement
Group A 100-160 5.0 - 15.0 0.00 - 0.75
Group B 160-240 15.0 - 30.0 0.50 - 1.25
Group C 240-300 25.0 - 40.0 1.00 - 1.50
The NOx reduction for Groups A, B and C is shown in Figure 3-12.

3-23
EPRI Licensed Material
Step Three: Determine Optimization Potential/Can Optimization Alone Meet Established Objectives?

45
40 Group C
% NOx Reduction 35 Group B
30
25
Group A
20
15
10
5
0
Increasing Operating Flexibility
Worsening Operating Condition of Existing Equipment

Figure 3-12
Utility Experience with Combustion Tuning & Optimization NOx Reduction
Achieved

The expected performance improvement should be adjusted further based on the


objective of the previous tuning as shown in Tables 3-2a through d.

x If the objective of the previous tuning was “safe operation,” use the upper end of the
projected performance for both NOx and heat rate, as shown in Table 3-2a.

Table 3-3
Previous Tuning Objective – Safe Operation

Project Classification NOx Heat Rate


Group A 10.0 - 15.0 0.25 - 0.50
Group B 22.5 - 30.0 0.75 - 1.25
Group C 32.5 - 40.0 1.25 - 1.50

x If the objective of the previous tuning was “heat rate improvement,” use the upper
end of the projected NOx reduction, but the lower end of the heat rate
improvement, as shown in Table 3-2b.

Table 3-4
Previous Tuning Objective – Heat Rate Improvement

Project Classification NOx Heat Rate


Group A 10.0 - 15.0 0.0 - 0.40
Group B 22.5 - 30.0 0.50 - 0.75
Group C 32.5 - 40.0 1.00 - 1.25

3-24
EPRI Licensed Material
Step Three: Determine Optimization Potential/Can Optimization Alone Meet Established Objectives?

x If the objective of the previous tuning was “NOx reduction,” use the lower end of
the projected NOx reduction range, but the upper end of the heat rate improvement,
as shown in Table 3-2c, and

Table 3-5
Previous Tuning Objective – NOx Reduction

Project Classification NOx Heat Rate


Group A 5.0 - 10.0 0.25 - 0.50
Group B 15.0 - 22.5 0.75 - 1.25
Group C 25.0 - 32.5 1.25 - 1.50
x If the objective of the previous tuning was “combined NOx reduction and heat rate
improvement,” use the lower end of both NOx reduction and heat rate
improvement, as shown in Table 3-2d.

Table 3-6
Previous Tuning Objective – NOx Reduction & Heat Rate Improvement

Project Classification NOx Heat Rate


Group A 5.0 - 10.0 0.0 - 0.40
Group B 15.0 - 22.5 0.50 - 0.75
Group C 25.0 - 32.5 1.00 - 1.25
The user is encourage to override the above performance predictions, if he/she has a
better understanding of expected performance improvements. For example, prior
efforts to improve heat rate may have proven that the maximum heat rate reduction
may be limited to a specific level which is outside the ranges provided in Table 3-2.

LOI, CO emissions, and opacity can be kept at present levels or improved slightly
depending on the level of improvements being sought for NOx and heat rate; the
higher the NOx and heat rate improvements sought, the lower the possibility for
significant LOI, CO and opacity improvements.

Compare potential performance improvements to project objectives and decide if


plant optimization is a feasible and suitable option.

If optimization seems to meet objectives, proceed to Step 4. If it does not, hardware


modifications should be considered. For NOx Control Retrofit Options, see the
following EPRI publications: 1) Retrofit NOx Controls for Coal-Fired Utility Boilers -
1996 Update Addendum (TR-102906-Addendum), and 2) Retrofit NOx Control
Guidelines for Gas- and Oil-Fired Boilers (TR-102413).

3-25
EPRI Licensed Material

4
STEP FOUR: IDENTIFY THE MOST COST-EFFECTIVE

TYPE OF OPTIMIZATION

Step 1
Tune unit &
Establish baseline performance

Step 2
Establish clear needs
& objectives
Consider optimization in
combination with other
options such as:
Step 3
Determine optimization potential/ z NOx controls (Low NOx
Can optimization alone meet burners, SNCR, reburning,
established objectives? NO and SCR)

z Hardware modifications
YES for heat rate improvements
Step 4
Identify the most cost-effective
type of optimization

Step 5
Select the best optimization
product for your application

4-1
EPRI Licensed Material
Step Four: Identify the Most Cost-Effective Type of Optimization

Types of Optimizations:

x Stand-alone (previously referred to as Off-line/One-time)

x On-line/advisory

x Closed-loop

The selection of the most appropriate and cost-effective optimization type depends on
the following:

x Availability of Digital Control Systems (DCS) and Data Acquisition Systems (DAS),

x The need for continuous vs. one-time optimization,

x The performance improvement objectives, and

x The cost-effectiveness of alternatives.

A. Availability of DCS and DAS

Availability of DCS and DAS are essential for on-line/advisory and closed-loop
optimization. DCS and DAS make stand-alone optimization easier to carry out, but
they are not essential. Therefore, if the plant under consideration does not have nor is there a
plan to install DAS and DCS, it is not suitable for on-line/advisory and closed-loop
optimization.

B. Continuous vs. One-time or Periodic Optimization

If continuous performance optimization is desirable, stand-alone systems are not suitable. One-
time or periodically repeated stand-alone optimization may be suitable and more cost-
effective in cases in which the plant needs to reach a certain performance level below
which there is no strong incentive to optimize further. An example is the case where
there is a need to limit NOx emissions beyond a certain level (e.g. 0.50 lbs/MBtu), but
there is not an incentive to achieve the minimum NOx possible.

If continuous optimization is needed and the desirable optimization objective is at the upper end
of the projected performance improvement range with optimization software, on-line/advisory or
closed-loop systems are required. Some utilities have decided to utilize closed-loop
optimization on the basis that it does not require continuous support from plant
performance engineers (after it has been installed and calibrated) and the plant
operator does not need to be involved continuously to implement optimum settings.

4-2
EPRI Licensed Material
Step Four: Identify the Most Cost-Effective Type of Optimization

C. Performance Improvement Objectives

If the performance improvement sought is in the upper portion of the projected performance
improvement range, on-line/advisory and closed-loop systems are more likely to achieve this
objective. Stand-alone optimization is feasible, but its cost-effectiveness needs to be
assessed in more detail with consideration given to site-specific requirements such as
the required frequency of optimizations, the availability and cost of plant performance
engineers, and the potential benefits at the plant and system levels. For example, if the
optimization is to be repeated very frequently, the costs of such activity may increase to
the same level or higher than on-line/advisory and closed-loop systems.

D. Cost-Benefit of Alternative Optimization Types

As Figure 4-1 shows, higher performance may be achieved with on-line/advisory and
closed-loop systems, but at a higher cost than stand-alone optimization. The cost
effectiveness of each option depends on the cost versus benefit as measured by net
present value (NPV), return on investment, payback period, and cost-benefit ratio.
These measurements of cost effectiveness can be calculated using the Table 4-1. Box 4-1
(on the next page) provides guidance on the use of Table 4-1.

Closed-Loop
On-Line/
Advisory
% Performance Stand-Alone
Improvement
(e.g., % NOx
Reduction)

Quick tuning
to new operating mode

Costs ($)

Figure 4-1
Optimization Cost Effectiveness

4-3
EPRI Licensed Material
Step Four: Identify the Most Cost-Effective Type of Optimization

Box 4-1 Software Guidance on Table 4-1

For system requirements, installation and loading of the Excel files included on the
floppy disk, see Appendix A. The Excel file “Table 4-1.xls” provided on the floppy
disk should be used in Step 4 of the guidelines to carry out a cost-benefit analysis of
alternative optimization types. A print out of the Excel spreadsheet appears on pages
4-5 to 4-6. The printed version is for illustration purposes and uses default values
which are based on a typical 500 MW coal-fired boiler. Step 4 of the guidelines walks
the user through the key questions which need to be addressed to adjust the default
values in the electronic version of Table 4-1 to better reflect their own technical
requirements and financial assumptions.

In the Excel file, values appearing in a blue font are user-defined inputs which the
spreadsheet uses to automatically calculate other parameters and cost-benefit
measures. The calculated values and the text appear in black font and they are locked.
To assure consistency, inputs which appear more than once in the spreadsheet are
linked so that the user inputs the value only once (where it appears in blue). The
spreadsheet begins with Up Front Costs and Annual Costs, continues with Up Front
(one time) Benefits and Annual Benefits, and at the bottom provides Cost-Benefit
Analysis Measures.

The user can examine the formulas used throughout the tables in several different
ways. The user can read a description of a formula in English by moving the Excel
cursor on to cells in the left most column to pop up the memo function. Only cells
with a small red spot in the upper right hand side of their cells contain memos. These
formula descriptions also are all listed in the manual as Appendix C.

The values that are used as defaults within Table 4-1 fall within a range that has been
found to be typical based on optimization experience to date. This experience and the
typical ranges are presented in this manual in shaded boxes. The general text in this
section provides background information on all the inputs while the text in the shaded
boxes provides step-by-step instructions.

4-4
EPRI Licensed Material
Step Four: Identify the Most Cost-Effective Type of Optimization

Table 4-1
Power Plant Optimization Cost-Benefit Analysis

COSTS Optimization Types


Stand-alone O n-line/advisory Closed-loop
Up Front Costs

Up Front Software License Fees ($) $30,000 $130,000 $170,000

Additional Computer Software and Hardware ($) $5,000 $5,000 $5,000


Com puter so ftw are $0 $0 $0
Com puter hardw are $5,000 $5,000 $5,000
Instrum entation and co ntrols (I&C) $0 $0 $0
Data acquisition system (DAS) $0 $0 $0

Installation and Calibration ($) $33,000 $44,040 $50,120


O utside technical support total $14,600 $14,600 $17,000
-Num ber of m an days 12 12 15
-Average daily rate for outside technical support $800 $800 $800
-Miscellaneous expenses (Trav el, reports, ov erhead, etc.) $5,000 $5,000 $5,000
In-house technical su pport total $18,400 $29,440 $33,120
-Num ber of m an days 25 40 45
-Average daily rate for in-house technical support $320 $320 $320
-Cost m ultiplier for ov erhead 2.3 2.3 2.3
Pow er plant dow ntim e/non-econom ic dispatch $0 $0 $0

Training ($) $0 $0 $0

Power Plant Hardware Modifications ($) $0 $0 $0

TOTAL UP FRONT COSTS $68,000 $179,040 $225,120

Annual Costs (O&M incl. Recalibration)


Annual Software License & Maintenance Fees ($) $5,000 $13,000 $17,000

Technical Support ($) $31,720 $24,040 $20,360


O utside technical support total $17,000 $13,000 $13,000
-Num ber of m an days 15.0 10.0 10.0
-Av erage daily rate for outside technical support $800 $800 $800
-Miscellaneous expenses (Trav el, reports, ov erhead, etc.) $5,000 $5,000 $5,000
In-house technical su pport $14,720 $11,040 $7,360
-Num ber of m an days 20 15 10
-Average daily rate for in-house technical support $320 $320 $320
-Cost m ultiplier for ov erhead 2.3 2.3 2.3

TOTAL ANNUAL COSTS $36,720 $37,040 $37,360

BENEFITS (Losses)

Up Front (one time) Benefits


NPV of Deferred Costs ($) $0 $0 $0
Deferred costs $0 $0 $0
How long does optim izatio n d elay investment? (in month s) 0 0 0
NPV of Avoided Costs ($) $0 $0 $0
Avoided costs $0 $0 $0
When w ould investm ent have been im plemented (in months) 0 0 0

TOTAL UP FRONT BENEFITS $0 $0 $0

Annual Benefits
Annual Avoided Costs ($/yr) $0 $0 $0

Fuel Cost Savings ($/yr) $130,165 $244,059 $406,765


Baseline heat rate (Btu/kWh) 9,000 9,000 9,000
Unit heat rate im provem ent (% Pts) 0.40 0.75 1.25
Fu el cost ($/MBtu) 1.27 1.27 1.27
Unit output (MW) 500 500 500
Capacity factor (%) 65.0 65.0 65.0

4-5
EPRI Licensed Material
Step Four: Identify the Most Cost-Effective Type of Optimization

Table 4-1 Cont’d.


O&M Impacts ($/yr) $0 $0 $0
Waterwall corrosion $0 $0 $0
Operating flexibility $0 $0 $0

Value of Change in Unit Availability ($/yr) $0 $0 $0


Change in equivalent availability (%) 0 0 0
Value of an additional % point ($/%-yr) 0 0 0

Value of Change in Unit Output ($/yr) $0 $0 $0


Change in output (MW) 0 0 0
Incremental cost of replacement power ($/MWh) 0.00 0.00 0.00
Capacity factor (%) 65 65 65
Percentage of operating time affected (%) 0 0 0

Benefits Due to Emission Reductions


NOx Emissions
Avoided fines/penalties ($/yr) $0 $0 $0
Annual value of NOx emission credits ($/yr) $0 $0 $0
-Value of NOx emission credits ($/ton removed) 0 0 0
NOx emission credits (tons/yr) 320.3 640.6 960.9
-NOx reference level for credits (lbs/MBtu) 0.500 0.500 0.500
-NOx emission reduction below reference level (%) 5.0 10.0 15.0
-Unit output (MW ) 500 500 500
-Unit baseline heat rate (Btu/kWh) 9,000 9,000 9,000
-Capacity factor (%) 65 65 65

SO2 Emissions
Avoided fines/penalties ($/yr) $0 $0 $0
Annual value of SO2 emission credits ($/yr) $6,150 $11,530 $19,217
-Value of SO2 emission credits ($/ton remov ed) 100 100 100
SO2 emissions reduction (tons/yr) 61.50 115.30 192.17
-Baseline SO2 emissions (lbs/MBtu) 1.20 1.20 1.20
-Baseline unit heat rate (Btu/kW h) 9,000 9,000 9,000
-Unit heat rate improvement (%) 0.40 0.75 1.25
-Unit output (MW ) 500 500 500
-Capacity factor (%) 65 65 65

CO Emissions
Avoided fines/penalties ($/yr) $0 $0 $0

Opacity
Avoided fines/penalties ($/yr) $0 $0 $0

CO2 Emissions
Annual value of CO2 emission credits ($/yr) $0 $0 $0
-Value of CO2 credits ($/ton remov ed) 0 0 0
CO2 emissions reduction (tons/yr) 10,686 20,036 33,393
-Baseline CO2 emissions (lbs/MBtu) 208.52 208.52 208.52
-Baseline unit heat rate (Btu/kWh) 9,000 9,000 9,000
-Unit heat rate improv ement (%) 0.40 0.75 1.25
-Unit output (MW) 500 500 500
-Capacity factor (%) 65 65 65

Annual benefits before diminishing effectiveness factor ($/yr) $136,314 $255,589 $425,982
Diminishing effectiveness factor 0.50 0.75 0.90
ACTUAL ANNUAL BENEFITS ($/yr) $68,157 $191,692 $383,384

FINANCIAL ASSUMPTIONS
Book life of the project (default 5 years) 5.0 5.0 5.0
Discount rate (%) (default 4.9%) 4.9 4.9 4.9

INTERMEDIARY FIGURES
Net annual benefits ($) $31,437 $154,652 $346,024
PV of future net annual benefits ($) $136,484 $671,417 $1,502,254
Annual depreciation (straightline) $13,600 $35,808 $45,024

COST-BENEFIT ANALYSIS RESULTS


Net Present Value (NPV) $68,484 $492,377 $1,277,134
Return on Investment (ROI as %) 26 66 134
Payback Period (simple payback in months) 26.0 13.9 7.8
Benefit-Cost Ratio 1.0 2.8 5.7

4-6
EPRI Licensed Material
Step Four: Identify the Most Cost-Effective Type of Optimization

Background and Instructions for Completing Table 4-1

COSTS

Costs for optimization are broken down into two categories: Up front costs (including
license fees, additional computer software and hardware, installation & calibration,
training, and, when applicable, power plant hardware modifications) and Annual costs
(including annual license fees and operating and maintenance costs for both outside
and in-house technical support).

UP FRONT COSTS

Up Front License Fees

Up front license fees may apply to a unit, a multi-unit power plant, or power system in
which the optimization software is used and may include other items such as:

x commercial software which are needed to operate the optimization system,

x technical support to install and calibrate the optimization system, and

x training.

Up Front License Fees

Default Inputs:
x Stand-alone: $30,000
x On-line/advisory: $130,000
x Closed-loop: $170,000

Vendors have quoted up front fees for stand-alone systems as low as $15,000 and
as high as $60,000 per boiler. Similarly, on-line/advisory and closed-loop
systems have been quoted as low as $100,000 and as high as $250,000 per boiler.
In most cases, these costs are for turn-key systems which include software license,
computer hardware, outside technical support, and training. In such cases, avoid
entering the costs twice; enter the cost once (e.g., as Up Front License Fees).
Annual licensing and/or maintenance fees, which are usually in the range of
10% of the Up front fee, are recorded under Annual O&M Costs (see further
explanation below). The buyer should clarify with the optimization software
vendors what are the proposed prices and what is included.

4-7
EPRI Licensed Material
Step Four: Identify the Most Cost-Effective Type of Optimization

Additional Computer Software and Hardware

Depending on the circumstances, additional components may be needed such as:

x Computer software which is required to operate the optimization system or is a


recommended add-on to make data analysis or electronic communication easier,

Computer Software - Default Input: $0

x Computer Hardware; In Table 4-1, it is assumed that an additional personal computer


is needed which is not included in the Up front fee. The computer hardware is
assumed to be a Pentium-based IBM-compatible system. A few optimization
software packages may require a more powerful computer such as a Sun
Microsystems Sparc. In the latter case, Table 4-1 should be updated to reflect higher
costs. In this entry you may also include computer-related components such as
modems and communication ports.

Computer Hardware - Default Input: $5,000

x Instrumentation and controls-related components; in most cases, especially in stand-


alone optimization, there is no need for special instrumentation or controls.
However, some instrumentation, such as CO monitor and LOI measurement device,
may be considered essential depending on the optimization objective. CO monitor is
essential in most cases. A LOI monitor may be necessary, especially in cases where
LOI is expected to be affected significantly or where LOI is already a concern.

Instrumentation and Controls (I&C) - Default Input: $0

x Data acquisition-related software and hardware; in most cases, the existing DAS is
adequate, or the optimization software includes the required DAS capabilities.
However, the adequacy of the DAS-optimization system interface should be
confirmed and if additional components are needed, they should be included in the
cost-benefit analysis.

Data Acquisition System (DAS) - Default Input: $0

Installation and Calibration

Installation of the software:

x In the case of stand-alone applications, installation is limited to establishing data


acquisition links which usually take less than a day,

4-8
EPRI Licensed Material
Step Four: Identify the Most Cost-Effective Type of Optimization

x In the case of on-line/advisory and closed-loop applications, 1-2 weeks should be


allowed for installation.

Calibration of the software:

x Stand-alone applications require a minimum of 60-80 “data sets” (complete sets of


data from steady state plant operation) per load, which means a minimum of 10
working days, assuming the data are acquired electronically and 6-10 sets of data
per (8-hour) day can be obtained. However, there are cases (especially units which
require longer to achieve steady state performance or when manual data input is
required) which performed only 3-4 tests per day. One factor which adds to the time
required to obtain data and calibrate the model is the need for LOI measurements.
If required, the test team may have to wait until adequate amount of ash has been
collected to measure LOI. If the model needs to be calibrated in more than one load,
the above estimate of time needs to be multiplied by the number of loads.

x Experience has shown that initial calibration takes 3-4 calendar months. Typical
level of effort is:

¡ 30-50 working days for on-line/advisory, and

¡ 35-55 working days for closed-loop.

Outside Technical Support: is usually included in the fixed fee charged for the
optimization software. However, it is important to clarify how much support is
provided (in terms of man-days in the field and support by phone or e-mail). Two-
three weeks of on-site support seem to be an appropriate level at this point in the
development of the software. In the future, these requirements may decrease. At
present, if the vendor claims that installation/ calibration can be done in less than the
average time (see Table 4-1), it should document this with data other utility sites.
Reduced technical support by the vendor may compromise the objectives of the
optimization program and/or may increase the work required by in-house staff.

Outside Technical Support - Defaults Inputs:


x Stand-alone: 12 man-days
x On-line/advisory: 12 man-days
x Closed-loop: 15 man-days

Typical average daily rates for outside technical support are $800/day, and
miscellaneous expenses for travel, report writing, etc. over the time period
required typically add up to $5,000.

4-9
EPRI Licensed Material
Step Four: Identify the Most Cost-Effective Type of Optimization

In-house Technical Support: is critical for the success of the project, but very often is
overlooked in the evaluation of the various options. Activities which should be
included are:

x time needed to collect coal and ash samples,

x time and costs for analyzing coal and ash samples

x increased emphasis on instrumentation calibration, and

x consultations between performance engineers and plant operators regarding


implementation of optimum setting.

Based on the above assessment regarding the duration of the installation and
calibration of optimization software, the following estimates should be considered:

In-house Technical Support - Default Inputs:


x Number of man-days: varies for each type of optimization.
¡ Stand-alone: 25 days (range is 20-30 days),
¡ On-line/advisory: 40 days (range is 30-60 days),
¡ Closed-loop: 45 days (range is 40-70 days).
x Average daily rate for in-house technical support: $320/day
x Cost multiplier for overhead: 2.3

Power Plant Downtime/Non-Economic Dispatch: In most cases, calibration of the


optimization software does not require a unit outage or load reduction. However, in
some cases non-economic dispatch may be needed to obtain data from operating
conditions which are outside the typical range.

Power Plant Downtime/Non-Economic Dispatch - Default Input: $0

Determining the cost of non-economic dispatch involves the following steps:


x define clearly (along with the optimization vendor) the tests which
result in non-economic operating conditions,
x determine their impact on key parameters, especially unit output (MW),
heat rate, O&M costs, reliability, and emission rates,
x estimate the time the unit will be in each non-economic dispatch, and
x estimate the total cost due to non-economic dispatch and insert value of
result in Table 4-1.

4-10
EPRI Licensed Material
Step Four: Identify the Most Cost-Effective Type of Optimization

Training

Training is usually included in the up front software license fee. The importance of
training relates to the plant owner’s strategy regarding long-term utilization of the
software, and the general plant O&M management approach. If the plant owner relies
more on outsourcing, limited training is needed (e.g., less than one week). However,
adequate “outside technical support” should be provided under the annual O&M costs.
Many plant owners prefer to build in-house expertise to use the software, in which
case, more training may be needed (e.g., two weeks).

In terms of normal operation of the optimization software, the need for training is the
highest for stand-alone and the lowest for closed-loop applications. Stand-alone
systems require well-trained staff, because of the need to repeat the optimization
frequently, if the desirable performance improvement is to be sustained. On-
line/advisory optimization requires similar training because the plant staff
(performance engineers and plant operators) needs to be well-aware of how to use the
optimization system because it decides whether or not to implement the optimum
settings. Closed-loop systems require minimum training (relative to the other two
options), they require more in-depth training for interfacing the optimization software
with the control system.

Training - Default Input: $0

Assume that training costs are included in the up front license fee.

Power Plant Hardware Modifications

If hardware modifications are included in the optimization project (see Step 3), the
capital costs associated with such modifications should be included. Because the
objective of most optimization projects is to use optimization software to avoid the need
for hardware modifications or reduce their scope, the default value of this entry is zero.

Power Plant Hardware Modifications Default Input: $0

ANNUAL COSTS (O&M Including Recalibration)

Annual O&M costs are expenses which incur every year starting immediately after the
initial installation and calibration has been completed. For the purposes of this cost-
benefit analysis, it is assumed that the up-front costs incur also at the end of calibration
period.

4-11
EPRI Licensed Material
Step Four: Identify the Most Cost-Effective Type of Optimization

Annual Software License and Maintenance Fees

In addition to the up front license fee (discussed above), very often vendors charge an
annual fee which varies considerably with the vendor and the market conditions.
Usually, this fee provides the user with:

x updated versions of the software, including advanced (new) features

x versions in new operating platforms (e.g., Windows NT), and

x remote maintenance and user support.

It is important to clarify both the price and the scope of the annual license/AF fee.

Annual Software License Fees - Default Inputs:

Annual license fees are assumed to be:


x $5,000 for stand-alone systems, and
x 10% of the up-front license fee for on-line/advisory and closed-loop
systems.

Technical Support

On-going technical support and maintenance depends on:

x the type of optimization; stand-alone and on-line/advisory usually require more


involvement of plant personnel than closed-loop, and

x recalibration frequency; plants which experience significant changes in the plant


operating objectives or characteristics (e.g., after a combustion NOx control retrofit
or fuel switching) will need more technical support, by both outside organizations
and in-house staff.

Recalibration is a potentially time-consuming activity especially for stand-alone


systems. From the on-line/advisory and closed-loop systems, some have automatic
(dynamic) recalibration capabilities, while others require the user to specify when they
are to be recalibrated (e.g., GNOCIS is recalibrated every 6 months).

Outside Technical Support: This is on-site technical support above and beyond what is
included in the annual license/maintenance fees (see above). Higher outside technical
support is needed for stand-alone optimization software, especially if the utility does
not have dedicated staff for such activity.

4-12
EPRI Licensed Material
Step Four: Identify the Most Cost-Effective Type of Optimization

Outside Technical Support - Default Inputs:


x Stand-alone: 15 man-days
x On-line/advisory: 10 man-days
x Closed-loop: 10 man-days
x Average daily rate for outside technical support: $800/day
x Miscellaneous expenses: $5,000 for travel, report writing, etc.

In-house Technical Support: In particular, stand-alone and on-line/advisory system


will require some commitment from the plant performance engineer, plant operator,
and test support staff to:

x monitor the optimization system and keep it calibrated,

x implement the optimum advice,

x periodically check certain instrumentation, and

x obtain flyash samples for LOI analysis, etc.

Provided that the optimization system works reliably and does not require major
reconfiguration and maintenance, closed-loop systems require less on-going technical
support than stand-alone or on-line/advisory systems. However, if the software
experiences problems or resetting of the control loops is required, technical support
from both in-house staff and outside organizations may be needed. Whether in-house
staff will be used or not depends on the level of training provided, their availability,
and preferences of the plant owner.

In-house Technical Support – Default Inputs:


x Stand-alone: 20 man-days
x On-line/advisory: 15 man-days
x Closed-loop: 10 man-days
x Average daily rate for in-house technical support: $320/day
x Cost multiplier for overhead: 2.3

It should be noted that all annual O&M costs associated with optimization software are
treated as fixed O&M.

4-13
EPRI Licensed Material
Step Four: Identify the Most Cost-Effective Type of Optimization

OPTIMIZATION BENEFITS

This section describes the assumptions that are used to determine the benefits of an
optimization project. Similar to the costs, the benefits are broken down into two
categories. Up front benefits consist of the benefits from deferring or avoiding the need
to install capital equipment (usually NOx control equipment). All the other benefits are
derived from more efficient plant operation and are thus counted annually. Annual
benefits include fuel cost savings, O&M impacts, improved unit availability, increased
unit output, and emission reductions.

UP FRONT (ONE TIME) BENEFITS

NPV of Deferred Costs

If an optimization package improves plant performance and thereby delays the


installation of emission control equipment, the plant operator benefits by being able to
use this capital for other purposes in the meantime. For example, an optimization
package could defer the need for installation of a low NOx burner or selective catalytic
reduction (SCR) system to year 2002 when maximum allowable NOx emission
requirements are expected to be reduced further. Given the large cost of these
environmental control options and the time frame involved, the value of these deferred
costs can be substantial.

Based on the input of the deferred costs, Table 4-1 determines the net present value of
this deferment using the discount rate provided by the user.

NPV of Deferred Costs - Default Input: $0

NPV of Avoided Costs

In some cases, the performance improvement from an optimization package may be


enough to avert the need for a capital investment that would have otherwise been
required. For example, an optimization package could eliminate the need to install
NOx controls (e.g., low NOx burners, reburning, SNCR and SCR), or it could reduce
the scope of the NOx control retrofit project (e.g., instead of low NOx burners with
overfire air, install only low NOx burners).

Table 4-1 takes into account the avoided costs and the point time this item would have
taken place and calculates its net present value by taking into account the time value of
money.

NPV of Avoided Costs - Default Input: $0

4-14
EPRI Licensed Material
Step Four: Identify the Most Cost-Effective Type of Optimization

ANNUAL BENEFITS

Table 4-1 provides a step-by-step process to determine the annual benefits due to
optimization. First the user is guided to provide inputs based on which the annual
benefits (“ideal annual benefits” reflecting the initial performance improvements) due
to optimization are estimated. Then, a “diminishing effectiveness factor” is applied to
take into account potential degradation of performance with time, after initial
optimization has been performed. These items are found at the bottom of the benefits
section of the spreadsheet, just before financial assumptions. Such degradation is real
and varies with the optimization type.

Diminishing effectiveness factor

Definition: percentage of the initial benefits which will actually be realized over time
given the gradual deviation between actual plant performance and software predictions.

Given industry experience, we estimate that the effectiveness of stand-alone


optimization will achieve 40-70% of their initial benefits. This is mainly due to
changes in the operating characteristics of the plant, including coal quality, plant
operators’ preferences, equipment degradation, etc. On-line/advisory
optimization is expected to maintain a higher level (60-90%) of the initial
benefits, while closed-loop will maintain an even higher level (80-95%). Default
inputs for the diminishing effectiveness factor used in Table 4-1 are as follows:

Default Inputs:
x Stand-alone: 0.50
x On-line/advisory: 0.75
x Closed-loop: 0.90
These default values will be updated based on further evaluation of actual
performance achieved by power plant optimization in utility boilers.

Annual Avoided Costs

Annual Avoided Costs are annual savings due to an optimization project which
avoided the implementation of an option with higher annual operating and
maintenance costs. Examples of such avoided or deferred costs include:

x increase in annual O&M costs due to a low NOx burner and overfire air
retrofit

x annual O&M costs associated with urea or ammonia injection of an SNCR


system which was avoided because of the utilization of optimization software

4-15
EPRI Licensed Material
Step Four: Identify the Most Cost-Effective Type of Optimization

x difference in annual O&M costs between (a) an SCR system which is designed
to achieve a certain NOx reduction and (b) a combination of optimization
software plus SCR system; the latter SCR has lower NOx emission at its inlet
and therefore has smaller catalyst and lower consumption of ammonia.

Annual Avoided Costs - Default Input: $0

Fuel Cost Savings

Annual fuel cost savings are calculated from the inputs listed in the shaded box below.
One of the key factors in the calculation is determination of the degree of heat rate
improvement from an optimization system. Heat rate is affected by a number of
operating parameters including:

x Excess O2,

x unburned carbon (LOI),

x CO emissions,

x Other unit operating variables (e.g., overfire air, combustion air distribution and
burners out of service) which may impact stack and steam temperatures,

x steam outlet temperatures, and

x auxiliary power consumption.

During the actual optimization, the impact of each of these parameters on heat rate
needs to be assessed in detail. For the purposes of these guidelines, the results of Step 3
are adequate to assess the cost-effectiveness of the different optimization options.

The baseline unit heat rate and the unit heat rate improvement used in the above
formula should be based on a weighted average which reflects unit dispatch profile.
The heat rate improvement range provided above is typical of coal-fired baseloaded
units. In case of intermediate load or cycling units, the heat rate improvement may be
higher (up to 4-5%).

4-16
EPRI Licensed Material
Step Four: Identify the Most Cost-Effective Type of Optimization

Fuel Cost Savings - Default Inputs:


x Baseline unit heat rate (Btu/kWh): 9,000
x Unit heat rate improvement (%): 0.40-1.25
(depending on type of optimization--see below)
x Fuel cost ($/MBtu): 1.27 3
x Unit size (MW): 500
x Capacity factor (%): 65
Unit heat rate improvements vary with optimization type and the specific
operating conditions of each unit. The user should input the heat rate
improvement predicted during Step 3 of these guidelines (see Tables 3-2a
through 3-2d) or should override it if s/he has a better estimate (based on site-
specific considerations). From the range developed in Step 3 (e.g., heat rate
improvement: 0.40 - 1.25%), stand-alone optimization is expected to achieve heat
rate improvement closer to the lower end of the range (e.g., 0.40%), on-
line/advisory in the middle (e.g., 0.75%), and closed-loop at the upper end of the
range (e.g., 1.25%). Default inputs used in Table 4-1:
x Stand-alone: 0.40 percentage points,
x On-line/advisory: 0.75 percentage points, and
x Closed-loop: 1.25 percentage points.

O&M Impacts

In addition to impacts which directly affect the unit heat rate (which have been
included in the previous input), there may be others impacts (both positive and
negative) on operation and maintenance of the unit including:

x impact on waterwall corrosion, and

x unit operating flexibility such as rate of load change and limited operating range of
certain control variables.

Waterwall corrosion may occur especially in cases where the optimization results in
lower (than baseline) excess O2 and/or staged combustion. However, there is not yet
adequate information to quantify the impacts due to waterwall corrosion. EPRI is
monitoring the impacts of staged combustion on waterwall corrosion and is expected to
release guidelines on how to assess such impacts. EPRI is carrying our research on
waterwall corrosion and will continue to provide the latest information in this field.

3
Default Fuel cost used $1.27/MBtu for Illinois #6 coal delivered to plants in the East/West Central US.
Source: EPRI Technical Assessment Guide (TAG), P-6587L, Vol. 1, 1989.

4-17
EPRI Licensed Material
Step Four: Identify the Most Cost-Effective Type of Optimization

Similarly, quantification of the benefits or costs due to reduced rate of load change or
limited operating flexibility is site-specific and not easy to generalize.

Considering that no such impacts have been documented in plants which have used
optimization software, we assume that these impacts are negligible.

O&M Impacts Default Input: $0

Value of Change in Unit Availability

Operating changes may have an impact on unit reliability and availability. Examples
of impacts include:

x waterwall corrosion may increase the number of forced outages, and

x coal-biasing increases the duty (amount of coal handled) of certain pulverizers


which may experience increased forced outages, if appropriate predictive
maintenance is not used.

In most cases, impacts on unit availability can be eliminated. Waterwall corrosion is


the only impact which needs to be assessed in more detail, especially for units which
have a history of corrosion.

Value of Change in Unit Availability - Default Inputs:


x Change in equivalent availability (%): 0
x Value of an additional % point ($/year-%): 0

Value of Change in Unit Output

In most cases, unit output does not increase as a result of optimization. This is mainly
because the objective of most optimization program has been to reduce NOx emissions
and/or heat rate while maintaining the same unit output. However, there may be cases
where a unit has been derated and optimization results in recovery of the lost capacity.
Incremental cost of replacement power is the cost differential between this and the next
unit in the dispatch order for obtaining the capacity change (gained or lost MW). In
some cases, it may be the price at which this capacity can be purchased in the open
market.

4-18
EPRI Licensed Material
Step Four: Identify the Most Cost-Effective Type of Optimization

Value of Change in Unit Output ($/yr) - Default Inputs:


x Change in output (MW): 0
x Incremental cost of replacement power ($/MWh): 0
x Capacity factor (%): 65
x Percentage of operating time affected (%): 0

Benefits Due to Emission Reductions

NOx, SO2, CO2, CO and opacity may be reduced as a result of power plant
optimization. In addition to the deferred and/or avoided costs which have been
mentioned already, the benefits from reducing these pollutants fall into the following
categories:

x Avoided Fines (Penalties); such fines may be imposed if the unit does not comply with
environmental regulations,

x Emission Credits; these are allowances which are accumulated as a result of emission
reductions.

For all pollutants, but especially for NOx, the emission reduction requirements should
be clarified to avoid double-counting. For example, if optimization helps the power
plant achieve compliance, either an avoided fine or a deferred/avoided cost should be
recorded, not both.

NOx Emissions

Avoided Fines/Penalties: NOx emissions are usually limited below a certain level (e.g.,
under CAAA requirements). While not always the case, penalties may be imposed by
Federal EPA, State agencies or local authorities if compliance is not achieved. If
combustion optimization achieves compliance and avoids penalties, they should be
included in Table 4-1 as benefits.

Avoided Fines/Penalties ($/yr) - Default Input: $0

Annual Value of NOx Emission Credits: Credits may be generated by reducing NOx
emissions below a certain level, usually the compliance level for the unit as dictated by
unit, plant or power system NOx requirements.

4-19
EPRI Licensed Material
Step Four: Identify the Most Cost-Effective Type of Optimization

Annual Value of NOx Emission Credits ($/yr) - Default Inputs:


x Value of NOx emission credits ($/ton NOx removed) 0
x NOx reference level for credits (lbs/MBtu) 0.50
x NOx emission reduction below reference level (%) 5-15%
(depending on the type of optimization)
x Unit output (MW) 500
x Unit baseline heat rate (Btu/kWh) 9,000
x Unit capacity factor (%) 65

NOx reference level could be either the baseline NOx emissions or a NOx emission
level below which NOx credits are accumulated. If the user knows the value of NOx
($/ton) and wants to estimate the total value due to the NOx reduction achieved by the
optimization project, s/he should use the baseline NOx emissions. Alternatively, NOx
credits may be accumulated after a certain level of NOx has been achieved. For T-fired
units, such NOx level may be 320 ppm (0.43 lbs/MBtu), which satisfies a presumed
compliance level of 340 ppm (0.45 lbs/MBtu) and provides some safety margin.

NOx emission reduction due to optimization has been estimated in Step 3 of these
guidelines. The following clarifications should be made:

x The % NOx reduction entered into the spreadsheet should be in reference to “NOx
reference level” which could be different from the baseline NOx emissions,

x From the NOx reduction range predicted in Step 3, stand-alone optimization is


expected to achieve NOx reduction at the lower end of the estimated range, on-
line/advisory in the middle and closed-loop in the upper end.

SO2 Emissions

Avoided Fines/Penalties: SO2 emissions are limited to a certain level either on a unit-
by-unit basis or through a system-wide maximum. Penalties which may be imposed by
Federal EPA, State agencies, or local authorities are site specific. Usually, combustion
optimization helps reduce SO2 emissions through improvements in plant efficiency and
heat rate. Because such improvements are usually no more than 1-2% for full load and
less than 5% at low loads, optimization is not expected to reduce SO2 emissions
significantly enough to be the main reason for avoiding penalties. However, if such
penalties are avoided through a combination of options with plant optimization being
one of them, a portion of the avoided penalties should be included in Table 4-1.

Avoided Fines/Penalties ($/yr) - Default Input: $0

4-20
EPRI Licensed Material
Step Four: Identify the Most Cost-Effective Type of Optimization

Annual Value of SO2 Emission Credits: Such credits can be generated by reducing SO 2
emissions below a certain level, usually the compliance level for the unit dictated by
unit, plant or power system SO2 requirements.

Annual Value of SO2 Emissions Credits ($/yr) - Default Inputs:


x Value of SO2 credits ($/SO2 ton removed): 100
x Baseline SO2 emissions (lbs/MBtu) 1.20
x Unit baseline heat rate (Btu/kWh) 9,000
x Unit heat rate improvement (%) 0.4 - 1.25
(depending on optimization type and specific unit operating
conditions)
x Unit output (MW) 500
x Unit capacity factor (%) 65

CO Emissions

CO emissions are usually regulated to 100 ppm. Most optimization projects are carried
out in such a way that this limit is not exceeded. Where CO emissions are above the
allowable limit, optimization could be used to reduce them. In this case, the project
should be credited for avoiding fines.

Avoided Fines/Penalties ($/yr) - Default Input: $0

Opacity

Similarly to CO emissions, opacity is regulated by local and federal standards.


Limiting opacity below the allowable limit is usually a constraint in power plant
optimization and therefore no deterioration is expected as a result of optimization. In
cases where the opacity does not meet the regulatory limit, the optimization project
should take credit for opacity reduction, including potential avoidance for fines.

Avoided Fines/Penalties ($/yr) - Default Input: $0

CO2 Emissions

Presently, there are no regulations limiting the release of CO2 emissions. While it is
unlikely that such regulations imposing fines would be enacted in the foreseeable
future, it is possible that CO2 emission reduction may have a value ($/ton). In this case,
power plant optimization which results in heat rate improvement should take into
account reduced CO2 emissions as an additional benefit. Most international
organizations (e.g the UN Inter-governmental Panel on Climate Change) have
suggested the values ranging from 20 to 100 $/ton of CO2 removed.

4-21
EPRI Licensed Material
Step Four: Identify the Most Cost-Effective Type of Optimization

Annual Value of CO2 Emission Credits ($/yr) - Default Inputs:


x Value of CO2 credits ($/ton CO2 removed): 0
x Unit baseline CO2 emissions (lbs/MBtu): 208.521
x Unit baseline heat rate (Btu/kWh): 9,000
x Unit heat rate improvement (%): 0.4 - 1.25
(depending on optimization type and specific unit
operating conditions)
x Unit output (MW): 500
x Unit capacity factor (%): 65
1
The Baseline CO2 emissions default 208.52 reflects the following assumptions: Illinois #6 coal
(see EPRI TAG for coal analysis and heating value) and 20% excess air.

Cost-Benefit Analysis Results

Because different accounting procedures and measures are used by different


companies, care must be used in interpreting the cost-benefit measures estimated in
Table 4-1. The beginning of the Cost-Benefit Results includes inputs for the book life of
the project and the assumed discount rate. Table 4-1 uses a default book life for the
investment (5 years) and a default discount rate (4.9%), but the users may input their
own assumptions. Intermediary financial figures that may be useful in decision making
are also provided. The cost-benefit analysis results are calculated at the bottom of the
spreadsheet. Based on the above inputs, Table 4-1 calculates the following cost-benefit
measures:

x Net present value of implementing each optimization option: NPV of optimization


by type = NPV of Net annual benefits (Annual benefits - Annual costs) - Up front
costs

NPV is the most useful measure of a project’s net benefits because it takes into
account the costs and benefits throughout the life of the project, as well as the time
value of money. Being measured in present dollars, NPV can be added up and
easily compared to other projects, even with fluctuations in revenues.

x Return on Investment (%): ROI = Net annual benefits (Annual benefits - Annual
costs) - annual depreciation / Up front costs

ROI does not take in to account the time value of money or cash flow profile of the
project. It also does not take into account the overall scale of a project relative to
other projects.

4-22
EPRI Licensed Material
Step Four: Identify the Most Cost-Effective Type of Optimization

x Payback Period (simple payback in months): PP = Up front costs / Net annual


benefits (Annual benefits - Annual costs which is the same as first-year net annual
savings)

The simple payback period is a useful tool for describing investment projects, but
ignores the order in which cash flows come within the payback period and
subsequent cash flows after the payback period.

x Benefit-Cost Ratio: BC Ratio = PV of total future benefits / Up Front Costs

Also known as the profitability index, the B-C ratio takes into account discounted
cash flows but, as a ratio, cannot be added up in the same way as you can add up
NPV values

4-23
EPRI Licensed Material

5
STEP FIVE: SELECT THE BEST OPTIMIZATION

PRODUCT FOR YOUR APPLICATION

Step 1
Tune unit &
Establish baseline performance

Step 2
Establish clear needs
& objectives
Consider optimization in
combination with other
options such as:
Step 3
Determine optimization potential/ z NOx controls (Low NOx
Can optimization alone meet burners, SNCR, reburning,
established objectives? NO and SCR)

z Hardware modifications
YES for heat rate improvements
Step 4
Identify the most cost-effective
type of optimization

Step 5
Select the best optimization
product for your application

5-1
EPRI Licensed Material
Step Five: Select the Best Optimization Product for your Application

Selecting an Optimization Package

In most cases, selection of an optimization product involves:

x development of design and performance specifications, and

x evaluation of alternative products.

The rigor of the selection process depends on:

x the type of optimization: a utility’s evaluation of software associated with one-time


optimization may not be as rigorous as evaluation of on-line/advisory or closed-
loop applications, because the latter implies longer-term commitment and higher
costs,

x number of power plants which will utilize optimization software: the larger the number of
plants and therefore the level of commitment, the more need for a rigorous
assessment, and

x the utility’s approach regarding procurement of products and services: some utilities may
prefer establishing a close working relationship with the software vendors in which
case informal evaluation and negotiations of contractual or joint venture terms
dictate the final selection of an optimization tool. In other cases, utilities may prefer
to thoroughly evaluate every optimization tool under consideration.

Independently of the level of detail, there are a number of key factors which should be
considered in the evaluation. The purpose of this section is to identify these factors and
provide general guidance on how to select the best optimization software for a given
project.

Key Factors

Key factors which should be considered in evaluating optimization products include:

x Demonstrated track record of the optimization product in similar applications,

x Experience of the software supplier in supporting product deployment,

x Total cost of applying the optimization product, and

x Benefits from the utilization of the optimization product.

In most cases, the first three factors determine the final selection. The fourth factor
(benefits) is very important too. However, it is often difficult to estimate the difference

5-2
EPRI Licensed Material
Step Five: Select the Best Optimization Product for your Application

in benefits between the various software. The few rigorous evaluations performed so
far have concluded that the expected benefits from various software for each type of
optimization are within r 5-10%, which is well within the level of accuracy of the
analysis. Any larger differences were based on benefits claimed by the vendors, but
not confirmed with actual field experience.

Box 5-1 (see next page) provides an example of a detailed software specification and
evaluation for neural network-based software which was carried out at Tennessee
Valley Authority’s (TVA) for the Kingston power plant.

Comments on the Key Factors for Evaluating Optimization Software

A. Demonstrated track record of the optimization product in similar applications

If the optimization software has been used in a power plant similar to the one under
consideration, the risks associated with the optimization project are lower and the
performance benefits can be predicted with better accuracy. Furthermore, the
personnel of the plant which utilizes the software can be contacted to provide feedback
on the overall experience.

Engineering judgement should be used to decide if certain experience is applicable to a


plant under consideration. Of course, the more similar the power plant is to ones
which have used plant optimization, the better. However, general optimization
experience is applicable to a broad categories of power plants. For example, experience
from the application of optimization software to a wall-fired boiler burning coal is
directly relevant to a T-fired boiler burning coal. However, the same experience is not
directly relevant to a coal-fired cyclone boiler or an oil-fired unit.

How to assess the experience of an optimization software?

x Visit EPRI’s Power Plant Optimization Web Site (http://www.epriweb.com/


gg/98funders/ppo/index.html); it includes an up-to-date list of power plants
which have used optimization software,

x A list of optimization applications up to May 1998 is included in EPRI’s publication


TR-111316 (Proceedings: Second Annual EPRI Workshop on Power Plant
Optimization, held in St. Louis, MO on May 12-13, 1998),

5-3
EPRI Licensed Material
Step Five: Select the Best Optimization Product for your Application

Box 5-1 TVA’s Experience in Selecting a Neural Network-based Optimization Software for
Kingston #9

In June 1997, TVA selected a neural network-based optimization software for its
Kingston #9 coal-fired unit. The objectives of this project were to:

x demonstrate that optimization software is a feasible and practical option for


performance improvement (especially NOx control)

x assess the costs and benefits of such an option, and

x build in-house expertise needed to carry out similar projects throughout the
TVA power system (tentatively 59 units have been identified for
optimization).

Because of the level of commitment and the potential benefits, TVA decided that the
optimization software selection deserved detailed specification and evaluation. TVA
took the following steps:

A. Assessment of experience base of commercial optimization software

An industry survey was carried out to familiarize the utility staff with the state of the
technology and industry’s experience. This was carried out mainly through requests to
software suppliers for information on their products and the industry sites using them.
Based on this information, TVA narrowed down the list of qualified bidders to four and
invited them to TVA’s offices for presentations and detailed discussions. Finally, TVA
visited selected utility sites which use such optimization software and held extensive
meetings with plant personnel. These meetings were considered to be particularly
useful.

B. Detailed specification document prepared and sent to the vendors

The specification included what the TVA team considered to be the best features of
commercially available software. These features were identified in the previous step
and included: sensor validation, model retraining, financial predictor, and contribution
analysis. Furthermore, the specification provided a description of the Kingston #9 unit,
the vendor scope of work, DCS/communication requirements, optimization software
capabilities, technical support requirements, implementation schedule, licensing
agreement preferences, and evaluation criteria.

C. Bid evaluation and vendor selection

Key evaluation criteria included: power plant optimization experience, neural network
experience, neural network support capabilities, training, documentation and overall
costs. TVA requested the prices of various options in order to assess the cost of
implementing optimization throughout the power system (enterprise license), at a

5-4
EPRI Licensed Material
Step Five: Select the Best Optimization Product for your Application

specific site (plant) and in a single unit.

As part of the evaluation process, TVA sent to the vendors a set of operational data
(approximately 30 megabytes of 10-minute averages representing 30 days plant
operation) and asked the vendors to analyze the data and identify the relationships
between the key variables. Most vendors responded within a week; one of them
responded within one working day (a 3-day weekend followed the time the data were
sent to the vendors). This “blind test” was particularly useful because it provided an
insight as to the vendors’ experience and capabilities. Follow-up questions showed
which vendors had extensive experience and which lacked understanding of power
plant engineering (design and operation), the utility business, and in some cases, neural
network capabilities.

D. Contract Award

A company-wide license was finally negotiated to purchase GNOCIS.

E. Implementation

Successful and timely implementation of the project required close coordination


between TVA and the vendor, especially on the following activities:

x TVA provided plant data for process model building prior to delivery,

x unit walk-downs and review of I/O points,

x identification of key independent and dependent parameters, and problem


formulation, and

x installation and calibration of the model at the site.

As a result, GNOCIS was installed as a closed-loop system in only 10 weeks. During


implementation, TVA is comparing the performance achieved with the optimization
system to pre-optimization (baseline) performance.

The TVA’s experience suggests that:

x the key factors which contributed to the final selection were: proven field
experience of the software, experienced team, and costs,

x the evaluation process, especially the “blind test,” was particularly useful in
assessing the experience of the suppliers and their ability to support the
application, and

x the performance and expected benefits of the evaluated products was “too
close to call.”

5-5
EPRI Licensed Material
Step Five: Select the Best Optimization Product for your Application

x Request from the vendors to provide a list of the sites which have used their
software, as well as key contacts,

x Call selected utilities (at least two for each software being considered) and asked
them about their overall experience,

x Visit at least one site for each optimization software;

¡ select the sites which resemble more closely the application you are
considering; for example, if you plan to install a closed-loop optimization
system, select a site which utilizes optimization software in a closed-loop
mode over one that is on-line/advisory; however, if you have not decided
which operating mode is best for your application, it may be worth
visiting both closed-loop and on-line/advisory sites to assess their
advantages and disadvantages,

¡ during the plant visit, it is more important to spend time with key plant
personnel rather than tour the site; especially in the case of closed-loop
systems where there is not much available to see. In most cases,
discussion with plant personnel provides invaluable insights into the
process of planning and implementing optimization systems.

B. Experience of the software vendor in supporting product deployment

The software vendor should have adequate experience in all aspects of power plant
optimization, including:

x power plant design and operation,

x utility business, and

x key components of the optimization software system, especially data acquisition, data
validation, neural networks or statistical analysis modules, and optimization
algorithms.

Most importantly, the vendors should understand the unit’s flexibility and capabilities
to establish realistic goals for the optimization program. Considering that some of the
power plant optimization vendors are small companies with limited track records, it
may be necessary to assess their financial depth and business viability.

A first assessment of the vendors’ experience can be done by asking them to submit
information on prior projects, as well as resumes of key personnel who will be involved
in an optimization project. A more thorough assessment requires direct (person-to-
person) interaction. Opportunities to do so, include:

5-6
EPRI Licensed Material
Step Five: Select the Best Optimization Product for your Application

x a working meeting between the utility and the optimization vendor to review the
requirements of the project, identify the key issues associated with the project, and
discuss the potential approach which could be followed,

x performing a “blind test” (see Box 5-1),

x carrying out a demonstration project in one unit before committing to a multi-unit or


system-wide optimization program.

C. Total cost of applying the optimization product

Table 4-1 can be used to evaluate alternative software products by revising the default
inputs to reflect data provided by the software vendors or developed by the utility. A
few comments on the Table 4-1 inputs follow.

x License Fee: It is important to clarify:

What is provided under the license fee. Is it a run-time version of the model or a tool
which allows utility staff to solve a variety of optimization problems? Does it
include such details regarding item such as:

¡ First year’s annual fee,

¡ Additional software which may be needed,

¡ Computer hardware,

¡ Number of days on-site for installation, calibration and technical support,

¡ Additional hours or days of technical support either on-site or via


telephone or email, and

¡ Days and number of people to be trained.

If these items are not included in a fixed price fee provided by the vendor,
they should be added to the total project cost estimate (Table 4-1).

x Computer hardware, I&C and DAS: to the extent that additional computer
hardware, instrumentation, controls (e.g., new DCS) and data acquisition
system are needed, the user should make sure that there is consistency in
assumptions between software; for example, if the utility decides to add an
on-line LOI analyzer, its cost should be added to all software being
evaluated.

5-7
EPRI Licensed Material
Step Five: Select the Best Optimization Product for your Application

x Installation & Calibration: In addition to the cost of outside technical support, which
is usually provided by the vendors as a fixed price, the utility should ask vendors to
estimate and document the duration of the installation and package calibration. For
example, a software package which requires a separate calibration at various loads,
will need more time to be calibrated than a model which treats load as a variable.

Particular attention should be paid to the data provided by the vendors in case they
differ significantly from the default values in Table 4-1.

x Training: Most optimization software packages are user friendly in terms of normal
utilization. Therefore, training needs and costs provided by the various vendors
should be similar. If not similar, it is worth clarifying further the differences. The
utility should consider asking the vendor to provide the costs of training as a
separate cost item. This is particularly important if the utility plans to build in-
house capability to do future optimization projects, in which case it may need more
training.

x Power Plant Hardware Modifications: usually plant hardware modifications do not


differ with optimization software being considered.

x Annual O&M Costs: The vendors should be asked to clarify the following:

¡ What does the annual fee include? Does it provide all new releases of
the software?

¡ How often and long does it take to recalibrate the model? Is it done
automatically or does the software requires “retraining” similar to the
original calibration? Note:

Ÿ some models “learn on-line,” but others need to be off-line to


be recalibrated,

Ÿ some models require separate calibration at each load which


is more time-consuming,

¡ Does recalibration require technical support from the vendor or can it


be completed by in-house staff?

The licensing fee and, in general, the contract with the vendor is negotiable and
depends on market conditions (level of competition, how badly the vendor wants the
job, potential future business as a result of the project under consideration, etc.).
Each vendor has some flexibility to reduce the price being offered (after all software
development expenses are sunk costs which the vendor hopes to recover), but a
significant percentage of the costs are labor costs associated with installation,

5-8
EPRI Licensed Material
Step Five: Select the Best Optimization Product for your Application

calibration, and technical support which can not be reduced significantly. In fact,
utilities should be careful to ensure that adequate level of technical support is included
in the vendor’s proposal; otherwise, they may have to increase the estimated level of
effort for in-house staff.

D. Benefits from the utilization of the optimization product

In general, differentiation between the expected benefits from one software versus
another is difficult because:

x there is a lack of adequate experience and information,

x the limited experience available suggests that there is no significant difference in the
final outcome between various models of the same optimization type, and

x utilities which have undertaken a comprehensive evaluation of different products


found that the product’s demonstrated experience, the capability of the vendor’s
team, and the costs were the dominant factors in the selection process.

If the utility decides to assess the potential performance improvements based on


information provided by the vendors, it should:

x make sure that the claimed benefits are due to the optimization software and not
due to other factors, for example:

¡ the baseline performance should reflect “well-tuned” operation; a


number of optimization projects have experience NOx emission
reductions in the 30-40% range, mainly because the combustion system
had not been tuned for many years,

¡ heat rate improvements may be influenced by weather conditions


(especially when plant testing includes both winter and summer
months) which affect the condenser backpressure and cooling water
temperature,

¡ the moisture of the coal is reduced significantly either because of


weather changes or because of changes in coal quality,

x performance improvements should represent acceptable operating conditions. In


some cases, results have been published which either include the best data points
from a series of different tests or include unacceptable operating conditions (e.g.,
excess air below the level most utilities consider safe for operation, or CO and LOI
above acceptable limits).

5-9
EPRI Licensed Material
Step Five: Select the Best Optimization Product for your Application

One well structured approach to estimate performance improvements is to perform a


“blind test.” However, such a test should be designed to be unbiased and as
representative as possible of actual plant operation. Important considerations for a
blind test:

x Select a representative set of operating data covering at least 30-days; the more
complete the data-set, the better; typical number of variables: 100-400; data
provided in 5-10 minute averages reflecting steady-state (not transient) conditions,

x State clearly the operating constraints and equipment limitations, so all vendors
abide by the same constraints,

x Provide clear optimization objectives, and

x Send the data set to vendors and ask them to provide the optimum settings of the
key control variables, the expected outcome (performance improvements), the
control variables in order of decreasing priority relative to the optimization
objective and the confidence level of the process models developed using the data.

While potentially useful, the blind test could be time-consuming for both the utility and
the vendors. If the plant does not have DCS, collecting such data may be a very time-
consuming activity. Also, evaluation of the results developed by the vendors requires
checking that all the operating constraints have been observed and the claimed
performance improvements can be confirmed by actual field experience.

Some vendors have designed service packages which are intended to assess the
performance improvement potential. The drawback for utilities is that they have to pay
for these assessments (usually priced at $10,000 to $30,000). However, in most cases
these costs are subtracted from future optimization projects. Furthermore, the vendors
may be willing to guarantee performance improvements. Such assessments may be
particularly suitable when a utility has to reduce the number of optimization products
it considers to two and needs more information on all aspects of the products (costs,
benefits, and experience of the vendor’s team) to make a decision.

5-10
EPRI Licensed Material

A
SOFTWARE USER’S GUIDE

System Requirements

Hardware Requirements

x Industry Standard Architecture (ISA) computer, such as IBM PC/AT or compatible.

x A graphics card compatible with Microsoft Windows version 3.0 or later, such as
IBM VGA, EGA, or Hercules graphics cards

x At least 2 MB of RAM

Software Requirements

x Operating system: MS-DOS version 3.1 or later and Microsoft Windows 95 or later
running in standard or 386 enhanced mode.

x Microsoft Excel Version 7.0 or later

Installation

1. You must have Microsoft Excel version 7.0 or later installed on your computer to
run the PPO Guidelines tables.

2. The PPO Guidelines disk containing the tables has been checked for viruses with
McAfee VirusScan Version 3.1.9 Deluxe and has been found to be free of viruses.

Due to some differences in Excel 7.0 and Excel 97, two sets of the Excel tables are
provided on the disk, each set in its own folder (subdirectory). The user should select
and install the appropriate version of the Excel tables. In addition to being saved into
separate folders, the Excel 97 files can be differentiated from those in Excel 7.0 by an
“E97” added to the name of the Excel file, e.g. Table 3-1E97 is Excel 97 while Table 3-1
is Excel 7.0. To optimize computer performance using the tables, copy the appropriate
tables (e.g. Table 3-1.xls, Table 4-1.xls, Table B-3.xls, Table B-5.xls, Table B-7.xls, Table

A-1
EPRI Licensed Material
Software User’s Guide

B-8.xls, Table B-9.xls, Table B-11.xls) from the disk (drive A:\) to your hard (usually
drive C:\). This can be accomplished by using Microsoft Windows Explorer:

x click on drive A:\

x open the folder containing the files saved in the version of Excel installed on
your computer,

x select all files, click Ctrl-A (all the files will be highlighted)

x click Edit

x Go to the new folder you have created on drive C:\ and double click on it

x Click Edit

x Click Paste

Close the Excel files if you opened them from disk initially and relaunch them as
needed from the copies that now reside on your hard drive.

Using the Software

The 3.5” disk that accompanies the Power Plant Optimization (PPO) Guidelines
contains tables in the form of Excel spreadsheets that can be used by the Guidelines
user to: 1) better understand how the Guidelines work and 2) actually carry out a cost-
benefit analysis including the potential performance improvements and resulting
financial savings that might be realized using PPO software on a specific boiler, given
specific technical data and financial assumptions.

The PPO Guidelines disk is meant to be used in tandem with the PPO Guidelines
manual. Both are tools utilized to lead the Guidelines user through a five step project
assessment process. To facilitate using both tools, a hard copy of every Excel table from
the disks is included in the manual at the point where it is discussed or used. The
tables on disk are not sequentially numbered because there are also numbered tables
that appear only in the manual.

In all the tables, values or text that appear in blue can be changed, while other values
and formulas that appear in black are locked. Default values which reflect typical
values are already entered, but the user should work their way through each table,
changing these default values to better reflect their own financial assumptions and the
technical circumstances of the boiler they are considering for optimization.

A-2
EPRI Licensed Material
Software User’s Guide

To help the user avoid mistakes, all the tables have built in warnings that appear when
a questionable input is entered. When an input outside a reasonable range for a given
cell is entered, a message appears warning the user (In Table 4-1 and the case study
tables based on 4-1 the message “Input outside typical range” appears in the first
empty cell below the entered input. In Table 3-1 and the case study tables based on it
the message “Bad Input” appears to the right of the input cell). Likewise, when an
alphanumeric is accidentally entered instead of a numeric value, the tables warn the
user. In Table 4-1 the message “Input Value, not Text” appears in the first empty cell
below the most recently entered input. In Table 3-1 the message “Input Value” appears
to the right of the input cell. These warning messages refer to the last input that has
been changed. For either type of error, the tables will not compute final results, cost-
benefit analysis results in Table 4-1 and Total Score for Table 3-1. The ranges that have
been programmed into the table are broad and should accommodate all plant
optimization scenarios. If for some reason, the user wishes to use inputs outside the
range limitations, he/she should contact EPRI Project Manager and ask for the table
password which is needed to unprotect the table and change the range limitations.

The following provides an overview of each Excel file:

Table 3-1

This table should be used during Step 3 of the guidelines. A print out of this table
appears on page 3-3. Based on site-specific considerations and the guidance provided
in the PPO manual, the user enters the appropriate score from 1 to 3. Using these input
scores, Table 3-1 calculates a Total Score between 100 and 300. Based on the Total
Score, a proposed project will fall into one of three categories (A, B, or C) which
indicates the potential range of improved boiler performance that can be achieved from
boiler optimization. Tables 3-2 and 3-2a to 3-2d on pages 3-24 and 3-25 of the manual
(they are not included on the disk) provide the performance improvements that can be
expected based on the Total Score from Tables 3-1.

Table 4-1

This table is a cost-benefit analysis of the potential boiler optimization project and
should be used during Step 4 of the Guidelines. A print out of the Excel file, appears
on pages 4-5 to 4-6 of the Guidelines. Step 4 of the manual walks the user through the
fine details related to refining the cost and benefit inputs to Table 4-1. Values that can
be changed appear in blue. To assure consistency, when the same value appears more
than once in a table, the value only appears in blue (i.e. is changeable) the first time it
appears. Subsequent appearances are written in black (i.e. are locked) and are linked to
the initial appearance.

A-3
EPRI Licensed Material
Software User’s Guide

Given the values entered, Table 4-1 automatically calculates the cost-benefit results (see
bottom of the table). The user can examine the formulas used throughout the table in
several different ways:

x read a description of the formulas in English by moving the Excel cursor on


to cells in the left most column to pop up the memo function. Only cells with
a small red dot in the upper right hand corner of the cell contain a memo,

x read the Excel math formulas by placing the Excel cursor directly on the
resulting cost-benefit values and looking at the Excel formula bar,

x read formula descriptions which are also listed in Appendix C of the manual.

Tables B-3, B-5, B-7, B-8, B-9, and B-11

The remaining Excel files are versions of Tables 3-1 and 4-1 that have been used for two
case studies described in Appendix B of the Guidelines. Simply reading the manual
and referring to the printed tables in the manual should be adequate to understand the
case studies. However, for users who would like to experiment with variations of the
case studies to better understand the dynamics of the analysis, all the Excel tables from
Appendix B are included on the disk. The following tables are based on Table 3-1:

x Table B-3 Case Study 1, Option 1

x Table B-5 Case Study 1, Option 2

x Table B-9 Case Study 2, single option analyzed

The following tables are based on Table 4-1 and finalize the analyses initiated in the
above options:

x Table B-7 Case Study 1, Option 1

x Table B-8 Case Study 1, Option 2

x Table B-11 Case Study 2, single option analyzed

User Tutorial

Appendix B provides two case studies illustrating how utilities used the PPO
Guidelines to carry out evaluation of different optimization types. To familiarize the
user with how these utilities used the software tables and how the user can utilize the
tables to carry out his/her own evaluation of optimization options for a specific boiler,
this tutorial walks the user through a few changes in the two primary tables, 3-1 and

A-4
EPRI Licensed Material
Software User’s Guide

4-1. By continuing the same process of changing one input at a time from the default
value in these tables to a value that more accurately reflects the circumstances of the
specific boiler and the financial assumptions of the user’s company, the tables calculate
the costs and benefits of various options.

While the case studies in Appendix B go into detail regarding technical parameters and
how to determine specific table inputs, this tutorial focuses instead on the mechanical
steps of inputting this data into the tables. For any boiler, the user would first carry out
Step 1 of the Guidelines by undertaking a quick tuning of the boiler and establishing its
baseline performance. The user would then carry out Step 2 by setting optimization
objectives.

Step 3 is the first step in the Guidelines to use a software tool, Table 3-1. The user
would open this table from his/her hard drive (see installation above) and save it
under a different name, e.g. “Table 3-1 Boiler XYZ” (for example, in Case Study 1, the
table is saved as “Table B-3” to easily identify it as the third table referenced in
Appendix B). Then, the user will modify one input at a time to reflect the requirements
and consideration of he specific boiler being evaluated.

Figure A-1 below shows the top and bottom parts of Table 3-1 (the jagged break in
vertical lines represents a jump in the table). The top box in Figure A-1, labeled
“Before,” shows Table 3-1 as it appears on the Guidelines disk. The bottom box in
Figure A-1, labeled “After,” shows how it should look after the user has saved it as
“Table 3-1 Boiler XYZ” and entered new inputs.

Breaking these changes down step-by-step, under the first topic “Information on the
last tune up,” the first category requiring an input is “When was unit last tuned?”
Reading from the shaded box presenting this question on page 3-4 of Guidelines
manual, the user will see this question as the first line requiring a score input in Table
3-1.

In this hypothetical case, boiler XYZ was tuned 18 months before which the Guidelines
indicate is a score of 2. In the table, since the default value that appears in blue in the
“Score” column is set at 1, the user should:

x click on this cell,

x delete the default value “1,”

x enter the number “2,” and

x delete the other options listed in the cell the right in the “Clarifications”
column so that the table clearly identifies the specific circumstances of this
boiler.

A-5
EPRI Licensed Material
Software User’s Guide

In the bottom box of Figure A-1, we see that based solely on this change, the table has
recalculated the ”Total Score” of boiler XYZ, changing from 100 to 130.

Before:
Criteria Score Clarifications

Information on the last tune up


- When was the unit last tuned? 1 Options: less than a year (enter 1); 1-2 years (enter 2); more than 2 years (enter 3)
- Tuning Objective/Tuned for: 1 Options: safe operation (enter 1); heat rate (enter 2); NOx (enter 3); heat rate & NOx (enter 4)
Unit Operating Flexibility (at full load)
- Fuel flow biasing capacitlity (e.g. mill capacity) 1 Options: no biasing (enter 1); some biasing, but no BOOS (enter 2); BOOS possible (enter 3)

TOTAL SCORE 100 Range: 100-300

After:
Criteria Score Clarifications

Information on the last tune up


- When was the unit last tuned? 2 18 months ago
- Tuning Objective/Tuned for: 1 Options: safe operation (enter 1); heat rate (enter 2); NOx (enter 3); heat rate & NOx (enter 4)
Unit Operating Flexibility (at full load)
- Fuel flow biasing capacitlity (e.g. mill capacity) 1 Options: no biasing (enter 1); some biasing, but no BOOS (enter 2); BOOS possible (enter 3)

TOTAL SCORE 130 Range: 100-300

Figure A-1
A Portion of Table 3-1 Before and After a Change is entered

The second category under the first topic is “Tuning Objective/Tuned for:” (see Figure
A-2 below). In the case of the boiler XYZ, let us assume that the objective was “safe
operation” which the shaded box on page 3-5 of the Guidelines indicates is a score of 1.
Since the default value in the “Score” column is already set at 1, the user does not need
to change the score. However, the user may delete the other options in the
“Clarifications” cell to the right of his/her input and add any comments they he/she
wishes pertaining to the tuning objective.

Continuing on with Step 3, the next topic in Table 3-1 is “Unit Operating Flexibility (at
full load).” The first category requiring an input is “Fuel flow biasing capability, (e.g.
mill capacity).” In the case of boiler XYZ, let us assume that some biasing is possible,
but there are no burners-out-of-service (BOOS). The Guidelines indicate this as a score
of 2. The user should:

x click on this cell,

x delete the default value “1,”

x and enter the correct value “2,” and

A-6
EPRI Licensed Material
Software User’s Guide

x change the Clarifications” column to reflect the specific circumstances of


boiler XYZ.

As shown in the “After” box of Figure A-2, with this change, the table has
automatically recalculated the Total Score for the boiler XYZ, changing from 130 to 133.

Before:
Criteria Score Clarifications

Information on the last tune up


- When was the unit last tuned? 2 18 months ago
- Tuning Objective/Tuned for: 1 Options: safe operation (enter 1); heat rate (enter 2); NOx (enter 3); heat rate & NOx (enter 4)
Unit Operating Flexibility (at full load)
- Fuel flow biasing capacitlity (e.g. mill capacity) 1 Options: no biasing (enter 1); some biasing, but no BOOS (enter 2); BOOS possible (enter 3)

TOTAL SCORE 130 Range: 100-300

After:
Criteria Score Clarifications

Information on the last tune up


- When was the unit last tuned? 2 18 months ago
- Tuning Objective/Tuned for: 1 Safe operation
Unit Operating Flexibility (at full load)
- Fuel flow biasing capacitlity (e.g. mill capacity) 2 Some biasing, but no BOOS

TOTAL SCORE 133 Range: 100-300

Figure A-2
A Portion of Table 3-1 Before and After a Second Input is Entered

By continuing on through all the topics and categories listed in Step 3 in this manner,
the user will tailor every row in the table to the specific boiler they are evaluating,
thereby completing the table. Based on the final Total Score, a proposed project will
fall into one of three categories (A, B, or C) which indicates the potential range of
improved boiler performance that can be achieved from boiler optimization.

In the hypothetical case of boiler XYZ, let us assume a final “Total Score” of 170 so that
we can see how the user would use this result from Table 3-1 to how he/she would use
Table 4-1. With a Total Score of 170, Table 3-2 on page 3-24 classifies the project as
Group B. Given the previous tuning objective of “safe operation,” Table 3-2a (on page
3-25) indicates the range of potential improvements in heat rate and NOx reduction.
The low end of the range can be reached using stand-alone optimization, the middle
end of the range by on-line/advisory, and the high end of the performance
improvement range can be met with closed-loop type optimization.

A-7
EPRI Licensed Material
Software User’s Guide

To determine the cost of reaching these improvements, the user should use Table 4-1 to
carry out a cost-benefit analysis. The cost for each type of optimization can then be
weighed against that project’s estimated performance improvements. The mechanics of
using Table 4-1 are the same as for Table 3-1. The user should open the file from
his/her hard drive, save it under a different name, and then work step-by-step through
the shaded boxes in Step 4 of the Guidelines manual to tailor all the inputs to the boiler
under consideration and the financial assumptions of his/her company.

Figure A-3 below shows the top and bottom parts of Table 4-1. The first box in Figure
A-3, labeled “Before,” shows Table 4-1 as it appears on the Guidelines disk. The
second box in Figure A-3, labeled “After,” shows how it should look after the user has
saved it as “Table 4-1 Boiler XYZ” and entered new inputs.

Breaking these change down step-by-step, under the first topic “Up Front Costs,” the
first category requiring an input is “Up Front Software License Fees.” Reading from
the shaded box presenting this cost category on page 4-7 of Guidelines manual, the user
will see this category as the first line in Table 4-1 with a value that appears in blue, i.e.
it is changeable.

A-8
EPRI Licensed Material
Software User’s Guide

Before:
COSTS Optimization Types
Stand-alone On-line/advisory Closed-loop
Up Front Costs

Up Front Software License Fees ($) $30,000 $130,000 $170,000

Additional Computer Software and Hardware ($) $5,000 $5,000 $5,000


Computer software $0 $0 $0
Computer hardware $5,000 $5,000 $5,000

COST-BENEFIT ANALYSIS RESULTS


Net Present Value (NPV) $68,484 $492,377 $1,277,134
Return on Investment (ROI as %) 26 66 134
Payback Period (simple payback in months) 26.0 13.9 7.8
Benefit-Cost Ratio 1.0 2.8 5.7

After:
COSTS Optimization Types
Stand-alone On-line/advisory Closed-loop
Up Front Costs

Up Front Software License Fees ($) $20,000 $130,000 $170,000

Additional Computer Software and Hardware ($) $5,000 $5,000 $5,000


Computer software $0 $0 $0
Computer hardware $5,000 $5,000 $5,000

COST-BENEFIT ANALYSIS RESULTS


Net Present Value (NPV) $78,484 $492,377 $1,277,134
Return on Investment (ROI as %) 34 66 134
Payback Period (simple payback in months) 22.1 13.9 7.8
Benefit-Cost Ratio 1.4 2.8 5.7

Figure A-3
A Portion of Table 4-1 Applied to Boiler XYZ; Before Use and After a Change is
Entered

For boiler XYZ, let us assume that the utility is considering application of optimization
to several boilers at the same time and that a optimization vendor that sells stand alone
optimization has offered a reduced up front software fee of $20,000 if applied to several
boilers. Since this amount is lower than default value in the “Stand alone” column, the
user should:

x click on this cell,

x delete the default value of $30,000,

x enter the correct value of $20,000,

x If the user has any comments to add to regarding this line item, the user can
input comments to the right of the optimization types columns (off the edge
of A-3).

A-9
EPRI Licensed Material
Software User’s Guide

In Figure A-3, all four measurements of project value listed under “Cost-Benefit
Analysis Results” have now been recalculated in the Stand-alone column to reflect this
improvement in price.

Continuing on with Step 4 (see Figure A-4), the next cost category is “Additional
Computer Software and Hardware ($).” In the case of boiler XYZ, let us assume that
the utility has an older computer system that is inadequate to deal with the processing
requirements of any of the optimization types and that a total of $10,000 is required to
purchase new computer equipment.

In Figure A-4, we see that Table 4-1 provides a default value of $5,000 for sub-category
“Computer hardware.” Since the case of boiler XYZ requires a greater investment, the
user should:

x click on the cell in the stand-alone column,

x delete the default value of $5,000,

x input the correct value of $10,000.

By doing so, the user will note that the table automatically recalculates the total cost for
“Additional Computer Software and Hardware ($),” increasing it from $5,000 to
$10,000 (appears in bold which above the Computer hardware sub-category). Since
Computer hardware is the only sub-category with a value entered, the “Additional
Computer Software and Hardware ($)” total equals the total computer hardware entry.

The user must repeat these changes in the cells for computer hardware in the columns
for “On-line/advisory” and “Closed-loop” as well. In the electronic version of the
table, the user will note that the values in these cells appear in blue (i.e. are changeable)
and are not linked to each other. The table is designed in this way so that varying
requirements for different optimization types can be entered and cost-benefit results
calculated accurately for each. The user should:

x click on the Computer hardware cell row in the On-line/advisory column,

x delete the default value of $5,000,

x input the correct value of $10,000, and

x repeat these steps in the Computer hardware cell row in the Closed-loop
column

As shown in the bottom box of Figure A-4, these changes have automatically been used
to recalculate the project value of the three optimization types. In this case, since the

A-10
EPRI Licensed Material
Software User’s Guide

cost of all three optimization types was increased from the default values, the project
values presented under Cost-Benefit Analysis Results have decreased. The projected
numbers for of Net Present Value, Return on Investment, and Benefit-Cost Ratio have
all dropped somewhat. The number for Payback Period has gone up, indicating a
longer period required for recouping the initial investment and consistent with a lower
project value.

Before:
COSTS Optimization Types
Stand-alone On-line/advisory Closed-loop
Up Front Costs

Up Front Software License Fees ($) $20,000 $130,000 $170,000

Additional Computer Software and Hardware ($) $5,000 $5,000 $5,000


Computer software $0 $0 $0
Computer hardware $5,000 $5,000 $5,000

COST-BENEFIT ANALYSIS RESULTS


Net Present Value (NPV) $78,484 $492,377 $1,277,134
Return on Investment (ROI as %) 34 66 134
Payback Period (simple payback in months) 22.1 13.9 7.8
Benefit-Cost Ratio 1.4 2.8 5.7

After:
COSTS Optimization Types
Stand-alone On-line/advisory Closed-loop
Up Front Costs

Up Front Software License Fees ($) $20,000 $130,000 $170,000

Additional Computer Software and Hardware ($) $10,000 $10,000 $10,000


Computer software $0 $0 $0
Computer hardware $10,000 $10,000 $10,000

COST-BENEFIT ANALYSIS RESULTS


Net Present Value (NPV) $73,484 $487,377 $1,272,134
Return on Investment (ROI as %) 30 64 130
Payback Period (simple payback in months) 24.0 14.3 8.0
Benefit-Cost Ratio 1.2 2.6 5.5

Figure A-4
A Portion of Table 4-1 Applied to Boiler XYZ; After a Second Group of Changes is
Entered

By continuing on through all the categories and sub-categories of costs and benefits
listed in Step 4 in this manner, the user will tailor every row in the table to the specific
boiler they are evaluating, thereby completing the table. With an estimate of the
potential performance improvements of each optimization type and an estimate of the
value of each optimization type, the utility will be well prepared to make a decision
regarding optimization on their boiler units.

A-11
EPRI Licensed Material
Software User’s Guide

The user is advised to review the case studies in Appendix B to familiarize him/herself
with the Guidelines before applying them to his/her own project.

A-12
EPRI Licensed Material
Case Studies

B
CASE STUDIES

Case Study 1: Allegheny Power’s Armstrong 1 Unit

Background

Allegheny Power has been a leader in utilizing combustion NOx controls and power
plant optimization software. Most of its power stations have been retrofitted with low
NOx burners including:

x Albright 1 and 2 utilizing DB Riley's CCV burners

x Albright 3 retrofitted with ABB/CE's LNCFS III

x Armstrong 1 and 2 retrofitted with Foster Wheeler's IFS burners and overfire
air

x Harrison units 1, 2, and 3 retrofitted with Foster Wheeler's IFS burners and
overfire air

x Smith 11 retrofitted with ABB/CE's LNCFS III.

These projects were driven mainly by the need to comply with the requirements of
Phase I of the Clean Air Act Amendment (CAAA). However since 1995, Allegheny has
focused its efforts in assessing the potential for further NOx emission reductions and
performance improvements utilizing power plant optimization software. Such
improvements are important in fine-tuning its future NOx compliance plans (CAAA
Title I and Phase II/ Title IV) and increasing its competitiveness in the post-
deregulation era.

As of May 1998, Allegheny has utilized optimization software in four power stations.
As shown in Table B-1, the results have been very encouraging. Simultaneous NOx
reduction and heat rate improvement was achieved in all units by utilizing
optimization software in stand-alone mode.

B-1
EPRI Licensed Material
Case Studies

Table B-1
Allegheny's Experience with Power Plant Optimization

Station Name Burner Type Optimization % NOx Reduction % Heat Rate


Software Used Achieved Improvement
Harrison 2 Front-wall Ultramax 20 0.5
Hatfield 1-3 Cell burners Ultramax 7 0.3
Ft. Martin 1 T-fired Ultramax 17 1.5
Smith 4 T-fired Boiler OP NA (ongoing) NA (ongoing)

In deciding what type of optimization to employ at Allegheny's Armstrong power


station, it was necessary to carry out a more detailed assessment. The reasons for such
assessment were:

x the number of control variables in this boiler may be much higher that in the
units shown in Table B-1; this is mainly due to the fact that coal flow rate
may be monitored in each of the 12 coal pipes;

x the potential for NOx emission trading requires increased flexibility and on-
line optimization;

x also, industry deregulation puts additional pressure to reduce production


costs, and

x it was considered important to employ software which are capable of


optimization at low loads and, if possible, during load following.

Such assessment was carried out using a beta version of the EPRI Power Plant
Optimization Guidelines. Based on the outcomes of this assessment, Allegheny is now
selecting specific software through competitive solicitation (note: this step is not
included in the PPO Guidelines).

Armstrong Unit 1

Armstrong 1 and 2 are front wall-fired boilers rated at 180 MWs each designed to burn
Eastern Bituminous coal (see Table B-2). They were originally designed and built by
Foster Wheeler in the mid-1950s, but were refurbished in the early 1990s (see Figure
B-1). Refurbishment included replacement of pressure parts and installation of Foster
Wheeler's IFS low NOx burners.

B-2
EPRI Licensed Material
Case Studies

Table B-2
Characteristics of Eastern Bituminous Coal Burned in Armstrong 1

Grindability 55
Proximate Analysis (as received)
Moisture 7.80
Volatile matter 31.82
Fixed carbon 49.05
Ash 11.33
Ash softening temperatures at reducing/oxidizing 1283/1378
conditions qC (qF)
Ultimate Analysis (% by weight)
Ash 11.33
Sulfur 1.94
H2 5.22
C 66.54
H2O 7.80
N2 1.35
O2 5.82
KJ/Kg. (Btu/lb) 27,928 (12,007)

Each unit utilizes two ball mills (see Figure B-2) feeding 12 burners which are arranged
in three rows along the front wall of the boiler. Significant imbalance has been
measured among coal pipes resulting in increased LOI (Loss On Ignition ). In most
cases, LOI averages at 12-14%. Plant engineers estimate that LOI could be reduced to
the 5-6% range with better coal flow balancing and unit optimization. Coal flow
balancing is expected to be achieved through the utilization of an electrostatic or
microwave-based coal flow measurement technique and control of primary air flow
rate. Depending on the effectiveness of coal flow balancing and optimization, a coal
additive may be used, too.

B-3
EPRI Licensed Material
Case Studies

Figure B-1
Armstrong Units 1 & 2 Boiler Arrangement

B-4
EPRI Licensed Material
Case Studies

Burners

1 2 3 4

12 5 6 11

7 8 9 10

1 3 5 2 4 6 7 9 11 8 10 12
Coal Coal
Conduits Conduits

3 way distributor

Ball mill Ball mill


pulverizer A pulverizer B

Figure B-2
Burner and Mill Arrangement

After the IFS burner installation, Armstrong 1 operates as an intermediate load unit and
generates an average 300 ppm (0.40 lbs/MBtu) of NOx emissions; as Figure B-3 shows,
NOx as low as 225 ppm (0.30 lbs/MBtu) and as high as 360 ppm (0.48 lbs/MBtu) have
been measured. Such performance satisfies present CAAA requirements, but further
tightening of NOx regulations is likely. For this reason, Allegheny is interested to
assess the potential for NOx reduction at Armstrong to assess its NOx compliance
options including system averaging.

As Figure B-4 shows, boiler efficiency varies considerably suggesting that heat rate
improvement of the order of 1% is feasible. However, such improvement may have to
be balanced against potential LOI and NOx emission reductions.

B-5
EPRI Licensed Material
Case Studies

0.5 375

0.45
N O x (Lb/M btu)

0.40 300

N O x (ppm )
0.35

0.30 225

0.25

0.20 150
50 100 150 200

Lo ad (G M W )

Figure B-3
Armstrong Unit 1 NOx Emissions After IFS Burner Installation

Boiler Efficiency
Boiler Efficiency

Load (G MW )

Figure B-4
Armstrong Unit 1 Boiler Efficiency After IFS Burner Installation

B-6
EPRI Licensed Material
Case Studies

Evaluation of Alternative Power Plant Optimization Options

As a first step, it was decided to evaluate the different types of optimization (stand-
alone, on-line/advisory and closed-loop) using the beta version of the EPRI Power
Plant Optimization Guidelines. Based on this evaluation, specific software will be
selected through competitive solicitation.

The 5-steps outlined in the Guidelines as applied to Armstrong 1 are described in the
following paragraphs.

Step 1: Quick Tuning and Establishment of Baseline Performance

Following the guidance in Step 1, a plant performance engineer finds that all plant
components are in good operating condition and decides that no changes should be
made. As a result, the baseline performance (NOx and boiler efficiency) is reflected by
the regression curves in Figures B-3 and B-4. Baseline LOI was measured at 13.2%.

Step 2: Objectives for Power Plant Optimization

Based on the above, it was determined that the primary objective would be to reduce
heat rate and LOI while maintaining NOx emissions at present levels. Preliminary
targets for heat rate and LOI reductions were set at:

x 1% improvement in heat rate, and

x LOI reduction from 13.2% to 5-6%.

While NOx emission reduction was not the primary objective, it was recognized that
NOx trading might increase the importance of NOx reduction in the future. To reflect
this, the value of NOx emissions for Allegheny was determined at an average of $400
per ton. This was based on average compliance costs and the potential value of NOx if
a trading system is established.

Other parameters, which relate to the objectives and were set at this step include:

x Incremental cost for replacement power: $20 per MWh; this was important
because Armstrong 1 is derated by 10 MWs due to opacity limits
approximately 30% of the time;

x Value of SO2 emissions: $100 per ton; note: baseline SO2 emissions were
473 ppm (1.1 lbs/MBtu);

x Project book life: 5 years; and

x Discount rate: 10.6%.


B-7
EPRI Licensed Material
Case Studies

Step 3: Determine Optimization Potential/Can Optimization Alone Meet


Established Objectives?

It was determined that two alternatives would be evaluated:

x Case 1: with monitoring of coal flow in each coal pipe and control of
imbalance through modulation of the secondary air sleeve dampers, and

x Case 2: no coal flow monitoring and control.

For each case, the electronic version of Table 3-1 of the Guidelines was used to
determine the potential performance improvement.

Case 1: Monitoring and controlling coal flow

Table B-3 is the result of tailoring Table 3-1 to the specific circumstances of Armstrong
1. The following bullets summarize the key observations and assumptions:

x Armstrong 1 has a Data Acquisition System (DAS) and Digital Control


System (DCS), so it can utilize any of the three optimization types

x The combustion system was tuned by Foster Wheeler within the last year.
Tuning objective was NOx emission reduction

x Some air flow biasing (more air to the upper elevation and lower air to the
lower elevation of burners) is possible

x Excess O2 could be reduced from the present level of 3.2% to 2.0-2.5%. To


achieve such reduction, a CO monitor should be installed

x Classifier settings and position of the coal nozzle could be adjusted to


optimize LOI and NOx emissions

x Re-orificing of coal pipes, monitoring of coal flow and control of primary air
are included in this option.

As shown in Table B-3, the Armstrong optimization project scores 168 points (out of 300
points) which Table 3-2 on page 3-24 of the Guidelines manual classifies as a Group B
project. Given the fact that the previous tuning (within the last year) focused on NOx
emission reduction, Table 3-2c on page 3-25 provides an even more refined estimate of
potential performance improvements

B-8
EPRI Licensed Material
Case Studies

Table B-3
Project Classification to Determine Potential Performance Improvements Due to Optimization
Armstrong 1/Advanced Control for Coal Flow Distribution

Criteria Score Clarifications

Information on the last tune up


- When was the unit last tuned? 1 Boiler retrofitted with IFS burners and tuned
- Tuning Objective/Tuned for: 3 In addition to FW tuning, Allegheny did some tuning to reduce CO emissions
Unit operating plexibility (at full load)
- Fuel flow biasing capability (e.g., mill capacity) 2 Some biasing; three levels of burners fed by two mills
- Air flow biasing capability 2 Some biasing
- Excess O2 range (min-max) 2 Flexibility limited by lack of CO monitor; running at 3.2%; possible reduction to 2-2.5%
- Burner tilts (for T-fired units) 1 No tilt
- Air and Gas dampers 3 Secondary air sleeve dampers
- PA/Fuel ratio 1 Tight range
- Other control variables 3 Mill outlet temperature and tempering air
Ability to change equipment settings
- Burner settings (e.g., registers, yaw, etc.) 3 Inner and outer sleeve dampers
- Pulverizer settings (e.g., spring tension; classifier; exit temp 3 Coal nozzle position could be adjusted
- Other equipment settings 2 Mill classifier settings could be adjusted
Hardware modifications
- Air distribution modifications 1 No air mods
- Coal pipe orificing 3 Significant coal flow imbalance; re-orificing and control of coal flow for each coal pipe
- Mill Modifications 1 No mill mods
- Other 1 No other mods

TOTAL SCORE (weighted average) 168 Group B

B-9
EPRI Licensed Material
Case Studies

x NOx Reduction: 15.0-22.5%, and

x Heat Rate Improvement: 0.75-1.25 percentage points.

Within these ranges, the projected improvements for the various types of optimization
are shown in Table B-4. (Note: it is assumed that closed-loop will achieve the upper
end of the projected range, the stand-alone will achieve the lower end and the on-
line/advisory the average).

Table B-4
Expected Performance Improvements with Optimization (Case 1)

Optimization Type NOx Emission Reduction (%) Heat Rate Reduction (% pts)
Stand-alone 15.00 0.750
On-Line/Advisory 18.75 1.000
Closed-loop 22.50 1.250

Also, it was estimated that the stand-alone option could regain 5 out of the 10 MWs lost
due to opacity limitations, while on-line/advisory and closed-loop could regain all 10
MWs.

Case 2: No Coal Flow Monitoring and Control

Case 2 is different from Case 1 in that no re-orificing of coal pipes and monitoring of
coal flow are included in this option. As a result (see Table B-5), the Total Score is
lower (153 out of 300 points). Table 3-2 on page 3-24 classifies this optimization project
as Group A and Table 3-2c on page 3-25 provides an even more refined estimate of
potential performance improvements:

x NOx Reduction: 5.0-10.0%, and

x Heat Rate Improvement: 0.25-0.50 percentage points.

Within these ranges, the projected improvements for the various types of optimization
are shown in Table B-6

B-10
EPRI Licensed Material
Case Studies

Table B-5
Project Classification to Determine Potential Performance Improvements due to Optimization
Armstrong 1/ No Coal Flow Distribution Control

Criteria Score Clarifications

Information on the last tune up


- When was unit last tuned? 1 Boiler retrofitted with IFS burners and tuned
- Tuning Objective/Tuned for: 3 In addition to FW tuning, Allegheny did some tuning to reduce CO emissions
Unit operating flexibility (at full load)
- Fuel flow biasing capability (e.g., mill capacity) 2 Some biasing; three levels of burners fed by two mills
- Air flow biasing capability 2 Some biasing
- Excess O2 range (min-max) 2 Flexibility limited by lack of CO monitor; running at 3.2%; possible reduction to 2-2.5%
- Burner tilts (for T-fired units) 1 No tilt
- Air and Gas dampers 3 Secondary air sleeve dampers
- PA/Fuel ratio 1 Tight range
- Other control variables 3 Mill outlet temperature and tempering air
Ability to change equipment settings
- Burner settings (e.g., registers, yaw, etc.) 3 Inner and outer dleeve dampers
- Pulverizer settings (e.g., spring tension; classifier; exit temp 3 Coal nozzle position could be adjusted
- Other equipment settings 2 Mill classifier settings could be adjusted
Hardware modifications
- Air distribution modifications 1 No air mods
- Coal pipe orificing 1 Significant coal flow imbalance; No control of coal flow for each coal pipe
- Mill Modifications 1 No mill mods
- Other 1 No other mods

TOTAL SCORE (weighted average) 153 Group A

B-11
EPRI Licensed Material
Case Studies

Table B-6
Expected Performance Improvements with Optimization (Case 2)

Optimization Type NOx Emission Reduction (%) Heat Rate Reduction (% pts)
Stand-alone 5.0 0.250
On-Line/Advisory 7.5 0.375
Closed-loop 10.0 0.500

Step 4: The Most Cost-effective Type of Optimization

For Case 1, all the optimization options come close to or surpass the preliminary targets
(objectives). For Case 2, all options fall short of achieving the desirable 1.0% heat rate
reduction. However, the projected NOx reduction and potential for LOI improvement
were sufficient to justify carrying out a cost-effectiveness analysis of all optimization
types for Armstrong 1.

Case 1

Table B-7 shows the inputs and results of the cost-benefit analysis for the three
optimization types given the assumption of coal flow monitoring and control. This
analysis takes into account:

x All the up front and annual costs, including in-house technical support
needed to install, calibrate, and maintain the software

x Benefits such as fuel savings due to heat rate improvement, increase unit
output (regaining lost MWs), and reduction of NOx and SO2 emissions.

Based on this analysis, closed-loop is the most cost-effective option for Armstrong 1.
This option is also the most appropriate considering the relatively high number of
control variables (a total of 20-30 including the coal flow rate or primary air in 12 coal
pipes). With such high number of variables, stand-alone optimization would be time-
consuming and impractical.

Case 2

The cost-benefit analysis and the results for Case 2 (no coal flow distribution control)
are shown in Table B-8 indicating again that the most cost-effective option for
Armstrong 1 is the closed-loop optimization.

B-12
EPRI Licensed Material
Case Studies

Table B-7
Power Plant Optimization Cost-Benefit Analysis--Armstrong 1
Advanced Control for Coal Flow Distribution

COSTS Optimization Types


Stand-alone O n-line/advisory Closed-loop
Up Front Costs

Up Front Software License Fees ($) $70,000 $130,000 $170,000

Additional Computer Software and Hardware ($) $5,000 $5,000 $5,000


Computer software $0 $0 $0
Computer hardw are $5,000 $5,000 $5,000
Instrumentation and controls (I&C) $0 $0 $0
Data acquisition system (DAS) $0 $0 $0

Installation and Calibration ($) $57,000 $46,600 $53,000


Outside technical support total $25,000 $14,600 $17,000
-Num ber of man days 25 12 15
-Av erage daily rate for outside technical support $800 $800 $800
-Miscellaneous expenses (Trav el, reports, overhead, etc.) $5,000 $5,000 $5,000
In-house technical support total $32,000 $32,000 $36,000
-Num ber of man days 40 40 45
-Av erage daily rate for in-house technical support $400 $400 $400
-Cost m ultiplier for ov erhead 2.0 2.0 2.0
Power plant downtime/non-economic dispatch $0 $0 $0

Training ($) $0 $0 $0

Power Plant Hardware Modifications ($) $0 $0 $0

TOTAL UP FRONT COSTS $132,000 $181,600 $228,000

Annual Costs (O&M incl. Recalibration)


Annual Software License & Maintenance Fees ($) $5,000 $13,000 $17,000

Technical Support ($) $33,000 $25,000 $21,000


Outside technical support total $17,000 $13,000 $13,000
-Num ber of man days 15.0 10.0 10.0
-Av erage daily rate for outside technical support $800 $800 $800
-Miscellaneous expenses (Trav el, reports, overhead, etc.) $5,000 $5,000 $5,000
In-house technical support $16,000 $12,000 $8,000
-Num ber of man days 20 15 10
-Av erage daily rate for in-house technical support $400 $400 $400
-Cost m ultiplier for ov erhead 2.0 2.0 2.0

TOTAL ANNUAL COSTS $38,000 $38,000 $38,000

BENEFITS (Losses)

Up Front (one time) Benefits


NPV of Deferred Costs ($) $0 $0 $0
Deferred costs $0 $0 $0
How long does optimization delay investment? (in months) 0 0 0
NPV of Avoided Costs ($) $0 $0 $0
Avoided costs $0 $0 $0
When would investm ent have been implemented (in m onths) 0 0 0

TOTAL UP FRONT BENEFITS $0 $0 $0

Annual Benefits
Annual Avoided Costs ($/yr) $0 $0 $0

Fuel Cost Savings ($/yr) $88,080 $117,440 $146,800


Baseline heat rate (Btu/kWh) 10,000 10,000 10,000
Unit heat rate improvement (% Pts) 0.750 1.000 1.250
Fuel cost ($/MBtu) 1.12 1.12 1.12
Unit output (MW) 171 171 171
Capacity factor (%) 70.0 70.0 70.0

B-13
EPRI Licensed Material
Case Studies

Table B-7 Cont’d.


O&M Impacts ($/yr) $0 $0 $0
Waterwall corrosion ($/yr) $0 $0 $0
Operating flexibility ($/yr) $0 $0 $0

Value of Change in Unit Availability ($/yr) $0 $0 $0


Change in equivalent availability (%) 0.0 0.0 0.0
Value of an additional % point ($/%-yr) 0 0 0

Value of Change in Unit Output ($/yr) $183,960 $367,920 $367,920


Change in output (MW) 5 10 10
Incremental cost of replacement power ($/MWh) 20.00 20.00 20.00
Capacity factor (%) 70 70 70
Percentage of operating time affected (%) 30 30 30

Benefits Due to Emission Reductions


NOx Emissions
Avoided fines/penalties ($/yr) $0 $0 $0
Annual value of NOx emission credits ($/yr) $141,557 $176,947 $212,336
-Value of NOx emission credits ($/ton removed) 400 400 400
NOx emission credits (tons/yr) 353.9 442.4 530.8
-NOx reference lev el for credits (lbs/MBtu) 0.450 0.450 0.450
-NOx emission reduction below reference lev el (%) 15.00 18.75 22.50
-Unit output (MW) 171 171 171
-Unit baseline heat rate (Btu/kW h) 10,000 10,000 10,000
-Capacity factor (%) 70 70 70

SO2 Emissions
Avoided fines/penalties ($/yr) $0 $0 $0
Annual value of SO2 emission credits ($/yr) $4,325 $5,767 $7,209
-Value of SO2 emission credits ($/ton remov ed) 100 100 100
SO2 emissions reduction (tons/yr) 43.25 57.67 72.09
-Baseline SO2 emissions (lbs/MBtu) 1.100 1.100 1.100
-Baseline unit heat rate (Btu/kW h) 10,000 10,000 10,000
-Unit heat rate improvement (%) 0.75 1.00 1.25
-Unit output (MW) 171 171 171
-Capacity factor (%) 70 70 70

CO Emissions
Avoided fines/penalties ($/yr) $0 $0 $0

Opacity
Avoided fines/penalties ($/yr) $0 $0 $0

CO2 Emissions
Annual value of CO2 emission credits ($/yr) $0 $0 $0
-Value of CO2 credits ($/ton removed) 0 0 0
CO2 emissions reduction (tons/yr) 8,199 10,932 13,666
-Baseline CO2 emissions (lbs/MBtu) 208.52 208.52 208.52
-Baseline unit heat rate (Btu/kWh) 10,000 10,000 10,000
-Unit heat rate improvement (%) 0.75 1.00 1.25
-Unit output (MW ) 171 171 171
-Capacity factor (%) 70 70 70

Annual benefits before diminishing effectiveness factor ($/yr) $417,923 $668,074 $734,265
Diminishing effectiveness factor 0.50 0.75 0.90
ACTUAL ANNUAL BENEFITS ($/yr) $208,961 $501,055 $660,838

FINANCIAL ASSUMPTIONS
Book life of the project (default 5 years) 5.0 5.0 5.0

Discount rate (%) (default 4.9%) 10.6 10.6 10.6

INTERMEDIARY FIGURES
Net annual benefits ($) $170,961 $463,055 $622,838
PV of future net annual benefits ($) $638,265 $1,728,766 $2,325,298
Annual depreciation (straightline) $26,400 $36,320 $45,600

COST-BENEFIT ANALYSIS RESULTS


Net Present Value (NPV) $506,265 $1,547,166 $2,097,298
Return on Investment (ROI as %) 110 235 253
Payback Period (simple payback in months) 9.3 4.7 4.4
Benefit-Cost Ratio 3.8 8.5 9.2

B-14
EPRI Licensed Material
Case Studies

Table B-8
Power Plant Optimization Cost-Benefit Analysis--Armstrong 1
Without Coal Distribution Control

COSTS Optimization Types


Stand-alone On-line/advisory Closed-loop
Up Front Costs

Up Front Software License Fees ($) $50,000 $130,000 $170,000

Additional Computer Software and Hardware ($) $5,000 $5,000 $5,000


Computer software $0 $0 $0
Computer hardware $5,000 $5,000 $5,000
Instrumentation and controls (I&C) $0 $0 $0
Data acquisition system (DAS) $0 $0 $0

Installation and Calibration ($) $34,600 $46,600 $53,000


Outside technical support total $14,600 $14,600 $17,000
-Number of man days 12 12 15
-Average daily rate for outside technical support $800 $800 $800
-Miscellaneous expenses (Trav el, reports, overhead, etc.) $5,000 $5,000 $5,000
In-house technical support total $20,000 $32,000 $36,000
-Number of man days 25 40 45
-Average daily rate for in-house technical support $400 $400 $400
-Cost multiplier for ov erhead 2.0 2.0 2.0
Pow er plant dow ntime/non-economic dispatch $0 $0 $0

Training ($) $0 $0 $0

Power Plant Hardware Modifications ($) $0 $0 $0

TOTAL UP FRONT COSTS $89,600 $181,600 $228,000

Annual Costs (O&M incl. Recalibration)

Annual Software License & Maintenance Fees ($) $5,000 $13,000 $17,000

Technical Support ($) $33,000 $25,000 $21,000


Outside technical support total $17,000 $13,000 $13,000
-Number of man days 15.0 10.0 10.0
-Average daily rate for outside technical support $800 $800 $800
-Miscellaneous expenses (Trav el, reports, overhead, etc.) $5,000 $5,000 $5,000
In-house technical support $16,000 $12,000 $8,000
-Number of man days 20 15 10
-Average daily rate for in-house technical support $400 $400 $400
-Cost multiplier for ov erhead 2.0 2.0 2.0

TOTAL ANNUAL COSTS $38,000 $38,000 $38,000

BENEFITS (Losses)

Up Front (one tim e) Benefits

NPV of Deferred Costs ($) $0 $0 $0


Deferred costs $0 $0 $0
How long does optimization delay investment? (in months) 0 0 0
NPV of Avoided Costs ($) $0 $0 $0
Avoided costs $0 $0 $0
When would investment have been implemented (in months) 0 0 0

TOTAL UP FRONT BENEFITS $0 $0 $0

Annual Benefits

Annual Avoided Costs ($/yr) $0 $0 $0

Fuel Cost Savings ($/yr) $29,360 $44,040 $58,720


Baseline heat rate (Btu/kWh) 10,000 10,000 10,000
Unit heat rate improvement (% Pts) 0.250 0.375 0.500
Fuel cost ($/MBtu) 1.12 1.12 1.12
Unit output (MW) 171 171 171
Capacity factor (%) 70.0 70.0 70.0

B-15
EPRI Licensed Material
Case Studies

Table B-8 Cont’d.


O&M Impacts ($/yr) $0 $0 $0
Waterwall corrosion ($/yr) $0 $0 $0
Operating flexibility ($/yr) $0 $0 $0

Value of Change in Unit Availability ($/yr) $0 $0 $0


Change in equivalent availability (%) 0.0 0.0 0.0
Value of an additional % point ($/%-yr) 0 0 0

Value of Change in Unit Output ($/yr) $183,960 $367,920 $367,920


Change in output (MW) 5 10 10
Incremental cost of replacement power ($/MWh) 20.00 20.00 20.00
Capacity factor (%) 70 70 70
Percentage of operating time affected (%) 30 30 30

Benefits Due to Emission Reductions


NOx Emissions
Avoided fines/penalties ($/yr) $0 $0 $0
Annual value of NOx emission credits ($/yr) $47,186 $70,779 $94,371
-Value of NOx emission credits ($/ton removed) 400 400 400
NOx emission credits (tons/yr) 118.0 176.9 235.9
-NOx reference level for credits (lbs/MBtu) 0.450 0.450 0.450
-NOx emission reduction below reference level (%) 5.00 7.50 10.00
-Unit output (MW ) 171 171 171
-Unit baseline heat rate (Btu/kWh) 10,000 10,000 10,000
-Capacity factor (%) 70 70 70

SO2 Emissions
Avoided fines/penalties ($/yr) $0 $0 $0
Annual value of SO2 emission credits ($/yr) $1,442 $2,163 $2,884
-Value of SO2 emission credits ($/ton removed) 100 100 100
SO2 emissions reduction (tons/yr) 14.42 21.63 28.84
-Baseline SO2 emissions (lbs/MBtu) 1.100 1.100 1.100
-Baseline unit heat rate (Btu/kW h) 10,000 10,000 10,000
-Unit heat rate improvement (%) 0.25 0.38 0.50
-Unit output (MW ) 171 171 171
-Capacity factor (%) 70 70 70

CO Emissions
Avoided fines/penalties ($/yr) $0 $0 $0

Opacity
Avoided fines/penalties ($/yr) $0 $0 $0

CO2 Emissions
Annual value of CO2 emission credits ($/yr) $0 $0 $0
-Value of CO2 credits ($/ton removed) 0 0 0
CO2 emissions reduction (tons/yr) 2,733 4,100 5,466
-Baseline CO2 emissions (lbs/MBtu) 208.52 208.52 208.52
-Baseline unit heat rate (Btu/kW h) 10,000 10,000 10,000
-Unit heat rate improvement (%) 0.25 0.38 0.50
-Unit output (MW) 171 171 171
-Capacity factor (%) 70 70 70

Annual benefits before diminishing effectiveness factor ($/yr) $261,948 $484,901 $523,895
Diminishing effectiveness factor 0.50 0.75 0.90
ACTUAL ANNUAL BENEFITS ($/yr) $130,974 $363,676 $471,506

FINANCIAL ASSUMPTIONS
Book life of the project (default 5 years) 5.0 5.0 5.0

Discount rate (%) (default 4.9%) 10.6 10.6 10.6

INTERMEDIARY FIGURES
Net annual benefits ($) $92,974 $325,676 $433,506
PV of future net annual benefits ($) $347,107 $1,215,875 $1,618,445
Annual depreciation (straightline) $17,920 $36,320 $45,600

COST-BENEFIT ANALYSIS RESULTS


Net Present Value (NPV) $257,507 $1,034,275 $1,390,445
Return on Investment (ROI as %) 84 159 170
Payback Period (simple payback in months) 11.6 6.7 6.3
Benefit-Cost Ratio 2.9 5.7 6.1

B-16
EPRI Licensed Material
Case Studies

Step 5: Select the Best Optimization Product for Your Application

In conclusion, it seems that the closed-loop optimization is the most appropriate and
cost-effective option for Armstrong 1. This is true especially in the case of monitoring
the coal flow in the individual coal pipes (Case 1), where the total number of control
variables is relatively high and continuous control and optimization is needed. If coal
flow monitoring is not included, all optimization types are suitable, but closed-loop is
the most cost-effective.

Selection of specific power plant optimization software will be carried out by


Allegheny following the guidance provided in Step 5 of the Guidelines manual. Such
evaluation is not described here because of the proprietary nature of the information
included.

Case Study 2: Northern States Power Riverside 7 Unit

Background

Riverside 7 consists of two front wall-fired boilers, vintage 1950s, and a steam
turbine/generator. The unit operates near full load and generates approximately
675 ppm (0.90 lbs/MBtu) of NOx emissions. While NSP plans to use NOx averaging to
comply with the Clear Air Act Amendment of 1990, system considerations suggest that
an additional NOx reduction of 20-40% from Riverside 7 is desirable.

Before considering hardware modifications, NSP decided to assess the possibility of


using PPO software to achieve this NOx reduction using the Beta Version of EPRI’s
Power Plant Optimization Guidelines. The results are revealing in terms of the
importance of the tuning and the need to consider site-specific features in the
evaluation of optimization options.

NSP’s NOx Compliance Plans and Future Needs

Northern States Power Co. (NSP) has used a combination of combustion NOx control
projects and system averaging to comply with requirements of the Clean Air Act
Amendment (CAAA) of 1990. Key NOx control retrofit projects include:

x Sherco 2 (a 725 MW T-fired boiler): retrofitted with low NOx burners and
overfire air

x King (a 550 MW cyclone boiler): to be retrofitted with overfire air in October


of 1999, and

B-17
EPRI Licensed Material
Case Studies

x Riverside 8 (a 245 MW cyclone boiler): to be retrofitted with overfire air in


October of 1999.

While these projects are expected to satisfy CAAA requirements, both at the unit and
power system level, NSP would like to have some additional means for controlling
NOx emissions as an "insurance policy" for unexpected events which can affect NOx
compliance. Such events include:

x forced outage of a nuclear plant would require higher utilization of NSP’s


coal-fired plants; hence increasing the total NOx emissions released by the
system;

x NOx reduction at King and Riverside 8 may be less than expected, especially
if the units experience waterwall corrosion problems due to reducing
atmosphere in the cyclone boilers; and

x so far, CAAA Title I has not imposed any requirements which can not be met
with NSP’s latest NOx compliance program, but it is possible that these
requirements may be more stringent in the future.

For this reason, power plant optimization is being considered for a number of units
including Riverside 7, Sherco 3, and Black Dog 3 and 4.

Description of Riverside 7

Riverside 7 is a 153 MW coal-fired unit consisting of two wall-fired boilers and one
steam turbine. The wall-fired boilers were built by Babcock & Wilcox in the 1950s and
burn subbituminous coal. The unit has two pulverizers feeding six burners arranged in
two rows (four burner in the bottom row and two in the top). Also, it is equipped with
a baghouse and a Westinghouse (WDPF) Digital Control System (DCS).

The unit is used for intermediate load, but recently has been operating more as
baseloaded. Full load NOx emissions average 675 ppm (0.90 lbs/MBtu). LOI averages
less than 1%, but in recent years has been highly variable. Occasionally, this variability
is not acceptable to buyers of the flyash and requires that it be trucked 53 miles (90 km
from Riverside) to Sherco for disposal.

Evaluation of Power Plant Optimization Software

As a first step, it was decided to evaluate the different types of optimization (stand-
alone, on-line/advisory and closed-loop) using the Beta Version of EPRI’s Power Plant
Optimization Guidelines. The specific software will be selected later (note: it is not

B-18
EPRI Licensed Material
Case Studies

included in this paper). The 5 steps outlined in the Guidelines are described in the
following paragraphs.

Step 1: Quick Tuning and Establishment of Baseline Performance

The first step was a quick walk-down/checking of the operating condition of key plant
components and control variable set-points. This review reveal the following:

x excess O2 is set at 2.3%; most likely, the boiler can operate at a lower level, but
for safety purposes and because of the absence of a CO monitor, 2.3% has
been set as a minimum operating level

x the air registers are set visually by operations. During this quick tuning
exercise, the burners were found to be set uniformly (in a scale of 1 to 9, the
registers were set at 6)

x potential parameters affecting NOx emissions and boiler performance which


can be changed during a tuning or optimization program include:

¡ primary air to fuel ratio, and

¡ improvement of coal fineness through adjustment of classifiers ball


loading.

The first operating adjustment made was to change the settings of the air registers as
follows:

x open the registers of the top row from position 6 to 8, and

x close the registers of the bottom row from 6 to 3.

The result of these changes was an immediate NOx reduction of approximately 8%.
Following this quick tuning, baseline NOx emissions were measured at approximately
600 ppm (0.80 lbs/MBtu).

In addition, the following steps were identified to improve performance in order of


priority:

1. Improvement of coal fineness through mill adjustments

2. Air and coal flow balancing including biasing of air towards the upper
elevation of burners

3. Application of optimization software

B-19
EPRI Licensed Material
Case Studies

4. Simple hardware modifications to achieve further NOx emission reduction, if


needed.

The main hardware modification recommended includes switching two coal pipes (see
Figure B-5) to allow some degree of fuel biasing (more fuel to the lower elevation,
Mill 1) in addition to air biasing. Such hardware modification is easy and inexpensive
and can result in 10-20% NOx reduction.

Present Arrangement

Mill 2
Mill 1

Modification

Mill 2 Mill 2
Mill 1 Mill 1

Alternative 1 Alternative 2

Figure B-5
Alternative Coal Pipe Arrangements for Improved NOx Control

B-20
EPRI Licensed Material
Case Studies

Step 2: Objectives for Power Plant Optimization

Based on the above, it was determined that the primary objective is to achieve the
maximum NOx reduction without adverse impacts on heat rate. A secondary objective
was to reduce the LOI variability.

Additional parameters which relate to the objective and affect the cost-benefit analysis
include:

x Value of NOx emission reduction 190 $/ton4, which is an industry average


for LNB retrofits,

x No emission credit will be provided for SO2 and CO2

x Project book life: 5 years; and

x Discount rate: 4.9%.

Step 3: Determine Optimization Potential/Can Optimization Alone Meet


Established Objectives?

Table B-9 is the result of tailoring Table 3-1 to the specific circumstances of Riverside 7.
The following bullets summarize the key observations and assumptions:

x No systematic tuning of the boilers had been performed in the last two years

x The last tuning had focused on combustion efficiency (heat rate)

x Air biasing is possible through adjustment of the air register settings

x Excess air could be reduced from 2.3% to 2.0%; further reduction may be
possible, but a CO monitor needs to be added

x Switching of two coal pipes to allow for fuel biasing is being included.

As shown in Table B-9, the Riverside optimization project scores 191 points (out of 300
points) which Table 3-2 on page 3-24 of the Guidelines manual classifies as a Group B
project. Given the fact that the previous tuning was done more than two years ago and

4
EPRI's "Retrofit NOx Controls for Coal-fired Utility Boilers-1996 Update Addendum" (TR-102906-A
dendum, May 1997), pp. I-11 and 6-2.

B-21
EPRI Licensed Material
Case Studies

focused on heat rate improvement, Table 3-2b on page 3-25 provides an even more
refined estimate of potential performance improvements:

x NOx reduction: 22.5-30.0%

x Heat rate improvement: 0.50-0.75 percentage points.

B-22
EPRI Licensed Material
Case Studies

Table B-9
Project Classification to Determine Potential Performance Improvements Due to Optimization—Riverside 7

Criteria Score Clarifications

Information on the last tune up


- When was the unit last tuned? 3 Last tuning more than two years ago
- Tuning Objective/Tuned for: 2 Focused on combustion efficiency (heat rate)
Unit operating flexibility (at full load)
- Fuel flow biasing capability (e.g., mill capacity) 1 Presently no fuel biasing is possible because the two mills feed both elevations of burne
- Air flow biasing capability 2 Some air flow biasing possible
- Excess O2 range (min-max) 1 Potential O2 reduction from 2.3 to 2.0%
- Burner tilts (for T-fired units) 1 No tilt avalaible
- Air and Gas dampers 1 No additional dampers available (except air registers)
- PA/Fuel ratio 1 Plant engineers suggested that the PA/Fuel ratio should not be adjusted
- Other control variables 1 No other control variables available
Ability to change equipment settings
- Burner settings (e.g., registers, yaw, etc. etc.) 2 Changes in air registers possible
- Pulverizer settings (e.g., spring tension; classifier; exit temp 2 Some adjustments possible
- Other equipment settings 1 No additional adjustments possible
Hardware modifications
- Air distribution modifications 1 None
- Coal pipe orificing 1 None
- Mill Modifications 1 None
- Other 3 Switching of coal pipes

TOTAL SCORE (weighted average) 191 Group B

B-23
EPRI Licensed Material
Case Studies

The projections for the various types of optimization are shown in Table B-10. (Note: it
is assumed that closed-loop will achieve the upper end of the projected range, the
stand-alone will achieve the lower end and the on-line/advisory the average).

Table B-10
Expected Performance Improvements with Optimization (Case 1)

Optimization Type NOx Emission Reduction (%) Heat Rate Reduction (% pts)
Stand-alone 22.50 0.500
On-Line/Advisory 26.25 0.625
Closed-loop 30.00 0.750

Step 4: The Most Cost-effective Type of Optimization

All optimization types satisfy the objectives set in Step 2. For this reason, the cost-
effectiveness of all optimization types will be evaluated to decide which type is most
suitable for Riverside 7.

Table B-11 is built on the template of Figure 4-1 and based on inputs for the Riverside 7
boiler, shows estimated cost-benefit analysis results for the three optimization types.
This analysis takes into account:

x All the up front and annual costs, including in-house technical support
needed to install, calibrate and maintain the software,

x Benefits such as fuel savings due to heat rate improvement, and reduction of
NOx and SO2 emissions.

Based on this analysis, closed-loop is the most cost-effective option for Riverside 7.

B-24
EPRI Licensed Material
Case Studies

Table B-11
Power Plant Optimization Cost-Benefit Analysis—Riverside 7

COSTS Optimization Types


Stand-alone On-line/advisory Closed-loop
Up Front Costs
Up Front Software License Fees ($) $20,000 $130,000 $170,000

Additional Computer Software and Hardware ($) $5,000 $5,000 $5,000


Computer software $0 $0 $0
Computer hardware $5,000 $5,000 $5,000
Instrumentation and controls (I&C) $0 $0 $0
Data acquisition system (DAS) $0 $0 $0

Installation and Calibration ($) $33,000 $44,040 $50,120


Outside technical support total $14,600 $14,600 $17,000
-Num ber of m an days 12 12 15
-Average daily rate for outside technical support $800 $800 $800
-Miscellaneous expenses (Trav el, reports, overhead, etc.) $5,000 $5,000 $5,000
In-house technical support total $18,400 $29,440 $33,120
-Num ber of m an days 25 40 45
-Average daily rate for in-house technical support $320 $320 $320
-Cost multiplier for overhead 2.3 2.3 2.3
Power plant downtim e/non-economic dispatch ($) $0 $0 $0

Training ($) $0 $0 $0

Power Plant Hardware Modifications ($) $0 $0 $0

TOTAL UP FRONT COSTS $58,000 $179,040 $225,120

Annual Costs (O&M incl. Recalibration)


Annual Software License & Maintenance Fees ($) $8,000 $13,000 $17,000

Technical Support ($) $31,720 $19,040 $15,360


Outside technical support total $17,000 $8,000 $8,000
-Num ber of m an days 15.0 10.0 10.0
-Average daily rate for outside technical support $800 $800 $800
-Miscellaneous expenses (Trav el, reports, overhead, etc.) $5,000 $0 $0
In-house technical support $14,720 $11,040 $7,360
-Num ber of m an days 20 15 10
-Average daily rate for in-house technical support $320 $320 $320
-Cost multiplier for overhead 2.3 2.3 2.3

TOTAL ANNUAL COSTS $39,720 $32,040 $32,360

BENEFITS (Losses)

Up Front (one time) Benefits


NPV of Deferred Costs ($) $0 $0 $0
Deferred costs $0 $0 $0
How long does optimization delay investment? (in months) 0 0 0

NPV of Avoided Costs ($) $0 $0 $0


Avoided costs $0 $0 $0
When would investment have been im plemented (in months) 0 0 0

TOTAL UP FRONT BENEFITS $0 $0 $0

Annual Benefits
Annual Avoided Costs ($/yr) $0 $0 $0

Fuel Cost Savings ($/yr) $48,036 $60,045 $72,053


Baseline heat rate (Btu/kWh) 10,240 10,240 10,240
Unit heat rate improvement (% Pts) 0.500 0.625 0.750
Fuel cost ($/MBtu) 1.00 1.00 1.00
Unit output (MW) 153 153 153
Capacity factor (%) 70.0 70.0 70.0

B-25
EPRI Licensed Material
Case Studies

Table B-11 Cont’d.

O&M Impacts ($/yr) $0 $0 $0


Waterwall corrosion ($/yr) $0 $0 $0
Operating flexibility ($/yr) $0 $0 $0

Value of Change in Unit Availability ($/yr) $0 $0 $0


Change in equivalent availability (%) 0.0 0.0 0.0
Value of an additional % point ($/%-yr) 0 0 0

Value of Change in Unit Output ($/yr) $0 $0 $0


Change in output (MW) 0 0 0
Incremental cost of replacement power ($/MWh) 0.00 0.00 0.00
Capacity factor (%) 70 70 70
Percentage of operating time affected (%) 0 0 0

Benefits Due to Emission Reductions


NOx Emissions
Avoided fines/penalties ($/yr) $0 $0 $0
Annual value of NOx emission credits ($/yr) $164,282 $191,662 $219,042
-Value of NOx emission credits ($/ton removed) 190 190 190
NOx emission credits (tons/yr) 864.6 1008.7 1152.9
-NOx reference lev el for credits (lbs/MBtu) 0.800 0.800 0.800
-NOx emission reduction below reference lev el (%) 22.50 26.25 30.00
-Unit output (MW ) 153 153 153
-Unit baseline heat rate (Btu/kW h) 10,240 10,240 10,240
-Capacity factor (%) 70 70 70

SO2 Emissions
Avoided fines/penalties ($/yr) $0 $0 $0
Annual value of SO2 emission credits ($/yr) $0 $0 $0
-Value of SO2 em ission credits ($/ton remov ed) 0 0 0
SO2 emissions reduction (tons/yr) 28.82 36.03 43.23
-Baseline SO2 emissions (lbs/MBtu) 1.200 1.200 1.200
-Baseline unit heat rate (Btu/kW h) 10,240 10,240 10,240
-Unit heat rate improvement (%) 0.50 0.63 0.75
-Unit output (MW ) 153 153 153
-Capacity factor (%) 70 70 70

CO Emissions
Avoided fines/penalties ($/yr) $0 $0 $0

Opacity
Avoided fines/penalties ($/yr) $0 $0 $0

CO2 Emissions
Annual value of CO2 emission credits ($/yr) $0 $0 $0
-Value of CO2 credits ($/ton removed) 0 0 0
CO2 emissions reduction (tons/yr) 5,008 6,260 7,512
-Baseline CO2 emissions (lbs/MBtu) 208.52 208.52 208.52
-Baseline unit heat rate (Btu/kW h) 10,240 10,240 10,240
-Unit heat rate im provement (%) 0.50 0.63 0.75
-Unit output (MW ) 153 153 153
-Capacity factor (%) 70 70 70

Annual benefits before diminishing effectiveness factor ($/yr) $212,318 $251,707 $291,096
Diminishing effectiveness factor 0.50 0.75 0.90
ACTUAL ANNUAL BENEFITS ($/yr) $106,159 $188,780 $261,986

FINANCIAL ASSUMPTIONS
Book life of the project (default 5 years) 5.0 5.0 5.0

Discount rate (%) (default 4.9%) 4.9 4.9 4.9

INTERMEDIARY FIGURES
Net annual benefits ($) $66,439 $156,740 $229,626
PV of future net annual benefits ($) $288,442 $680,482 $996,916
Annual depreciation (straightline) $11,600 $35,808 $45,024

COST-BENEFIT ANALYSIS RESULTS


Net Present Value (NPV) $230,442 $501,442 $771,796
Return on Investment (ROI as %) 95 68 82
Payback Period (simple payback in months) 10.5 13.7 11.8
Benefit-Cost Ratio 4.0 2.8 3.4

B-26
EPRI Licensed Material
Case Studies

Step 5: Select the Best Optimization Product for Your Application

The conclusions reached based on the above analysis are:

x Quick tuning which should be carried out in Step 1 has the potential to reduce
NOx emissions by approximately 10-15%. Such tuning involves mainly:

¡ Resetting the air registers in such a way that air biasing towards the top
elevation of burners is created,

¡ Tuning of the mills to improve coal fineness, and

¡ Addition of CO monitor to reduce the excess O2 level ,

x Simple hardware modifications should be considered, if additional NOx


reduction is required. For example, switching two coal pipes (see Figure B-6)
may reduce NOx by another 10-15% without significant costs and
performance penalties,

x Optimization: employ an optimization program, preferably in closed-loop


mode, to achieve up to 30% NOx reduction (10% above and beyond the levels
achieved by hardware modifications), 0.50-0.75 percentage point heat rate
improvement , and reduction in LOI variability being experienced presently.

Selection of specific power plant optimization software will be carried out by Northern
States Power following the guidance provided in Step 5 of the Guidelines manual.
Such evaluation is not described here because of the proprietary nature of the
information included.

The projections for the various types of optimization are shown in Table B-10. (Note: it
is assumed that closed-loop will achieve the upper end of the projected range, the
stand-alone will achieve the lower end and the on-line/advisory the average).

B-27
EPRI Licensed Material

C
FORMULAS

Fuel Cost Savings

Annual fuel cost savings ($/yr) = (876/106) x Baseline Heat Rate (Btu/kWh) x Heat
Rate Improvement (%) x Fuel Price ($/MBtu) x Unit Size (MW) x Capacity Factor (%)

Value of Change in Unit Availability

Value of change in unit availability ($/yr) = Increase in equivalent availability (%) x


Value of additional % point ($/yr-%)

Value of Change in Unit Output

This benefit category quantifies the incremental energy value of increased maximum
unit output. No credit is taken for “capacity value” in the system asset sense. If
capacity is created, enter the decrease in unit output (maximum continuous rating) as a
negative capacity addition.

Value of change in unit output ($/yr) = Change in output (MW) x Incremental cost of
replacement power ($/MWh) x Capacity factor (%/100) x Hours to year conversion
factor 8760 x Percentage of operating time affected (%/100)

NOx Emissions

Annual NOx reduction (tons/yr) = NOx compliance level or level below which NOx
credits are being accumulated (lbs/MBtu) x % NOx emission reduction below
compliance level due to optimization (%) x Unit output (MW) x Unit heat rate
(Btu/kWh) x Unit capacity factor (%) x (876 x 0.5/10 9)

Value of NOx emission credits ($/yr) = Annual NOx reduction (tons/yr) x Value of
NOx credits ($/ton of NOx removed)

C-1
EPRI Licensed Material
Formulas

SO2 Emissions

Annual SO2 reduction (tons/yr) = Baseline SO2 emissions (lbs/MBtu) x Baseline heat
rate (Btu/kWh) x Heat rate improvement (%) x Unit output (MW) x Unit capacity factor
(%) x (876 x 0.5/109)

Value of SO2 emission credits ($/yr) = Annual SO2 reduction (tons/yr) x Value of SO2
credits ($/ton of SO2 removed)

CO2 Emissions

Annual CO2 reduction (tons/yr) = Baseline CO2 emissions (lbs/MBtu) x Unit heat rate
(Btu/kWh) x heat rate improvement (%) x Unit output (MW) x Unit capacity factor (%)
x Pounds to million tons conversion factor (876 X 0.5/109)

Value of CO2 credits ($/yr) = Annual CO2 reduction (tons/yr) x Value of CO2 credits
($/ton of CO2 removed)

C-2

S-ar putea să vă placă și