Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III - Stage I)

at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

1.0 GENERAL AND PRELIMINARIES

1.1 Provide Performance Bond amounting to 5% of the Contract Sum shall be


deposited with the Employer as required by Clause 5 of the Condition of
Contract. Lump Sum

1.2 Provide Insurance (Contractor's All Risk / Workman Compensastion /

Socso) in accordance with General Conditions of Contract. Lump Sum

1.3 To provide CIDB's Levy contribution and compliance with CIDB Act 520
(Amendment 2011) Lump Sum

1.4 Site management and job expenses. Lump Sum

1.5 Mobilisation of personnel, constructional plant and equipment. Lump Sum

1.6 Provide and maintain survey instrument in accordance with the S.O.
requirement. The instrument will be reverted to the Contractor at the
end of the contract. Lump Sum

1.7 Provide and maintain one (1) no. mobile phone including internet
services for S.O.
The Basic Specifications of the Mobile Phone shall be as follows:-
1) 14mp Camera
2) 256 GB Memory
3) 4G/LTE Support Lump Sum

1.8 Provide and maintain S.O. site office, including all furniture, equipment
and fitting as specified. Lump Sum

1.9 Supply personnels, materials and equipment to carry out all quality
control tests. Lump Sum

1.10 Provide for work programme, progress reporting and taking progress
photographs of works. Lump Sum

1.11 Provide and maintain all temporary works including removal from site,
upon completion of Works. Lump Sum

1.12 Demobilisaiton of personnel and constructional plant and equipment.


Lump Sum

1.13 Clearing up Site on completion, in accordance with Specification. Lump Sum

To Collection

375791317.xlsx - SOT 1 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III - Stage I)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

1.14 Site Surveys


The Contractor shall employ a licensed Land Surveyor to carry out a site
survey before work commences, and to assist in establishing boundaries
and setting out the works. On completion of the works, a licensed Land
Surveyor to carry out a further site survey and produce as-built drawings.
Details of grid lines, setting out stations, bench marks, prolfiles etc. Shall
be recorded on a setting out drawing. Lump Sum

1.15 Existing Services


The Contractor shall ascertain the exact position of existing cables, pipes,
ducts, sewers, surface water drains, service mains and the like, under or
over the site and other areas affected by the works, whether indicated on
the drawings or not. He shall uphold, protect and maintain the same
during the execution of the works to the satisfaction of the S.O and make
good or pay for making good all damage thereto and any consequential
damage of loss arising out of such damage.

The Contractor shall not interfere with the operation of services without
the consent of service autorities, or private owners, or the S.O as
appropriate.

If services have to be temporarily terminated or diverted, the Contractor


shall give the necessary notices to the appropriate Authorities, arrange
for the work to be carried out and pay all charges in connection
therewith.

The Contractor shall divert, any drains and waterways encountered


during the progress of the works and subsequently reinstate to the S.O's
approval if diversion is temporary. Lump Sum

1.16 Traffic Control


The Contractor shall ascertain and comply with all regulations concerning
the carrying out of work in both public roads and roads within the site
and give the necessary notices. No road shall be temporarily or
permanently closed except any for which the Contractor has obtained the
necessary permission from the Authorities.

The Contractor shall apply the necessary traffic control, traffic warning
signs, beacon lights and barriers in private and public roads for carrying
the work, together with any necessary diversions to maintain traffic flow. Lump Sum

To Collection

375791317.xlsx - SOT 2 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III - Stage I)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

1.17 Exsiting Roads and Properties


The Contractor will be responsibe for making good any damage to
existing private and/or public roads, kerbs, crossing, and properties etc.
caused by the carrying out of the works and shall maintain the aforesaid
in their original condition to the satisfaction of the S.O and the relevant
authority. Lump Sum

To Collection

375791317.xlsx - SOT 3 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III - Stage I)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

2.0 SITE CLEARING & EARTHWORKS

2.1 SITE CLEARING


Clear and grub areas within the site boundary and remove all vegetation
and debris from site to the contractor's own tip all to the satisfaction of
the S.O. The contractor shall sort the permission of the S.O regarding
the extend and method of clearing and cutting prior to the
commencement of the works. The Contractor is deemed to have visited
the site and ascertain for himself the true extend and nature of the site
including types of vegetation and items to be cleared. No further claim in
this connection shall be ertertained. Lump Sum

2.2 EARTHWORKS

a) Bulk excavation to the required founding levels of pump stations, screen


chamber, manholes and etc, partly cut and level, partly cut, load,
transport within site, deposit and spread excavated materialin areas to be
filled and thoroughly compact in layers to the required levels as directed. Lump Sum

b) To allow for all necessary temprorary shoring and bracing for excavation

of Pump stations, screen chamber, manholes and etc. Lump Sum

c) Supply,deliver, lay, compact and regrade suitable fill material to form


platform for new pumping station including the desludging and drying up
of part of the pond as per drawings and specification Lump Sum

3.0 SEWERAGE WORKS

3.1 Setting out pipe line, excavate trench, get out, part return, fill in, well
ram and remainder cart away from site, level, grade, ram bottom, trim
sides and including planking and strutting. Lump Sum

3.2 To allow for all necessary temprorary shoring and bracing for excavation
of trenches for the sewer lines. Lump Sum

3.3 To construct class 'B' sewer pipe bedding to receive vitrified clay pipes/
conc. Pipe class 'z' (lined internally with 12mm thk high Alumina cement
lining) / DICL pipes, incl. Grade 25 concrete, steel reinforcement and
formworks. (Piling measured seperately) Lump Sum

3.4 Supply, lay, grade and compact in layers 600mm imported sand fill
material to specification requirements Lump Sum

3.5 Supply, lay, grade and compact 20mm crushed stones to specification
requirements Lump Sum

To Collection

375791317.xlsx - SOT 4 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III - Stage I)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

3.6 Backfilling of excavate trench with selected suitable earth fill material and
compact to specification requirement. Lump Sum

3.7 Approved vitrified clay pipe to BS EN295:1991 with and including spigot
and socket joint and laid in trench all in accordance with the
Maunufacturer's Instruction.

i) for 220mm diameter vitrified clays pipes. Lump Sum

iii) for 375mm diameter vitrified clays pipes. Lump Sum

3.8 Approved 200mm diameter DICL pipe to BS 4772 with and including Lump Sum
spigot, socket jointand. All DICL pipes laid in ground shall be fitted with
3.9 approved
Constructionpolyethylene
of sewersleeve
manholeand to specification
including requirement.
concrete, All ductile
reinforcement,
iron
formwork, manhole cover, fitting, fixing, backfill, etc. (piling fusion
fittings shall be coated internally and externally with approved
bonded epoxy
measured applied strictly in accordance with the coating
seperately)
manufacturer's instructions under factory conditions.

a) Manhole internal size 1500 mm x 1500 mm x 2000 mm deep to


invert level, constructed of 230 mm thick Grade 30 base
reinforced with T12 and T10 reinforcement bars laid on and
including 50 mm thick lean concrete (Grade 15) blinding; 230mm
thick Grade 30 wall reinforced with T12 and T10 reinforcement
bars, including 12mm thick plastering on both sides to wall in
sulphate resisting cement and sand (1:3) trowelled smooth
including 225mm diameter half round vetrified clay channel and
section all bedded and jointed in cement mortar and benching
manhole bottom around channel in grade 20 concrete and
finished smooth to fall, 150mm thick Grade 30 suspended cover
slab reinforced with T12 reinforcement steel bars and including
forming 600 diameter opening for and including 600mm diameter
medium duty pattern C.I manhole cover and frame to MS
1228:1991, set cover in thick grease and sand, and malleable
cast iron steps built in brickwork wall at 300mm centres
staggered, and including all necessary excavation, cart away,
formwork and jointing to services all constructed as per detailed
drawing (Type 1).

as per detailed drawing.

i) MH 2 (Taman Putri, Angsana & Signature Park) Lump Sum

To Collection

375791317.xlsx - SOT 5 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III - Stage I)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

b) Manhole internal size 2400 mm x 2400 mm x 5500 mm deep to


invert level, constructed of 300 mm thick Grade 30 base
reinforced with T16 reinforcement bars laid on and including 50
mm thick lean concrete (Grade 15) blinding; 300mm thick Grade
30 wall reinforced with T12 and T16 reinforcement bars, including
12mm thick plastering on both sides to wall in sulphate resisting
cement and sand (1:3) trowelled smooth including 225mm
diameter half round vetrified clay channel and section all bedded
and jointed in cement mortar and benching manhole bottom
around channel in grade 20 concrete and finished smooth to fall,
150mm thick Grade 30 suspended cover slab reinforced with T12
and T16 reinforcement steel bars and including forming 600
diameter opening for and including 600mm diameter medium duty
pattern C.I manhole cover and frame to MS 1228:1991, set cover
in thick grease and sand, and malleable cast iron steps built in
brickwork wall at 300mm centres staggered, and including all
necessary excavation, cart away, formwork and jointing to
services all constructed as per detailed drawing (Type 2).

Taman Li Hua
1) MH1 Lump Sum
2) MH2 Lump Sum
3) MH3 Lump Sum

Taman Putri, Angsana and Signature Park


4) MH1 Lump Sum

3.10 Provision for temporary diversion of incoming sewage from


existing sewerage line at all sites. Lump Sump

3.11 Testing of the completed sewerage system.

a) The sewer shall be tested in sections consisting of the length of pipe


between two adjacent manholes. Sewers shall be subjected to a Water
Test, for which the Contractor shall provide all the necessary testing
apparatus and labour which may be required for the proper testing of the
sewers. These tests shall carried out before backfilling and again after
completion of backfilling and reinstatement.
Lump Sum

To Collection

375791317.xlsx - SOT 6 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III - Stage I)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

b) Clearing pipeline of obstruction.


After testing of the pipelines as specified, the interior of the pipelines
shall be inspected to ascertain that the pipes are entriely clear of
obstruction and that the invert is smooth. These tests shall be carried out
in accordance to the specification. Lump Sum

4.0 SEWERAGE PUMPING STATIONS

4.1 Supply and construct sewerage pumping station including Sluice Valve,
piping, grit chamber, lift well internal size 5m x 5m x 11.41m deep to
invert level, valve chamber, ms covers, etc. all as shown and specified in
the drawing and Specification (piling measured seperately). (Taman Li
Hua) Lump Sum

4.3 Supply and construct sewerage pumping station including Sluice Valve,
piping, grit chamber, lift well internal size 5m x 5m x 7.6m deep to invert
level, valve chamber, ms covers, etc. all as shown and specified in the
drawing and Specification (piling measured seperately). (Angsana,
Taman Putri & Signature Park)
Lump Sum

To Collection

375791317.xlsx - SOT 7 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III - Stage I)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

5.0 DEMOLITION OF EXISTING PUMP STATION AND OTHER


STRUCTURES

Generally, care is to be taken to minimise the noise and dust nuisance


due to the demolition works, the Contractor shall ensure that debris from
the domolition do not fall or hit on undersirable places, traffic,
equipment, personnel and commutors.

Materials and debris are not to be dumped where they are likely to cause
obstruction to the Employer and the public. All such materials to be
removed shall be cart away immediately after the demolition to the
Contrator's own tip at his own cost.

5.1 LI HUA SITE

a Demolition of existing structures e.g lift stations, sedimentation tanks,


manholes and etc. Any usable building materials which may be found on
the site shall remain the property of the Employer. The contractor shall
take all necessary care to remove, dismantle and detach any item to be
salvage from the demolition works e,g all sewer fittings, pump sets,
valves and other accessories or as instructed by the S.O and return to
BDA, all to the satisfaction of the S.O. Lump Sum

b To carefully and gently remove, dismantle, take down , strip-off as


instructed the electric posts with fittings and attached cables and return
to SESCo at contractor own cost. Lump Sum

c To treat the sedimentation tank by desludging the sedimentation tank


and then filling the treated sedimentation tank with imported sand and
suitable fill material as per drawing and specifications Lump Sum

5.2 SIGNATURE PARK SITE


a Demolition of existing structures e.g lift stations, manholes and etc. Any
usable building materials which may be found on the site shall remain the
property of the Employer. The contractor shall take all necessary care to
remove, dismantle and detach any item to be salvage from the demolition
works e,g all sewer fittings, pump sets, valves and other accessories or
as instructed by the S.O and return to BDA, all to the satisfaction of the
S.O. Lump Sum

b To carefully and gently remove, dismantle, take down , strip-off as


instructed the electric posts with fittings and attached cables and return
to SESCo at contractor own cost. Lump Sum

To Collection

375791317.xlsx - SOT 8 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III - Stage I)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

6.0 PILING (ALL PROVISIONAL)

6.1 The following in Pump Stations (2 nos)

a Supply only 150mm x 150mm x 6.0m long precast reinforced concrete


grade 45 initial pile, complete with pile shoe. m 360 44.05

b Supply only 150mm x 150 mm x 6.0m long precast reinforced concrete


grade 45 extension pile. m 720 40.60

c Supply only 150mm x 150 mm x 3.0m long precast reinforced concrete


grade 45 extension pile. m 180 40.60

d Handle, pitch, drive and joint 150mm x 150mm precast reinforced


concrete piles m 1260 23.00

e Cut and break away head od 150mm x 150mm precast reinforced


concrete pile at required level, expose reinforcement bar and cast into
pile cap. No 60 19.09

6.2 The following in screen chamber

a Supply only 150mm x 150 mm x 6.0m long precast reinforced concrete


grade 45 initial pile, complete with pile shoe. m 192 44.05

b Supply only 150mm x 150mm x 6.0m long precast reinforced concrete


grade 45 extension pile. m 384 40.60

c Supply only 150mm x 150mm x 3.0m long precast reinforced concrete


grade 45 extension pile. m 96 40.60

d Handle, pitch, drive and joint 150mm x 150mm precast reinforced


concrete piles m 672 100.05

e Cut and break away head od 150mm x 150mm precast reinforced


concrete pile at required level, expose reinforcement bar and cast into
pile cap. No 32 23.00

To Collection

375791317.xlsx - SOT 9 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III - Stage I)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

6.3 BAKAU PILING (ALL PROVISIONAL)

6.3.1 The following along the sewer lines

a Supply and transport to site 100mm dia.x 3.6m length bakau piles.
m 4320 5.00

b Handle, pitch and drive 100mm dia. bakau piles m 4320 2.88

c Cut off piles heads and dispose off site. nos 600 2.88

d Supply and install 100 mm diameter (internal) pile joints fabricated from
3mm thk ms plates nos 600 23.00

6.3.2 The following in Manhole Type 1

a Supply and transport to site 100mm dia.x 3.6m length bakau piles.
m 144 9.20

b Handle, pitch and drive 100mm dia. bakau piles m 144 2.88

c Cut off piles heads and dispose off site. nos 20 2.88

d Supply and install 100 mm diameter (internal) pile joints fabricated from
3mm thk ms plates nos 20 23.00

6.3.3 The following in Manholes Type 2

a Supply and transport to site 100mm dia.x 3.6m length bakau piles.
m 576 9.20

b Handle, pitch and drive 100mm dia. bakau piles m 576 2.88

c Cut off piles heads and dispose off site. nos 80 2.88

d Supply and install 100 mm diameter (internal) pile joints fabricated from
3mm thk ms plates nos 80 23.00

To Collection

375791317.xlsx - SOT 10 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III - Stage I)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

7.0 WATER SUPPLY TO PUMP STATIONS


Allow for taping off existing water supply pipe and connecting to new
25mm diameter GI pipe and the requisite plumbing services, including all
necessary approved connecting fittings and accessories, and necessary
excavation, carting away. Lump Sum
Rate to include obtaining approval and obtaining water meter from LAKU

8.0 FENCING AND GATE FOR PUMP STATIONS


2000MM high (above ground) galvanised chain link fencing constructed
on flat and undulating ground surfaces all constructed as per detail
drawings. Lump Sum

9.0 OTHER CIVIL WORKS FOR PUMP STATIONS SITE


Construct concrete pavement surrounding the pump as per drawings
Lump Sum

10.0 Contingency Sum Lump Sum

11.0 Others not listed in the above but deemed necessary for the completion
of the project

To Collection

375791317.xlsx - SOT 11 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III - Stage I)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

COLLECTION

1 Page 1

2 Page 2

3 Page 3

4 Page 4

5 Page 5

6 Page 6

7 Page 7

8 Page 8

9 Page 9

10 Page 10

11 Page 11

12 From M & E Works - Schedule 1 of Summary of Prices (SOP 1)

TOTAL CARRIED FORWARD TO FORM OF TENDER (EXCLUDING GST 6%) RM

375791317.xlsx - SOT 12 / 214


e III - Stage I)

AMOUNT (RM)

90,000.00

12,500.00

8,000.00

15,000.00

5,000.00

5,000.00

5,700.00

10,000.00

10,000.00

4,000.00

5,000.00

5,000.00

5,000.00

180,200.00

375791317.xlsx - SOT 13 / 214


e III - Stage I)

AMOUNT (RM)

25,000.00

25,000.00

10,000.00

60,000.00

375791317.xlsx - SOT 14 / 214


e III - Stage I)

AMOUNT (RM)

25,000.00

25,000.00

375791317.xlsx - SOT 15 / 214


e III - Stage I)

AMOUNT (RM)

36,379.00

45,800.00

59,500.00

47,000.00

100,100.00

91,000.00

108,100.00

16,720.00

16,600.00

521,199.00

375791317.xlsx - SOT 16 / 214


e III - Stage I)

AMOUNT (RM)

29,000.00

34,500.00

24,400.00

10,500.00

4,800.00

103,200.00

375791317.xlsx - SOT 17 / 214


e III - Stage I)

AMOUNT (RM)

15,600.00
13,300.00
14,500.00

19,500.00

50,000.00

45,600.00

158,500.00

375791317.xlsx - SOT 18 / 214


e III - Stage I)

AMOUNT (RM)

15,200.00

345,500.00

323,500.00

684,200.00

375791317.xlsx - SOT 19 / 214


e III - Stage I)

AMOUNT (RM)

15,000.00

1,500.00

30,000.00

15,000.00

1,500.00

63,000.00

375791317.xlsx - SOT 20 / 214


e III - Stage I)

AMOUNT (RM)

15,856.20

29,228.40

7,307.10

28,980.00

1,145.40

8,456.64

15,588.48

3,897.12

67,233.60

736.00

178,428.94

375791317.xlsx - SOT 21 / 214


e III - Stage I)

AMOUNT (RM)

21,600.00

12,420.00

1,725.00

13,800.00

1,324.80

414.00

57.50

460.00

5,299.20

1,656.00

230.00

1,840.00

60,826.50

375791317.xlsx - SOT 22 / 214


e III - Stage I)

AMOUNT (RM)

50,000.00

15,000.00

75,000.00

10,000.00

150,000.00

375791317.xlsx - SOT 23 / 214


e III - Stage I)

AMOUNT (RM)

180,200.00

60,000.00

25,000.00

521,199.00

103,200.00

158,500.00

684,200.00

63,000.00

178,428.94

60,826.50

150,000.00

389,380.00

2,573,934.44

375791317.xlsx - SOT 24 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

GRAND SUMMARY OF TENDER

ITEM DESCRIPTION

1 Taman Li Hua

2 Sample Park

3 Taman Angsana, Taman Putri & Signature Park

4 Mechanical and Electrical Works

TOTAL COST OF CONTRACT RM

375791317.xlsx - Grand Summary of Tender 25 / 214


d Works (Phase III)

AMOUNT (RM)

848,130.36

148,499.53

1,105,495.68

389,380.00

2,491,505.56

375791317.xlsx - Grand Summary of Tender 26 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER
TAMAN LI HUA

Unit Qty Rate (RM)


ITEM DESCRIPTION

1.0 GENERAL AND PRELIMINARIES

1.1 Provide Insurance in accordance with General Conditions of Contract.


Lump Sum

1.2 Provide Performance Bond amounting to 5% of the Contract Sum shall be


deposited with the Employer as required by Clause 5 of the Condition of
Contract. Lump Sum

1.3 To provide Levy contribution under the Construction Industry (Collection


of Levy) Regulations 1996. Lump Sum

1.4 Site management and job expenses. Lump Sum

1.5 Mobilisation of personnel, constructional plant and equipment. Lump Sum

1.6 Provide and maintain survey instrument in accordance with the S.O.
requirement. The instrument will be reverted to the Contractor at the
end of the contract. Lump Sum

1.7 Provide and maintain one (1) no. mobile phone including internet
services for S.O.
The Basic Specifications of the Mobile Phone shall be as follows:-
1) 14mp Camera
2) 256 GB Memory
3) 4G/LTE Support Lump Sum

1.8 Provide and maintain S.O. site office, including all furniture, equipment
and fitting as specified. Lump Sum

1.9 Supply personnels, materials and equipment to carry out all quality
control tests. Lump Sum

1.10 Provide for work programme, progress reporting and taking progress
photographs of works. Lump Sum

1.11 Contractor to supply as-built drawings to contract requirement Lump Sum

1.12 Provide and maintain all temporary works including removal from site,
upon completion of Works. Lump Sum

1.13 Demobilisaiton of personnel and constructional plant and equipment.


Lump Sum

1.14 Clearing up Site on completion, in accordance with Specification. Lump Sum

To Collection

375791317.xlsx - Li Hua 27 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER
TAMAN LI HUA

Unit Qty Rate (RM)


ITEM DESCRIPTION

1.15 Site Surveys


The Contractor shall employ a licensed Land Surveyor to carry out a site
survey before work commences, and to assist in establishing boundaries
and setting out the works. On completion of the works, a licensed Land
Surveyor to carry out a further site survey and produce as-built drawings.
Details of grid lines, setting out stations, bench marks, prolfiles etc. Shall
be recorded on a setting out drawing. Lump Sum

1.16 Existing Services


The Contractor shall ascertain the exact position of existing cables, pipes,
ducts, sewers, surface water drains, service mains and the like, under or
over the site and other areas affected by the works, whether indicated on
the drawings or not. He shall uphold, protect and maintain the same
during the execution of the works to the satisfaction of the S.O and make
good or pay for making good all damage thereto and any consequential
damage of loss arising out of such damage.

The Contractor shall not interfere with the operation of services without
the consent of service autorities, or private owners, or the S.O as
appropriate.

If services have to be temporarily terminated or diverted, the Contractor


shall give the necessary notices to the appropriate Authorities, arrange
for the work to be carried out and pay all charges in connection
therewith.

The Contractor shall divert, any drains and waterways encountered


during the progress of the works and subsequently reinstate to the S.O's
approval if diversion is temporary.
Lump Sum

1.17 Traffic Control


The Contractor shall ascertain and comply with all regulations concerning
the carrying out of work in both public roads and roads within the site
and give the necessary notices. No road shall be temporarily or
permanently closed except any for which the Contractor has obtained the
necessary permission from the Authorities.

The Contractor shall apply the necessary traffic control, traffic warning
signs, beacon lights and barriers in private and public roads for carrying
the work, together with any necessary diversions to maintain traffic flow. Lump Sum

To Collection

375791317.xlsx - Li Hua 28 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER
TAMAN LI HUA

Unit Qty Rate (RM)


ITEM DESCRIPTION

1.18 Exsiting Roads and Properties


The Contractor will be responsibe for making good any damage to
existing private and/or public roads, kerbs, crossing, and properties etc.
caused by the carrying out of the works and shall maintain the aforesaid
in their original condition to the satisfaction of the S.O and the relevant
authority. Lump Sum

To Collection

375791317.xlsx - Li Hua 29 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER
TAMAN LI HUA

Unit Qty Rate (RM)


ITEM DESCRIPTION

2.0 SITE CLEARING & EARTHWORKS

2.1 SITE CLEARING


Clear and grub areas within the site boundary and remove all vegetation
and debris from site to the contractor's own tip all to the satisfaction of
the S.O. The contractor shall sort the permission of the S.O regarding
the extend and method of clearing and cutting prior to the
commencement of the works. The Contractor is deemed to have visited
the site and ascertain for himself the true extend and nature of the site
including types of vegetation and items to be cleared. No further claim in
this connection shall be ertertained. Lump Sum

2.2 EARTHWORKS

a) Bulk excavation to the required founding levels of pump stations, screen


chamber, manholes and etc, partly cut and level, partly cut, load,
transport within site, deposit and spread excavated materialin areas to be
filled and thoroughly compact in layers to the required levels as directed. Lump Sum

b) To allow for all necessary temprorary shoring and bracing for excavation

of Pump stations, screen chamber, manholes and etc. Lump Sum

c) Supply,deliver, lay, compact and regrade suitable fill material to form


platform for new pumping station including the drying up of part of the
pond as per drawings and specification Lump Sum

3.0 SEWERAGE WORKS

3.1 Setting out pipe line, excavate trench, get out, part return, fill in, well
ram and remainder cart away from site, level, grade, ram bottom, trim
sides and including planking and strutting. Lump Sum

3.2 To allow for all necessary temprorary shoring and bracing for excavation
of trenches for the sewer lines. Lump Sum

3.3 To construct class 'B' sewer pipe bedding to receive vitrified clay pipes/
conc. Pipe class 'z' (lined internally with 12mm thk high Alumina cement
lining) / DICL pipes, incl. Grade 25 concrete, steel reinforcement and
formworks. (Piling measured seperately) Lump Sum

3.4 Supply, lay, grade and compact in layers 600mm imported sand fill
material to specification requirements Lump Sum

3.5 Supply, lay, grade and compact 20mm crushed stones to specification
requirements Lump Sum

3.6 Backfilling of excavate trench with selected suitable earth fill material and
compact to specification requirement. Lump Sum

To Collection

375791317.xlsx - Li Hua 30 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER
TAMAN LI HUA

Unit Qty Rate (RM)


ITEM DESCRIPTION

3.7 Approved vitrified clay pipe to BS EN295:1991 with and including spigot
and socket joint and laid in trench all in accordance with the
Maunufacturer's Instruction.

i) for 375mm diameter vitrified clays pipes. m 106.02 230.00

3.8 Approved 200mm diameter DICL pipe to BS 4772 with and including
spigot, socket jointand. All DICL pipes laid in ground shall be fitted with
approved polyethylene sleeve and to specification requirement. All ductile
iron fittings shall be coated internally and externally with approved fusion m 25 420.00
bonded epoxy applied strictly in accordance with the coating
manufacturer's instructions under factory conditions.

To Collection

375791317.xlsx - Li Hua 31 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER
TAMAN LI HUA

Unit Qty Rate (RM)


ITEM DESCRIPTION

3.7 Construction of sewer manhole including concrete, reinforcement,


formwork, manhole cover, fitting, fixing, backfill, etc. (piling measured
seperately)

B) Manhole internal size 2400 mm x 2400 mm x 5500 mm deep to


invert level, constructed of 300 mm thick Grade 30 base
reinforced with T16 reinforcement bars laid on and including 50
mm thick lean concrete (Grade 15) blinding; 300mm thick Grade
30 wall reinforced with T12 and T16 reinforcement bars, including
12mm thick plastering on both sides to wall in sulphate resisting
cement and sand (1:3) trowelled smooth including 225mm
diameter half round vetrified clay channel and section all bedded
and jointed in cement mortar and benching manhole bottom
around channel in grade 20 concrete and finished smooth to fall,
150mm thick Grade 30 suspended cover slab reinforced with T12
and T16 reinforcement steel bars and including forming 600
diameter opening for and including 600mm diameter medium duty
pattern C.I manhole cover and frame to MS 1228:1991, set cover
in thick grease and sand, and malleable cast iron steps built in
brickwork wall at 300mm centres staggered, and including all
necessary excavation, cart away, formwork and jointing to
services all constructed as per detailed drawing (Type 2).

Taman Li Hua
1) MH1 Lump Sum
2) MH2 Lump Sum
3) MH3 Lump Sum

To Collection

375791317.xlsx - Li Hua 32 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER
TAMAN LI HUA

Unit Qty Rate (RM)


ITEM DESCRIPTION

3.8 Testing of the completed sewerage system.

a) The sewer shall be tested in sections consisting of the length of pipe


between two adjacent manholes. Sewers shall be subjected to a Water
Test, for which the Contractor shall provide all the necessary testing
apparatus and labour which may be required for the proper testing of the
sewers. These tests shall carried out before backfilling and again after
completion of backfilling and reinstatement.
Lump Sum

b) Clearing pipeline of obstruction.


After testing of the pipelines as specified, the interior of the pipelines
shall be inspected to ascertain that the pipes are entriely clear of
obstruction and that the invert is smooth. These tests shall be carried out
in accordance to the specification.
Lump Sum

4.0 SEWERAGE PUMPING STATIONS

4.1 Supply and construct sewerage pumping station including Sluice Valve,
piping, grit chamber, lift well internal size 5m x 5m x 11.41m deep to
invert level, valve chamber, ms covers, etc. all as shown and specified in
the drawing and Specification (piling measured seperately). (Taman Li
Hua) Lump Sum

5.0 DEMOLITION OF EXISTING PUMP STATION AND OTHER


STRUCTURES

Generally, care is to be taken to minimise the noise and dust nuisance


due to the demolition works, the Contractor shall ensure that debris from
the domolition do not fall or hit on undersirable places, traffic,
equipment, personnel and commutors.

Materials and debris are not to be dumped where they are likely to cause
obstruction to the Employer and the public. All such materials to be
removed shall be cart away immediately after the demolition to the
Contrator's own tip at his own cost.

5.1 LI HUA SITE

a Demolition of existing structures e.g lift stations, manholes and etc. Any
usable building materials which may be found on the site shall remain the
property of the Employer. The contractor shall take all necessary care to
remove, dismantle and detach any item to be salvage from the demolition
works e,g all sewer fittings, pump sets, valves and other accessories or
as instructed by the S.O and return to BDA, all to the satisfaction of the
S.O. Lump Sum

To Collection

375791317.xlsx - Li Hua 33 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER
TAMAN LI HUA

Unit Qty Rate (RM)


ITEM DESCRIPTION

b Partial demolition of existing sedimentation tank as shown in the


drawings. The demolished sedimentation tank shall be desludged and to
be filled with sand to required level. All waste and debris from the works
shall be disposed to sites approved by the Employer. Lump Sum

To Collection

375791317.xlsx - Li Hua 34 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER
TAMAN LI HUA

Unit Qty Rate (RM)


ITEM DESCRIPTION

6.0 PILING (ALL PROVISIONAL)

6.1 The following in Pump Stations (3 nos)

a Supply only 150mm x 150mm x 6.0m long precast reinforced concrete


grade 45 initial pile, complete with pile shoe. m 180 44.05

b Supply only 150mm x 150 mm x 6.0m long precast reinforced concrete


grade 45 extension pile. m 360 40.60

c Supply only 150mm x 150 mm x 3.0m long precast reinforced concrete


grade 45 extension pile. m 90 40.60

d Handle, pitch, drive and joint 150mm x 150mm precast reinforced


concrete piles m 630 23.00

e Cut and break away head od 150mm x 150mm precast reinforced


concrete pile at required level, expose reinforcement bar and cast into
pile cap. No 30 19.09

6.2 The following in screen chamber

a Supply only 150mm x 150 mm x 6.0m long precast reinforced concrete


grade 45 initial pile, complete with pile shoe. m 96 44.05

b Supply only 150mm x 150mm x 6.0m long precast reinforced concrete


grade 45 extension pile. m 192 40.60

c Supply only 150mm x 150mm x 3.0m long precast reinforced concrete


grade 45 extension pile. m 48 40.60

d Handle, pitch, drive and joint 150mm x 150mm precast reinforced


concrete piles m 336 100.05

e Cut and break away head od 150mm x 150mm precast reinforced


concrete pile at required level, expose reinforcement bar and cast into
pile cap. No 16 23.00

6.3 BAKAU PILING (ALL PROVISIONAL)

6.3.1 The following along the sewer lines

a Supply and transport to site 100mm dia.x 3.6m length bakau piles.
m 360 9.2

b Handle, pitch and drive 100mm dia. bakau piles m 360 2.88

c Cut off piles heads and dispose off site. nos 100 2.88

To Collection

375791317.xlsx - Li Hua 35 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER
TAMAN LI HUA

Unit Qty Rate (RM)


ITEM DESCRIPTION

6.3.3 The following in Manholes Type 2

a Supply and transport to site 100mm dia.x 3.6m length bakau piles.
m 432 9.20

b Handle, pitch and drive 100mm dia. bakau piles m 432 2.88

c Cut off piles heads and dispose off site. nos 60 2.88

d Supply and install 100 mm diameter (internal) pile joints fabricated from
3mm thk ms plates nos 60 23.00

7.0 WATER SUPPLY TO PUMP STATIONS


Allow for taping off existing water supply pipe and connecting to new
25mm diameter GI pipe and the requisite plumbing services, including all
necessary approved connecting fittings and accessories, and necessary
excavation, carting away. Lump Sum
Rate to include obtaining approval and obtaining water meter from LAKU

8.0 FENCING AND GATE FOR PUMP STATIONS


2000MM high (above ground) galvanised chain link fencing constructed
on flat and undulating ground surfaces all constructed as per detail
drawings. Lump Sum

9.0 OTHER CIVIL WORKS FOR PUMP STATIONS SITE


Construct concrete pavement surrounding the pump as per drawings
Lump Sum

10.0 Contingency Sum Lump Sum

11.0 Others not listed in the above but deemed necessary for the completion
of the project

To Collection

375791317.xlsx - Li Hua 36 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER
TAMAN LI HUA

Unit Qty Rate (RM)


ITEM DESCRIPTION

COLLECTION

1 Page 1

2 Page 2

3 Page 3

4 Page 4

5 Page 5

6 Page 6

7 Page 7

8 Page 8

9 Page 9

10 Page 10

TOTAL CARRIED FORWARD TO FORM OF TENDER RM

375791317.xlsx - Li Hua 37 / 214


Phase III)

AMOUNT (RM)

4,000.00

4,000.00

4,000.00

4,000.00

3,000.00

1,000.00

5,700.00

5,000.00

2,500.00

1,500.00

1,000.00

1,500.00

1,500.00

2,500.00

41,200.00

375791317.xlsx - Li Hua 38 / 214


Phase III)

AMOUNT (RM)

3,000.00

7,000.00

1,000.00

11,000.00

375791317.xlsx - Li Hua 39 / 214


Phase III)

AMOUNT (RM)

8,000.00

8,000.00

375791317.xlsx - Li Hua 40 / 214


Phase III)

AMOUNT (RM)

1,200.00

27,179.00

37,500.00

47,000.00

15,100.00

15,000.00

20,068.00

1,300.00

1,500.00

4,000.00

169,847.00

375791317.xlsx - Li Hua 41 / 214


Phase III)

AMOUNT (RM)

24,384.60

10,500.00

34,884.60

375791317.xlsx - Li Hua 42 / 214


Phase III)

AMOUNT (RM)

15,552.17
13,279.47
15,552.17

44,383.80

375791317.xlsx - Li Hua 43 / 214


Phase III)

AMOUNT (RM)

6,361.00

1,325.00

345,511.09

15,000.00

368,197.09

375791317.xlsx - Li Hua 44 / 214


Phase III)

AMOUNT (RM)

25,000.00

25,000.00

375791317.xlsx - Li Hua 45 / 214


Phase III)

AMOUNT (RM)

7,928.10

14,614.20

3,653.55

14,490.00

572.70

4,228.32

7,794.24

1,948.56

33,616.80

368.00

3,312.00

1,035.00

287.50

93,848.97

375791317.xlsx - Li Hua 46 / 214


Phase III)

AMOUNT (RM)

3,974.40

1,242.00

172.50

1,380.00

15,000.00

5,000.00

15,000.00

10,000.00

51,768.90

375791317.xlsx - Li Hua 47 / 214


Phase III)

AMOUNT (RM)

41,200.00

11,000.00

8,000.00

169,847.00

34,884.60

44,383.80

368,197.09

25,000.00

93,848.97

51,768.90

848,130.36

375791317.xlsx - Li Hua 48 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER
Sample Park

Unit Qty Rate (RM)


ITEM DESCRIPTION

1.0 GENERAL AND PRELIMINARIES

1.1 Provide Insurance in accordance with General Conditions of Contract.


Lump Sum

1.2 Provide Performance Bond amounting to 5% of the Contract Sum shall be


deposited with the Employer as required by Clause 5 of the Condition of
Contract. Lump Sum

1.3 To provide Levy contribution under the Construction Industry (Collection


of Levy) Regulations 1996. Lump Sum

1.4 Site management and job expenses. Lump Sum

1.5 Mobilisation of personnel, constructional plant and equipment. Lump Sum

1.6 Provide and maintain survey instrument in accordance with the S.O.
requirement. The instrument will be reverted to the Contractor at the
end of the contract. Lump Sum

1.7 Provide and maintain one (1) no. mobile phone including internet
services for S.O.
The Basic Specifications of the Mobile Phone shall be as follows:-
1) 14mp Camera
2) 256 GB Memory
3) 4G/LTE Support Lump Sum

1.8 Provide and maintain S.O. site office, including all furniture, equipment
and fitting as specified. Lump Sum

1.9 Supply personnels, materials and equipment to carry out all quality
control tests. Lump Sum

1.10 Provide for work programme, progress reporting and taking progress
photographs of works. Lump Sum

1.11 Contractor to supply as-built drawings to contract requirement Lump Sum

1.12 Provide and maintain all temporary works including removal from site,
upon completion of Works. Lump Sum

1.13 Demobilisaiton of personnel and constructional plant and equipment.


Lump Sum

1.14 Clearing up Site on completion, in accordance with Specification. Lump Sum

To Collection

375791317.xlsx - Sample Park 49 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER
Sample Park

Unit Qty Rate (RM)


ITEM DESCRIPTION

1.15 Site Surveys


The Contractor shall employ a licensed Land Surveyor to carry out a site
survey before work commences, and to assist in establishing boundaries
and setting out the works. On completion of the works, a licensed Land
Surveyor to carry out a further site survey and produce as-built drawings.
Details of grid lines, setting out stations, bench marks, prolfiles etc. Shall
be recorded on a setting out drawing. Lump Sum

1.16 Existing Services


The Contractor shall ascertain the exact position of existing cables, pipes,
ducts, sewers, surface water drains, service mains and the like, under or
over the site and other areas affected by the works, whether indicated on
the drawings or not. He shall uphold, protect and maintain the same
during the execution of the works to the satisfaction of the S.O and make
good or pay for making good all damage thereto and any consequential
damage of loss arising out of such damage.

The Contractor shall not interfere with the operation of services without
the consent of service autorities, or private owners, or the S.O as
appropriate.

If services have to be temporarily terminated or diverted, the Contractor


shall give the necessary notices to the appropriate Authorities, arrange
for the work to be carried out and pay all charges in connection
therewith.

The Contractor shall divert, any drains and waterways encountered


during the progress of the works and subsequently reinstate to the S.O's
approval if diversion is temporary.
Lump Sum

1.17 Traffic Control


The Contractor shall ascertain and comply with all regulations concerning
the carrying out of work in both public roads and roads within the site
and give the necessary notices. No road shall be temporarily or
permanently closed except any for which the Contractor has obtained the
necessary permission from the Authorities.

The Contractor shall apply the necessary traffic control, traffic warning
signs, beacon lights and barriers in private and public roads for carrying
the work, together with any necessary diversions to maintain traffic flow. Lump Sum

To Collection

375791317.xlsx - Sample Park 50 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER
Sample Park

Unit Qty Rate (RM)


ITEM DESCRIPTION

1.18 Exsiting Roads and Properties


The Contractor will be responsibe for making good any damage to
existing private and/or public roads, kerbs, crossing, and properties etc.
caused by the carrying out of the works and shall maintain the aforesaid
in their original condition to the satisfaction of the S.O and the relevant
authority. Lump Sum

To Collection

375791317.xlsx - Sample Park 51 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER
Sample Park

Unit Qty Rate (RM)


ITEM DESCRIPTION

2.0 SITE CLEARING & EARTHWORKS

2.1 SITE CLEARING


Clear and grub areas within the site boundary and remove all vegetation
and debris from site to the contractor's own tip all to the satisfaction of
the S.O. The contractor shall sort the permission of the S.O regarding
the extend and method of clearing and cutting prior to the
commencement of the works. The Contractor is deemed to have visited
the site and ascertain for himself the true extend and nature of the site
including types of vegetation and items to be cleared. No further claim in
this connection shall be ertertained. Lump Sum

2.2 EARTHWORKS

a) Bulk excavation to the required founding levels of pump stations, screen


chamber, manholes and etc, partly cut and level, partly cut, load,
transport within site, deposit and spread excavated materialin areas to be
filled and thoroughly compact in layers to the required levels as directed. Lump Sum

b) To allow for all necessary temprorary shoring and bracing for excavation

of Pump stations, screen chamber, manholes and etc. Lump Sum

3.0 SEWERAGE WORKS

3.1 Setting out pipe line, excavate trench, get out, part return, fill in, well
ram and remainder cart away from site, level, grade, ram bottom, trim
sides and including planking and strutting. Lump Sum

3.2 To allow for all necessary temprorary shoring and bracing for excavation
of trenches for the sewer lines. Lump Sum

3.3 To construct class 'B' sewer pipe bedding to receive vitrified clay pipes/
conc. Pipe class 'z' (lined internally with 12mm thk high Alumina cement
lining) / DICL pipes, incl. Grade 25 concrete, steel reinforcement and
formworks. (Piling measured seperately) Lump Sum

Supply, lay, grade and compact in layers 600mm imported sand fill
material to specification requirements Lump Sum

Supply, lay, grade and compact 20mm crushed stones to specification


requirements Lump Sum

To Collection

375791317.xlsx - Sample Park 52 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER
Sample Park

Unit Qty Rate (RM)


ITEM DESCRIPTION

3.4 Backfilling of excavate trench with selected suitable earth fill material and
compact to specification requirement. Lump Sum

3.5 Approved vitrified clay pipe to BS EN295:1991 with and including spigot
and socket joint and laid in trench all in accordance with the
Maunufacturer's Instruction.

iii) for .225mm diameter vitrified clays pipes. m 87.65 42.50

3.6 Approved 200mm diameter DICL pipe to BS 4772 with and including
spigot, socket jointand. All DICL pipes laid in ground shall be fitted with
approved polyethylene sleeve and to specification requirement. All ductile
iron fittings shall be coated internally and externally with approved fusion m 23 420.00
bonded epoxy applied strictly in accordance with the coating
manufacturer's instructions under factory conditions.

To Collection

375791317.xlsx - Sample Park 53 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER
Sample Park

Unit Qty Rate (RM)


ITEM DESCRIPTION

3.8 Testing of the completed sewerage system.

a) The sewer shall be tested in sections consisting of the length of pipe


between two adjacent manholes. Sewers shall be subjected to a Water
Test, for which the Contractor shall provide all the necessary testing
apparatus and labour which may be required for the proper testing of the
sewers. These tests shall carried out before backfilling and again after
completion of backfilling and reinstatement.
Lump Sum

b) Clearing pipeline of obstruction.


After testing of the pipelines as specified, the interior of the pipelines
shall be inspected to ascertain that the pipes are entriely clear of
obstruction and that the invert is smooth. These tests shall be carried out
in accordance to the specification.
Lump Sum

4.0 DISCONNECTION OF EXISTING SEWERS

Generally, care is to be taken to minimise the noise and dust nuisance


due to the demolition works, the Contractor shall ensure that debris from
the domolition do not fall or hit on undersirable places, traffic,
equipment, personnel and commutors.

Materials and debris are not to be dumped where they are likely to cause
obstruction to the Employer and the public. All such materials to be
removed shall be cart away immediately after the demolition to the
Contrator's own tip at his own cost.

4.1 To remove existing sewer pipeline including temporary diversion works of


Lump Sum
the sewers.

4.2 To carefully and gently remove, dismantle, take down , strip-off as


instructed the electric posts with fittings and attached cables and return
to SESCo at contractor own cost. Lump Sum

To Collection

375791317.xlsx - Sample Park 54 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER
Sample Park

Unit Qty Rate (RM)


ITEM DESCRIPTION

5.0 PILING (ALL PROVISIONAL)

5.1 BAKAU PILING (ALL PROVISIONAL)

5.1.1 The following along the sewer lines

a Supply and transport to site 100mm dia.x 3.6m length bakau piles.
m 288 9.2

b Handle, pitch and drive 100mm dia. bakau piles m 288 2.88

c Cut off piles heads and dispose off site. nos 80 2.88

5.1.2 The following in Manhole Type 1

a Supply and transport to site 100mm dia.x 6.0m length bakau piles.
m 144 9.20

b Handle, pitch and drive 100mm dia. bakau piles m 144 2.88

c Cut off piles heads and dispose off site. nos 40 2.88

d Supply and install 100 mm diameter (internal) pile joints fabricated from
3mm thk ms plates nos 40 23.00

6.0 Contingency Sum Lump Sum

7.0 Others not listed in the above but deemed necessary for the completion
of the project

To Collection

375791317.xlsx - Sample Park 55 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER
Sample Park

Unit Qty Rate (RM)


ITEM DESCRIPTION

COLLECTION

1 Page 1

2 Page 2

3 Page 3

4 Page 4

5 Page 5

6 Page 6

7 Page 7

TOTAL CARRIED FORWARD TO FORM OF TENDER RM

375791317.xlsx - Sample Park 56 / 214


Phase III)

AMOUNT (RM)

2,000.00

2,000.00

1,000.00

4,000.00

3,000.00

1,500.00

5,700.00

2,000.00

2,500.00

1,500.00

1,000.00

1,500.00

1,500.00

3,000.00

32,200.00

375791317.xlsx - Sample Park 57 / 214


Phase III)

AMOUNT (RM)

3,000.00

7,000.00

1,000.00

11,000.00

375791317.xlsx - Sample Park 58 / 214


Phase III)

AMOUNT (RM)

5,000.00

5,000.00

375791317.xlsx - Sample Park 59 / 214


Phase III)

AMOUNT (RM)

1,200.00

5,500.00

14,400.00

10,000.00

10,000.00

13,033.00

1,000.00

1,000.00

56,133.00

375791317.xlsx - Sample Park 60 / 214


Phase III)

AMOUNT (RM)

2,600.00

3,725.13

9,660.00

15,985.13

375791317.xlsx - Sample Park 61 / 214


Phase III)

AMOUNT (RM)

4,200.00

1,000.00

5,000.00

1,500.00

11,700.00

375791317.xlsx - Sample Park 62 / 214


Phase III)

AMOUNT (RM)

2,649.60

828.00

230.00

1,324.80

414.00

115.00

920.00

10,000.00

16,481.40

375791317.xlsx - Sample Park 63 / 214


Phase III)

AMOUNT (RM)

32,200.00

11,000.00

5,000.00

56,133.00

15,985.13

11,700.00

16,481.40

148,499.53

375791317.xlsx - Sample Park 64 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER
Taman Signature Angsana and Putri

Unit Qty Rate (RM)


ITEM DESCRIPTION

1.0 GENERAL AND PRELIMINARIES

1.1 Provide Insurance in accordance with General Conditions of Contract.


Lump Sum

1.2 Provide Performance Bond amounting to 5% of the Contract Sum shall be


deposited with the Employer as required by Clause 5 of the Condition of
Contract. Lump Sum

1.3 To provide Levy contribution under the Construction Industry (Collection


of Levy) Regulations 1996. Lump Sum

1.4 Site management and job expenses. Lump Sum

1.5 Mobilisation of personnel, constructional plant and equipment. Lump Sum

1.6 Provide and maintain survey instrument in accordance with the S.O.
requirement. The instrument will be reverted to the Contractor at the
end of the contract. Lump Sum

1.7 Provide and maintain one (1) no. mobile phone including internet
services for S.O.
The Basic Specifications of the Mobile Phone shall be as follows:-
1) 14mp Camera
2) 256 GB Memory
3) 4G/LTE Support Lump Sum

1.8 Provide and maintain S.O. site office, including all furniture, equipment
and fitting as specified. Lump Sum

1.9 Supply personnels, materials and equipment to carry out all quality
control tests. Lump Sum

1.10 Provide for work programme, progress reporting and taking progress
photographs of works. Lump Sum

1.11 Contractor to supply as-built drawings to contract requirement Lump Sum

1.12 Provide and maintain all temporary works including removal from site,
upon completion of Works. Lump Sum

1.13 Demobilisaiton of personnel and constructional plant and equipment.


Lump Sum

1.14 Clearing up Site on completion, in accordance with Specification. Lump Sum

To Collection

375791317.xlsx - Signature 65 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER
Taman Signature Angsana and Putri

Unit Qty Rate (RM)


ITEM DESCRIPTION

1.15 Site Surveys


The Contractor shall employ a licensed Land Surveyor to carry out a site
survey before work commences, and to assist in establishing boundaries
and setting out the works. On completion of the works, a licensed Land
Surveyor to carry out a further site survey and produce as-built drawings.
Details of grid lines, setting out stations, bench marks, prolfiles etc. Shall
be recorded on a setting out drawing. Lump Sum

1.16 Existing Services


The Contractor shall ascertain the exact position of existing cables, pipes,
ducts, sewers, surface water drains, service mains and the like, under or
over the site and other areas affected by the works, whether indicated on
the drawings or not. He shall uphold, protect and maintain the same
during the execution of the works to the satisfaction of the S.O and make
good or pay for making good all damage thereto and any consequential
damage of loss arising out of such damage.

The Contractor shall not interfere with the operation of services without
the consent of service autorities, or private owners, or the S.O as
appropriate.

If services have to be temporarily terminated or diverted, the Contractor


shall give the necessary notices to the appropriate Authorities, arrange
for the work to be carried out and pay all charges in connection
therewith.

The Contractor shall divert, any drains and waterways encountered


during the progress of the works and subsequently reinstate to the S.O's
approval if diversion is temporary.
Lump Sum

1.17 Traffic Control


The Contractor shall ascertain and comply with all regulations concerning
the carrying out of work in both public roads and roads within the site
and give the necessary notices. No road shall be temporarily or
permanently closed except any for which the Contractor has obtained the
necessary permission from the Authorities.

The Contractor shall apply the necessary traffic control, traffic warning
signs, beacon lights and barriers in private and public roads for carrying
the work, together with any necessary diversions to maintain traffic flow. Lump Sum

To Collection

375791317.xlsx - Signature 66 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER
Taman Signature Angsana and Putri

Unit Qty Rate (RM)


ITEM DESCRIPTION

1.18 Exsiting Roads and Properties


The Contractor will be responsibe for making good any damage to
existing private and/or public roads, kerbs, crossing, and properties etc.
caused by the carrying out of the works and shall maintain the aforesaid
in their original condition to the satisfaction of the S.O and the relevant
authority. Lump Sum

To Collection

375791317.xlsx - Signature 67 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER
Taman Signature Angsana and Putri

Unit Qty Rate (RM)


ITEM DESCRIPTION

2.0 SITE CLEARING & EARTHWORKS

2.1 SITE CLEARING


Clear and grub areas within the site boundary and remove all vegetation
and debris from site to the contractor's own tip all to the satisfaction of
the S.O. The contractor shall sort the permission of the S.O regarding
the extend and method of clearing and cutting prior to the
commencement of the works. The Contractor is deemed to have visited
the site and ascertain for himself the true extend and nature of the site
including types of vegetation and items to be cleared. No further claim in
this connection shall be ertertained. Lump Sum

2.2 EARTHWORKS

a) Bulk excavation to the required founding levels of pump stations, screen


chamber, manholes and etc, partly cut and level, partly cut, load,
transport within site, deposit and spread excavated materialin areas to be
filled and thoroughly compact in layers to the required levels as directed. Lump Sum

b) To allow for all necessary temprorary shoring and bracing for excavation

of Pump stations, screen chamber, manholes and etc. Lump Sum

3.0 SEWERAGE WORKS

3.1 Setting out pipe line, excavate trench, get out, part return, fill in, well
ram and remainder cart away from site, level, grade, ram bottom, trim
sides and including planking and strutting. Lump Sum

3.2 To allow for all necessary temprorary shoring and bracing for excavation
of trenches for the sewer lines. Lump Sum

3.3 To construct class 'B' sewer pipe bedding to receive vitrified clay pipes/
conc. Pipe class 'z' (lined internally with 12mm thk high Alumina cement
lining) / DICL pipes, incl. Grade 25 concrete, steel reinforcement and
formworks. (Piling measured seperately) Lump Sum

Supply, lay, grade and compact in layers 600mm imported sand fill
material to specification requirements Lump Sum

Supply, lay, grade and compact 20mm crushed stones to specification


requirements Lump Sum

To Collection

375791317.xlsx - Signature 68 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER
Taman Signature Angsana and Putri

Unit Qty Rate (RM)


ITEM DESCRIPTION

3.4 Backfilling of excavate trench with selected suitable earth fill material and
compact to specification requirement. Lump Sum

3.5 Approved vitrified clay pipe to BS EN295:1991 with and including spigot
and socket joint and laid in trench all in accordance with the
Maunufacturer's Instruction.

ii) for 220m diameter vitrified clays pipes. m 318 85.00

3.6 Approved 200mm diameter DICL pipe to BS 4772 with and including
spigot, socket jointand. All DICL pipes laid in ground shall be fitted with
approved polyethylene sleeve and to specification requirement. All ductile
iron fittings shall be coated internally and externally with approved fusion m 25 420.00
bonded epoxy applied strictly in accordance with the coating
manufacturer's instructions under factory conditions.

To Collection

375791317.xlsx - Signature 69 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER
Taman Signature Angsana and Putri

Unit Qty Rate (RM)


ITEM DESCRIPTION

3.7 Construction of sewer manhole including concrete, reinforcement,


formwork, manhole cover, fitting, fixing, backfill, etc. (piling measured
seperately)

A) Manhole internal size 1500 mm x 1500 mm x 2000 mm deep to


invert level, constructed of 230 mm thick Grade 30 base
reinforced with T12 and T10 reinforcement bars laid on and
including 50 mm thick lean concrete (Grade 15) blinding; 230mm
thick Grade 30 wall reinforced with T12 and T10 reinforcement
bars, including 12mm thick plastering on both sides to wall in
sulphate resisting cement and sand (1:3) trowelled smooth
including 225mm diameter half round vetrified clay channel and
section all bedded and jointed in cement mortar and benching
manhole bottom around channel in grade 20 concrete and
finished smooth to fall, 150mm thick Grade 30 suspended cover
slab reinforced with T12 reinforcement steel bars and including
forming 600 diameter opening for and including 600mm diameter
medium duty pattern C.I manhole cover and frame to MS
1228:1991, set cover in thick grease and sand, and malleable
cast iron steps built in brickwork wall at 300mm centres
staggered, and including all necessary excavation, cart away,
formwork and jointing to services all constructed as per detailed
drawing (Type 1).

as per detailed drawing.

i) MH 1 (Taman Putri, Angsana & Signature Park) Lump Sum

To Collection

375791317.xlsx - Signature 70 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER
Taman Signature Angsana and Putri

Unit Qty Rate (RM)


ITEM DESCRIPTION

cont'd

B) Manhole internal size 2400 mm x 2400 mm x 5500 mm deep to


invert level, constructed of 300 mm thick Grade 30 base
reinforced with T16 reinforcement bars laid on and including 50
mm thick lean concrete (Grade 15) blinding; 300mm thick Grade
30 wall reinforced with T12 and T16 reinforcement bars, including
12mm thick plastering on both sides to wall in sulphate resisting
cement and sand (1:3) trowelled smooth including 225mm
diameter half round vetrified clay channel and section all bedded
and jointed in cement mortar and benching manhole bottom
around channel in grade 20 concrete and finished smooth to fall,
150mm thick Grade 30 suspended cover slab reinforced with T12
and T16 reinforcement steel bars and including forming 600
diameter opening for and including 600mm diameter medium duty
pattern C.I manhole cover and frame to MS 1228:1991, set cover
in thick grease and sand, and malleable cast iron steps built in
brickwork wall at 300mm centres staggered, and including all
necessary excavation, cart away, formwork and jointing to
services all constructed as per detailed drawing (Type 2).

Taman Putri, Angsana and Signature Park


1) MH 1 Lump Sum
2) MH 2 Lump Sum
3) MH 3 Lump Sum

To Collection

375791317.xlsx - Signature 71 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER
Taman Signature Angsana and Putri

Unit Qty Rate (RM)


ITEM DESCRIPTION

3.8 Testing of the completed sewerage system.

a) The sewer shall be tested in sections consisting of the length of pipe


between two adjacent manholes. Sewers shall be subjected to a Water
Test, for which the Contractor shall provide all the necessary testing
apparatus and labour which may be required for the proper testing of the
sewers. These tests shall carried out before backfilling and again after
completion of backfilling and reinstatement.
Lump Sum

b) Clearing pipeline of obstruction.


After testing of the pipelines as specified, the interior of the pipelines
shall be inspected to ascertain that the pipes are entriely clear of
obstruction and that the invert is smooth. These tests shall be carried out
in accordance to the specification.
Lump Sum

4.0 SEWERAGE PUMPING STATIONS

4.1 Supply and construct sewerage pumping station including Sluice Valve,
piping, grit chamber, lift well internal size 5m x 5m x 7.6m deep to invert
level, valve chamber, ms covers, etc. all as shown and specified in the
drawing and Specification (piling measured seperately). (Angsana,
Taman Putri & Signature Park)
Lump Sum

To Collection

375791317.xlsx - Signature 72 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER
Taman Signature Angsana and Putri

Unit Qty Rate (RM)


ITEM DESCRIPTION

5.0 DEMOLITION OF EXISTING PUMP STATION

Generally, care is to be taken to minimise the noise and dust nuisance


due to the demolition works, the Contractor shall ensure that debris from
the domolition do not fall or hit on undersirable places, traffic,
equipment, personnel and commutors.

Materials and debris are not to be dumped where they are likely to cause
obstruction to the Employer and the public. All such materials to be
removed shall be cart away immediately after the demolition to the
Contrator's own tip at his own cost.

5.3 SIGNATURE PARK SITE


a Demolition of existing structures e.g lift stations, manholes and etc. Any
usable building materials which may be found on the site shall remain the
property of the Employer. The contractor shall take all necessary care to
remove, dismantle and detach any item to be salvage from the demolition
works e,g all sewer fittings, pump sets, valves and other accessories or
as instructed by the S.O and return to BDA, all to the satisfaction of the
S.O. Lump Sum

b To carefully and gently remove, dismantle, take down , strip-off as


instructed the electric posts with fittings and attached cables and return
to SESCo at contractor own cost. Lump Sum

6.0 PILING (ALL PROVISIONAL)

6.1 The following in Pump Stations

a Supply only 150mm x 150mm x 6.0m long precast reinforced concrete


grade 45 initial pile, complete with pile shoe. m 180 44.05

b Supply only 150mm x 150 mm x 6.0m long precast reinforced concrete


grade 45 extension pile. m 360 40.60

c Supply only 150mm x 150 mm x 3.0m long precast reinforced concrete


grade 45 extension pile. m 90 40.60

d Handle, pitch, drive and joint 150mm x 150mm precast reinforced


concrete piles m 630 23.00

e Cut and break away head od 150mm x 150mm precast reinforced


concrete pile at required level, expose reinforcement bar and cast into
pile cap. No 30 19.09

To Collection

375791317.xlsx - Signature 73 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER
Taman Signature Angsana and Putri

Unit Qty Rate (RM)


ITEM DESCRIPTION

6.2 The following in screen chamber

a Supply only 150mm x 150 mm x 6.0m long precast reinforced concrete


grade 45 initial pile, complete with pile shoe. m 96 44.05

b Supply only 150mm x 150mm x 6.0m long precast reinforced concrete


grade 45 extension pile. m 192 40.60

c Supply only 150mm x 150mm x 3.0m long precast reinforced concrete


grade 45 extension pile. m 48 40.60

d Handle, pitch, drive and joint 150mm x 150mm precast reinforced


concrete piles m 336 100.05

e Cut and break away head od 150mm x 150mm precast reinforced


concrete pile at required level, expose reinforcement bar and cast into
pile cap. No 16 23.00

6.3 BAKAU PILING (ALL PROVISIONAL)

6.3.1 The following along the sewer lines

a Supply and transport to site 100mm dia.x 3.6m length bakau piles.
m 1500 9.2

b Handle, pitch and drive 100mm dia. bakau piles m 1500 2.88

c Cut off piles heads and dispose off site. nos 500 2.88

6.3.2 The following in Manhole Type 1

a Supply and transport to site 100mm dia.x 3.6m length bakau piles.
m 420 9.20

b Handle, pitch and drive 100mm dia. bakau piles m 420 2.88

c Cut off piles heads and dispose off site. nos 60 2.88

d Supply and install 100 mm diameter (internal) pile joints fabricated from
3mm thk ms plates nos 60 23.00

6.3.3 The following in Manholes Type 2

a Supply and transport to site 100mm dia.x 3.6m length bakau piles.
m 864 9.20

b Handle, pitch and drive 100mm dia. bakau piles m 864 2.88

c Cut off piles heads and dispose off site. nos 120 2.88

d Supply and install 100 mm diameter (internal) pile joints fabricated from
3mm thk ms plates nos 120 23.00

To Collection

375791317.xlsx - Signature 74 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER
Taman Signature Angsana and Putri

Unit Qty Rate (RM)


ITEM DESCRIPTION

7.0 WATER SUPPLY TO PUMP STATIONS


Allow for taping off existing water supply pipe and connecting to new
25mm diameter GI pipe and the requisite plumbing services, including all
necessary approved connecting fittings and accessories, and necessary
excavation, carting away. Lump Sum

Rate to include obtaining approval and obtaining water meter from LAKU

8.0 FENCING AND GATE FOR PUMP STATIONS


2000MM high (above ground) galvanised chain link fencing constructed
on flat and undulating ground surfaces all constructed as per detail
drawings. Lump Sum

9.0 OTHER CIVIL WORKS FOR PUMP STATIONS SITE


Construct concrete pavement surrounding the pump as per drawings
Lump Sum

10.0 Contingency Sum Lump Sum

11.0 Others not listed in the above but deemed necessary for the completion
of the project

To Collection

375791317.xlsx - Signature 75 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER
Taman Signature Angsana and Putri

Unit Qty Rate (RM)


ITEM DESCRIPTION

COLLECTION

1 Page 1

2 Page 2

3 Page 3

4 Page 4

5 Page 5

6 Page 6

7 Page 7

8 Page 8

9 Page 9

10 Page 10

11 Page 11

TOTAL CARRIED FORWARD TO FORM OF TENDER RM

375791317.xlsx - Signature 76 / 214


Phase III)

AMOUNT (RM)

16,000.00

16,000.00

8,000.00

8,000.00

6,000.00

2,500.00

5,700.00

5,000.00

2,500.00

1,500.00

3,000.00

6,000.00

1,500.00

3,000.00

84,700.00

375791317.xlsx - Signature 77 / 214


Phase III)

AMOUNT (RM)

16,000.00

5,000.00

5,000.00

26,000.00

375791317.xlsx - Signature 78 / 214


Phase III)

AMOUNT (RM)

25,000.00

25,000.00

375791317.xlsx - Signature 79 / 214


Phase III)

AMOUNT (RM)

8,000.00

13,100.00

22,000.00

75,000.00

66,000.00

75,000.00

14,420.42

14,097.74

287,618.16

375791317.xlsx - Signature 80 / 214


Phase III)

AMOUNT (RM)

22,500.00

27,030.00

10,500.00

60,030.00

375791317.xlsx - Signature 81 / 214


Phase III)

AMOUNT (RM)

4,779.72

4,779.72

375791317.xlsx - Signature 82 / 214


Phase III)

AMOUNT (RM)

19,529.39
22,410.84
10,844.44

52,784.66

375791317.xlsx - Signature 83 / 214


Phase III)

AMOUNT (RM)

35,000.00

12,900.00

323,256.86

371,156.86

375791317.xlsx - Signature 84 / 214


Phase III)

AMOUNT (RM)

15,000.00

1,500.00

7,928.10

14,614.20

3,653.55

14,490.00

572.70

57,758.55

375791317.xlsx - Signature 85 / 214


Phase III)

AMOUNT (RM)

4,228.32

7,794.24

1,948.56

33,616.80

368.00

13,800.00

4,312.50

1,437.50

3,864.00

1,207.50

172.50

1,380.00

7,948.80

2,484.00

345.00

2,760.00

87,667.72

375791317.xlsx - Signature 86 / 214


Phase III)

AMOUNT (RM)

15,000.00

8,000.00

15,000.00

10,000.00

48,000.00

375791317.xlsx - Signature 87 / 214


Phase III)

AMOUNT (RM)

84,700.00

26,000.00

25,000.00

287,618.16

60,030.00

4,779.72

52,784.66

371,156.86

57,758.55

87,667.72

48,000.00

1,105,495.68

375791317.xlsx - Signature 88 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

COST OF ESTIMATION

Unit Qty
ITEM DESCRIPTION

3.0 SEWERAGE WORKS

3.1 Setting out pipe line, excavate trench, get out, part return, fill in, well
ram and remainder cart away from site, level, grade, ram bottom, trim
sides and including planking and strutting. m3 843.075 15.5

3.2 600mm Depth Sand fill m3 422.2053 35

3.3 To construct class 'B' sewer pipe bedding to receive vitrified clay
pipes/ conc. Pipe class 'z' (lined internally with 12mm thk high Alumina
cement lining) / DICL pipes, incl. Grade 25 concrete, steel
reinforcement and formworks. (Piling measured seperately)

550mm Wide x 212.5mm thick of concrete surround to the following


soil pipes. (pipe measured separately) m3 34.98

Alumina added plaster on internal face m2 292.2

Steel reinforcement kg 33197.31

Formwork
m2 1200

Supply, lay, grade and compact in layers 600mm imported sand fill
material to specification requirements m3 422.2053 29.7

Supply, lay, grade and compact 20mm crushed stones to specification


requirements m3 159 77.1
Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

COST OF ESTIMATION

Unit Qty
ITEM DESCRIPTION

3.5 Approved vetrified clay pipe to BS EN295:1991 with and including


spigot and socket joint and laid in trench all in accordance with the
Maunufacturer's Instruction.

ii) for 350mm diameter vetrified clays pipes. m 150 200

iii) for 220mm diameter vetrified clays pipes. m 500 320

3.7 Approved 200mm dia. DI Pipe m 95.7 677

3.9 Construction of sewer manhole including concrete, reinforcement,


formwork, manhole cover, fitting, fixing, backfill, etc. (piling measured
seperately)

a) Manhole internal size 1140 mm x 940 mm x 1200 mm deep to


invert level, constructed of 150 mm thick Grade 20 base
reinforced with 2 layer BMC A10 fabric mesh reinforcement laid
on and including 50 mm thick lean concrete (Grade 15) blinding;
225 mm thick brickwork wall in well burnt clay bricks including
12mm thick plastering on both sides to wall in sulphate resisting
cement and sand (1:3) trowelled smooth including 225mm
diameter half round vetrified clay channel and section all bedded
and jointed in cement mortar and benching manhole bottom
around channel in grade 20 concrete and finished smooth to fall,
150mm thick Grade 20 suspended cover slab reinforced with
and including 1 layer BMC A8 mesh reinforcement and including
forming 550mm x 550mm opening for and including 550mm x
550 mm medium duty pattern C.I manhole cover and frame to
MS 1228:1991, set cover in thick grease and sand, and
malleable cast iron steps built in brickwork wall at 300mm
centres staggered, and including all necessary excavation, cart
away, formwork and jointing to services all constructed as per
detailed drawing (Type 1). No 4
Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

COST OF ESTIMATION

Unit Qty
ITEM DESCRIPTION

b) Manhole internal size 1140mm x 940 mm x 1500mm deep to invert


level all as last described. No 6

c) Manhole internal size 1140mm x 940 mm x 1760mm deep to invert


level all as last described. No 8

d) Manhole internal size 1140mm x 940 mm x 1800mm deep to invert


level all as last described. No 2

e) Manhole internal size 1140mm x 940 mm x 1830mm deep to invert


level all as last described. No 1

f) Manhole internal size 1140mm x 940 mm x 1880mm deep to invert


level all as last described. No 3

g) Manhole internal size 1800 mm x 1800 mm x 2100 mm deep to


invert level, constructed of 230 mm thick Grade 20 base
reinforced with Y12 reinforcement bars laid on and including 50
mm thick lean concrete (Grade 15) blinding; 230mm thick Grade
20 wall reinforced with Y12 and Y16 reinforcement bars, 225
mm thick brickwork wall in well burnt clay bricks including 12mm No 10
thick plastering on both sides to wall in sulphate resisting
h) Manhole
cement and internal
sandsize(1:3)
1800mm x 1800
trowelled mm x 2240mm
smooth includingdeep to invert
225mm
level all as half
diameter last described.
round vetrified clay channel and section all bedded No 1
and jointed in cement mortar and benching manhole bottom
I) around channel
Manhole in grade
internal size 1800mm20 xconcrete
1800 mmand finisheddeep
x 2340mm smooth to fall,
to invert
150mm
level thick
all as last Grade
described.20 suspended cover slab reinforced with No 2
Y12 and Y16 reinforcement steel bars and including forming 600
j) diameterinternal
Manhole opening sizefor and including
1800mm 600mm
x 1800 mm diameter
x 2760mm deepmedium
to invert
duty all
level pattern
as lastC.I manhole cover and frame to MS 1228:1991, set
described. No 7
cover in thick grease and sand, and malleable cast iron steps
k) built in brickwork
Manhole wall
internal size at 300mm
1800mm centres
x 1800 staggered,
mm x 2950mm and
deep to invert
including
level all as all
lastnecessary
described. excavation, cart away, formwork and No 3
jointing to services all constructed as per detailed drawing
l) (Type 2).internal size 1800mm x 1800 mm x 3100mm deep to invert
Manhole
level all as last described. No 4

m) Manhole internal size 1800mm x 1800 mm x 3200mm deep to invert


level all as last described. No 2

n) Manhole internal size 1800mm x 1800 mm x 3250mm deep to invert


level all as last described. No 1

o) Manhole internal size 1800mm x 1800 mm x 3480mm deep to invert


level all as last described. No 5

p) Manhole internal size 1800mm x 1800 mm x 3500mm deep to invert


level all as last described. No 4

q) Manhole internal size 1800mm x 1800 mm x 3590mm deep to invert


level all as last described. No 2

r) Manhole internal size 1800mm x 1800 mm x 4000mm deep to invert


level all as last described. No 6
Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

COST OF ESTIMATION

Unit Qty
ITEM DESCRIPTION

s) Manhole internal size 1800mm x 1800 mm x 4250mm deep to invert


level all as last described. No 1

t) Manhole internal size 1800mm x 1800 mm x 4340mm deep to invert


level all as last described. No 1

u) Manhole internal size 1800mm x 1800 mm x 4500mm deep to invert


level all as last described. No 1

v) Manhole internal size 1800mm x 1800 mm x 4660mm deep to invert


level all as last described. No 1

3.10 Testing of the completed sewerage system.


The sewer shall be tested in sections consisting of the length of pipe
between two adjacent manholes. Sewers shall be subjected to a
Water, at the discretion of the Employer, for which the Contractor shall
provide all the necessary testing apparatus and labour which may be
required for the proper testing of the sewers. These tests shall carried
out before backfilling and again after completion of backfilling and
reinstatement. Lump Sum

TOTAL SEWER AMOUNT


s (Phase III)

Rate (RM) AMOUNT (RM)

150.00 126,461.25

40.25 16,993.76

440.34 15,403.09

27.60 8,064.72

4.14 137,436.86

55.20 66,240.00

227,144.68

34.16 14,420.42

88.67 14,097.74
s (Phase III)

Rate (RM) AMOUNT (RM)

230.00 34,500.00

361.60 180,800.00

778.55 74,507.24

900.00 3,600.00
s (Phase III)

Rate (RM) AMOUNT (RM)

900.00 5,400.00

1,000.00 8,000.00

1,120.00 2,240.00

1,120.00 1,120.00

1,120.00 3,360.00

4,500.00 45,000.00

4,700.00 4,700.00

4,900.00 9,800.00

5,450.00 38,150.00

5,750.00 17,250.00

5,900.00 23,600.00

5,900.00 11,800.00

6,000.00 6,000.00

6,100.00 30,500.00

6,600.00 26,400.00

6,650.00 13,300.00

6,700.00 40,200.00
s (Phase III)

Rate (RM) AMOUNT (RM)

6,800.00 6,800.00

6,800.00 6,800.00

6,900.00 6,900.00

7,200.00 7,200.00

15,000.00 15,000.00

1,249,189.76
Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

1.0 GENERAL AND PRELIMINARIES

1.1 Provide Insurance in accordance with General Conditions of Contract.


Lump Sum

1.2 Provide Performance Bond amounting to 5% of the Contract Sum shall be


deposited with the Employer as required by Clause 5 of the Condition of
Contract. Lump Sum

1.3 To provide Levy contribution under the Construction Industry (Collection


of Levy) Regulations 1996. Lump Sum

1.4 Site management and job expenses. Lump Sum

1.5 Mobilisation of personnel, constructional plant and equipment. Lump Sum

1.6 Provide and maintain survey instrument in accordance with the S.O.
requirement. The instrument will be reverted to the Contractor at the
end of the contract. Lump Sum

1.7 Provide and maintain one (1) no. mobile phone including internet
services for S.O.
The Basic Specifications of the Mobile Phone shall be as follows:-
1) 14mp Camera
2) 256 GB Memory
3) 4G/LTE Support Lump Sum

1.8 Provide and maintain S.O. site office, including all furniture, equipment
and fitting as specified. Lump Sum

1.9 Supply personnels, materials and equipment to carry out all quality
control tests. Lump Sum

1.10 Provide for work programme, progress reporting and taking progress
photographs of works. Lump Sum

1.11 Contractor to supply as-built drawings to contract requirement Lump Sum

1.12 Provide and maintain all temporary works including removal from site,
upon completion of Works. Lump Sum

1.13 Demobilisaiton of personnel and constructional plant and equipment.


Lump Sum

1.14 Clearing up Site on completion, in accordance with Specification. Lump Sum

To Collection

375791317.xlsx - Putri 97 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

1.15 Site Surveys


The Contractor shall employ a licensed Land Surveyor to carry out a site
survey before work commences, and to assist in establishing boundaries
and setting out the works. On completion of the works, a licensed Land
Surveyor to carry out a further site survey and produce as-built drawings.
Details of grid lines, setting out stations, bench marks, prolfiles etc. Shall
be recorded on a setting out drawing. Lump Sum

1.16 Existing Services


The Contractor shall ascertain the exact position of existing cables, pipes,
ducts, sewers, surface water drains, service mains and the like, under or
over the site and other areas affected by the works, whether indicated on
the drawings or not. He shall uphold, protect and maintain the same
during the execution of the works to the satisfaction of the S.O and make
good or pay for making good all damage thereto and any consequential
damage of loss arising out of such damage.

The Contractor shall not interfere with the operation of services without
the consent of service autorities, or private owners, or the S.O as
appropriate.

If services have to be temporarily terminated or diverted, the Contractor


shall give the necessary notices to the appropriate Authorities, arrange
for the work to be carried out and pay all charges in connection
therewith.

The Contractor shall divert, any drains and waterways encountered


during the progress of the works and subsequently reinstate to the S.O's
approval if diversion is temporary.
Lump Sum

1.17 Traffic Control


The Contractor shall ascertain and comply with all regulations concerning
the carrying out of work in both public roads and roads within the site
and give the necessary notices. No road shall be temporarily or
permanently closed except any for which the Contractor has obtained the
necessary permission from the Authorities.

The Contractor shall apply the necessary traffic control, traffic warning
signs, beacon lights and barriers in private and public roads for carrying
the work, together with any necessary diversions to maintain traffic flow. Lump Sum

To Collection

375791317.xlsx - Putri 98 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

1.18 Exsiting Roads and Properties


The Contractor will be responsibe for making good any damage to
existing private and/or public roads, kerbs, crossing, and properties etc.
caused by the carrying out of the works and shall maintain the aforesaid
in their original condition to the satisfaction of the S.O and the relevant
authority. Lump Sum

To Collection

375791317.xlsx - Putri 99 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

2.0 SITE CLEARING & EARTHWORKS

2.1 SITE CLEARING


Clear and grub areas within the site boundary and remove all vegetation
and debris from site to the contractor's own tip all to the satisfaction of
the S.O. The contractor shall sort the permission of the S.O regarding
the extend and method of clearing and cutting prior to the
commencement of the works. The Contractor is deemed to have visited
the site and ascertain for himself the true extend and nature of the site
including types of vegetation and items to be cleared. No further claim in
this connection shall be ertertained. Lump Sum

2.2 EARTHWORKS

a) Bulk excavation to the required founding levels of pump stations, screen


chamber, manholes and etc, partly cut and level, partly cut, load,
transport within site, deposit and spread excavated materialin areas to be
filled and thoroughly compact in layers to the required levels as directed. Lump Sum

b) To allow for all necessary temprorary shoring and bracing for excavation

of Pump stations, screen chamber, manholes and etc. Lump Sum

d) Extra over for forming embankements and trimming to form uniform


slope Lump Sum

3.0 SEWERAGE WORKS

3.1 Setting out pipe line, excavate trench, get out, part return, fill in, well
ram and remainder cart away from site, level, grade, ram bottom, trim
sides and including planking and strutting. Lump Sum

3.2 To allow for all necessary temprorary shoring and bracing for excavation
of trenches for the sewer lines. Lump Sum

3.3 To construct class 'B' sewer pipe bedding to receive vitrified clay pipes/
conc. Pipe class 'z' (lined internally with 12mm thk high Alumina cement
lining) / DICL pipes, incl. Grade 25 concrete, steel reinforcement and
formworks. (Piling measured seperately)
Lump Sum

Supply, lay, grade and compact in layers 600mm imported sand fill
material to specification requirements Lump Sum

Supply, lay, grade and compact 20mm crushed stones to specification


requirements Lump Sum

To Collection

375791317.xlsx - Putri 100 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

3.4 Backfilling of excavate trench with selected suitable earth fill material and
compact to specification requirement. Lump Sum

3.5 Approved vitrified clay pipe to BS EN295:1991 with and including spigot
and socket joint and laid in trench all in accordance with the
Maunufacturer's Instruction.

ii) for 300mm diameter vitrified clays pipes. Lump Sum

iii) for 375mm diameter vitrified clays pipes. Lump Sum

3.6 Approved 200mm diameter DICL pipe to BS 4772 with and including
spigot, socket jointand. All DICL pipes laid in ground shall be fitted with
approved polyethylene sleeve and to specification requirement. All ductile
iron fittings shall be coated internally and externally with approved fusion
bonded epoxy applied strictly in accordance with the coating
manufacturer's instructions under factory conditions.
Lump Sum

To Collection

375791317.xlsx - Putri 101 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

3.7 Construction of sewer manhole including concrete, reinforcement,


formwork, manhole cover, fitting, fixing, backfill, etc. (piling measured
seperately)

A) Manhole internal size 1500 mm x 1500 mm x 2000 mm deep to


invert level, constructed of 230 mm thick Grade 30 base
reinforced with T12 and T10 reinforcement bars laid on and
including 50 mm thick lean concrete (Grade 15) blinding; 230mm
thick Grade 30 wall reinforced with T12 and T10 reinforcement
bars, including 12mm thick plastering on both sides to wall in
sulphate resisting cement and sand (1:3) trowelled smooth
including 225mm diameter half round vetrified clay channel and
section all bedded and jointed in cement mortar and benching
manhole bottom around channel in grade 20 concrete and
finished smooth to fall, 150mm thick Grade 30 suspended cover
slab reinforced with T12 reinforcement steel bars and including
forming 600 diameter opening for and including 600mm diameter
medium duty pattern C.I manhole cover and frame to MS
1228:1991, set cover in thick grease and sand, and malleable
cast iron steps built in brickwork wall at 300mm centres
staggered, and including all necessary excavation, cart away,
formwork and jointing to services all constructed as per detailed
drawing (Type 1).

as per detailed drawing.

1) MH 3 (Taman Putri, Angsana & Signature Park) Lump Sum


1) MH 10 (Taman Putri, Angsana & Signature Park) Lump Sum
1) MH 11 (Taman Putri, Angsana & Signature Park) Lump Sum
2) MH 2 (Sample Park) Lump Sum

To Collection

375791317.xlsx - Putri 102 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

cont'd

B) Manhole internal size 2400 mm x 2400 mm x 5500 mm deep to


invert level, constructed of 300 mm thick Grade 30 base
reinforced with T16 reinforcement bars laid on and including 50
mm thick lean concrete (Grade 15) blinding; 300mm thick Grade
30 wall reinforced with T12 and T16 reinforcement bars, including
12mm thick plastering on both sides to wall in sulphate resisting
cement and sand (1:3) trowelled smooth including 225mm
diameter half round vetrified clay channel and section all bedded
and jointed in cement mortar and benching manhole bottom
around channel in grade 20 concrete and finished smooth to fall,
150mm thick Grade 30 suspended cover slab reinforced with T12
and T16 reinforcement steel bars and including forming 600
diameter opening for and including 600mm diameter medium duty
pattern C.I manhole cover and frame to MS 1228:1991, set cover
in thick grease and sand, and malleable cast iron steps built in
brickwork wall at 300mm centres staggered, and including all
necessary excavation, cart away, formwork and jointing to
services all constructed as per detailed drawing (Type 2).

Taman Li Hua
1) MH1 Lump Sum
2) MH 1 Lump Sum
Taman Putri, Angsana and Signature Park
3) MH 1 Lump Sum
4) MH 2 Lump Sum
5) MH 3 Lump Sum
6) MH 4 Lump Sum
7) MH 5 Lump Sum
8) MH 6 Lump Sum
9) MH 7 Lump Sum
10 ) MH 8 Lump Sum
11 ) MH 9 Lump Sum
12 ) MH 12 Lump Sum
13 ) MH 13 Lump Sum

To Collection

375791317.xlsx - Putri 103 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

3.8 Testing of the completed sewerage system.

a) The sewer shall be tested in sections consisting of the length of pipe


between two adjacent manholes. Sewers shall be subjected to a Water
Test, for which the Contractor shall provide all the necessary testing
apparatus and labour which may be required for the proper testing of the
sewers. These tests shall carried out before backfilling and again after
completion of backfilling and reinstatement.
Lump Sum

b) Clearing pipeline of obstruction.


After testing of the pipelines as specified, the interior of the pipelines
shall be inspected to ascertain that the pipes are entriely clear of
obstruction and that the invert is smooth. These tests shall be carried out
in accordance to the specification.
Lump Sum

4.0 SEWERAGE PUMPING STATIONS

4.1 Supply and construct sewerage pumping station including Sluice Valve,
piping, grit chamber, lift well internal size 3.5m x 3.5m x 9.41m deep to
invert level, valve chamber, ms covers, etc. all as shown and specified in
the drawing and Specification (piling measured seperately). (Taman Li
Hua) Lump Sum

4.2 Supply and construct sewerage pumping station including Sluice Valve,
piping, grit chamber, lift well internal size 3.5m x 3.5m x 3.81m deep to
invert level, valve chamber, ms covers, etc. all as shown and specified in
the drawing and Specification (piling measured seperately). (Sample
Park) Lump Sum

4.3 Supply and construct sewerage pumping station including Sluice Valve,
piping, grit chamber, lift well internal size 3.5m x 3.5m x 7.6m deep to
invert level, valve chamber, ms covers, etc. all as shown and specified in
the drawing and Specification (piling measured seperately). (Angsana,
Taman Putri & Signature Park)
Lump Sum

To Collection

375791317.xlsx - Putri 104 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

5.0 DEMOLITION OF EXISTING PUMP STATION

Generally, care is to be taken to minimise the noise and dust nuisance


due to the demolition works, the Contractor shall ensure that debris from
the domolition do not fall or hit on undersirable places, traffic,
equipment, personnel and commutors.

Materials and debris are not to be dumped where they are likely to cause
obstruction to the Employer and the public. All such materials to be
removed shall be cart away immediately after the demolition to the
Contrator's own tip at his own cost.

5.1 LI HUA SITE

a Demolition of existing structures e.g lift stations, manholes and etc. Any
usable building materials which may be found on the site shall remain the
property of the Employer. The contractor shall take all necessary care to
remove, dismantle and detach any item to be salvage from the demolition
works e,g all sewer fittings, pump sets, valves and other accessories or
as instructed by the S.O and return to BDA, all to the satisfaction of the
S.O. Lump Sum

b To carefully and gently remove, dismantle, take down , strip-off as


instructed the electric posts with fittings and attached cables and return
to SESCo at contractor own cost. Lump Sum

5.2 SAMPLE PARK SITE

a Demolition of existing structures e.g lift stations, manholes and etc. Any
usable building materials which may be found on the site shall remain the
property of the Employer. The contractor shall take all necessary care to
remove, dismantle and detach any item to be salvage from the demolition
works e,g all sewer fittings, pump sets, valves and other accessories or
as instructed by the S.O and return to BDA, all to the satisfaction of the
S.O. Lump Sum

b To carefully and gently remove, dismantle, take down , strip-off as


instructed the electric posts with fittings and attached cables and return
to SESCo at contractor own cost. Lump Sum

To Collection

375791317.xlsx - Putri 105 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

5.3 SIGNATURE PARK SITE


a Demolition of existing structures e.g lift stations, manholes and etc. Any
usable building materials which may be found on the site shall remain the
property of the Employer. The contractor shall take all necessary care to
remove, dismantle and detach any item to be salvage from the demolition
works e,g all sewer fittings, pump sets, valves and other accessories or
as instructed by the S.O and return to BDA, all to the satisfaction of the
S.O. Lump Sum

b To carefully and gently remove, dismantle, take down , strip-off as


instructed the electric posts with fittings and attached cables and return
to SESCo at contractor own cost. Lump Sum

6.0 PILING (ALL PROVISIONAL)

6.1 The following in Pump Stations (3 nos)

a Supply only 150mm x 150mm x 6.0m long precast reinforced concrete


grade 45 initial pile, complete with pile shoe. m 318 44.05

b Supply only 150mm x 150 mm x 6.0m long precast reinforced concrete


grade 45 extension pile. m 636 40.60

c Supply only 150mm x 150 mm x 3.0m long precast reinforced concrete


grade 45 extension pile. m 159 40.60

d Handle, pitch, drive and joint 150mm x 150mm precast reinforced


concrete piles m 1113 23.00

e Cut and break away head od 150mm x 150mm precast reinforced


concrete pile at required level, expose reinforcement bar and cast into
pile cap. No 318 19.09

6.2 The following in screen chamber

a Supply only 150mm x 150 mm x 6.0m long precast reinforced concrete


grade 45 initial pile, complete with pile shoe. m 72 44.05

b Supply only 150mm x 150mm x 6.0m long precast reinforced concrete


grade 45 extension pile. m 144 40.60

c Supply only 150mm x 150mm x 3.0m long precast reinforced concrete


grade 45 extension pile. m 36 40.60

d Handle, pitch, drive and joint 150mm x 150mm precast reinforced


concrete piles m 252 100.05

To Collection

375791317.xlsx - Putri 106 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

e Cut and break away head od 150mm x 150mm precast reinforced


concrete pile at required level, expose reinforcement bar and cast into
pile cap. No 72 23.00

6.3 BAKAU PILING (ALL PROVISIONAL)

6.3.1 The following along the sewer lines

a Supply and transport to site 100mm dia.x 3.6m length bakau piles.
m 4320 9.2

b Handle, pitch and drive 100mm dia. bakau piles m 4320 2.88

c Cut off piles heads and dispose off site. nos 1200 2.88

6.3.2 The following in Manhole Type 1

a Supply and transport to site 100mm dia.x 6.0m length bakau piles.
m 288 9.20

b Handle, pitch and drive 100mm dia. bakau piles m 288 2.88

c Cut off piles heads and dispose off site. nos 80 2.88

d Supply and install 100 mm diameter (internal) pile joints fabricated from
3mm thk ms plates nos 80 23.00

6.3.3 The following in Manholes Type 2

a Supply and transport to site 100mm dia.x 3.6m length bakau piles.
m 1814.4 9.20

b Handle, pitch and drive 100mm dia. bakau piles m 288 2.88

c Cut off piles heads and dispose off site. nos 80 2.88

d Supply and install 100 mm diameter (internal) pile joints fabricated from
3mm thk ms plates nos 80 23.00

To Collection

375791317.xlsx - Putri 107 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

7.0 TURFING
Supply and spot turfing of 225mm x 225mm in size of approved grass
spaced at 500mm c/c bothways to embankment slope and buffer zone,
including the provision of 100mm thick top soil as specified. Lump Sum

8.0 WATER SUPPLY TO PUMP STATIONS


Allow for taping off existing water supply pipe and connecting to new
25mm diameter GI pipe and the requisite plumbing services, including all
necessary approved connecting fittings and accessories, and necessary
excavation, carting away. Lump Sum
Rate to include obtaining approval and obtaining water meter from LAKU

9.0 FENCING AND GATE FOR PUMP STATIONS


2000MM high (above ground) galvanised chain link fencing constructed
on flat and undulating ground surfaces all constructed as per detail
drawings. Lump Sum

10.0 OTHER CIVIL WORKS FOR PUMP STATIONS SITE


Construct concrete pavement surrounding the pump as per drawings
Lump Sum

10.0 Contingency Sum Lump Sum

11.0 Others not listed in the above but deemed necessary for the completion
of the project

To Collection

375791317.xlsx - Putri 108 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

COLLECTION

1 Page 1

2 Page 2

3 Page 3

4 Page 4

5 Page 5

6 Page 6

7 Page 7

8 Page 8

9 Page 9

10 Page 10

11 Page 11

12 Page 12

18 From M & E Works - Schedule 1 of Summary of Prices (SOP 1)

TOTAL CARRIED FORWARD TO FORM OF TENDER RM

375791317.xlsx - Putri 109 / 214


Phase III)

AMOUNT (RM)

8,000.00

90,000.00

8,000.00

8,500.00

5,000.00

5,000.00

5,700.00

10,000.00

10,000.00

4,000.00

4,500.00

5,000.00

5,000.00

5,000.00

173,700.00

375791317.xlsx - Putri 110 / 214


Phase III)

AMOUNT (RM)

25,000.00

20,000.00

10,000.00

30,000.00

375791317.xlsx - Putri 111 / 214


Phase III)

AMOUNT (RM)

25,000.00

25,000.00

375791317.xlsx - Putri 112 / 214


Phase III)

AMOUNT (RM)

30,000.00

13,100.00

130,000.00

45,000.00

171,000.00

150,000.00

227,144.68

14,420.42

14,097.74

794,762.83

375791317.xlsx - Putri 113 / 214


Phase III)

AMOUNT (RM)

45,000.00

34,500.00

180,800.00

74,507.24

334,807.24

375791317.xlsx - Putri 114 / 214


Phase III)

AMOUNT (RM)

4,779.72
4,779.72
4,779.72
4,779.72

19,118.89

375791317.xlsx - Putri 115 / 214


Phase III)

AMOUNT (RM)

15,552.17
13,279.47

19,529.39
22,410.84
10,844.44
12,264.87
12,467.79
11,818.45
11,818.45
10,235.68
9,626.92
10,398.01
14,091.15

174,337.62

375791317.xlsx - Putri 116 / 214


Phase III)

AMOUNT (RM)

72,000.00

15,000.00

285,511.09

#REF!

#REF!

#REF!

375791317.xlsx - Putri 117 / 214


Phase III)

AMOUNT (RM)

15,000.00

1,500.00

15,000.00

1,500.00

33,000.00

375791317.xlsx - Putri 118 / 214


Phase III)

AMOUNT (RM)

15,000.00

1,500.00

14,006.31

25,818.42

6,454.61

25,599.00

6,070.62

3,171.24

5,845.68

1,461.42

25,212.60

130,139.90

375791317.xlsx - Putri 119 / 214


Phase III)

AMOUNT (RM)

1,656.00

39,744.00

12,420.00

3,450.00

2,649.60

828.00

230.00

1,840.00

16,692.48

828.00

230.00

1,840.00

80,752.08

375791317.xlsx - Putri 120 / 214


Phase III)

AMOUNT (RM)

20,000.00

50,000.00

15,000.00

15,000.00

10,000.00

110,000.00

375791317.xlsx - Putri 121 / 214


Phase III)

AMOUNT (RM)

173,700.00

30,000.00

25,000.00

794,762.83

334,807.24

19,118.89

174,337.62

#REF!

33,000.00

130,139.90

80,752.08

110,000.00

354,000.00

#REF!

375791317.xlsx - Putri 122 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

1.0 GENERAL AND PRELIMINARIES

1.1 Provide Insurance in accordance with General Conditions of Contract.


Lump Sum

1.2 Provide Performance Bond amounting to 5% of the Contract Sum shall be


deposited with the Employer as required by Clause 5 of the Condition of
Contract. Lump Sum

1.3 To provide Levy contribution under the Construction Industry (Collection


of Levy) Regulations 1996. Lump Sum

1.4 Site management and job expenses. Lump Sum

1.5 Mobilisation of personnel, constructional plant and equipment. Lump Sum

1.6 Provide and maintain survey instrument in accordance with the S.O.
requirement. The instrument will be reverted to the Contractor at the
end of the contract. Lump Sum

1.7 Provide and maintain one (1) no. mobile phone including internet
services for S.O.
The Basic Specifications of the Mobile Phone shall be as follows:-
1) 14mp Camera
2) 256 GB Memory
3) 4G/LTE Support Lump Sum

1.8 Provide and maintain S.O. site office, including all furniture, equipment
and fitting as specified. Lump Sum

1.9 Supply personnels, materials and equipment to carry out all quality
control tests. Lump Sum

1.10 Provide for work programme, progress reporting and taking progress
photographs of works. Lump Sum

1.11 Contractor to supply as-built drawings to contract requirement Lump Sum

1.12 Provide and maintain all temporary works including removal from site,
upon completion of Works. Lump Sum

1.13 Demobilisaiton of personnel and constructional plant and equipment.


Lump Sum

1.14 Clearing up Site on completion, in accordance with Specification. Lump Sum

1.15 Site Surveys


The Contractor shall employ a licensed Land Surveyor to carry out a site
survey before work commences, and to assist in establishing boundaries
and setting out the works. On completion of the works, a licensed Land
Surveyor to carry out a further site survey and produce as-built drawings.
Details of grid lines, setting out stations, bench marks, prolfiles etc. Shall
be recorded on a setting out drawing. Lump Sum

375791317.xlsx - calculation 123 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

To Collection

375791317.xlsx - calculation 124 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

1.16 Existing Services


The Contractor shall ascertain the exact position of existing cables, pipes,
ducts, sewers, surface water drains, service mains and the like, under or
over the site and other areas affected by the works, whether indicated on
the drawings or not. He shall uphold, protect and maintain the same
during the execution of the works to the satisfaction of the S.O and make
good or pay for making good all damage thereto and any consequential
damage of loss arising out of such damage.

The Contractor shall not interfere with the operation of services without
the consent of service autorities, or private owners, or the S.O as
appropriate.

If services have to be temporarily terminated or diverted, the Contractor


shall give the necessary notices to the appropriate Authorities, arrange
for the work to be carried out and pay all charges in connection
therewith.

The Contractor shall divert, any drains and waterways encountered


during the progress of the works and subsequently reinstate to the S.O's
approval if diversion is temporary.
Lump Sum

1.17 Traffic Control


The Contractor shall ascertain and comply with all regulations concerning
the carrying out of work in both public roads and roads within the site
and give the necessary notices. No road shall be temporarily or
permanently closed except any for which the Contractor has obtained the
necessary permission from the Authorities.

The Contractor shall apply the necessary traffic control, traffic warning
signs, beacon lights and barriers in private and public roads for carrying
the work, together with any necessary diversions to maintain traffic flow. Lump Sum

1.18 Exsiting Roads and Properties


The Contractor will be responsibe for making good any damage to
existing private and/or public roads, kerbs, crossing, and properties etc.
caused by the carrying out of the works and shall maintain the aforesaid
in their original condition to the satisfaction of the S.O and the relevant
authority. Lump Sum

To Collection

375791317.xlsx - calculation 125 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

2.0 SITE CLEARING & EARTHWORKS

2.1 SITE CLEARING


Clear and grub areas within the site boundary and remove all vegetation
and debris from site to the contractor's own tip all to the satisfaction of
the S.O. The contractor shall sort the permission of the S.O regarding
the extend and method of clearing and cutting prior to the
commencement of the works. The Contractor is deemed to have visited
the site and ascertain for himself the true extend and nature of the site
including types of vegetation and items to be cleared. No further claim in
this connection shall be ertertained. Lump Sum

2.2 EARTHWORKS

a) Bulk excavation to the required founding levels of pump stations, screen


chamber, manholes and etc, partly cut and level, partly cut, load,
transport within site, deposit and spread excavated materialin areas to be
filled and thoroughly compact in layers to the required levels as directed. Lump Sum

b) To allow for all necessary temprorary shoring and bracing for excavation

of Pump stations, screen chamber, manholes and etc. Lump Sum

d) Extra over for forming embankements and trimming to form uniform


slope Lump Sum

3.0 SEWERAGE WORKS

3.1 Setting out pipe line, excavate trench, get out, part return, fill in, well
ram and remainder cart away from site, level, grade, ram bottom, trim
sides and including planking and strutting. Lump Sum

375791317.xlsx - calculation 126 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

3.2 To allow for all necessary temprorary shoring and bracing for excavation
of trenches for the sewer lines. Lump Sum

3.3 To construct class 'B' sewer pipe bedding to receive vitrified clay pipes/
conc. Pipe class 'z' (lined internally with 12mm thk high Alumina cement
lining) / DICL pipes, incl. Grade 25 concrete, steel reinforcement and
formworks. (Piling measured seperately)
Lump Sum

Supply, lay, grade and compact in layers 600mm imported sand fill
material to specification requirements Lump Sum

Supply, lay, grade and compact 20mm crushed stones to specification


requirements Lump Sum

To Collection

375791317.xlsx - calculation 127 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

3.4 Backfilling of excavate trench with selected suitable earth fill material and
compact to specification requirement. Lump Sum

3.5 Approved vitrified clay pipe to BS EN295:1991 with and including spigot
and socket joint and laid in trench all in accordance with the
Maunufacturer's Instruction.

ii) for 300mm diameter vitrified clays pipes. Lump Sum

iii) for 375mm diameter vitrified clays pipes. Lump Sum

3.6 Approved 200mm diameter DICL pipe to BS 4772 with and including
spigot, socket jointand. All DICL pipes laid in ground shall be fitted with
approved polyethylene sleeve and to specification requirement. All ductile
iron fittings shall be coated internally and externally with approved fusion
bonded epoxy applied strictly in accordance with the coating
manufacturer's instructions under factory conditions.
Lump Sum

To Collection

375791317.xlsx - calculation 128 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

3.10 Construction of sewer manhole including concrete, reinforcement,


formwork, manhole cover, fitting, fixing, backfill, etc. (piling measured
seperately)

A) Manhole internal size 1500 mm x 1500 mm x 2000 mm deep to


invert level, constructed of 230 mm thick Grade 30 base
reinforced with T12 and T10 reinforcement bars laid on and
including 50 mm thick lean concrete (Grade 15) blinding; 230mm
thick Grade 30 wall reinforced with T12 and T10 reinforcement
bars, including 12mm thick plastering on both sides to wall in
sulphate resisting cement and sand (1:3) trowelled smooth
including 225mm diameter half round vetrified clay channel and
section all bedded and jointed in cement mortar and benching
manhole bottom around channel in grade 20 concrete and
finished smooth to fall, 150mm thick Grade 30 suspended cover
slab reinforced with T12 reinforcement steel bars and including
forming 600 diameter opening for and including 600mm diameter
medium duty pattern C.I manhole cover and frame to MS
1228:1991, set cover in thick grease and sand, and malleable
cast iron steps built in brickwork wall at 300mm centres
staggered, and including all necessary excavation, cart away,
formwork and jointing to services all constructed as per detailed
drawing (Type 1).

as per detailed drawing.

1) MH 3 (Taman Putri, Angsana & Signature Park) Lump Sum


1) MH 10 (Taman Putri, Angsana & Signature Park) Lump Sum
1) MH 11 (Taman Putri, Angsana & Signature Park) Lump Sum
2) MH 2 (Sample Park) Lump Sum

To Collection

375791317.xlsx - calculation 129 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

cont'd

B) Manhole internal size 2400 mm x 2400 mm x 5500 mm deep to


invert level, constructed of 300 mm thick Grade 30 base
reinforced with T16 reinforcement bars laid on and including 50
mm thick lean concrete (Grade 15) blinding; 300mm thick Grade
30 wall reinforced with T12 and T16 reinforcement bars, including
12mm thick plastering on both sides to wall in sulphate resisting
cement and sand (1:3) trowelled smooth including 225mm
diameter half round vetrified clay channel and section all bedded
and jointed in cement mortar and benching manhole bottom
around channel in grade 20 concrete and finished smooth to fall,
150mm thick Grade 30 suspended cover slab reinforced with T12
and T16 reinforcement steel bars and including forming 600
diameter opening for and including 600mm diameter medium duty
pattern C.I manhole cover and frame to MS 1228:1991, set cover
in thick grease and sand, and malleable cast iron steps built in
brickwork wall at 300mm centres staggered, and including all
necessary excavation, cart away, formwork and jointing to
services all constructed as per detailed drawing (Type 2).

Taman Li Hua
1) MH1 Lump Sum

Sample Park
1) MH 1 Lump Sum

375791317.xlsx - calculation 130 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

Taman Putri, Angsana and Signature Park


2) MH 1 Lump Sum

3) MH 2 Lump Sum

5) MH 3 Lump Sum

6) MH 4 Lump Sum

375791317.xlsx - calculation 131 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

7) MH 5 Lump Sum

8) MH 6 Lump Sum

9) MH 7 Lump Sum

375791317.xlsx - calculation 132 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

10 ) MH 8 Lump Sum

11 ) MH 9 Lump Sum

12 ) MH 12 Lump Sum

375791317.xlsx - calculation 133 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

13 ) MH 13 Lump Sum

To Collection

375791317.xlsx - calculation 134 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

3.11 Testing of the completed sewerage system.

a) The sewer shall be tested in sections consisting of the length of pipe


between two adjacent manholes. Sewers shall be subjected to a Water
Test, for which the Contractor shall provide all the necessary testing
apparatus and labour which may be required for the proper testing of the
sewers. These tests shall carried out before backfilling and again after
completion of backfilling and reinstatement.
Lump Sum

b) Clearing pipeline of obstruction.


After testing of the pipelines as specified, the interior of the pipelines
shall be inspected to ascertain that the pipes are entriely clear of
obstruction and that the invert is smooth. These tests shall be carried out
in accordance to the specification.
Lump Sum

4.0 SEWERAGE PUMPING STATIONS

4.1 Supply and construct sewerage pumping station including Sluice Valve,
piping, grit chamber, lift well internal size 3.5m x 3.5m x 9.41m deep to
invert level, valve chamber, ms covers, etc. all as shown and specified in
the drawing and Specification (piling measured seperately). (Taman Li
Hua) Lump Sum

4.2 Supply and construct sewerage pumping station including Sluice Valve,
piping, grit chamber, lift well internal size 3.5m x 3.5m x 3.81m deep to
invert level, valve chamber, ms covers, etc. all as shown and specified in
the drawing and Specification (piling measured seperately). (Sample
Park) Lump Sum

4.3 Supply and construct sewerage pumping station including Sluice Valve,
piping, grit chamber, lift well internal size 3.5m x 3.5m x 7.6m deep to
invert level, valve chamber, ms covers, etc. all as shown and specified in
the drawing and Specification (piling measured seperately). (Angsana,
Taman Putri & Signature Park)
Lump Sum

To Collection

375791317.xlsx - calculation 135 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

6.0 DEMOLITION OF EXISTING PUMP STATION

Generally, care is to be taken to minimise the noise and dust nuisance


due to the demolition works, the Contractor shall ensure that debris from
the domolition do not fall or hit on undersirable places, traffic,
equipment, personnel and commutors.

Materials and debris are not to be dumped where they are likely to cause
obstruction to the Employer and the public. All such materials to be
removed shall be cart away immediately after the demolition to the
Contrator's own tip at his own cost.

6.1 LI HUA SITE

b Demolition of existing structures e.g lift stations, manholes and etc. Any
usable building materials which may be found on the site shall remain the
property of the Employer. The contractor shall take all necessary care to
remove, dismantle and detach any item to be salvage from the demolition
works e,g all sewer fittings, pump sets, valves and other accessories or
as instructed by the S.O and return to BDA, all to the satisfaction of the
S.O. Lump Sum

c To carefully and gently remove, dismantle, take down , strip-off as


instructed the electric posts with fittings and attached cables and return
to SESCo at contractor own cost. Lump Sum

6.2 SAMPLE PARK SITE

b Demolition of existing structures e.g lift stations, manholes and etc. Any
usable building materials which may be found on the site shall remain the
property of the Employer. The contractor shall take all necessary care to
remove, dismantle and detach any item to be salvage from the demolition
works e,g all sewer fittings, pump sets, valves and other accessories or
as instructed by the S.O and return to BDA, all to the satisfaction of the
S.O. Lump Sum

c To carefully and gently remove, dismantle, take down , strip-off as


instructed the electric posts with fittings and attached cables and return
to SESCo at contractor own cost. Lump Sum

To Collection

375791317.xlsx - calculation 136 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

6.7 SIGNATURE PARK SITE


b Demolition of existing structures e.g lift stations, manholes and etc. Any
usable building materials which may be found on the site shall remain the
property of the Employer. The contractor shall take all necessary care to
remove, dismantle and detach any item to be salvage from the demolition
works e,g all sewer fittings, pump sets, valves and other accessories or
as instructed by the S.O and return to BDA, all to the satisfaction of the
S.O. Lump Sum

c To carefully and gently remove, dismantle, take down , strip-off as


instructed the electric posts with fittings and attached cables and return
to SESCo at contractor own cost. Lump Sum

7.0 PILING (ALL PROVISIONAL)

7.1 The following in Pump Stations (16 nos)

a Supply only 150mm x 150mm x 6.0m long precast reinforced concrete


grade 45 initial pile, complete with pile shoe. m 318 44.045

b Supply only 150mm x 150 mm x 6.0m long precast reinforced concrete


grade 45 extension pile. m 636 40.595

c Supply only 150mm x 150 mm x 3.0m long precast reinforced concrete


grade 45 extension pile. m 159 40.595

d Handle, pitch, drive and joint 150mm x 150mm precast reinforced


concrete piles m 1113 23

e Cut and break away head od 150mm x 150mm precast reinforced


concrete pile at required level, expose reinforcement bar and cast into
pile cap. No 318 19.09

375791317.xlsx - calculation 137 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

7.2 The following in screen chamber

a Supply only 150mm x 150 mm x 6.0m long precast reinforced concrete


grade 45 initial pile, complete with pile shoe. m 72 44.045

b Supply only 150mm x 150mm x 6.0m long precast reinforced concrete


grade 45 extension pile. m 144 40.595

c Supply only 150mm x 150mm x 3.0m long precast reinforced concrete


grade 45 extension pile. m 36 40.595

d Handle, pitch, drive and joint 150mm x 150mm precast reinforced


concrete piles m 252 100.05

e Cut and break away head od 150mm x 150mm precast reinforced


concrete pile at required level, expose reinforcement bar and cast into
pile cap. No 72 23

To Collection

375791317.xlsx - calculation 138 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

7.3 BAKAU PILING (ALL PROVISIONAL)

7.3.1 The following along the sewer lines

a Supply and transport to site 100mm dia.x 3.6m length bakau piles.
m 4320 9.2

b Handle, pitch and drive 100mm dia. bakau piles m 4320 2.875

c Cut off piles heads and dispose off site. nos 1200 2.875

7.3.2 The following in Manhole Type 1

a Supply and transport to site 100mm dia.x 6.0m length bakau piles.
288
m 9.2

b Handle, pitch and drive 100mm dia. bakau piles m 288 2.875

c Cut off piles heads and dispose off site. (In no. 65) nos 80 2.875

d Supply and install 100 mm diameter (internal) pile joints fabricated from
3mm thk ms plates nos 80 23

7.3.3 The following in Manholes Type 2

a Supply and transport to site 100mm dia.x 6.0m length bakau piles.
m 1814.4 9.2

375791317.xlsx - calculation 139 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

b Handle, pitch and drive 100mm dia. bakau piles m 1814.4 2.875

c Cut off piles heads and dispose off site. (In no. 1134) nos 504 2.875

d Supply and install 100 mm diameter (internal) pile joints fabricated from
3mm thk ms plates nos 504 23

To Collection

375791317.xlsx - calculation 140 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

8.0 TURFING
Supply and spot turfing of 225mm x 225mm in size of approved grass
spaced at 500mm c/c bothways to embankment slope and buffer zone,
including the provision of 100mm thick top soil as specified. Lump Sum

10.0 WATER SUPPLY TO PUMP STATIONS


Allow for taping off existing water supply pipe and connecting to new
25mm diameter GI pipe and the requisite plumbing services, including all
necessary approved connecting fittings and accessories, and necessary
excavation, carting away.
Lump Sum
Rate to include obtaining approval and obtaining water meter from LAKU

12.0 FENCING AND GATE FOR PUMP STATIONS


2000MM high (above ground) galvanised chain link fencing constructed
on flat and undulating ground surfaces all constructed as per detail
drawings. Lump Sum

13.0 Contingency Sum Lump Sum

14.0 Others not listed in the above but deemed necessary for the completion
of the project

To Collection

375791317.xlsx - calculation 141 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

COLLECTION

1 Page 1

2 Page 2

3 Page 3

4 Page 4

5 Page 5

6 Page 6

7 Page 7

8 Page 8

9 Page 9

10 Page 10

11 Page 11

12 Page 12

13 Page 13

14 Page 14

15 Page 15

16 Page 16

17 Page 17

18 From M & E Works - Schedule 1 of Summary of Prices (SOP 1)

19 Upgrading of Oxidation pond to aerated lagoon

TOTAL CARRIED FORWARD TO FORM OF TENDER RM

375791317.xlsx - calculation 142 / 214


Phase III)

AMOUNT (RM)

10,000.00

20,000.00

5,000.00

4,000.00

4,500.00

15,000.00

25,000.00

15,000.00

50,000.00

375791317.xlsx - calculation 143 / 214


Phase III)

AMOUNT (RM)

148,500.00

375791317.xlsx - calculation 144 / 214


Phase III)

AMOUNT (RM)

80,000.00

20,000.00

25,000.00

125,000.00

375791317.xlsx - calculation 145 / 214


Phase III)

AMOUNT (RM)

30,000.00

26,000.00

130,000.00

45,000.00

171,000.00

375791317.xlsx - calculation 146 / 214


Phase III)

AMOUNT (RM)

100,000.00

227,144.68

14,420.42

14,097.74

757,662.83

375791317.xlsx - calculation 147 / 214


Phase III)

AMOUNT (RM)

45,000.00

34,500.00

180,800.00

74,507.24

334,807.24

375791317.xlsx - calculation 148 / 214


Phase III)

AMOUNT (RM)

4,779.72
4,779.72
4,779.72
4,779.72

19,118.89

375791317.xlsx - calculation 149 / 214


Phase III)

AMOUNT (RM)

15,552.17

13,279.47

375791317.xlsx - calculation 150 / 214


Phase III)

AMOUNT (RM)

19,529.39

22,410.84

10,844.44

12,264.87

375791317.xlsx - calculation 151 / 214


Phase III)

AMOUNT (RM)

12,467.79

11,818.45

11,818.45

375791317.xlsx - calculation 152 / 214


Phase III)

AMOUNT (RM)

10,235.68

9,626.92

10,398.01

375791317.xlsx - calculation 153 / 214


Phase III)

AMOUNT (RM)

14,091.15

174,337.62

375791317.xlsx - calculation 154 / 214


Phase III)

AMOUNT (RM)

60,000.00

2,000.00

285,511.09

#REF!

#REF!

375791317.xlsx - calculation 155 / 214


Phase III)

AMOUNT (RM)

15,000.00

1,500.00

15,000.00

1,500.00

33,000.00

375791317.xlsx - calculation 156 / 214


Phase III)

AMOUNT (RM)

15,000.00

1,500.00

14,006.31

25,818.42

6,454.61

25,599.00

6,070.62

375791317.xlsx - calculation 157 / 214


Phase III)

AMOUNT (RM)

3,171.24

5,845.68

1,461.42

25,212.60

1,656.00

115,295.90

375791317.xlsx - calculation 158 / 214


Phase III)

AMOUNT (RM)

39,744.00

12,420.00

3,450.00

2,649.60

828.00

230.00

1,840.00

16,692.48

375791317.xlsx - calculation 159 / 214


Phase III)

AMOUNT (RM)

5,216.40

1,449.00

11,592.00

96,111.48

375791317.xlsx - calculation 160 / 214


Phase III)

AMOUNT (RM)

50,000.00

90,000.00

100,000.00

200,000.00

440,000.00

375791317.xlsx - calculation 161 / 214


Phase III)

AMOUNT (RM)

148,500.00

125,000.00

757,662.83

334,807.24

19,118.89

174,337.62

#REF!

#REF!

#REF!

33,000.00

#REF!

#REF!

#REF!

115,295.90

96,111.48

440,000.00

1,717,000.00

1,000,000.00

#REF!

375791317.xlsx - calculation 162 / 214


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Base Rate


ITEM DESCRIPTION

Pumping Station Li Hua

1.0 Concrete

1.1 To supply, lay and vibrate G30 concrete m3 118.63 409.3

1.2 To supply, lay and vibrate G25 mass concrete m3 0.799 382.9
Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Base Rate


ITEM DESCRIPTION

1.3 To supply, lay lean concrete m3 2.276 400

4.0 Sulphate resistance cement plaster finished with a steel float

4.1 To internal surface of grit chamber m2 215.952 27

4.2 To internal surface of pump sump m2 232.896 27


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Base Rate


ITEM DESCRIPTION

5.0 To supply, fabricate and fix steel reinforcement bars


T12 kg 1070 3.6
Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Base Rate


ITEM DESCRIPTION
Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Base Rate


ITEM DESCRIPTION

T16 kg 9586 3.6


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Base Rate


ITEM DESCRIPTION
Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Base Rate


ITEM DESCRIPTION

T20 kg 14800 3.6

A8 m2 3.23 19.4

6.0 Formwork as described to reinforced concrete works

To sides of grit chamber, pump sump, discharge manhole,


and overflow sump m2 373.456 48
Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Base Rate


ITEM DESCRIPTION

7.0 Excavation, get out, part return, fill in, well ram and cart
away from site, level, ram bottom. Trim sides and including
planking and strutting

7.1 not exceeding 1.5m m3 30.75 19.9

Excavation, get out, part return, fill in, well ram and cart
away from site, level, ram bottom. To include temporary
bracing and shoring

7.2 exceeding 1.5m and not exceeding 3.00m deep m3 48


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Base Rate


ITEM DESCRIPTION

7.3 exceeding 3.0m and not exceeding 4.50m deep m3 24

7.4 exceeding 4.50m and not exceeding 6.00m deep m3 24

7.4 exceeding 6.00m and not exceeding 10.00m deep m3 64


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Base Rate


ITEM DESCRIPTION

8.0 Grit Chamber MS grating covers (1000x1800) No 1 600

9.0 Pump Sump MS grating covers (1400x2200) No 1 1450

10.0 Valve chamber chequered plate cover Type I No 1 104

11.0 Valve chamber chequered plate cover Type II No 1 120

12.0 Stainless Steel Static Screen(900 x 500) No 1 305

13.0 Stainless Steel Basket ((500x300x300) No 1 800

14.0 GI Cat Ladder to grit chamber m 9

15.0 GI Cat Ladder to pump sump m 10

16.0 300 x 300 CI Penstock c/w Hand wheel No 1 450

TOTAL AMOUNT
ssociated Works (Phase III)

Rate (RM) AMOUNT (RM)

470.70 55,838.55

440.34 351.83
ssociated Works (Phase III)

Rate (RM) AMOUNT (RM)

460.00 1,046.96

31.05 6,705.31

31.05 7,231.42
ssociated Works (Phase III)

Rate (RM) AMOUNT (RM)

4.14 4,429.80
ssociated Works (Phase III)

Rate (RM) AMOUNT (RM)


ssociated Works (Phase III)

Rate (RM) AMOUNT (RM)

4.14 39,686.04
ssociated Works (Phase III)

Rate (RM) AMOUNT (RM)


ssociated Works (Phase III)

Rate (RM) AMOUNT (RM)

4.14 61,272.00

22.31 72.06

55.20 20,614.77
ssociated Works (Phase III)

Rate (RM) AMOUNT (RM)

197,248.74

22.89 703.71

150.00 7,200.00
ssociated Works (Phase III)

Rate (RM) AMOUNT (RM)

78.00 1,872.00

78.00 1,872.00

78.00 4,992.00
ssociated Works (Phase III)

Rate (RM) AMOUNT (RM)

15,936.00

690.00 690.00

1,667.50 1,667.50

119.60 119.60

138.00 138.00

350.75 350.75

920.00 920.00

3,361.00 30,249.00

3,361.00 33,610.00

517.50 517.50

68,262.35
Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Base Rate


ITEM DESCRIPTION

Pumping Station Putri

1.0 Concrete

1.1 To supply, lay and vibrate G30 concrete m3 118.63 409.3

1.2 To supply, lay and vibrate G25 mass concrete m3 0.799 382.9
Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Base Rate


ITEM DESCRIPTION

1.3 To supply, lay lean concrete m3 2.276 400

4.0 Sulphate resistance cement plaster finished with a steel float

4.1 To internal surface of grit chamber m2 159.52 27

4.2 To internal surface of pump sump m2 171.68 27


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Base Rate


ITEM DESCRIPTION

5.0 To supply, fabricate and fix steel reinforcement bars


T12 kg 5555 3.6
Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Base Rate


ITEM DESCRIPTION
Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Base Rate


ITEM DESCRIPTION

T16 kg 9670 3.6


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Base Rate


ITEM DESCRIPTION
Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Base Rate


ITEM DESCRIPTION

T20 kg 14400 3.6

A8 m2 3.23 19.4

6.0 Formwork as described to reinforced concrete works

To sides of grit chamber, pump sump, discharge manhole,


and overflow sump m2 267.28 48
Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Base Rate


ITEM DESCRIPTION

7.0 Excavation, get out, part return, fill in, well ram and cart
away from site, level, ram bottom. Trim sides and including
planking and strutting

7.1 not exceeding 1.5m m3 30.75 19.9

Excavation, get out, part return, fill in, well ram and cart
away from site, level, ram bottom. To include temporary
bracing and shoring

7.2 exceeding 1.5m and not exceeding 3.00m deep m3 48


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Base Rate


ITEM DESCRIPTION

7.3 exceeding 3.0m and not exceeding 4.50m deep m3 24

7.4 exceeding 4.50m and not exceeding 6.00m deep m3 24

7.4 exceeding 6.00m and not exceeding 10.00m deep m3 64


Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Base Rate


ITEM DESCRIPTION

8.0 Grit Chamber MS grating covers (1000x1800) No 1 600

9.0 Pump Sump MS grating covers (1400x2200) No 1 1450

10.0 Valve chamber chequered plate cover Type I No 1 104

11.0 Valve chamber chequered plate cover Type II No 1 120

12.0 Stainless Steel Static Screen(900 x 500) No 1 305

13.0 Stainless Steel Basket ((500x300x300) No 1 800

14.0 GI Cat Ladder to grit chamber m 9

15.0 GI Cat Ladder to pump sump m 10

16.0 300 x 300 CI Penstock c/w Hand wheel No 1 450

TOTAL AMOUNT
ssociated Works (Phase III)

Rate (RM) AMOUNT (RM)

470.70 55,838.55

440.34 351.83
ssociated Works (Phase III)

Rate (RM) AMOUNT (RM)

460.00 1,046.96

31.05 4,953.10

31.05 5,330.66
ssociated Works (Phase III)

Rate (RM) AMOUNT (RM)

4.14 22,997.70
ssociated Works (Phase III)

Rate (RM) AMOUNT (RM)


ssociated Works (Phase III)

Rate (RM) AMOUNT (RM)

4.14 40,033.80
ssociated Works (Phase III)

Rate (RM) AMOUNT (RM)


ssociated Works (Phase III)

Rate (RM) AMOUNT (RM)

4.14 59,616.00

22.31 72.06

55.20 14,753.86
ssociated Works (Phase III)

Rate (RM) AMOUNT (RM)

204,994.51

22.89 703.71

150.00 7,200.00
ssociated Works (Phase III)

Rate (RM) AMOUNT (RM)

78.00 1,872.00

78.00 1,872.00

78.00 4,992.00
ssociated Works (Phase III)

Rate (RM) AMOUNT (RM)

15,936.00

690.00 690.00

1,667.50 1,667.50

119.60 119.60

138.00 138.00

350.75 350.75

920.00 920.00

3,361.00 30,249.00

3,361.00 33,610.00

517.50 517.50

68,262.35
Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty
ITEM DESCRIPTION

Type 2 & 3 Manhole

3.7 Construction of sewer manhole including concrete, reinforcement,


formwork, manhole cover, fitting, fixing, backfill, etc. (piling measured
seperately)

b) Manhole internal size 1800 mm x 1800 mm x 5500 mm deep to


invert level, constructed of 300 mm thick Grade 30 base
reinforced with T16 reinforcement bars laid on and including 50
mm thick lean concrete (Grade 15) blinding; 300mm thick Grade
30 wall reinforced with T12 and T16 reinforcement bars,
including 12mm thick plastering on both sides to wall in sulphate
resisting cement and sand (1:3) trowelled smooth including
225mm diameter half round vetrified clay channel and section all
bedded and jointed in cement mortar and benching manhole
bottom around channel in grade 20 concrete and finished
smooth to fall, 150mm thick Grade 30 suspended cover slab
reinforced with T12 and T16 reinforcement steel bars and
including forming 600 diameter opening for and including
600mm diameter medium duty pattern C.I manhole cover and
frame to MS 1228:1991, set cover in thick grease and sand, and
malleable cast iron steps built in brickwork wall at 300mm
centres staggered, and including all necessary excavation, cart
away, formwork and jointing to services all constructed as per
detailed drawing (Type 2).

Manhole internal size 2400 mm x 2400 mm x 5500 mm deep

1 Normal plaster on external face m2 47.5 24

2 Alumina added plaster on internal face m2 47.5 18

3 G30 Conc. m3 16.4

4 Lean conc. m3 0.45

5 Steel reinforcement m2 1717.2

6 Medium duty cover and frame nos 1 160

7 Benching and VCP channel l/s 1 150

8 Gal. Steps m 51

9 Formworks m2 94.52

10 Earthworks m3 40.6
Cost reduction per 100mm in height

2 Normal plaster on external face m2 0.86

3 Alumina added plaster on internal face m2 0.86

4 G30 Conc. m3 0.3

6 Steel reinforcement m2 31.22

10 Formworks m2 1.7

Total cost reduction per 100 mm height


orks (Phase III)

Rate (RM) AMOUNT (RM)

27.60 1,311.00

20.70 983.25 300 5.5 2.4 27.94 59.2328


230 4.5 1.8
470.70 7,719.48 1.30434783 1.22222222 1.33333333 34.42 72.9704
2.12560386
460.00 207.00 7.736 16.40032

4.14 7,109.21 0.26 0.5512

184.00 184.00 810 1717.2

172.50 172.50 1 1.7

15.00 765.00 1 1.7

55.20 5,217.50 30 51

150.00 6,090.00
55.6 94.52
23,668.94

Earthworks per manhole


Breadth 2.6 Perimeter 12
Width 2.6 25776
27.60 23.74 Depth 6 635.502959
40.56
20.70 17.80

470.70 141.21

4.14 129.25

55.20 93.84

405.84
0.442
Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

Unit Qty Rate (RM)


ITEM DESCRIPTION

Type 1 Manhole

3.7 Construction of sewer manhole including concrete, reinforcement,


formwork, manhole cover, fitting, fixing, backfill, etc. (piling
measured seperately)

a) Manhole internal size 1500 mm x 1500 mm x 2000 mm deep


to invert level, constructed of 230 mm thick Grade 30 base
reinforced with T12 and T10 reinforcement bars laid on and
including 50 mm thick lean concrete (Grade 15) blinding;
230mm thick Grade 30 wall reinforced with T12 and T10
reinforcement bars, including 12mm thick plastering on both
sides to wall in sulphate resisting cement and sand (1:3)
trowelled smooth including 225mm diameter half round
vetrified clay channel and section all bedded and jointed in
cement mortar and benching manhole bottom around
channel in grade 20 concrete and finished smooth to fall,
150mm thick Grade 30 suspended cover slab reinforced with
T12 reinforcement steel bars and including forming 600
diameter opening for and including 600mm diameter medium
duty pattern C.I manhole cover and frame to MS 1228:1991,
set cover in thick grease and sand, and malleable cast iron
steps built in brickwork wall at 300mm centres staggered,
and including all necessary excavation, cart away, formwork
and jointing to services all constructed as per detailed
drawing (Type 1).

MH 1 (1.5m x 1.5m x 2.0m)

1 Normal plaster on external face m2 33 10.00

2 Alumina added plaster on internal face m2 33 13.00

3 G30 Conc. m3 4.7 310.00

4 Lean conc. m3 0.47 250.00

5 Steel Reinforcement
kg 340 4.14
6 Medium duty cover and frame

nos 1 184.00

7 Benching and VCP channel l/s 1 172.50

8 Gal. Steps m 30 15.00

9 Earthworks m 10.143 22.89

Earthworks per manhole

Breadth 2.1

Width 2.1

Depth 2.3

10.143
(Phase III)

AMOUNT (RM)

330.00

429.00
wall rebar x Base Rebar (x)
1,457.00 depth 2 width 2
perimeter 8 breadth 2
117.50 rebar 0.01 rebar 0.01
distance distance
between between
rebar 0.175 rebar 0.175
Length of Length of
1,407.60 rebar 9 Rebar 3
No of rebar 11.4285714 No of rebar 11.4285714
Total Total
Length of Length of
184.00 Rebar 102.857143 Rebar 34.2857143
Weight of Weight of
Rebar 126.925714 Rebar 42.3085714
172.50

450.00

232.12

19.9 22.885
4,779.72

rebar y Base Rebar (y)


depth 2 width 2
perimeter 8 breadth 2
rebar 0.012 rebar 0.012
distance distance
between between
rebar 0.2 rebar 0.2
Length of Length of
Perimeter 12 rebar 3.2 Rebar 3.2

9880.8 No of rebar 40 No of rebar 10


Total Total
Length of Length of
974.14966 Rebar 128 Rebar 32
Weight of Weight of
Rebar 113.664 Rebar 56.832

Grand
total of
rebar
weight 339.7303
1.5 1.5 2
1.1 1.1 1.2
1.65 1.65 2.4
3.96 6.534

8.32 32.9472
8.32

0.36 0.9801

0.12 0.4752

Concrete Volume
Wall
Wall
Thickness 0.23
depth 2
perimeter 8
3.68
total
concrete
volume 4.6601
Decommissioning and Diversion of Existing Oxidation Ponds and Associated Works (Phase III)
at Tun Hussein Onn Road, Bintulu

SUMMARY OF TENDER

1.0 GENERAL AND PRELIMINARIES 710,000.00

2.0 SITE CLEARING & EARTHWORKS 600,000.00

3.0 SEWERAGE WORKS 3,720,000.00

4.0 SEWERAGE PUMPING STATIONS 1,100,000.00

5.0 DEMOLITION OF EXISTING OXIDATION POND AND LIFT STATION 1,132,000.00

6.0 PILING (ALL PROVISIONAL) 272,444.00

7.0 TURFING 50,000.00

8.0 WATER SUPPLY TO PUMP STATIONS 90,000.00

9.0 FENCING AND GATE FOR PUMP STATIONS 100,000.00

10.0 Contingency Sum 200,000.00

11.0 M/E WORKS 1,717,000.00

12.0 UPGRADING OF OXIDATION POND TO AERATED POND 1,000,000.00

TOTAL CARRIED FORWARD TO FORM


OF TENDER RM 10,691,444.00