Session on Finance
Sidharth Sinha
Indian Institute of Management, Ahmedabad
The views expressed here are those of the presenter and do not necessarily reflect the views or policies
of the Asian Development Bank (ADB), or its Board of Directors, or the governments they represent.
Forms of Government Support for Road Concessions
Cross-Border Infrastructure: A Toolkit
• Land acquisition
Expropriation of right of way for toll road construction. Cost
of land acquired maybe borne either by the government or
the concessionaire.
• Revenue support
Revenue support is usually done with a minimum
threshold for compensation paid by the governments
During construction
During operation
Grant Supported BOTs
Cross-Border Infrastructure: A Toolkit
Grant During
Grant During Construction
Operations
Lower, as the grant amount Higher as the entire
Extent of
in capital structure reduces initial project investment
funds
the amount of equity & debt is raised through debt &
leveraging
raised in the project equity
Lower Higher part of lender
Lender dues entirely met dues assured through
Lender through toll revenues grant disbursement
protection during operations
regardless of project
revenues
Grant amount to be Grant amount to be
Cash flow
disbursed by road agency disbursed by road
impact from
within a short span of time, agency over a longer
road agency’s
and during actual asset period of time, after
perspective
(road) creation creation of asset
Government Support for Road Concessions (continued)
Cross-Border Infrastructure: A Toolkit
• Shadow toll
Government pays toll to the concessionaires according
to the vehicle - kilometers of the traffic counted
automatically. This provides for a means of introducing
private financing without stimulating resistance to tolling.
Possible financial burden/ fiscal inflexibility in later years
may hinder transition to real tolling.
Government Support for Road Concessions (continued)
Cross-Border Infrastructure: A Toolkit
• Bridge specifications
An 8 lane link across the river Yamuna
A 552 meter long main bridge, 3 minor bridges
8 lane approach roads on embankments
A 27 lane automated toll plaza
NOIDA
Indpt. Engineer
Concession Agreement
Indpt. Auditor
Shareholders
NTBCL
Agreement
Loan Agreement
O&M Contract
Banks/FIs EPC Contract Investors
• The Delhi Noida Bridge Project was the first large private
sector initiative in the surface transport sector.
• NTBCL had to contend with several governments,
multiple departments, and ever changing political and
bureaucratic interfaces.
• As the first project of its kind, it did not have the
advantage of precedence, either in documentation or with
respect to financing.
• The project was also implemented during a fragile
political and economic environment in the country and
state/s.
Concession Agreement - Toll Determination
• Recovery of costs through fees/tolls:
Cross-Border Infrastructure: A Toolkit
Interest rate • All debt contracted are based on fixed rate of interest
Risk Mitigation Framework - 2
Risk Mitigation
Cross-Border Infrastructure: A Toolkit
IL&FS 360.0
NOIDA 100.0
IFCI 50.0
FCD Issue 207.8
International Funds 400.0
Intertoll (O&M Operator) 106.2
Total Equity 1224.0
Debt
Deep Discount Bond issue 500.0
IL&FS (World Bank L/C) 600.0
RTL from FIs/Banks 1758.0
Total Debt 2858.0
Public Issue
Cross-Border Infrastructure: A Toolkit
• This was also the first initial public offering with take out
financing arrangement
Take-Out Financing
Cross-Border Infrastructure: A Toolkit
Rs. Million
Year ended 31 March 2001 2002 2003 2004 2005 30.9. 2005
Total income 13 118 187 259 317 189
Total expenses 8 65 82 82 91 51
Operating profit 5 53 105 176 226 138
Interest/Finance charges 50 426 337 346 374 193
Depreciation 9 62 63 2 2 1
Miscellaneous expenditure
written off 2 15 15 15 15 8
Net profit before tax (56) (450) (311) (186) (165) (63)
Less provision for tax / FBT 0
Adjusted net profit after tax
and extraordinary items (56) (450) (311) (186) (165) (63)
Cross-Border Infrastructure: A Toolkit
12
/6 Closing Price
/2
00
10
15
20
25
30
35
40
0
5
2
3/
6/
2 00
3
6/
6/
2 00
3
9/
6/
2 00
12 3
/6
/2
00
3
3/
6/
2 00
4
6/
6/
2
Date
00
4
9/
6/
2 00
12 4
/6
/2
00
4
3/
6/
2 00
5
6/
6/
2 00
5
NTBCL Share Price History
9/
6/
2 00
12 5
/6
/2
00
5
Debt Restructuring
• Original project debt was contracted at an average cost of
Cross-Border Infrastructure: A Toolkit
15% pa.
• In view of the downward interest rate trends and revised
cash flow projections, the effective cost of term loans was
reduced to 8.5% pa.
• DDBs were restructured w.e.f. Nov 2004 with revised
interest yield of 8.5% pa and are proposed be refinanced in
the current financial year.
• The debt restructuring exercise has been fully completed
and the current carrying cost of debt is 8.5% pa with
complete repayment by 2017.
Valuation of Company
Cross-Border Infrastructure: A Toolkit
• Market capitalization
=Rs. 35*122.4 million= Rs.4,284 million