Documente Academic
Documente Profesional
Documente Cultură
5
6
1
3
8
4
7
9
10 209792
Sequence
1 Overhead guard, Headlamps 6 Radiator cover
2 Batteries, Cables 7 Floor plate, Floor mat
3 Steering wheel 8 Air hose, Air cleaner
4 Gas springs 9 Exhaust pipe
5 Engine cover, Seat 10 Fuel hoses (without LPG engine models)
5-1
POWER TRAIN
Controls
2
4
4 5
6 1
210118
Sequence
1 Brake pipe 4 Connector (Throttle, Stop lamp switches)
2 Inching cable, Clevis pin, Washer, Snap pin 5 Pedal assembly
3 Oil tank 6 Accelerator bracket
Installation
Follow the removal sequence in reverse.
5-2
POWER TRAIN
1
5
3
2
To engine
A
To engine
4
7
To engine
8
A
210120
Sequence
1 LPG tank 5 Water hose
2 Tank bracket 6 LPG hose
3 LPG hose 7 Water hose
4 LPG pipe 8 Vaporizer assembly
Start by:
(a) Draining the coolant hose from the engine by removing
the drain plug.
(b) Draining the coolant from the radiator by loosening the
cock at the bottom of the radiator.
5-3
POWER TRAIN
4 5
7
6 3
2
1
11
8
10
9
209796
Sequence
1 Reserve tank 7 Cooler hose (between radiator and powershift
2 Hose (upper) transmission)
3 Hose (lower) 8 Cooling fan
4 Hose (between hydraulic tank and control 9 Fan belt
valve) 10 Fan guard
5 Hose (between hydraulic tank and oil pump) 11 Universal joint (between transmission and
6 Hose (between oil pump and steering control reduction/differential gears)
valve)
5-4
POWER TRAIN
209797
Sequence
1 Transmission mounting bolt 3 Engine and transmission assembly
2 Engine mounting bolt
Start by:
(a) Lifting the engine and transmission assembly with a
hoist and slings.
5-5
POWER TRAIN
Installation
Follow the removal sequence in reverse.
Frame-side
engine mount 209798
5-6
POWER TRAIN
5
1
6
4 8
9
10
209800
Sequence
1 Overhead guard, Headlamps 6 Radiator cover
2 Batteries, Cables 7 Floor plate, Floor mat
3 Steering wheel 8 Air hose, Air cleaner
4 Gas springs 9 Exhaust pipe
5 Engine cover, Seat 10 Fuel hose
5-7
POWER TRAIN
Controls
This section describes only removal and installation
procedures specific to diesel-engine trucks. Follow the
instructions for the gasoline-engine trucks in the preceding
sections for the common procedures.
Sequence
1 Throttle cable
209802
5-8
POWER TRAIN
5
7
3
2
1
8
11
6
10
209804
Sequence
1 Reserve tank 7 Cooler hose (between radiator and powershift
2 Hose (upper) transmission)
3 Hose (lower) 8 Cooling fan
4 Hose (between hydraulic tank and control 9 Fan belt
valve) 10 Fan guard
5 Hose (between hydraulic tank and oil pump) 11 Universal joint (between transmission and
6 Hose (between oil pump and steering control reduction/differential gears)
valve)
5-9
POWER TRAIN
209805
Sequence
1 Transmission mounting bolt 3 Engine and transmission assembly
2 Engine mounting bolt
5-10