Documente Academic
Documente Profesional
Documente Cultură
Key Achievements for the above core activities during the reporting period as bellow:
1. providing CMIS training to ISD Engineers
The training has been provided to central ISD staff. The training were delivered through on job
oriented approach and each manager were asked to use the system for his daily work. The users and
passwords were provided for the staff.
3. Construction monitoring and supervision to ensure the projects gets completed within quality,
time and budget. This is a repetitive task, the engineers around the country has focused on
timely completion of the project and compliance with the quality.
Progress of EQUIP supported Projects- Old CC-EQUIPI-II and A.F projects, December
31, 2017
S.No Total Completed Ongoing Not Started Reasons( Stopped Reasons( p Terminated
Contracted/ problems) roblems)
Planned
3 166 Missing All these are missing components for EQUIP I&II NCB projects in which
Components missing components were are not included in original contacts are now included
for EQUIP in new procurement plan out of which 121 are completed, 8 are stopped due to
I&II Old contractor weakness and security, 3 are not started due to security, weakness of
NCB contractor and some are newly contracted, and 12 are ongoing.
Projects
Center 16 15 15 11 15
South 26 22 16 25 30
Sent to provincial senior engineers for taking
East 11 19 4 8 5
corrective
West 0 7 10 12 10
actions accordingly
North 4 6 20 0 13
Total 57 69 65 56 73
Regarding in term of compliance to ESS regulations refreshment in projects construction sites ESS
Team follow up the Environmental Cod of Practices (ECoP)
.This will help the contractor to be applied the ESS issues in the project construction sites. Thetable
as below for contractor’s indifferent provinces.
Center 16 6 204
South 16 5 36
North 10 8 96
Total 63 31 495
Designing
Repacking
Preparing and arranging 415 incomplete projects for repacking process in some of the provinces as
:bellow
Maidan Wardak province- 1, Hira province- 5, Hilmand province- 6, Noristan province- 7, Panjshir
province- 15 and Jowzjan province 20 projects, missing components for 78 projects & components
for 56 projects- Faryab
Amendment
ISD Evaluation team evaluates W.B projects during 50% and upon completion of 100% as well.
When there are defections at any project during both percentages, so the problem are being shared
with ISD-plan department and they contact with the contractor and relevant PED for tacking
action. Once the defections solve by the targeted company after the confirmation from
ISD/EQUIP provincial engineers or M&E engineers the company can get their remaining
payment. On other hand, monitoring team monitor the projects on a regular basis as ISD/EQUIP
zonal managers or engineers from the center go to the sites and observe the ongoing projects for
efficiency and timely implementation. Besides, M&E department invites involved construction
companies to avoid any delay.
Infrastructure Services Department (MoE)/ EQUIP Semiannual Activity Report (January 2017-
June 30, 2017)
ISD database team has already developed an advanced CMIS system, for which many tasks
undertaken. This system utilized CMIS jointly using back-end SQL server and frontend is
developed in asp.net MVC. The newly developed CMIS system of ISD consisted of many
modules such as Plan, M&E, Survey, Design, Contract management unit, Finance
department, Work permission, and other system related sub-modules. As team work we have
done the following tasks for the CMIS development.
After completing the system front and back-end development, we have hosted our system at
sub-domain of EMIS at MoE. The URL of our CMIS is www.emis.cmis.af . All World Bank
projects are entered in the CMIS. Still we are modifying our CMIS according to the need and
request of ISD. There are many other modules which are under consideration to be developed
in the future, for such modules we have done the requirement analysis, and design. We are
working to develop the reminded modules and computerized all the departments.
Future work
CMIS provide an easy way to track construction projects from initial state of project award to
final state of project handover. All user of the system can easily communicate to track their
tasks by having a user and password. For future to enhance the CMIS we have listed these
modules to be developed.
a. Due to MoE delay and low procumbent process ISD could not be able to meet the deadline of
December, 2017 to complete all the planned projects as 246 projects are under procurement
process.
b. There are security threats in the some provinces due to instability.
c. Amendments of the projects ( boundary walls etc)
d. Long payment and time extension process
Infrastructure Services Department (MoE)/ EQUIP Semiannual Activity Report (January 2017-
June 30, 2017)
Recommendations
As the ISD-EQUIP project ended earlier the completion remaining work and the World Bank didn’t
agree to provide MoE with new time extension, so 541 incomplete projects need facilities and staff for
clearance of invoices in order to have valid data for the future actions and it will help MoE and other
donors know how many projects are still to be completed including required budget. MoE should
work hard for finding budget in order to finalize the remaining work of ISD-EQUIP project in the
center and province for efficiency.
Infrastructure Services Department (MoE)/ EQUIP Semiannual Activity Report (January 2017-
June 30, 2017)
Success Stories
ISD-EQUIP reporting officer has visited some of the school in Kunar province where he has
conducted face to face interviews with some students in order to know how efficient the
World Bank intervention regarding constructing school building is. The depictive narration is
as per bellow:
wall which can effectively prevent us from noices and distractions. We are happy and request
MoE/EQUIP to futheur their support as there still many students who do not have school
buildings and other compoents in their schools in Afghanistan.”