Documente Academic
Documente Profesional
Documente Cultură
Issued by
Compiled by: The Center of Technical & Economic Consultancy for Electric
Power Construction under the Ministry of Electric Power
Industry
The Standardization Department of the Federation of Chinese
Electric Power Enterprises
Approved by: The Ministry of Electric Power Industry of P.R.C
Since The Code for Erection and Acceptance of Electric Power Construction (Section
of Steam Boiler Set) (SDJ245-88) was issued and implemented, it has played an active
role in promoting the electric power industry construction and the quality of the boiler
construction of power stations. With the rapid development of socialist market
economy in China, the development in electric power industry and improvement in
power generation quality have provided essential guarantee for development of social
economy. In order to meet the requirements for safe, economical, stable and full”
operation of thermal power plant on, adapt to the demand for the construction of large
sets and new equipment, we have organized the personnel concerned to modify and
supplement the previous Code, and have made large alteration to it, for which, we
have organized three seminars and assessments.
The national standards, industrial standards and documents used or cited by this Code
are ones currently in use that were issued before Jan. 1996. 36 new standards are
issued, and 14 former ones are replaced, one standard, which was numbered 26 in
appendix XVI in the former standard, was cancelled. With the introduction of new
standards, much modification are made to this Code, such as connection by
high-strength bolts, installation of oil tank, welding process and quality, erection of
piping, pump mounting, start-up commissioning of the whole set, chemical cleaning,
adjustment of relief valve, and steam flushing, etc.
With development of new equipment, technique and materials, more new articles are
added to the Code, where 10 articles are added for “3.5 Circulating Pump” under “3
Heating Surface”; and 20 articles are added to “5.5 Smoke Desulfurization Device”
under “5 Smoke, Wind, Coal Piping and Attachment”; 10 sub-articles are added to
“7.3.5MPS (ZGM) Medium-Speed Coal pulverizer” under “7.3 Coal Pulverizer”; and
6 appendixes are newly added; 4 appendixes are modified and updated; and one
appendix is canceled.
This Code is examined and approved by the Ministry of Electric Power Industry, and
was issued on Jan. 4, 1996 in form of No. 6 DJ [1996] File, numbered DL/T5047-95,
and which will be enforced as May 1st, 1996, the former Standard SDJ245-88 is
abolished immediately.
Compiled by: The Consulting Center for Electric Power Construction Technology &
Economy of the Ministry of Electricity Industry
The Standardization Department of the Federation of Chinese Electric
Power Enterprises
Co-editors: Electric Power Construction Research Institute of the Ministry of
Electric Power Industry
Chief editors: Fan Jiuzhou, Tao Hengsheng
Table of Contents
ISSUED BY...................................................................................................................................... I
PREFACE ........................................................................................................................................1
3 HEATING SURFACE...........................................................................................................26
Of Edge irons
2.2.1 Before erecting the boiler, a countercheck of foundation shall be carried out
according to the acceptance record, and shall meet the following requirements:
2.2.1.1 Be in compliance with the design and national standard—The Code for
Construction and Acceptance of Concrete Structure Engineering. For the allowable
deviation of the boiler foundation, see appendix C;
2.2.1.2 The positioning axial line shall be checked against the reference point for
building the plant and shall be free from error;
2.2.1.3 The allowable deviations in the ruling of the boiler foundation are:
a) Column spacing 10m 1mm
>10m 2mm
b) Corresponding diagonal lines of columns 20m 5mm
>20m 8mm
2.2.1.4 When the foot bolts for the steel framework are pre-buried, the requirements
for the positioning plates are:
a) Distance deviation between columns 1/1000 of distance 5mm
b) Deviation in corresponding diagonal lines of column 8mm
2.2.2 The secondary grouting distance shall be no less than 50mm between foundation
surface and base plate of the patten; all foundation surfaces shall be frosted, and the
points for placing edge irons shall be chiseled to be flat.
2.2.3 When installing with edge irons, they shall meet the following requirements:
2.2.3.1 The surfaces of edge irons shall be flat, and shall be planed to be flat if
necessary;
2.2.3.2 The number shall not exceed 3 pieces for each group of edge irons, and the
width generally is 80~120mm, the length shall be about 10mm longer than the base
plates of the patten, and the thicker ones will be placed at the lower layer. When the
secondary grouting interval is more than 100mm, it is allowable to place a framework
formed by profiled steel plus a edge iron;
2.2.3.3 The edge irons shall be placed under the vertical rib plates of the pillar base
plates, the total force-bearing area of the edge iron under each pillar shall be
calculated based on/on the basis of the design load-bearing capacity of the column,
and the unit force-bearing capacity of the edge iron shall be no more than 60% of
design concrete strength of the foundation;
2.2.3.4 After erecting the edge irons, a hand hammer shall be used for an inspection
to ensure that it is free from looseness, and spot-weld the edge irons together, then
weld them with the patten’s base plate.
2.3 Boiler Framework Combination
2.3.1 The column butting and frame combination shall be conducted on a firm
combination stand, and the stand shall be leveled.
2.3.2 When the boiler framework is combined, usually an elevation line of 1m is first
drawn on the column as follows:
2.3.2.1 For a bearing structure, a point of 1m elevation is determined for the pillar
largely based on the main card head’s elevation while considering the elevations of
most card heads and that of the column top;
2.3.2.2 For a suspended structure, generally, one will determine the 1m elevation for
the pillar based on the elevation of the big beam of the top plate or that of the column
top surface, and the shrinkage value of the column shall be taken into consideration
based on the technical documents of the equipment.
2.3.3 When the boiler steel framework is combined, attention shall be given to the
welding sequence and reservation of proper allowance for welding shrinkage, so as to
ensure that the combined size will exceed allowable deviation after welding.
2.3.4 For the allowable deviations for combined steel boiler frameworks, see table
2.3.4.
Table 2.3.4 Allowable Deviations for Combined Steel Boiler Frameworks
unit: mm
No. Items to be checked Allowable deviation
1/1000 of distance, max. no more than
1 Distance between columns 1)
10
2 Parallelism between columns 1/1000 of length, max. no more than 10
3 Elevation of beam 2)
5
4 Parallelism between beams 1/1000 of length, max. no more than 5
1.5/1000 of length, max. no more than
5 Corresponding diagonal lines of combination unit
15
6 Relative mismatch between beam and column’s central lines 5
Distance between guard plate frame inside and column’s central +5
7
line 0
8 Distance between beams of top plate 3)
3
Verticality of platform support to column, truss and guard plate 2/1000 of length
9
framework
10 Platform’s elevation 10
11 Relative position of platform to the column’s central line 10
Notes:
1) For a bearing structure, it shall better have a positive deviation for column distance.
2) The deviation in elevation of beam for bearing steam drum, coal economizer, re-heater,
over-heater and air pre-heater shall be –50mm; and the installation requirements for rigid platform
are the same as that for beam.
3) The beam distance for top plate of suspending structure refers to the distance between central lines
of main hoisting holes.
2.4 Erection and Secondary Grouting for Boiler Framework
2.4.1 When aligning the boiler framework for installation, one can do that based on
the reference elevation of the plant, measuring the 1m elevation of each column,
which can be adjusted with the edge irons under the column; for steel column base
plates with adjusting bolts, one can adjust the elevation with the adjusting bolts.
2.4.2 When erecting the boiler framework, a layer (section) shall be aligned once it is
erected; it is strictly forbidden to conduct the next operation on an unaligned
framework, so as to prevent any deviation that can’t be corrected after erection.
2.4.3 When a welded boiler framework is erected, it shall be first be aligned and
fixed by spot welding, and proper allowance for welding shrinkage shall be left; and
formal welding can only be carried out after re-checking the dimensions and
confirming they meet requirements. For welding, attention shall be paid to the
welding sequence, and avoid excessive error in erection dimension after welding.
2.4.4 During and after hoisting the boiler framework, the stability of structure shall
be ensured, and temporary reinforcement can be made where necessary; after hoisting,
the verticality of columns and deflection of main beams as well as dimension of each
point shall be double checked.
2.4.5 When aligning and putting in place the framework combinations with furnace
walls, one shall maintain the design clearance between furnace wall and heating
surface and that of between furnace walls.
2.4.6 When a boiler adopts a suspended structure, the arc cushion plate on column
top shall be erected in accordance with the technical document of equipment, and the
cushion plates shall be in correct direction, and the upper and lower plates shall be in
good contact.
2.4.7 When high strength bolts are used, they shall be stored, transported, kept,
mounted, inspected and accepted in accordance with the technical document from the
manufacturer; if the manufacturer has no clear specification, one shall follow The
Instructions for Design, Construction and Acceptance of High-strength Bolt
Connection for Steel Structure (JGJ82-91); and shall meet the following basic
requirements:
2.4.7.1 The high-strength bolt connection kit (composed of one bolt, one nut and
one washer) shall be supplied by the manufacturer in complete sets, and they shall be
furnished with quality certificate;
2.4.7.2 The type dimensions and technical conditions of anti-shear high-strength
bolt connection kit shall be in compliance with Anti-shear High-strength Bolt
Connection kit for Steel Structures – Type Dimension (GB3632-83) and Anti-shear
High-strength Bolt Connection kit for Steel Structures – Technical Condition
(GB3633-83);
2.4.7.3 For the anti-shear high-strength bolt connection kit transported to the
construction site, one shall check timely the bolt wedge load-bearing capacity,
guaranteed load bearing capacity for nut, hardness of nut and washer, average
tightening shaft force of connection kit and the freak coefficient, and the inspection
results shall be in compliance with regulations(GB3633-83). They can be put into use
only after they are qualified;
2.4.7.4 The anti-slip coefficient of the friction surface shall be inspected in
accordance with Clause 3.3.2 of (JGJ82-91). The min. value inspected shall be no less
than the design value. When it doesn’t meet this, the friction surface of the structure
shall be re-treated, and the treated structure surface shall be re-inspected;
2.4.7.5 The inspection and testing way for high strength bolt connection kit shall be
in compliance with the following standards:
a) The tension test for bolt material shall follow The Metal Tension Testing Method
(GB228-87);
b) The impact test for bolt material shall follow The Metal Charpy (U-notch) Impact
Testing Method (GB229-84);
c) The wedge loading test shall follow The Mechanical Performance for
Fasteners--Bolts, Screws and Studs (GB3098.1-82);
d) The test on guaranteed load capacity for nut shall follow The Mechanical
Performance for Fasteners—Nuts (GB3098.2-82);
e) For bolt, the hardness test shall follow (GB3098.1-82), and for nuts, shall follow
(GB3098.2-82); for hardness test of a washer, four points on its surface shall be
selected arbitrarily, and then the average value of three points is obtained.
2.4.8 The erection welded-seam bearing installed load (including dead weight), the
amount, thickness and length of positioning weld points shall be determined
according to calculation; and for the erection welded-seam without bearing of
installed load (including dead weight), the total length of positioning weld points shall
be no less than 10% of its welded seam length, and not be less than 50mm.
2.4.9 The allowable deviations for erection of boiler framework are shown in Table
2.4.9.
Table 2.4.9 Allowable Deviations for Erection of Boiler Steel Framework
unit: mm
No. Items to be checked Allowable deviation
6 Corresponding diagonal lines in upper and lower planes of 1.5/1000 of length, max. not more than 15
each column
7 Elevation of beam2) 5
8 Levelness of beam 5
Note: the notes for the table are same as that of Table 2.3.4.
2.4.10 For reinforced concrete boiler framework, one shall pay attention to the
following :
2.4.10.1 Before construction of the reinforced concrete boiler framework, the position,
mode of anchoring and design load, etc. of the pre-buried parts shall be checked on
the basis of the construction drawing;
2.4.10.2 Attention shall be given to the coordination of construction of reinforced
concrete boiler framework and erection of boiler body so as to avoid mutual
influence;
2.4.10.3 Before installation of the boiler device, the geometric dimension, elevation
and settlement of reinforced concrete boiler framework shall be rechecked according
to the acceptance record. The deviation in diagonal lines of reinforced concrete
columns shall be no more than 15mm. The reinforced concrete framework of boiler
shall be in compliance with The Code for Construction and Acceptance of Concrete
Structure Engineering . For allowable deviations, see Appendix D.
2.4.11 The steel-pipe concrete pillar and construction of concrete in the pipes shall
meet the design specifications. After pouring the concrete, it is strictly forbidden to
heat under high temperature and weld by large area on the pillar surface.
2.4.12 There shall be sufficient expansion clearance at the bolt connection point
with an expansion displacement, and see to the direction of expansion.
2.4.13 The platform and ladders shall be erected as early as possible in coordination
with the boiler framework to promote the stability of the frame and safety of
construction. The welding connection shall be secured in time; and the connection
through steeve and clamping apparatus shall be tightened timely, steeve and clamping
apparatus shall not be sufficient in quantities.
2.4.14 The columns for rails shall be vertical, and the spacing shall be even; a pillar
shall be built at the corner. The vertical rails at the same side on platforms of different
floors shall be on the same vertical line as much as possible. For platform, ladder, rails,
columns and enclosing plates, after erection, they shall be flat and firm, and the joints
shall be smooth.
2.4.15 Don’t cut short or extend ladders ad lib, or change the slant of ladders, or
change the heights of upper/lower steps and distance between the connecting
platforms.
2.4.16 The corrugated type outer guard plates shall be well kept. And try to avoid
collision and damage, the abutting of lines shall be consistent, and the fasteners shall
be sufficient in quantities; when seam joggling and lap joint is adopted, gathering of
ash and water shall be avoided.
2.4.17 The showering device and ash nozzle for the ash chamber shall have correct
mounting position and angle, the joints shall be tight and leak free, and the swing
device shall be free from obstruction.
2.4.18 There shall be no crack, sand hole and roughness in the surface of water
ash-flushing tile in the ash ditch of the ash chamber. The deviation in mounting slant
is 2, and the roughness on surfaces between tiles along the flow direction shall be
no more than 5mm.
2.4.19 After the alignment of framework is completed, one shall fix the pedestal on
the foundation in accordance with the drawing. When the reinforced bars are fixed
through the welding method, the reinforcements shall be heated and bent and was
stuck to the base plate of the pedestal (stick as close as possible to the vertical rib
plate), the heating temperature generally shall be no more than 1000C, and the length
seam between the reinforcement and vertical rib plates shall be 6~8 times the
reinforcement diameter, and a double side welding is adopted.
2.4.20 The time for the secondary grouting of the boiler foundation generally is:
when the patten is welded and fixed with reinforcements, that can be done after the
hoisting of large components of the boiler is completed; when the patten is fixed by
foot bolts or adjusted by bolts, that can be done after aligning the first section of the
framework.
2.4.21 Before the secondary grouting of the boiler foundation, one shall check to see
whether the edge irons, foot bolts and foundation reinforcements are completed, and
clean away the oil dust, welding slag and foreign matters on the base surface.
2.4.22 The secondary grouting of the boiler foundation shall be in compliance with
the drawing(s) and The Code for Construction and Acceptance of Concrete Structure
Engineering.
2.6.1 The water- and sand-sealed trough body shall be erected flatly, tightly and free
from leakage.
2.6.2 The connection between water- and sand-sealed flashboard shall be tightly
connected with equipment (e.g. header, etc.), the connecting points shall be tight and
free from leakage; the flashboard can expand freely, and under hot state, the
flashboard will have relative displacement with the slot body.
2.6.3 After the erection of the water- and sand-sealed trough and before filling the
sealing media, record of the heat expansion clearance shall be made, and the slot
inside shall be cleaned so that no foreign matter is left.
2.6.4 The welded seam of the corrugated type expansion joint shall be tight, and the
corrugated type joint shall be in perfect state; during the erection, the cold draw value
or shrinkage shall be in compliance with the requirement of drawing, and shall be well
documented; the welded seam of the internal protective iron plate shall built at the
inlet side of the media.
2.6.5 The requirements for the faying surface of sealing device fixed by the bolts and
secure fastening of bolt are same as that of Clause 2.5.2.
2.6.6 The position for oval bolt hole at the connecting point for the steam drum,
header housing and sealing iron plate shall be correctly adjusted, and it shall not
hinder the heat expansion of the steam drum and header.
2.6.7 The sealing iron plate welded on the heating surface generally shall be erected
and welded before hydraulic pressure test of the heating surface, and the welded seam
shall pass leak tightness test and be free from leakage; if some points must be erected
and welded after hydraulic pressure test, reliable technical measures shall be required.
2.6.8 The channel of the ventilation beam shall be unblocked; the welded seam shall
be tight and free from leakage; during erection, heat expansion clearance shall be
reserved.
2.6.9 Before the ignition and starting-up the boiler, air-pressure test shall be carried
out to check its air tightness, and the testing pressure will be based on the technical
documents of the equipment; in case of no specification, positive-pressure test can be
conducted with a pressure 0.5kPa higher than the operating pressure of the furnace
chamber.
2.8.1.3 When erecting the horizontal pipe-box air pre-heater, the up and down
direction should be paid much attention to, and wrong installation is forbidden;
2.8.1.4 The plug-in wear sleeve pipe shall have a proper pore, generally it can be
inserted with a slight force, and its projecting height shall meet the design requirement;
the butting anti-wear sleeve pipe shall be vertical to the pipe plate plane, and shall not
skew; the welding shall be secure and the number of spot-welding shall be no less
than two points;
2.8.1.5 After erection, the pipe type air pre-heater will pass air-pressure test
simultaneously with the test of cold and hot air channel, and there shall be no leakage;
and before starting-up the boiler set, an overall check shall be conducted before the
startup of the boiler unit. There shall be no foreign matters and dust inside the pipes.
2.8.2 Rotary type air pre-heater
2.8.2.1 The equipment check and inspection shall be in compliance with Clause 2.1,
7.1 and 7.2 of this Code.
2.8.2.2 The split stator (or rotor), after erection, shall be firmly connected according
to the regulations of technical documents of equipment, and the mismatched edges of
the joints shall be removed through abrasion.
2.8.2.3 The heat conductive components, after mounted into sector cabin, shall not
be loose, otherwise corrugated plate or positioning plate shall be added; the erection
of the heat conductive components of the rotor shall be conducted after rotor barring
is qualified; during construction, attention shall be given to the overall balance of the
rotor, so as to avoid blockage between heat conductive components;
2.8.2.4 The adjusting bolts of the seal unit shall be flexible and operate well, and
shall have adequate adjusting allowance;
2.8.2.5 The distance between the nozzle of soot blowing and flushing devices and
any point on the end face of the stator (rotor) shall be no less than the dimension
specified in the technical document for the equipment;
2.8.2.6 For lantern cycloidal speed reductor, before erection, idle operation of 2h is
required (simulating the actual working state), during the period, normal operation
and no leakage shall be ensured; before the actuator is started formally, the turning
motor shall be off-line automatically.
2.8.2.7 The roundness of the transmission shroud belt (subject to the pin shaft) shall
match that of the rotor (or stator), and the erection clearance between pin shaft and
transmission gear shall be in compliance with the technical document of equipment;
2.8.2.8 The roundness of the rotor (or stator) shall meet the following requirements:
a) Rotor: to measure the roundness at sealing surface at periphery of the rotor,
and the allowable deviations are as follows:
1) diameter 6.5 m 2mm
2) 10m diameter > 6.5m 3mm
3) 15m diameter > 10m 4mm
b) Stator: to measure the roundness at outer diameter of the casing, and the
deviation shall meet the technical documents of the equipment, generally, the
allowable deviations are as follows:
1) diameter 6.5 m 10mm
2) 10m diameter > 6.5m 2mm
3) 15m diameter > 10m 14mm
2.8.2.9 After the erection of fixing and lock units specified in the technical
document of equipment is completed, a careful check shall be carried out to ensure
that the fixing is secure and the lock is reliable.
2.8.3 Air-shield rotary type air pre-heater
2.8.3.1 The allowable deviations of the stator’s levelness (to measure 8 points at
periphery) shall be in compliance with the technical documents of the equipment,
generally, the allowable deviations are:
a) diameter 6.5 m 3mm
b) 10m diameter > 6.5m 4mm
c) 15m diameter > 10m 5mm
2.8.3.2 The movable bearing of the stator shall be level, and the upper and lower
contact surfaces of the pin rollers shall contact well in length direction, after aligning
the stator, the stop block shall be installed in accordance with the technical documents
of the equipment;
2.8.3.3 The graphite bar of the guiding graphite bearing shall be slightly drawn into
the slot, and the radial clearance between it and the shaft shall be no more than
0.1mm;
2.8.3.4 When erecting the telescopic joints on the air channel framework, the
distance a between the connecting angle steels of the telescopic joints and the sealing
surface (fig. 2.8.3.4) consistent, and the allowable deviations are:
a) diameter 6.5 m 6mm
b) 10m diameter > 6.5m 8mm
c) 15m diameter > 10m 10mm
The distance b between the
connecting angle steels of the
telescopic joints and the stator end
(fig.2.8.3.4) shall be in
compliance with the technical
Fig.2.8.3.4 Schematic diagram of the distance documents of the equipment, and
between the connecting angle steels of the generally it shall be no more than
telescopic joints and the sealing surface 4mm;
2.8.3.5 The upper and lower air shields shall be aligned before they are fixed on the
shaft, and be sure that the rotation should be synchronous. According to the
measurement on periphery of the air shield, the deviation shall be no more than
10mm;
2.8.3.6 The clearance between the external circle of the rotary air shield and the
internal wall of the flue shall be even, and there shall be no friction during the
rotation;
2.8.3.7 The neck joints of the dynamic and static parts of the air duct shall be
concentric, and the allowable deviation of concentricity shall be no more than 3mm;
2.8.3.8 The seal unit at neck shall be erected exactly and reliably, and the contacting
tightness of the seal surfaces shall ensure an overall contact.
2.8.3.9 The dynamic and static joining points of the soot blowing and flushing unit
shall be in compliance with the technical document of equipment, and shall not be
blocked and be free from leakage.
2.8.4 Rotary heating-surface air pre-heater
2.8.4.1 The allowable deviations of flatness in assembling the upper and lower end
plates are:
a) diameter 6.5 m 2mm
b) 10m diameter > 6.5m 3mm
c) 15m diameter > 10m 4mm
2.8.4.2 The allowable deviation in levelness of upper and lower beams shall be no
more than 2mm;
2.8.4.3 The rotor shall be erected vertically. According to the measurement on upper
end of the main shaft, the allowable deviation of levelness shall be no more than
0.05mm. The rotor shall be concentric with the casing, and the concentricity deviation
shall be no more than 0.05mm, and the peripheral clearance shall be even;
2.8.4.4 The main shaft and the rotor, when assembled, shall be concentric, and the
deviation of verticality of the main shaft and the rotor is:
a) diameter 6.5 m 1mm
b) diameter > 6.5m 2mm
2.8.4.5 The cold-state sealing clearance of axial, radial and peripheral sealing shall
be adjusted in accordance with the technical documents of the equipment; and the
erection direction for the angle plate must be in compliance with the rotation direction
of the rotor;
2.8.4.6 The erection of pressurized oil lubrication system shall be executed in
accordance with 7.3.1.28~7.3.1.37 “Erection of oil system”;
2.8.4.7 The heat insulation layer in the central tube shall be in compliance with the
technical documents of the equipment;
2.8.4.8 The erection of the tracking unit for sealing clearance shall be in compliance
with the drawing.
2.8.5 Sub-item commissioning of the rotary air pre-heater
2.8.5.1 The general requirement for the sub-item commissioning shall be in
accordance with Clause 7.2.11;
2.8.5.2 The rotation direction of the air pre-heater shall be in compliance with the
design one;
2.8.5.3 The sealing clearance shall be in compliance with the technical documents
of the equipment;
2.8.5.4 The axial and radial runout of rotor (or air shield’s flange outer diameter),
generally, shall be no more than the value shown in Table 2.8.5.4.
Table 2.8.5.4 The Axial and Radial Runout of Rotor (air shield)
Outer diameter of rotor or air shield Axial runout (mm) Radial runout (mm)
Rotor Air shield Rotor Air shield
diameter 6.5m 2 4 2 (8) 1)
10
10m diameter > 6.5m 3 6 4 (10) 13
15m diameter > 10m 4 8 4 (14) 16
Note 1)The values in brackets are radial runouts when using H-type cast iron sealing blocks.
3.1.1 Before erection, the heating surface equipment shall be completely checked
against the supply list, packing list and drawing to check whether there are any defects
such as crack, flaw, chap, flattened sign, sand hole and lamination, etc.; if the depth of
outer defect is more than 10% of the defined thickness of the pipe, Clause 1.1.6 of this
Code shall be applied; emphasis shall be put on the inspection of force-bearing
welded seam at components bearing heavy load, and the height of welded seam must
be in compliance with the drawing(s).
3.1.2 During the butt joint, attention should be given to inspection of the allowable
deviation (which is shown in Appendix F) in outer diameter and wall thickness of the
pipes on the heating surface, if the deviation exceeds the specifications of national
standard, Clause 1.1.6 of this Code shall be applied.
3.1.3 The materials of the alloy steel components shall be in compliance with the
technical document of equipment; before erection, the material must be re-checked,
and mark shall be made at obvious positions; after erection, the marks shall be
checked, and if the marks are not clear, the materials shall be re-checked again.
3.1.4 Before assembly and erection, the pigging test shall be carried out for the
heating surface pipe, the balls for which are steel ones, and shall be numbered and
strictly managed. The ball shall not be left within the pipeline. After the pigging test,
the pipes shall be reliably enclosed, and records shall be made; the ball diameters for
‘ball-pass’ test are as that shown in Table 3.1.4.
3.1.5 Generally, no calibration is required for the heating surface; if it does need to
be calibrated, the platform for calibrating the pipe shall be firm, and its flatness shall
be no more than 5mm, and the lining-out dimensional error shall be no more than
1mm.
3.1.6 The allowable deviations in erection for such main devices as the steam drum,
header and heating surface are:
3.1.6.1 Elevation 5mm
3.1.6.2 Levelness steam drum 2mm, header 3mm
3.1.6.3 Distance between each other 5mm
Note: for suspended boiler, the emphasis shall be put on upper header, and the allowable deviation in distance
between heating surface pipe rows is 5mm.
3.1.7 The heating surface pipes shall be mechanically cut as much as possible. If
they are cut by flame, one shall remove the cinder and unflat surface. Before
connecting the heating surface pipes, one shall first make bevels according to the
drawing, and the matching clearances shall be even. 10~15mm to the end at both
outside and inside of the pipe, oil and iron rust before welding shall be removed till
metal shines.
3.1.8 The end surface for matching of the heating surface pipe shall be vertical to
the pipe’s central line, and the slant of the end surface ∆f (fig. 3.1.8) shall be in
compliance with Table 3.1.8.
Table 3.1.8 Slant of End Surface of Pipe unit:mm
Nominal diameter D Slant of the end surface ∆f
D 60 0.5
60 < D 108 0.8
108 < D 159 1
159 < D 219 1.5
219 < D 2 Fig. 3.1.8 Schematic diagram
of slant end surface for a pipe
3.1.9 The butt joint of welded parts require a flush inner wall, and the mismatching
value shall meet the following requirements.
3.1.9.1 The local mismatching value of the single-surface welded butting shall be no
more than 10% of the wall thickness, and shall be no more than 1 mm;
3.1.9.2 The local mismatching value of the double-surface welded butting shall be no
more than 10% of the wall thickness, and shall be no more than 3 mm.
3.1.10 Before assembling and erecting the heating surface components, to check the
manufacture quality of crator, the quality certificate of manufacturer (quality warranty
paper) and safety inspection qualification notification from the manufacturer shall be
first checked. A visual inspection shall be conducted on the manufacturing crators of
such main components as water-cooling wall, coal economizer, over-heater and
re-heater, etc. In case of any disqualification, Clause 1.1.6 of this Code shall be
applied before the construction is approved.
For components of heating surface of a boiler up to 670t/h, if no safety inspection has
been carried out, in addition to the inspection of the quality certificate (quality
warranty paper) from the manufacturer and appearance inspection, radiographic
detection inspection shall be conducted for the main components by different
materials and specifications whose 1/1000, that is, no less than 2 crators shall be
sampled for inspection. In case of any disqualification, re-inspection of two times the
above said samples shall be conducted, if the disqualification still occurs, Clause 1.1.6
is applied before the construction is approved.
3.1.11 The matching deviation for pipes on heating surface shall be checked with a
straight rule, and shall be no more than 2mm from the seam at the position 200mm
away from the welded seam center.
3.1.12 The butt welding point for heating surface pipe shall not be placed at the
bending points of the pipe, and the distance from the welding point to the
bend-starting point of the pipe shall be no less than the pipe diameter, and shall be no
less than 100mm (except for welded, wrought and cast pipes); and the distance from
the supporting hanger edge shall at least be 50mm.
3.1.13 For the butt welding point of barrel, the distance from the welding point to
the bend-starting point of the bulkhead shall be no less than the wall thickness plus
15mm, and shall be no less than 25mm or more than 50mm; the distance between two
butt welding points shall be no less than the pipe diameter, and shall be no less than
150mm.
3.1.14 Before hoisting the heating surface assemblies, one shall first get ready for
the hoisting, recheck each supporting points, positions of hoisting points and
dimensions of the hoisting rods.
3.1.15 Mechanical way shall be adopted when opening holes on the steam drum,
header, pressure-bearing pipe and equipment, and no flame cutting shall be used, no
metallic chip and other foreign matters shall fall, and it is noted that this shall be done
before blowing the pipes.
3.1.16 The alloy steel bolts for application with a working temperature not less than
500C and of a diameter more than 30 mm shall go through hardness test. The
hardness value will be in accordance with Table A3 in Appendix A of The Code of
Erection and Acceptance of Electric Power Construction (Section of Piping).
3.1.17 The heating surface pipes shall be clean, and no foreign matters shall fall in
during the erection.
3.3.6 There shall be clearance between adjacent light tubes of water-cooling wall,
and for pipe sections with relative displacement during operation, expansion clearance
shall be reserved.
3.3.7 Be noted that the steel material used in splicing the gap between diaphragm
walls must be in compliance with drawing.
3.3.8 The cold drawing of the water-cooling wall shall be in compliance with the
technical documents of the equipment, and records shall be made.
3.4 Over-heater, Re-heater, Coal Economizer and Desuperheater
3.4.1 When assembling and erecting such snake-shaped tubes as over heater,
re-heater and coal economizer, first the header shall be aligned and fixed, then the
reference snake-shaped tube be erected. When erecting the reference snake-shaped
tube, he shall carefully check the butt joint between the snake-shaped tube and the
header pipes as well as the length deviation from the header center to the end of the
snake-shaped tube, and erect the rest pipes after aligning and fixing the reference
snake-shaped tube.
3.4.2 When heating and straightening the alloy steel components, the heating
temperature is generally controlled under the critical temperature Ac1 of the steel
(refer to Appendix B).
3.4.3 The allowable deviations for assembling and erecting the over heater and
re-heater assembly are shown in Table 3.4.3.
3.4.4 The allowable deviations for assembling and erecting the coal economizer are
shown in Table 3.4.4.
3.4.5 For the anti-wear unit of the heating surface, expansion clearance shall be
reserved at the joints, and it shall not hinder the circulation of smoke.
3.4.6 The allowable deviation in flatness of over heater tube row for hover pipe is
5mm, and the distances between tubes shall be even.
3.4.7 The assembling and erection of the over heater of wall-wrapping pipe can
refer to Clause 3.3 of this Code.
3.4.8 Before erection, for the water-spraying temperature reducer, the assembling
and enclosing certificate provided by the manufacturer shall be checked and visual
inspection shall be carried out; each adapter socket shall be unblocked, and the
welding shall be correct.
3.4.9 For pipes of heating surface for which the fault can’t be treated after erection,
a single-pipe water-pressure test or non-destructive flaw detection shall be carried out
once before erection. The testing pressure is 1.5 times of the working pressure, and
after the hydraulic pressure test, gathered water in the pipe shall be removed.
5.3.4.3 The operating apparatus for measuring powder shall be installed at proper
place of the running layer for the boiler; the operating mechanism shall be firm, easy
to operate, and the powder level indication shall be clear, consistent with the actual
position of the buoy in the powder bin;
5.3.4.4 The steel wire of the powder measuring unit shall be soft, generally with a
diameter of 3.6~4.8mm, and joining in the middle shall be avoided; it shall move
smoothly in the guiding pulley; where the steel wire passes floor slab, it shall be
equipped with wall-passing guide pipe; the number of guiding pulley shall be as few
as possible, and the pulley itself shall run flexibly;
5.3.5 Fire fighting device
5.3.5.1 The injecting direction of the coal-powder fire-fighting device that extending
into pipe or equipment must be the same as that for the coal powder;
5.3.5.2 The inletting pipe head installed in the fire fighting unit at top of the coal bin
top shall be equipped with spreading unit, and its injecting direction shall be parallel
with the bin cover, so that the injected media can be spread and cover the whole coal
bin but will not directly onto the coal powder;
5.3.5.3 The inlet pipe head of the fire fighting unit at the heating surface at tail of the
fuel (coal) boiler shall be equipped with diffusing unit, so that the injected media can
be diffused and cover the whole tail space;
5.3.5.4 After installing the fire fighting unit, the pipe before the secondary valve
shall go though the water (steam, gas) pressure test with a working pressure and be
qualified; before starting the boiler set, water- (steam-, gas-) connected test shall be
carried out; if the drawing specifies to use diaphragm, the diaphragm must go through
pressure-breaking test with the working media, after it is checked to be qualified, it
will be replaced by diaphragm with the same specification.
5.3.6 Supporting hanger
5.3.6.1 The supporting hangers shall be erected in accordance with The Code of
Erection and Acceptance of Electric Power Construction—Section of Pipe;
5.3.6.2 The supporting hanger with constant force shall be installed and adjusted in
accordance with design requirement;
5.3.6.3 During installation of pipes, it is strictly forbidden to overload the supporting
hanger, so as to ensure the personal and equipment safety.
5.4.3.4 The water piping and nozzle position and angle for water film dust arrestor
shall meet requirement from the drawing, if without specification, the angle deviation
for nozzle periphery shall be 2, and the nozzle central line generally shall be 10
downward in relative to the level surface. Before erecting the nozzle, one shall first
flush the water piping, only after that is qualified, can the nozzle be mounted. At the
initial phase when the nozzle is put into operation, one shall check whether it has any
sign of being blocked;
After the erection of water film dust arrestor, one shall carry out test on water film,
which shall be even;
After the erection of Venturi tube, one shall carry out water injecting test, and
the water film shall be even and complete, the surface of water splashing plate shall
be smooth and flat, its angle shall meet requirements from drawing.
5.4.4 Electric dust arrestor
5.4.4.1 The check on the foundation before erection for electric dust arrestor shall
follow “The Code for Erection and Acceptance of Concrete Structure Engineering”,
and it shall be checked to be acceptable;
5.4.4.2 When the pillar under the base beam is steel one, the allowable deviations for
the erection of the pillar are:
a) Distance between pillars 1/1000 of the distance between pillars, and not
more than 10mm
b) Verticality of pillars 1/1000 of pole height, and not more than 10mm
c) Elevation at top of pillar 5mm, not more than 2mm for mutual deviation
between pillars
5.4.4.3 Allowable deviations in erection of the base beams:
a) The upper planes of beams shall be in the same plane, and the levelness
deviation shall be no more than 5mm;
b) The deviation in level distances for central lines of base beam for each electric
field shall be no more than 5mm, and the length difference between two diagonal lines
shall be no more than 7mm;
c) The deviation of level distance of an integral base beam shall be no more than
5mm, and the length difference between two diagonal lines shall be no more than
9mm.
5.4.4.4 The allowable deviations in erection of columns are:
a) Distance between columns 1/1000 of distance between columns, and not
more than 10mm
b) Verticality of columns 1/1000 of column height, and not more than
10mm
c) Elevation at top of pole 5mm
5.4.4.5 The allowable deviations in erection of crossbeam are:
a) Elevation of crossbeam 5mm
b) Distance between longitudinal central lines of two adjacent crossbeams
5mm
5.4.4.6 The combination and erection of anode plates shall meet the following
requirements:
a) The hoisting and handling of anode-plate containers shall be hoisted and
cushioned in accordance with the marked positions, if it has no mark, the hoisting
points, cushioning positions and hoisting equipment will not make anode plate
deformed
b) When combining anode plates, individual anode plates shall be checked, the
flatness shall be no more than 5mm, and the distortion shall be no more than 4mm, the
plate surface shall be free from burr and sharp angle;
c) After combining anode plates, the bending in a plane shall be no more than
10mm, the difference between two diagonal lines shall be no more than 5mm; and
suspension check and calibration one by one shall be had if it is necessary;
d) When combined anode plates are fixed by bolts at two ends, the fasteners and
fastening torque shall be in compliance with technical document of equipment; after
fastening, the nuts shall go through standstill welding, and it shall have no burrs or
sharp angles at the welded seams;
e) The hoisting for anode plates shall use special measures and tools, and it shall
not make permanent deformation in the plates during hoisting.
5.4.4.7 The erection for anode-plate suspension system shall meet the following
requirements:
a) If the supporting for anode system adopts quartz bushings, a careful inspection
shall be carried out, and they shall be free from such defects as crack; during the
erection, it is strictly forbidden to knock or pry or press; after erection, one shall fill
the sealing packing timely;
b) The four porcelain poles of the same group shall be adjusted to be in the same
plane, and the allowable flatness shall be no more than 1mm;
c) The central line of the insulation bushing shall coincide with that of the
hoisting rod, and the deviation between them shall be no more than 10mm.
5.4.4.8 The erection of the big framework for cathode shall meet the following
requirements:
a) The big framework for cathode shall be vertical to the level surface, and the
allowable deviation in verticality is 1/1000 of framework height, and shall not be
more than 10mm;
b) In the same electric field, the central lines of two big frameworks shall be in
the central plane along the air flow direction of the field, and the deviation in flatness
shall be no more than 5mm, the distance deviation is 2.5mm.
5.4.4.9 The erection of the small framework for cathode shall meet the following
requirements:
a) After welding, the flatness deviation of the small framework for cathode shall
be no more than 10mm, and the length difference for two diagonal lines shall be no
more than 5mm; and one shall have suspension check and calibration for the
combined small framework for cathode if it is necessary;
b) The cathode line tensions shall be even and proper, and the small framework
shall not deform due to combining the cathode line;
c) After combination, all bolts and nuts on the small framework and cathode lines
shall go through standstill welding, and it shall be free from burrs at the welding
points.
5.4.4.10 The anode plate and small framework for cathode shall be erected to be
vertical to the level surface, and the deviation in verticality is 1/1000 of the height,
and will not be more than 10mm; in the whole channel, the distance deviation
between the same poles and that between different poles shall be no more than 10mm;
after installing cathode and anode system, all positioning part and fasteners shall be
welded firmly, and the materials and specifications for all fasteners shall meet design
requirements;
5.4.4.11 The erection of vibrating system shall meet the following requirements:
a) The vibrator shall be fixed firmly, for those using top vibrating way, they shall
be able to rise freely, and the hook is flexibly, the vibrating hammer shall beat in the
center of the hammer stand, and the allowable deviation is 3mm;
b) For those using side vibrating way, the levelness deviation of its vibrating
shaft shall be no more than 1.5mm, and the coaxiality deviation shall be 1mm
between two adjacent bearing stands, and be 3mm in the whole length;
c) The contacting position deviation for the hammer and bearing anvil for side
vibrating way will be 2mm in horizontal direction and 5mm in vertical direction;
d) The contacting way between the hammer and the bearing anvil shall not be
points, and the linear contacting length shall be more than 2/3 the hammer thickness;
e) The hammer shall rotate flexibly, not blocked, free from collision.
5.4.4.12 The erection of the casing and ashpit shall meet the following requirements:
a) The spoiler for the electric dust arrestor, air flow distributor (deflector,
distributing plate, etc) must be erected in accordance with design requirement;
b) The casing and ashpit must be welded in accordance with design requirement,
after welding, they will go through test by permeating oil, then they will go through
air tightness check as a whole;
c) The inlet and outlet flange and various door holes shall be tight;
d) The electric heating unit for the ashpit must go through Power On test before
heat insulation, and it must be ensured to be perfect; for the steam heater used, its
pipes and accessories must meet design requirements, before heat insulation, it must
go through a water-pressure test with a pressure not less than 1.25 times of working
pressure;
e) The heat insulation can be conducted only after all work and tests in the
insulation layer are completed, and the laying of heat insulation layer must follow the
technical documents of the equipment.
5.4.4.13 After the air leakage test for the electric dust arrestor is qualified, one can
have cold air distribution test, and make necessary adjustment based on the testing
results; the criteria of the air distribution evenness at inlet fracture shall meet The
Electric Dust arrestor for Coal Power Plant (DL/T514-93) and the technical
document of equipment;
5.4.4.14 After erection of the electric dust arrestor, one shall carry out internal cleaning and
check, the inside shall be free from any foreign matters, and the provisional fixing iron parts shall
be cut away, and ground to be smooth. After it is checked to be qualified, certificate for that shall
be signed, and the manhole shall be closed or it shall be locked with padlock; when the electric
parts are erected, pressure-increasing test shall be carried out under dry load with power
on.
heater shall pass hydraulic pressure test with a pressure of 1.25× working pressure;
6.3.3.2 The oil returning pipe placed at lower level shall be led to the tank center
and lifted, so as to avoid short circuit in oil supply;
6.3.3.3 The opening and closing of the inspection hole and fuel-measuring hole shall
be flexible, and the washer on the faying surface shall be tightened firmly;
6.3.3.4 The buoy of the fuel level measuring unit shall pass tightness test, and the
two guiding rails of the buoy shall be parallel to each other and are in the same
vertical plane, the steel wire joint connecting the buoy shall be firm, and the up and
down movement of the buoy shall be unblocked;
6.3.3.5 The surface of the fuel level scale shall be flat, the graduation shall be
accurate, and the color is clear, the up and down movement of the pointer shall be
unblocked;
6.3.3.6 The circulating part of the fire preventor, breathing valve and relief valve
shall be unblocked, the breathing valve surface shall be tight and not be stuck, its
material and weight must be in compliance with the drawing; for the relief valve,
before the fuel tank receiving fuel, it shall be filed with fuel, and record shall be made
for that;
6.3.3.7 The erection position deviation of the rotary siphon bolt shall be no more
than 5mm. After erection for the siphon bolt, rotation test shall be made, and the
rotation shall be flexible, the rotation angle indication shall be correct, and the rotating
part shall be sealed well.
6.3.4 The erection of the pipes connected with the tank shall be conducted after the
foundation is settled and tested to be acceptable.
(a) Diagram for clearance between the shaft journal and bush at top and both ends;
(b) Diagram for clearance between shaft bush end and baffle ring
1) The contacting angle between the shaft journal and working bush surface is
45~90, to check the working bush surface with color mark, and the contact shall be
no less than 1 point/cm2;
2) When the shaft journal is in the assembled bush, the fitting clearance shall
generally meet the requirements of Table 7.2.3.2; at the rotating direction of the shaft,
it shall have longitudinal oil guiding slot at the bush mouth.
qualified, the testing pressure is 1.25 × of the max. pressure of the cooling water
used;
7.2.5.3 The spacing washers between the bearing seat and platen shall be no more
than 3 (excluding the isolating pieces), the area of the washer shall be no less than the
bearing surface of the bearing seat;
7.2.5.4 Radial clearance between the shaft and shaft sealing collar shall be in
accordance with the technical documents of the equipment, the peripheries shall be
even; generally the radial clearance is 1.5~2.0mm for sliding bearing, and 0.3~0.6 mm
for rolling bearing; the sealing root shall be firmly inserted into the slot, contact
evenly with the shaft with proper tightness;
7.2.5.5 The oil content for rolling bearing using lubricating grease shall generally
not be more than 2/3 of the volume of the whole bearing chamber for low speed
machine, and shall be no more than 1/2 for machine with a speed of more than 1500
r/min;
7.2.5.6 The fuel level meter shall be firmly fixed, and shall not have oil leakage; the
upper end of the level meter shall be open to the atmosphere; the breather of closed oil
chamber shall be clean and unblocked; for various fuel level meters on mechanical
units, one shall re-measure the graduations of them during erection; the rollers at
bottom of the rolling bearing shall be immersed in fuel 1/3 ~ 1/2;
7.2.5.7 The oil ring shall be in normal round shape, and the ring shall have even
thickness, the surface is smooth, the interface is firm, the oil ring is unblocked in the
slot; generally the fuel liquid immerses 1/4 of the oil ring diameter.
7.2.6 The erection of the shaft coupling (back wheel) shall meet the following
requirements:
7.2.6.1 The couplings shall be used in pair, better not use them in serial;
7.2.6.2 When assembling the couplings, never place in washers or impact and beat
the shaft to get tight;
7.2.6.3 When centering two coupling halves, generally, the allowable deviation in
their peripheries and ends (i.e. max. difference between clearances measured at two
ends of the diameter) can follow Table 7.2.6.3:
7.3.5.4 The erection and alignment of the reductor shall meet the following criteria:
a) The clearance between the reductor and base frame’s contacting surfaces
(before tightening bolts) shall be less than 0.1mm, otherwise, the contacting surface
shall be treated, and no cushions shall be added in between the contacting surfaces;
b) The central line deviation for reductor and base frame shall be 0.4 mm;
c) The allowable deviation for the levelness at top of the reductor shall be less
than 0.2/1000;
d) The upper plane of the sliding guideway shall be in equal height and flush, and
flush with the platen supporting surface; between the guideway and platen, it shall not
have any projecting welded seam joints, otherwise, they shall be buffed to be flush.
7.3.5.5 The erection and alignment of the base shall meet the following criteria:
a) The upper plane of the base and the bottom plane of primary air chamber shall
be straight and flat;
b) The levelness deviation for the upper plane of the base shall be less than
2mm/m, and the levelness deviation for the machined surface of the bearing ring shall
be less than 0.1mm/m;
c) The concentricity deviation of the upper bearing ring on the base and center of
output flange of the reductor shall be less than 0.3mm/m;
d) The deviation in elevation of the upper plane of the base is 0~10 mm;
e) No clearance is allowed between the contacting surfaces of plate at top of
anchoring seat and the frame plate, otherwise, the plate shall be adjusted.
7.3.5.6 The erection and alignment of the labyrinth (sealing unit) and driving disk
(yoke) shall meet the following criteria:
a) It shall not have any clearance between the contacting surfaces of the
reductor’s output flange and the driving disk (yoke);
b) The radial clearance deviation between the reductor’s output flange and the
driving disk (yoke) rabbet shall be less than 0.05mm;
c) For the clearance of labyrinth sealing, the radial one is 0.1 ~ 0.25 mm, and the
clearance deviation for both sides shall be less than 0.05mm;
d) The clearance between the driving disk (yoke) and upper ring of the labyrinth
is 1.5 ~2.5 mm;
e) For the clearance between the base sealing ring and labyrinth, the radial
deviation at both sides shall be less than 1mm;
f) When tightening driving disk (yoke), the tightening torque shall be in
accordance with the technical documents of the equipment, the record shall be made.
7.3.5.7 The erection and alignment of the milling ring (disk), housing and nozzle
shall meet the following criteria:
a) It shall have no clearance between the contacting surfaces of milling disk and
driving disk (yoke);
b) The central deviation for the upper part of the housing shall be less than 3mm,
and the deviation in elevation is 0 ~ 10 mm, the levelness deviation shall be less than
0.1/1000;
c) For the radial clearance between the nozzle ring and milling ring, and the axial
clearance between the nozzle ring and the section flange of the milling ring, the
deviation for both shall not be 0.5mm respectively.
7.3.5.8 The erection and alignment of the milling roller and lower pressing ring
(support) shall meet the following criteria:
a) The tips of the positioning bars (aligning bars) for the three milling rollers join
at one point, and coincide with the center of the coal pulverizer, the deviation in
elevation and center shall be no more than 3mm;
b) The clearance between the pressing ring (support) guiding plate and tangential
supporting plate shall be even, it can be adjusted by adding shims on the bearing plate
of the tangential support at the housing.
7.3.5.9 For the erection of the lubricating and hydraulic system (including oil
thinning station and hydraulic station), in addition to the technical documents of the
equipment, it shall meet requirements in Clause 7.3.1.28 ~ 7.3.1.37 and 7.3.4.10;
7.3.5.10 For sub-item commissioning, in addition to the technical documents of the
equipment and Clause 7.2.11 of this Code, it shall meet the following requirements:
a) This coal pulverizer shall not be started and commissioning at cold state, but
after the boiler starts and goes commissioning and before putting in coal;
b) Before sub-item commissioning, one shall commission the lubricating and
hydraulic system to be qualified, and the relief valve for oil pump shall be adjusted to
be qualified;
c) To check and calibrate once the instruments, so as to ensure safety, reliability
and correct indication;
d) One can have air tightness test for the coal pulverizer when commissioning the
primary air blower and sealing air blower, and the testing pressure is 0.1 MPa, after
the check is qualified, the certificate shall be signed.
7.8.3.3 There shall be a 1 ~ 1.5 mm clearance at the matching point of the bushes,
and a soft metallic shim shall be added between them;
7.8.3.4 The oil-filling hole on the bush shall be clean and unobstructed.
7.8.4 The assembling of the piston shall meet the following requirements:
7.8.4.1 The piston ring shall go through light-passing check in the cylinder, and the
points where light passes shall be no more than two, and the distance between the
light-passing point and the foreshaft of the piston ring shall be more than 30 arc
length (except for plastic ring); or if one checks with a 0.05 mm feeler gauge the
clearance between the piston ring and the cylinder wall, the gauge can not enter;
7.8.4.2 The lateral distance of the piston ring in piston seat slot shall be 0.05 ~ 0.10
mm, and the matching clearance of the piston ring shall be in accordance with the
technical documents of the equipment, generally, it is 3/1000 ~ 5/1000 of the piston
diameter; for the piston rings of the same piston group, the matching positions shall be
90 ~ 120 misaligned;
7.8.4.3 The connection between the piston and piston rod, piston rod and cross head
shall be firm, and they can swivel flexibly, but not loose; the locking unit shall not be
loose, and the oil hole shall be unblocked;
7.8.4.4 To check the clearance at dead points at both ends of the cylinder by way of
lead pressing, so as to verify the travel of the piston, and the value shall be in
accordance with the technical documents of the equipment.
7.8.5 The assembling of the air-distributing component shall meet the following
requirements:
7.8.5.1 The positions of the air inlet and outlet valves shall be correct, and the
contact between the valve diaphragm and valve seat shall be tight; kerosene will be
used to check the oil leakage, which shall be no more than 2 drops/min; the valve
diaphragm spring tensions shall be consistent, and the travel of valve diaphragm shall
be in accordance with the technical documents of the equipment, generally, it is 3 ~
4mm;
7.8.5.2 The valve cap bolts shall be tightened evenly, the back cap shall be locked;
the cylinder cushion (copper cushion or asbestos rubber cushion) shall be coated with
black lead powder;
7.8.5.3 The air filter shall be clean and good for using, before assembling, it shall be
coated with viscous oil in accordance with the technical documents of the equipment.
7.8.6 The levelness of the unit body will be based on the shaft journal and the main
faying surface, and the deviation in longitudinal and transversal direction shall be no
more than 0.15/1000 of its length.
7.8.7 The erection of oil system shall be in accordance with the technical documents
of the equipment, and guarantee each component (oil pump, oil tubes, oil valve, oil
filter, etc.) to be clean, unobstructed, tight, and free from leakage, the oil tubes shall
be free from sharp bending or folded flat, etc.
7.8.8 The intermediate cooler and gas accumulator shall pass hydraulic pressure test,
the test pressure shall meet the requirements of Table 7.8.8.
Table 7.8.8 Test Pressure MPa
Working pressure p Test pressure Working pressure p Test pressure
1.25p but no less than
0.49 1.5p but no less than 0.2 > 0.49
p+0.3
7.8.9 The pressure gage shall be mounted at a point with small vibration amplitude,
and shall be fixed firmly.
7.8.10 The sub-item commissioning, in addition to the technical documents of the
equipment and Clause 7.2.11 of this Code, shall also meet the following requirements:
7.8.10.1 When rotating it by hand, the rotation shall be easy to operate and free
from blockage;
7.8.10.2 The unloading valve and relief valves at different levels shall be sensitive;
7.8.10.3 The commissioning of the air compressor under dry load shall meet the
following requirements:
a) To remove air absorbing and discharging valves of different stages;
b) Start up the compressor, then stop it, check all components, check it, after
confirming it has no abnormal signs, run it in sequence 5, 30 min and 4 ~ 8h, the
lubrication shall be normal;
c) During the running, no abnormal sound is allowed, and the fasteners shall
remain secure;
d) The rising in the oil pressure, oil temperature and at the friction parts shall
meet design specification.
7.8.10.4 The commissioning of compressor under the air load shall meet the
following requirements:
a) One air filter is first installed, then air suction and exhaust valves are mounted
gradually, start the compressor to conduct purging; start from stage I, connect stage by
stage to purge, till the air exhausted is clean, but the purging time at each stage shall
be no less than 30min, the purging pressure at different stages shall be in accordance
with the technical documents of the equipment;
b) After purging, one shall dismount air absorbing and exhausting valves of
different stages and purge them to be clean, and check whether it has any damage;
c) To run 1h when the air exhausting pressure is 1/4 rated pressure, run 2h at 1/2
rated pressure and 2h at 3/4 rated pressure, the running time under rated pressure shall
be in accordance with the technical documents of the equipment.
7.8.10.5 Check each component in accordance with the technical documents of the
equipment, and make record, after the test is qualified, the lubricant shall be replaced.
25mm × 25mm;
b) The centers of the piston cylinder, piston rod sealing box and cross head shall
be in the same line;
c) The thread fitting of the piston rod and cross head slider shall be good, and the
cross heat thrust bolt shall have no looseness;
d) The lubricating oil hole in the crosshead slider shall be unobstructed.
7.9.2.3 The oil-water separating tank, Z shaped pipe, valve box and oil box must
meet the following requirements:
a) The welding of the oil-water separating tank shall be in perfect state, and the
welding shall be firm;
b) The insides of oil-water separating tank, Z shaped pipe, valve box and oil box
must be clean and without any foreign matters;
c) The flange faying surface shall be cleaned to be clear, and the sealing ring
shall have no damage;
d) The valve box surface shall have no gas porosity, sand hole and crack;
e) The spring for the valve spring shall have no defect, and the spool as well as
the sealing surface shall be free from damage and opened parts, etc.;
f) All valves on the oil-separating pump body shall be lapped and pass hydraulic
pressure test;
g) The outlets of the oil observing valve, oil level observing valve, mud slurry
observing valve shall be in the same direction, otherwise they shall be adjusted with
shims.
7.9.2.4 To check the air tank:
a) The faying surfaces of flanges shall be perfect and without damage;
b) The pressure gage adaptor shall be cleaned to be clear;
c) The explosion-proof sheet in the air tank shall pass pressure explosion test;
d) The tank body shall pass hydraulic pressure test.
7.9.2.5 For the erection of the oil insulation pump, the levelness in longitudinal and
transversal direction shall be no more than 0.1 mm/m;
7.9.2.6 The mounting of the motor shall be based on the oil insulation pump, and the
parallelism between the motor shaft and speed variator’s active shaft shall be no more
than 0.15 mm, and the wheel slot for the pulley of motor and speed variator shall be in
the same plane;
7.9.2.7 When mounting the outer supporting bearing for the motor of the oil
separating pump, it shall be concentric with the two bearings in the motor;
7.9.2.8 The exhaustion valve, oil replenishing valve of the oil-water separating tank
and the pipes o the oil tank shall be firmly connected;
7.9.2.9 Air accumulator shall be furnished on the inlet pipe of the oil-insulating
pump;
7.9.2.10 For the sub-item commissioning of the oil-insulating pump, it shall meet
the following requirements:
a) The pump body and attachments all have been installed, and accepted to be
qualified;
b) The ash handling system is mounted, and can be put into operation;
c) The sub-item commissioning for the air compressor has been qualified;
d) The sluicing pipe is unobstructed (generally one shall use pumped water from
high-pressure cleaning pump to check);
e) The flushing of the inlet pipe for the oil-insulating pump has been qualified;
f) To rotate by hand the unit, it shall rotate steadily and without blockage.
7.9.2.11 For the sub-item commissioning of the oil-insulating pump, in addition to
Clause 7.2.11 of this Code, it shall also meet the following requirements:
a) Before commissioning of the oil-insulating pump, the valve on the outlet pipe
shall be in fully opened state;
b) The commissioning will be carried out in two steps, i.e. commissioning with
clean water and that with grout;
c) Before starting the pump, one shall adjust the oil-water boundary surface for
the separating tank in accordance with the method specified by the manufacturer;
d) After starting the pump, the oil-water boundary surface for the separating
tank shall be adjusted;
e) During the commissioning, the fluctuation at the boundary surface shall be
frequently checked and exhausted air and replenished oil;
f) The commissioning with clean water shall be no less than 4h;
g) When feeding grout, the grout’s grainness shall be in accordance with the
technical documents of the equipment;
h) The outlet pressure for the pump when water comes out from the pipe, outlet
pressure of the pump when the grout comes out from the pipe, and change in outlet
pressure of the pump caused by change in grout concentration shall be recorded.
Machine
8.3.1 The erection of the plow-type coal unloader shall meet the following
requirements:
8.3.1.1 The coal unloader shall be flexible, the weight hammer is at a proper
position, and can unload the coal completely;
8.3.1.2 The coal unloading section shall be straight and flat, and meet design
requirements.
8.3.2 The coal-unloading platform is accepted and checked, and meets Appendix P.
8.3.3 The erection of the coal-distributing vehicle and the track for impeller-type
coal poker shall meet the following requirements:
8.3.3.1 The track shall be firmly and reliably connected with the framework, and the
datum deviation of the track surface shall be no more than 10 mm;
8.3.3.2 The track shall be flat and straight, the bending fluctuation shall be no more
than 1/1000 of the length, and not be more than 5mm for the whole length;
8.3.3.3 The difference in relative elevations at top of two tracks shall be no more
than 3mm;
8.3.3.4 The deviation in track distances shall be no more than 2mm;
8.3.3.5 The clearance at track joints shall be no more than 3mm.
8.3.4 The distance between wheels of the coal-distributing vehicle and the
impeller-type coal poker shall be compliant with the track distance, and it shall have
no blockage between the wheels and the steel track.
8.3.5 The distance from the impeller of the impeller-type coal poker to the platform
shall meet design requirement, and the impeller shall not come into collision with the
platform.
8.3.6 For the sub-item commissioning of the coal-distributing vehicle and the
impeller-type coal poker, in addition to Clause 7.2.11 of this Code, it shall also meet
the following requirements:
8.3.6.1 The to-and-fro travel along the track shall meet design requirements;
8.3.6.2 Each operation shall be flexible and correct, and can stop at predetermined
position;
8.3.6.3 During running, the wheel contacts well with the track, and it is free from
lifting-up and edge-engagement phenomena;
8.3.6.4 The vibration amplitude of the mechanical components shall be no more than
0.2 mm;
8.3.6.5 It shall have no eccentricity when the tape is passing the coal-distributing
vehicle.
8.4 Magnet Separator
8.4.1 The magnet separator can be erected only after it is checked to be qualified by
an electrician.
8.4.2 The erection angle of the magnet separator and the distance between the
attracting iron surface and adhesive tape surface shall meet the design requirements,
and their hanging units shall be firm.
9.2.6 The grouting agent for various refractory concretes shall meet the following
requirements:
9.2.6.1 The silicate cement, common silicate cement shall meet The Silicate Cement,
Common Silicate Cement (GB175-92), the slag silicate cement shall meet The Slag
Silicate Cement, Volcano Ash Silicate Cement and Fine Coal Ash Silicate Cement
(GB1344-92);
9.2.6.2 The high-alumina cement shall meet The High-alumina Cement (GB201-81);
9.2.6.3 The phosphoric acid shall meet The Industrial Phosphoric Acid (GB2091-92),
it has phosphoric acid of 85%, and when using, it shall be thinned to desired
concentricity by adding water;
9.2.6.4 Water glass (i.e. sodium silicate) shall meet the requirement on four classes of
products in The Sodium Silicate (GB4209-84); its modulus shall be no less than 2.2,
and the specific weight Be (at 20C) shall not be lower than 39.
9.2.7 The aggregates for refractory concrete, generally, shall be clay refractory brick
pieces, sintered clay grog or sintered alumina grog, but for furnace wall at special
positions (e.g. base wall for liquid deslagging furnace, liner for cyclone furnace, etc.)
shall be in accordance with the technical documents of the equipment; the items to be
inspected for various aggregates are shown in Table 9.2.7.
Table 9.2.7 Inspection Items for the Aggregates for Refractory Concrete
Sintered clay sintered alumina
Item Refractory clay brick piece
aggregate aggregate
Volume weight
Refractoriness
Grainness
Al2O3 content
9.2.8 The silicate cement refractory concrete, slag silicate cement refractory
concrete and water glass refractory concrete shall be added with mixing agents, those
with a fineness less than 0.088 mm shall be more than 70%; other technical conditions
and inspection items for various mixing agents are the same as that for its aggregate.
Note: for the slag silicate cement refractory concrete with a limit using temperature of 700C, if the slag content is
more than 50%, it can go without adding mixing agents.
Table 9.6.5 Allowable Deviations for Furnace wall in which Tubes are Laid
mm
No. Inspection item Technical requirement Allowable deviation
1 Flatness after plastering surface Not more than per meter 5
Single layer 5
2 Thickness +15
The whole wall
-10
9.7.1.2 The max. grain size of grout shall be less than 50% of the seams between
bricks;
9.7.1.3 The refractory grout mixed manually shall be soaked one day and night by
water;
9.7.1.4 The viscosity of grout shall be selected based on the seams between bricks;
9.7.1.5 The grout shall be clean, but have no foreign matters and inflammable
articles.
9.7.2 The general requirements for masonry for boiler are:
9.7.2.1 The allowable deviations in seams between bricks for masonry are shown in
Table 9.7.2.1;
9.7.2.2 For the refractory brick in the furnace wall, broken brick with a length less
than 1/3 shall not be used; for each layer, the amount of broken brick with a length
higher than 1/3 shall be no more than 3;
9.7.2.3 When cutting bricks, special tool or machine instead of hand hammer shall be
used; the surface of broken brick shall be ground flat, and the broken surface and
point with notch(s) shall not be masoned in the surface facing the fire;
9.7.2.4 For laying bricks, generally the turnout left shall be in step type, but not
joints of vertical and tooth shape; only when masoning combined bricks, it is
permitted to leave tooth shaped joints with 1/4 ~1/2 brick length;
9.7.2.5 When masoning refractory bricks on beam, carrier frame or refractory
concrete, it is permissible to align with small amount of refractory plastic material, but
not use soft and loose material to fill the bottom;
9.7.2.6 When laying bricks, the grout seams must be misaligned and seams shall be
pressed, it shall have no vertical through seams between upper and lower layers; when
laying bricks in several layers, it shall not have through seams inside and outside; the
grout of the brick seams must be plump and even;
9.7.2.7 When masoning the brick wall, one shall remove the grout extruded out from
the wall surface from time to time; it shall have no accumulated ash or other foreign
matters in the refractory wall which will block the wall and pipe;
9.7.2.8 Unless specially specified in the technical documents of the equipment,
generally, for the inner wall of refractory bricks and outer wall of heat-insulation
bricks, it is not allowed to have involvement masoning;
9.7.2.9 When laying heat-insulation bricks, for some individual points with notch(s)
or fragment, they shall be filled tightly with grout and small pieces of heat-insulation
materials, the flatness deviation of heat-insulation wall surface shall be no more than
5 mm/m.
9.7.3 The laying of draw-hook bricks shall meet the following requirements:
9.7.3.1 The two draw-hook bricks opposite to each other must be aligned each other,
and its surface facing fire shall be in the same plane with the wall where they are;
9.7.3.2 The end facing fire of draw-hook brick shall be slightly lower, generally it
would better be –10 mm;
9.7.3.3 The clearance between draw-hook bricks and gas pipes shall be filled with
heat-insulation fillers.
9.7.4 When laying the refractory bricks on the brick-supporting board, it shall meet
the following requirements:
9.7.4.1 The wall surfaces of refractory bricks upper and lower the brick-supporting
board shall be in the same plane; and for a furnace wall with combined bricks, the
misalignment between the wall surfaces upper and lower the brick-supporting board
shall be no more than 10 mm;
9.7.4.2 In between the profiled bricks at lower place and the brick-supporting board
and at rear of the profiled bricks, wet heat-insulation fillers shall be filled.
9.7.5 When building the furnace wall at drag hook and latch hook of water-cooling
wall, it shall meet the following requirements:
9.7.5.1 The brick wall shall not block the water-cooling wall’s ear board or influence
the expansion in water-cooling wall;
9.7.5.2 The points near to the drag hook and latch hook shall be carefully filled with
heat-insulation filler.
9.7.6 The masoning of the round arch of the burner shall meet the following
requirements:
9.7.6.1 Before masoning, test match for the arch bricks shall be first had;
9.7.6.2 The allowable deviation and elevation is of the round arch is 5 mm;
9.7.6.3 The extending line of the brick seam for the round arch shall pass the circle
center;
9.7.6.4 When constructing the upper and lower half round arch, the bricks adjacent
to the round arch must be laid at the same time.
9.7.7 The masoning of the arch shall meet the following requirements:
9.7.7.1 The masoning shall be started from both ends toward the center;
9.7.7.2 The extending line of the brick seam for the arch shall pass the circle center;
9.7.7.3 The number of bricks for the arch shall be odd;
9.7.7.4 After masoning the arch, for arch with a span more than 600 mm, the arch
support can only be dismantled at least after 2 ~ 3 hours;
9.7.7.5 The height deviation for arch is 5 mm.
9.7.8 When continuing to lay bricks on the arch, one shall first lay vertical bricks,
whose lower end shall be seamed based on the arc of the arch, and the height of the
vertical brick shall be more than 1/3 brick length, and be consistent with the
horizontal brick seam in corresponding brick layer.
9.7.9 The masoning of suspended bricks shall meet the following requirements:
9.7.9.1 The flatness deviation of suspended bricks shall be no more than 4 mm;
9.7.9.2 When cutting profiled bricks, never weaken the strength at the main force
carrying points, when dressing the hanging holes for suspended bricks, never make
the fitting clearance be more than 5mm.
9.7.10 The masoning of the slant guard plate wall shall meet the following
requirements:
9.7.10.1 Never level the furnace wall by filling grout;
9.7.10.2 The flatness deviation of the slant guard plate wall shall be no more than 4
mm/m.
9.7.11 The masoning of the brick wall for the ash chamber shall meet the following
requirements:
9.7.11.1 The refractory bricks above the water spraying unit of the ash chamber shall
project from the wall surface;
9.7.11.2 The bricks of the slope section for the ash chamber shall not be laid along
the slope direction.
9.7.12 The expansion seam of the brick wall and clearance at different parts shall
meet Clause 9.1.7 and 9.1.8.
9.7.13 The allowable deviation of flatness, levelness, verticality and thickness for
the brick wall shall meet the requirements of Table 9.7.13
Blowpipe coefficient = (steam flow for purging pipe2 ×specific volume of steam when
purging the pipe)/(rated load flow 2 ×specific volume of steam at rated load)
10.5.5.4 The controlling parameters for purging can be calculated in advance or
determined by actual measurement at the purging; while meeting 10.5.5.1 and
10.5.5.2, after opening fully the controlling door and the outlet pressure of the
overheater is up to value in Table 10.5.5.4, generally, it can meet the requirement as
the blowpipe coefficient at different points is more than 1; at this time the
corresponding steam output of the boiler is 60% ~ 70% rated steam output;
10.5.5.5 The pressure dropping when purging steam drum boiler shall be controlled
to be within the range that the saturated temperature dropping is not more than 42C;
10.5.5.6 During the purging process, it shall have at least one cooling with boiler
stopped (for more than 12h), so as to cool the overheater, reheater and their pipes, and
improve the purging effect.
10.5.6 When purging with steam the reheating boiler, one can purge it in one time
(without dividing into different phases) by connecting the primary and secondary
systems in serial (it’s short as ‘one-step’ way), but one must add a particle collector
(garbage collector) on the cool section of the reheating steam; when using ‘one-step’
way, the particle collector must meet the following requirements:
10.5.6.1 The resistance is less than 0.1MPa;
10.5.6.2 The strength meets requirement for parameters of steam;
10.5.6.3 With good performance in collecting foreign matters.
10.5.7 In order to reduce noise pollution to the environment, when have steam
purging for boiler and its pipes of 670t/h, one had better add a silencer at the steam
exhaustion port.
10.5.8 Criteria for purging quality:
10.5.8.1 The blowpipe coefficient is more than 1 for overheater, reheater and their
pipes;
10.5.8.2 At the temporary steam exhaustion pipe at end of the pipe to be purged (or
at steam exhaustion port), to set up a target board, which can be made of aluminum
sheet, its width is about 8%of the inner diameter of the steam-exhaustion pipe, the
length is just to stride longitudinally the inner diameter of the pipe; while
guaranteeing the blowpipe coefficient, check successively twice by replacing the
target board, the grain size of spots on the target board shall be no more than 0.8 mm,
and the amount of spots shall be no more than 8, in this case, one can regard the
purging as qualified.
10.5.9 After flushing and purging the pipes, one shall sort out the record and have
certificate signed.
Fig. 3
Table 5 unit: mm
Thickness of steel plate (S)
1≤S≤4 4≤S≤12 12≤S≤18 18<S
Fig. 4
Table 6 unit: mm
δ1 δ2 δ3
Symbol
L≤300 L>300 H≤250 H>250 h≤300 h>300
+2 +3
Value ≤2 ≤3 ≤3 ≤5
0 0
Fig.5
4.3.3 The deviation of distance l1 and l2 between ribbed plates or baffle plates, and
the abutted gap between the cover and formed steel, see Fig.6 .
Fig. 6
4.3.4 The transverse or longitudinal slant dimension (δ) that the strengthened plate
or the ribbed plate relates to the web (Fig.7), should be not greater than 3 mm, when
the height H is not greater than 600 mm; and should be not greater than 5 mm, when
H is greater than 600 mm.
4.3.5 The dimension deviation of full-length L refers to Table 7.
Fig.7
Table 7 unit: mm
Dimension deviation
Name of Full-length of the component L
component 1001~ 3001~ 5001~ 8001~ 10001~
≤1000 >15000
3000 5000 8000 10000 15000
0 0 0 0 +2 +2 +2
Column
-4 -4 -4 -4 -6 -6 -6
Beam,Cross 0 0 0 0 0 0 0
-4 -6 -8 -10 -10 -10 -10
beam
Brace, 0 0 0 0 0 0 0
backbone -3 -3 -3 -4 -4 -6 -8
0 0 0 0 0 0 0
Frame
-6 -8 -10 -12 -12 -12 -12
0 0 0 0 0 0 0
Girder
-3 -5 -6 -8 -9 -12 -12
Table 8 unit: mm
Height of plate beam, H H>3000
H≤1600 1600<H≤3000
Dimension deviation ±3 ±5 ±8
4.4.2 The offset of the web central position refers to Fig. 8, the longitudinal slant of
the web refers to Fig. 9, and the transverse slant of the web, Fig 10.
Fig. 8 Fig. 9
4.4.3 The allowed slant (Δ) of swing plate and the allowed bend (Δ1) of local
buckling (Fig. 11) refer to Table 9 and Table 10.
Table 9 unit: mm
Height of plate beam, H >1600
≤1600
Allowed slant, Δ
≤3 ≤5
Fig. 10
Fig. 11
Table 10 unit: mm
Position occurred bend Within 1mm from two ends Central position
allowed bend, Δ1
≤5 ≤10
4.4.4 The deviation of distance l1 and l2 between strengthened plates or ribbed plates
refers to Fig. 6, the transverse or longitudinal slant refers to Clause 4.3.4.
4.4.5 The allowed deviation of the dimension between two support points of plate
beam is ±10 mm.
4.4.6 The dimension deviation of the full-length of plate beam, L, is ±15 mm to the
main beam, 0/-10 mm to the sub beam.
4.4.7 The local flatness of plate beam web, Δ(Fig.12), should be not bigger than 5
mm within any 1 m2 of surface.
Fig. 12
4.4.8 The side camber of plate beam should be not bigger than the 1/1000 of full
length, and not bigger than 10 mm.
4.4.9 The upward vertical deflection f1 (Fig. 13) refers to Table 11, the downward
vertical deflection f2 (Fig. 13) is not bigger than 5 mm.
Fig. 13
Table 11
4.4.10 The twist of plate beam(Fig. 14), should be not greater than 1/1000 of the full
length of plate beam, and not bigger than 10 mm, when the height of plate beam is not
bigger than 2 m; and not bigger than 1/1000 of the full length of plate beam, as well as
16 mm.
Fig. 14
4.4.11 The dimension error of the height (h) of plate beam top bracket refers to Fig.
15, plane slant of bracket, δ1 and δ2, both of them should not be greater than 3 mm.
4.4.12 The dimension error of the distance(l1) between central line of plate beam top
bracket and reference line(Fig. 17), is ±3 mm, when l1 is greater than 2 mm, and ±5
mm when l1 is bigger than 2 m.
Fig. 15 Fig. 16
4.5 Beam (plate beam excluded)
4.5.1 The dimension error of the full
length of beam refers to Table 7.
4.5.2 Both the side camber and deflection
of beam should be not greater than
1/1000 of the full length of beam, as well
as not bigger than 10 mm.
4.5.3 The twist of beam (see Fig. 14)
Fig. 17 should be not greater 1/1000 of the full
length of beam, as well as not bigger than
10 mm.
4.5.4 The dimension deviation of top bracket height (h) of beam and plane slant of
the bracket refer to Clause 4.4.11.
4.5.5 The dimension deviation of the distance between central line of top bracket of
beam and reference line refers to Clause 4.4.12.
4.6 Column
4.6.1 The dimension error of the full length of column refers to Table 7.
4.6.2 The verticality between base plate and central lime of column refers to Fig. 18.
4.6.3 The linearity of column should be not greater than 1/1000 of the full length, as
well as not bigger than 10 mm.
4.6.4 The twist of column (see Fig. 14) should be not greater than 1/1000 of the full
length of column, as well as not bigger than 10 mm.
4.6.5 The dimension error Δl1 (Fig. 18) of the assemble height (l1) of top bracket of
beam, is ±2 mm, when l1 is not greater than 4 m, and is +2/-4 mm, when l1 is greater
than 4 m.
Fig. 18
4.6.6 The plane slant of top bracket of column refers to Clause 4.4.11.
4.7 Frame and Girder
4.7.1 The dimension error of the full length (L) of frame (include safe plate frame,
top safe plate frame or other rectangle frames) or girder refers to Table 7.
4.7.2 The length error, side camber and deflection of the two diagonals of frame
refer to Table 12.
Table 12 unit: mm
Length of frame side, L L>5000
L≤2500 2500<L≤5000
4.7.3 The side camber and deflection of girder refer to Table 13.
Table 13 unit: mm
Length of girder or table, L L>10000
L≤6000 6000<L≤10000
4.7.4 The intersection point of axes of slant brace of girder should locate on the
cross bar of girder, and the offset of the intersection point Δ1 (Fig. 19) should be not
greater than 10 mm, the position offset of perpendicular bar Δ2 (Fig. 19) should be not
greater than 5 mm.
4.8 Platform and stair
4.8.1 Reliable anti-slip precautions must be made for platform plate, stair and foot
paddle.
4.8.2 The dimension error of platform length is 0/-2 mm over per 1 m, as well as not
bigger than 0/-10 mm.
Fig 19
Fig. 18
Appendix B The reference data for critical temperature of steel
[Excerpt from The Code for Construction and Acceptance of Concrete Structure
Engineering (GB/ 50204-92)]
[Excerpt from The Code for Construction and Acceptance of Concrete Structure
Engineering (GB/ 50204-92)]
≤5 m 5
>5 m, <10 m 10
Verticality
2 Column 1/1000 of marked
≥10 m
height and ≤20
Marked height of
≤5 m 0~-5
shouldered top surface and
column top >5 m 0~-8
Beam and beam of Position of central to positioned axis 5
3
crane Marked height of top surface of beam 0~-5
Position of lower chord central line to positioned axis 5
1/250 of house
4 House frame Girder, arch house frame
Verticality frame height
Thin web girder 5
Position of component central line to positioned axis 5
5 Scuttle frame 1/300 of scuttle
Verticality
frame height
Position of base central line to positioned axis 5
6 Bracket frame
Verticality 10
Levelness of lower surface Plastering 5
7 Plate
between adjacent plates Not plastering 3
Horizontal position 10
8 Stair balcony
Marked height ±5
Position of central to positioned axis 3
Verticality 3
9 Huge wall plate Slant-in(or slant-out) of wall at every floor 2
Verticality over whole height of building 10
Height difference of wall plate butted gap ±5
Appendix E Manufacturing and assembling tolerance of pipe type
[Excerpt from Technical condition for pipe type air pre-heater (JB/T1616-93)]
Fig. 1
4.2.4 The diameter error of tube hole should be not bigger than 1~0 mm.
4.2.5 The dimension error of center distance t, t1, t2 or t3 (Fig.2) between adjacent
longitudinal or transverse tube holes are ±2 mm. The dimension error of center
distances between outermost adjacent longitudinal or transverse tube holes, L or L1, is
±3 mm.
4.3 Tube box
Fig. 2
4.3.1 The dimension error of tube box height is ±4 mm if the tube box height is not
greater than 3 m, and ±6 mm if it is greater than 3 m.
4.3.2 The height difference (h1-h2) between that of any two side arises among four
arises of tube box, h1 and h2 (Fig. 1), should be not greater than 4 mm if the height of
tube box is not bigger than 3 m, and is not greater than 6 mm if the height is bigger
than 3 m.
4.3.3 The dimension error of the distance from intermediate tube plate in tube box to
top tube plate, h3, or to bottom tube plate, h4, is ±4 mm.
4.3.4 Both length error (Δa) of tube box length (a), or width error (Δb) of tube box
width (b), are ±4 mm, if tube box length (a) or width (b) are not greater than 2 m, and
are ±6 mm if greater than 2 m.
4.3.5 The length difference (l3-l4) between two diagonals l3 and l4 (Fig. 1) in side
face between adjacent tube plates of tube box, is not greater than 5 mm, when tube
box height is not bigger than 3 m, and not greater than 10 mm if the height bigger than
5 m.
Appendix F The allowable deviation for outer diameter and wall
Diameter ≤500
2
10 Diameter>500 3
Verticality of pipe flange for flue, air and coal powder
Frame size<1500×1500 3
Frame size 1500×1500~2500×2500 5
11 Frame size 2500×2500 7
12 Height of telescopic node ±5
Length of telescopic seat ±3
Appendix H The allowable deviation for masonry construction
[Excerpt from The Code for Erection and Acceptance of Brick Engineering (GBJ
203-83)]
H.1 The allowable deviation of dimension and position for brick construction
should be in accordance with the definition in Table H.1.
3 ≤10 m - 10 10
Full Check with altometer or
height plumb-line and rule
〉10 m - 20 20
Full height - 30 - 30 - 25 20 15
5 - 20 - 20 - 10 7 5 Check with straight rule with 2 m length and wedge feeler for
Flatness
of plane
[Excerpt from The Code of Erection and Acceptance of Electric Power Construction
(Section of Building Engineering) (SDJ 69-87)]
[Excerpt from The code for erection and acceptance for the installation engineering of
mechanical devices TJ 231(I)-75 Clause 2 appendix 4]
When edge iron group is set on concrete foundation or ground, its area can be
calculated approximately as following:
10 6 (Q1 Q2 )
AC
R
Where,
A – area of edge iron
C – safety coefficient, varies from 1.5~3
Q1 – load on edge iron due to weight of equipment, etc
Q2 – pressure distributed on the edge iron after tighten the ground bolt (using
allowed tensile strength of ground bolt to instead of is permitted), N
R – tensile strength of concrete of foundation or ground (using design brand
of concrete to instead of), Pa
Appendix L End face clearance of flexible cylinder pin coupling
[Excerpt from The code for erection and acceptance for the installation engineering of
mechanical devices TJ 231(I)-75 Table 1-4-6, Clause 61 chapter 1]
Fig. M
Appendix N Axial run-out of main bearing
[Excerpt from The code for erection and acceptance for the installation engineering of
mechanical devices”TJ 231(VI)-78, item 3, Clause 80 chapter 1]
The central line of two hollow spindles should be in a line, measuring at the end face
of main bearing with dial indicator, its axial run-out should be in accordance with the
definition in Table N.
≤5000
0.6 0.8 1.0
>5000~10000 0.7 0.9 1.1
0.8 1.0 1.2
>10000
Appendix P Standard for coal-unloading platform
at coal-unloading outlet
[Excerpt from The code for erection and acceptance for the installation engineering of
mechanical devices TJ 231(IV)-78, chapter 2, vol.1]
[Excerpt from The Guideline for Chemical Cleaning for Boiler of A Thermal Power Plant (SD135-86)]
[Excerpt from Boiler Supervising Instructions for Electric Power Industry (SD
167-85)]
The startup pressure of safety valve should be adjusted and checked according to the
definition in Table T, except that there is special description by manufacturer.
The reverse pressure difference of safety valve should be 4%~7% of startup pressure
in general, and the maximum must be not greater than 10 of startup pressure.
The safety valve should be of good seal function under operation pressure.
165
Appendix U Terminology relative to the rule
(The Appendix for tip)
U.1 Distance error: the allowable deviation of relative dimension between design
centerlines of boiler structure and equipment components during installation (for example,
between columns, beams, water cooling walls and steel structure).
U.2 Length difference between diagonals: the length difference between two
diagonals of designed square or rectangle of boiler structure, equipment component
outer form (for example, foundation, column, furnace chamber, etc.)
U.3 Marked error: the difference between installation height of boiler structure,
equipment component and its design marked height, in general, with reference to 1 m
marked height of steel frame. Each field relative to boiler body (steel frame, metal
structure, heating surface, flow passage, cavity wall heat insulation etc.) should use
the measuring instrument passed measurement certificate rest.
U.4 Parallelism: the parallelism between two lines or planes parallel to each other,
the error of it should be the minimum difference between vertical distance at two ends
of the two parallel lines or planes.
U.5 Verticality: the difference between right angle and the angle between two planes
or axes and plane that should be perpendicular to each other. The error of it denotes
with the angle between the axes or plane and ideal vertical line, or the rate between
unit length of reference vertical line and the minimum distance Δ of the measured line
or plane, for example, Δ/m.
U.6 Relative offset: both the installation position and design center line of two
components (structures pipes etc) are offset, when their directions are opposite,
Relative offset is the sum of the absolute value of two offset. If their directions are
same, but the value is different, relative offset is the difference of the absolute value of
two offsets.
U.7 Concentricity: it indicates that two circle objects installed on the same axis are
needed to con-center (for example, endplate and round tank body, center line of
spindle with hole at both ends and center line of round tank body, journal of rotating
part of air pipe in helicoids air preheater, rotary lamina adjusting device of blower),
the concentricity is the distance between two centers.
U.8 Roundness:the difference between the perimeter (part or local) of a huge round
object (stator or rotator of helicoids air preheater, rotary air shield, shield of blower
etc.) and the perimeter of ideal circle.
U.9 Flatness: the offset of a plane deviating from ideal plane. In case of plane of
equipment (for example water cooling wall), the offset is the distance difference
between two parallel planes indicating its concave and convex; incase of cavity wall
and heat insulation plane, the offset express as Δ/m.
U.10 Radial run-out: dial indicator point to the axis of measured section, rotate the
rotator, the radial run-out is the difference between max. and min. digital among
checking point(usually, divide into 8 points or 16 points)
U.11 Axial run-out: also refers to “end face run-out”, set 2 dial indicators to the
opposite position on a circle with given diameter at end face, turn rotator, the axial
166
run-out is the half of the difference between maximum and minimum digital both the
indicator recorded simultaneously.
U12. Horizontal offset: indicates longitudinal and transverse horizontal center line of
boiler drum, couple box (it is need to check that the horizontal line stroke hole marked
by manufacturer is correct), check the stroke hole in 4 sides are installed in the same
horizontal plane. The height difference between 2 points in longitudinal or transverse
is longitudinal or transverse horizontal offset.
U.13 Ellipticity: the difference between maximum and minimum diameter of
cylindrical spindle or hole (ring) in a transverse section, divided by nominal diameter,
expressed in percentage. The center of ellipse is uncertain, maximum and minimum
diameter may in any direction.
U.14 Levelness: the difference of level between components that are required to
install in the same horizontal plane. Usually, measure the absolute difference between
every point with level rule, leveler or “U”-shaped pipe.
167
Appendix V Description on words in the rule
(The Appendix for tip)
V.3 Word for recommendation, and that has some choice, should do so primarily if
there is the condition:
For positive, use word “would better” or “can”; for negative, use word “should
not” or “may not”
V.4 For some standard data, the word “generally” means the summary value when
there is not data provided by manufacturer or from design.
168