Sunteți pe pagina 1din 3

Cable-stayed bridge completed

across James River


Twin box girder concept
saves time and materials

BY M.K. HURD

View from above, looking down


toward the James River, shows how
13 cables thread through the pylon to
support points in the deck. The 126-
foot-wide deck is composed of two
58-foot girders, typically 10 feet
apart. The center space is occupied
by precast delta frames and a cast-in-
place slab over the 1,530-foot
continuous length of the main
structure.

he newly completed cable- Now, howe ve r, bid results on the construction processes provide the

T stayed box girder bridge


over the James River near
Richmond, Virginia, has a
630-foot main span that is expect-
ed to set a new trend in the devel-
James River Bridge suggest that the
cable-stay concept may have con-
siderable merit in the 500- to 700-
foot span range. When bids were re-
ceived in February 1985, all were for
key to success of this moderate span
cable-stay. Cost-effectiveness of the
project rests on maximum repeti-
tiveness in both casting and erec-
tion operations. Identical precast
opment of cable-stay bridges. The the concrete scheme and none for box girder sections—a trapezoid
six-lane bridge is part of the Vir- the steel alternate. The low bid of with wide flanges or wings at the
ginia Department of Tra n s p o rt a- $34 million was 20% below esti- t o p — we re used for the entire
tion’s plan for an I-295 bypass east mates for the steel design and b ri d g e, including approach spans
of the state capital. Overall length of brought the bridge cost to about $75 and the cable-stayed center section.
the structure is 4,680 feet. per square foot of deck. Final price Twin girders, each 58 feet wide,
Historically the cable-stay con- is now reported at $35.6 million, less make up the parallel roadways of
cept has been used for long spans of than 5% above the bid price. the bridge. By means of precast
800 feet or more—a range in which t ra n s verse frames, referred to as
the unstayed box girder cross sec- Why so cost-effective? delta frames, placed between the
tion is too heavy to be competitive. Simplified design concepts and twin box girders at the section
where the stays are anchored into
the deck, loads from both girders
are transferred to the center plane
of suspension. Two single-shaft py-
lons carry the system of 13 stays
along the longitudinal axis of the
structure. This scheme requires less
material than an equivalent single
deck on the full width, and the
investment in special equipment
is significantly reduced, creating
advantages in the speed of
construction.

Precasting simplified
The concept of repetition was
carried through from the pile foun-
dations to the main span erection
c yc l e. In precasting, only four basic
shapes—box piers, box girder seg-
ments, pylons, and delta frames—
were produced. Variations in each
of these shapes were typically limit-
ed to items such as blockouts, num-
ber of post-tensioning ducts, and
type of deviation saddle for the ex-
ternal post-tensioning system. Even
the stay anchorage segments of
the main span were distinguished
only by the addition of an internal
diagonal strut.
Concrete for the project was sup-
plied by three local production
plants and delivered to the job
in ready mix trucks. Most of
the concrete was specified at 5500
psi, with 4500 or 6000 psi in a few
Twin box girders 10 feet apart are supported by a series of
transverse precast delta frames. Using the delta frames (see special areas.
closeup in the photo) made it possible to have identical box Using a long bed form, the box
girder units in both the approach spans and the main spans. girder segments were match cast.
That is, each segment was cast
against the one which would be
next to it in the erected position, to
assure a good fit of the adjoining
pieces of precast.

Substructure and pylons


Foundations for the bridge rest
on 24-inch-square prestressed dri-
ven piles with 250-ton service load
capacity. Using the high-capacity
piles reduced both the number of
piles and the size of the footings.
Typical foundations have 10 or 12
piles. However the combined foot-
ings for the main span piers and py-
lon are supported by 88 piles.
The box piers, varying from 64 to
144 feet tall, are made up mostly of
14-foot-high precast segments, 8x18 of the main span. The stays, made of and cast-in-place closures were
feet in cross section. They were from 72 to 90 strands, 0.6-inch in di- made at the top and bottom con-
stacked, several at a time, with ameter, are continuous through the nection points.
epoxy in the joints and then ve rt i- towers, passing through a curved After this closure concrete had
cally post-tensioned. steel pipe. Stays range from 92 to reached 2500-psi strength, post-
The towers or pylons which sup- 620 feet in length. The design per- tensioning took place, and then
port the two-single planes of stay mits future replacement of any one the stay was threaded from one an-
cables were cast in place from the stay while maintaining traffic on the chorage through the polyethylene
footing to roadway elevation, using bridge. stay pipe up over the pylon and back
a climbing form. Then precast pylon The main span of the bridge was down to the other anchorage.
segments were hauled over the al- built by cantilevering precast girder Stressing of the stay completed the
ready erected roadway and lifted in- segments from each pylon and fi- erection cycle for a 20-foot-long,
to position by crane. nally making a short closure pour 126-foot-wide section of the bridge.
when they met at the middle of the Experienced crews completed such
Approach span erection river. The main-span segments were a cycle in less than a week.
The span-by-span erection 10 feet long, a length selected for
method was used for the 150-foot compatibility with lifting equip- Completion of the structure
approach spans. Each span consists ment and the 20-foot spacing of stay Work on the James River Bridge
of seven typical segments each 20 began in April 1985, and the last
feet long, with a 6-inch cast-in-place cantilever segment was erected in
WHAT DOES $35 MILLION BUY?
closure and a diaphragm segment May 1989. Filling the remaining 1-
over the pier at each end. Triangu- foot-4-inch gap with cast-in-place
lar erection trusses were first According to the bridge designer, concrete completed the structure.
brought into position for a given Figg and Muller Engineers, the The James River Bridge will be-
span. Then each of the 140-ton box James River Bridge weighs come the cornerstone of the I-295
girder segments was hauled over the 140,660 tons. This includes connection from Richmond to Pe-
previously completed deck and low- tersburg, reducing congestion for
ered onto the trusses by long-stroke 66,648 cubic yards of commuters and through traffic
h yd raulic jacks. concrete alike. Its presence has already stim-
The girder segment that goes over 7,826,425 pounds of reinforc- ulated industrial and residential de-
the pier was placed on its bearing ing steel velopment in previously isolated ar-
and aligned. Then abutting faces of eas on each side of the ri ve r, and it
3,568,382 pounds of prestress-
the girder segments were coated will become a gateway to the city for
ing/post-tensioning
with epoxy before they were post- navigation traffic on the ri ve r.
tensioned together using four tem- steel
p o ra ry stressing bars. The contrac-
tor then formed and cast the 6-inch And if all the steel wires, bars, and Credits
closure at either end of the span. rods were laid out end-to-end, Owner: The State of Virginia, Depart-
Once the cast-in-place concrete had they would reach from New York ment of Transportation, Richmond,
to Los Angeles and back...and Virginia
reached 2500 psi, the entire span
could be post-tensioned to com- then some! A total of 6,517 miles. Designer: Figg and Muller Engineers,
Inc., Tallahassee, Florida
plete the span erection and make
Contractor: A joint venture of S. J.
the span self supporting. The post- Groves and Sons Company, Min-
tensioning tendons were arranged anchorages at the deck level. neapolis, Minnesota, and Kiewit East-
in a draped configuration on the The main span erection was just ern Company, Omaha, Nebraska
outside of the concrete girders. as repetitive as that of the approach
These previously erected approach spans, but the segments were Acknowledgment
spans provided considerable stabil- brought in by barge and lifted indi- Much of the information on which this
ity during erection of the main span. vidually from river level. For each story was based comes from a draft
20-foot length of bridge the cycle in- prepared by James Farris of the Vir-
Main span erected by volved the following steps. First one ginia Department of Transportation
cantilever method 10-foot box girder segment per lane and W. Denney Pate of Figg and
Muller Engineers, Inc.
The 630-foot main span provides was lifted, coated with epoxy at the
145 feet of vertical clearance and end, and secured by post-tension-
300 feet of horizontal clearance, ing. Next a stay anchor segment for
thereby allowing unrestricted navi- each lane (also 10 feet long) was lift-
gation in the shipping channel. The ed, coated with epoxy, and secured PUBLICATION#C890775
two 300-foot-tall pylons each sup- by post-tensioning. Then the pre- Copyright © 1989, The Aberdeen Group
port 13 cable stays for suspension cast delta frame was lifted into place All rights reserved

S-ar putea să vă placă și