Documente Academic
Documente Profesional
Documente Cultură
BY M.K. HURD
he newly completed cable- Now, howe ve r, bid results on the construction processes provide the
Precasting simplified
The concept of repetition was
carried through from the pile foun-
dations to the main span erection
c yc l e. In precasting, only four basic
shapes—box piers, box girder seg-
ments, pylons, and delta frames—
were produced. Variations in each
of these shapes were typically limit-
ed to items such as blockouts, num-
ber of post-tensioning ducts, and
type of deviation saddle for the ex-
ternal post-tensioning system. Even
the stay anchorage segments of
the main span were distinguished
only by the addition of an internal
diagonal strut.
Concrete for the project was sup-
plied by three local production
plants and delivered to the job
in ready mix trucks. Most of
the concrete was specified at 5500
psi, with 4500 or 6000 psi in a few
Twin box girders 10 feet apart are supported by a series of
transverse precast delta frames. Using the delta frames (see special areas.
closeup in the photo) made it possible to have identical box Using a long bed form, the box
girder units in both the approach spans and the main spans. girder segments were match cast.
That is, each segment was cast
against the one which would be
next to it in the erected position, to
assure a good fit of the adjoining
pieces of precast.