DURATION (201 CALENDAR DAYS)
DESCRIPTION Dec 21-31 January 1-31, 2017 February 1-28, 2017 March 1-31, 2018 April 1-30, 2018 May 1-31, 2018 June 1-30, 2018 Jul 1-9

Project Manager 1 1 1 1 1 1 1 1
Structural Engineer 1 1 1 1 1 1 1 0
Project Engineer 1 1 1 1 1 1 1 1
Site Engineer 1 1 1 1 1 1 1 1
Safety Engineer 1 1 1 1 1 1 1 1
Construction Foreman 1 1 1 1 1 1 1 1
Payloader Operator 1 1 1 1 0 0 0 0
Dumptruck Operator 1 1 1 1 0 0 0 0
Backhoe Operator 1 1 1 1 0 0 0 0
Heavy Equipment Operator 0 0 0 1 1 0 0 0
Transit Mixer Operator 0 0 0 0 1 1 1 0
Water Truck Driver 0 0 0 0 1 1 1 0
Carpenter 4 4 4 4 4 2 2 0
Steelman 6 6 6 6 6 4 4 0
Mason 0 0 0 4 4 4 2 0
Laborer 8 8 8 14 14 14 14 6
Warehouseman 1 1 1 1 1 1 1 1