Documente Academic
Documente Profesional
Documente Cultură
discussions, stats, and author profiles for this publication at: https://www.researchgate.net/publication/260516690
CITATIONS READS
0 100
1 author:
Ashutosh Garg
Furnace Improvements Services
14 PUBLICATIONS 59 CITATIONS
SEE PROFILE
All content following this page was uploaded by Ashutosh Garg on 05 March 2014.
A New Approach to
Improving Heater Efficiency
Figure 1.Typical 4 pass heater with feed being Figure 2. Conventional scheme for improve the
heated from 450 to 600° F efficiency
1
PRODUCTIVITY IMPROVEMENT DESIGN MODIFICATION
Table 1
Parameter Units Operating
Value
Total Heater Duty MMBtu/hr 158
Radiant Heat Duty MMBtu/hr 120.09
(Process)
Convection Heat MMBtu/hr 37.91
Duty
Figure 4. Scheme of a reformer heater with
Firing Rate MMBtu/hr 234
(right) and without (left) the Split Flow technology.
Efficiency % 67.5
2
DESIGN MODIFICATION PRODUCTIVITY IMPROVEMENT
STACK
CONVECTION
SECTION
INLET Burners
OUTLET
Figure 7. FIS Split Flow Scheme. Patented tech-
nology.
Figure 5. Reformer heater before the revamp. sure drop across went up by 50%.
The conventional design is shown in Fig-
ered heat from flue gases in the three convection ure 6. In order to keep the pressure drop low, the
sections. They were entering the convection sec- number of parallel passes had to be increased in
tion at 428° F and 459° F respectively. the convection section leading to very wide con-
The existing heater consists of 3 separate vection sections. Since all the feed had to be
convection sections and 3 stacks (Figure 5). This heated in series , it required large pipe sizes. The
heater design is very old and new heaters have pipe design becomes difficult as the temperatures
single convection sections. The convection sec- are high and thermal expansion needs to be taken
tions were of different size, first one was 4 tubes care of. The heater foundation could not sustain
wide, second was 6 tubes wide and the third one the new convection section loads. A grade
was only 2 tubes wide. Radiant section was di- mounted stack had to be installed.
vided by bridge walls. The stack dampers in the The conventional efficiency improvement
stack were not working well. scheme suffered from the following disadvantages.
The conventional design would be to pre- The process side pressure drop went up. The large
heat the process fluid in the convection section piping size was required to keep pressure drop
first and then send it to the radiant section. In low. Due to the large convection sections and
this design, the heat is recovered by the feed in grade mounted stack, the cost of the scheme was
the convection section and then by the reboiler estimated at 6 million Dollars.
coils. This would have improved the efficiency to Split flow technique divides the process
the desired level of 86%. fluid into two streams (Figure 7). The convection
The major disadvantage was an increase section heats approximately 25 – 30% of the total
in pressure drop across each coil. Due to inherent flow and the rest is heated by the radiant section
construction of the convection section with multi- to the same temperature. The exiting fluids from
ple return bends in the convection coil, the pres- both sections are then combined into one stream.
In the split flow design for this reformer
STACK
DAMPER
REBOILER CONVECTION
COIL SECTION
PROCES
S COIL
RADIANT
SECTION
INLET
OUTLET
3
PRODUCTIVITY IMPROVEMENT DESIGN MODIFICATION
Table 2 Table 3
Original Split flow Before After
Parameter Item
Design Design Revamp Revamp
Pressure Drop, psi 3.1 2.1 Capacity, BPD 18,500 24,000
Firebox temperature, °F 1,615 1,551 Heat Duty, MMBtu/hr 158 194.5
Radiant flux, Btu/hr ft² 19,823 15,047 Heat Release, MMBtu/hr 234 225
Radiant tube metal temp, °F 1,151 1,120 Efficiency, % 67.5 86.6
Firing rate, MMBtu/hr 116.35 82.65 Stack Temp., °F 1,092 478
heater (Figure 8), the convection sections are nar- Fuel Savings, $/annum 5.8 Million*
rower and lighter and as a result could be sup- *Based on $6.0 / MM Btu
ported on the existing heater structure with minor to 15000 Btu/hr ft2. The tube metal temperature
reinforcements. The split flow piping is smaller. went down by 30° F. The firing rate went down by
We used only 16-18 inch pipe size as compared to 33%.
26 inch pipe in the conventional scheme. The Table 3 compares some of the most im-
stacks could be reused after the new dampers portant parameters in the heaters operation be-
were installed on the stacks. The flow to the split fore and after the revamp. As you can see, with
coil was controlled using restriction orifices in each the split flow technology, the heater was able to
split flow line. This way the pressure drop was process 24,000 BPD of feed, up from 18,500 BPD.
balanced. The heat duty was up by 20% and yet the firing
Table 2 compares the performance of the stayed the same. Efficiency of the heater was in-
heater before and after the revamp. This data creased by almost 20%. The stack temperature
shows that the pressure drop across the cell 1 was reduced by 600° F. The project payout in less
went down from 3.1 to 2.1 psi. It would have than 6 months.
gone up by 50% in the conventional scheme. The Figure 9 shows the reformer before re-
reduction in pressure drop was a significant bene- vamp and after revamp. The Split flow technique
fit to the client for yield improvement. The firebox provides efficient solutions to pressure drop and
temperature was reduced from 1615 to 1551° F. capacity problems. It provides an inexpensive effi-
The radiant flux decreased from 20000 Btu/hr ft 2 cient alternative with a short payback time.
Figure 9.
The Reformer
Heater before
(left) and
after (right)
the FIS Split
Flow revamp
for efficiency
improve-
ments.
The Author
Ashutosh Garg is currently working as a Thermal Engineer at Furnaces Improvements in Sugar Land, TX. He has more than
35 years of experience in design, engineering and troubleshooting of furnaces and combustion systems for the refining and
petrochemical industries. He graduated from Indian Institute of Technology, Kanpur, India, in chemical engineering in 1974.
He started as a graduate engineer in an ammonia plant. This was followed by six years in KTI India and eight years at EIL,
New Delhi, in the heater group. He joined KTI Corp., San Dimas, California, in 1990, and moved to Houston in 1992. He has
published several articles on fired heaters and burners in trade magazines. He is a registered professional engineer and a
member of AIChE, API & ASME.
4
View publication stats