INSTALLATION METHOD
OF THE M&E WORKS

  JSC.,
VIET TRUONG THANH TRADING&ENGINEERING SERVICE   Page 1 
INSTALLATION METHOD OF THE M&E WORKS
   
VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,
Office: Room 310 - CT 2B – Me Tri Ha Urban – Tu Liem District – Ha Noi City – Viet Nam
  Tel : ( +84-4 ) 3 787 71 57 Fax : ( +84-4 ) 3 787 71 45
  E-mail : viettruongthanh.js@gmail.com

INDEX
Pages
INDEX.................................................................................................................. 2
PURPOSE AND SCOPE ......................................................................................... 3
1. Purpose For M&E Works......................................................................................... 3
2. Scope Of Works .................................................................................................... 3
PREPARING WORKS............................................................................................ 5
1. Document Preparing works .................................................................................... 5
2. Site Plan layout...................................................................................................... 5
3. Man power and facilities......................................................................................... 5
INSTALLATION METHOD OF MECHANICAL WORKS ........................................... 6
1. Machinery Erection Works for MVAC System............................................................ 6
2. Piping work for MVAC system ................................................................................. 9
3. Ducting work for MVAC system............................................................................... 11
4. Air Compressor Machine erection works .................................................................. 12
5. Fire Fighting system works ..................................................................................... 13
6. Plumping system works.......................................................................................... 14

INSTALLATION METHOD OF ELECTRICAL WORKS ............................................. 16


1. Electrical equipment erection works ....................................................................... 16
2. Cable trunking and cable leader installation works ................................................... 18
3. Lighting installation works ...................................................................................... 19
4. Cabling installation and connection work ................................................................. 20
5. HV Cable terminal installation works ....................................................................... 22
6. LV Cable terminal installation works ........................................................................ 25
7. CCTV installation works.......................................................................................... 25
8. Data and Telephone system installation works......................................................... 26

THE END

  JSC.,
VIET TRUONG THANH TRADING&ENGINEERING SERVICE   Page 2 
INSTALLATION METHOD OF THE M&E WORKS
   
VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,
Office: Room 310 - CT 2B – Me Tri Ha Urban – Tu Liem District – Ha Noi City – Viet Nam
  Tel : ( +84-4 ) 3 787 71 57 Fax : ( +84-4 ) 3 787 71 45
  E-mail : viettruongthanh.js@gmail.com

PURPOSE AND SCOPE.


1. PURPOSE FOR M&E WORKS.
We acknowledge that the project has to be executed according to international professional
standards and quality requirements. With our qualification have been Supply, Engineering and
Installation in Industrial and Residence Project, we will be the purpose of these guidelines
installation programme for execution of the work as:
+ Site Inspection and checking infacstructure of Industrial Park at project location for power
supply, water supply, water drainage, communication connection and other facilities….
+ Contact with the Owner and Consultant engineering for Site Office Layout submit and
approval with a convenient and safety location. Preparing Site Office, Warehouse and
Workshop, checking and prepared Tools, uniform, safety tools….
+ To take out insurance for Officers, labors and equipment for guarantee of Labors and
equipment at site.
+ To submit with the Owner and Consultanting engineering of Manpower list for this project
with personel detail (Position, mobile…) and Company information for an indispensable job.
+ To submit with the Owner and Consutanting engineering of Time Schedule has been
approval to co-ordinate in project progress.
+ Regrouping equipments, materials and tools at site completed.
+ Checking to order all equipment with supplier for delivery time, drawing manufacturing
approval, assembly schedule, Testing and commissioning and erection schedules.
+ To work out a optimal plan, convenient for Transportation, Logistic of equipments and
materials to located and installation at site.
+ Checking and testing equipments, before regroupding at site. To co-ordinate with Audit
company and supplier for checking and testing equipment.
+ To co-ordinate with Consultanting Engineering and Civil contractor before excavation work,
foundation works, steel re-bars, concrete pilling…for underground piping works, conduit
piping work, M&E equipment foundation and other works.
+ Proceed with M&E works follows Construction progress.
+ Regrouping Main equipments for M&E works at site for preparing installation M&E works.
+ Lifting and Installation equipment for M&E works.
+ To co-ordinate with Consultanting Engineering and Civil Contractor to improved work at site.
+ To completed installation M&E works.
+ To co-ordinate with Consultanting Engineering and the Owner for Inspection & Testing of
M&E works has been finished installation works.
+ To co-ordinate with Consultanting Engineering and the Owner for Checking Unload and Full
Loading of M&E equipments, before acceptance this works.
+ Checking to improved M&E works.
+ Instruction Manual Operation, Acceptance works and Hand-over.

2. SCOPE OF WORKS.
This item is description for the supply and installation of the M&E works. M&E scope of works
description of the followings systems:
ELECTRICAL WORKS
1. Transformer and Switchgear.
2. Distribution Panels.

  JSC.,
VIET TRUONG THANH TRADING&ENGINEERING SERVICE   Page 3 
INSTALLATION METHOD OF THE M&E WORKS
   
VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,
Office: Room 310 - CT 2B – Me Tri Ha Urban – Tu Liem District – Ha Noi City – Viet Nam
  Tel : ( +84-4 ) 3 787 71 57 Fax : ( +84-4 ) 3 787 71 45
  E-mail : viettruongthanh.js@gmail.com

3. Generator system.
4. Lighting Panels.
5. Lighting Fixture and Emergency Lighting.
6. Socket and power outlet.
7. Lightning protection.
8. Earthing system.
9. CCTV system.
10. Telephone and LAN system.
11. Fire Alarm system.
12. Cables, cable trays, cable trunking.
MECHANICAL WORKS
1. Air Conditioning system.
2. Ventilation system.
3. Cooling water system.
4. Air Compressor system.
5. Domestic Water supply system.
6. Drainage water system.
7. Fire fighting system.

  JSC.,
VIET TRUONG THANH TRADING&ENGINEERING SERVICE   Page 4 
INSTALLATION METHOD OF THE M&E WORKS
   
VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,
Office: Room 310 - CT 2B – Me Tri Ha Urban – Tu Liem District – Ha Noi City – Viet Nam
  Tel : ( +84-4 ) 3 787 71 57 Fax : ( +84-4 ) 3 787 71 45
  E-mail : viettruongthanh.js@gmail.com

PREPARING WORKS
1. Document Preparing works.
+ After received to start of work command from the Owner, we will submit Manpower list shall
be joint to this project for The Owner to monitoring and to issue an Entry Card licence.
+ To report with Police and local authorities for execution the work and submitted Manpower
list with detail information (name, address, telephone…).
+ To submit with the Owner and Consutanting engineering of Time Schedule has been
approval to co-ordinate in project progress. Site report approved by the Owner with stamp
will be prepared after start of work.
+ To submit with the Owner and Consutanting engineering of Catalogue and technical drawing
for M&E equipment in 02 weeks, after the Owner signed contract for the Owner and
Consultanting Engineering approved.
2. Site Plan layout.
+ Site plan layout shall be specify location by the Owner for execution of the M&E works as
well as site storage for regrouping materials, tools… and set up temporary electrical, water
supply, telephone to carry out works at site. Also the contractor will be set up 01 Generator
100kVA for emergency power supply for site office and workshop.
+ The M&E Contractror will be set up temporary fence for Site plan layout, also set up 01
guard house for this area. Beside the contractor will be set up workshop for fabrication duct,
sleeve, piping, hangers, support and accessories for M&E works with waste area following
LEED requirement.
+ To set up site storage with 03 container volume is 40ft and storage is to maintain good,
equipments and tools.
+ Site office shall be setup with 02 container 40ft in office area included: office area, meeting
room for management project.
3. Man power and facilities.
+ Manpower: will be set up followings capacity of Project (see detail in Organization Chart).
+ Machinery and Tools: see detail in tender document.
+ Materials: all material used to carry out of M&E works the contractor shall submit product
data sheet and sample to the Owner and Consultanting Engineering, also available with
technical specification, standard.

  JSC.,
VIET TRUONG THANH TRADING&ENGINEERING SERVICE   Page 5 
INSTALLATION METHOD OF THE M&E WORKS
   
VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,
Office: Room 310 - CT 2B – Me Tri Ha Urban – Tu Liem District – Ha Noi City – Viet Nam
  Tel : ( +84-4 ) 3 787 71 57 Fax : ( +84-4 ) 3 787 71 45
  E-mail : viettruongthanh.js@gmail.com

INSTALLATION METHOD OF MECHANICAL WORKS


A. MACHINERY ERECTION WORKS FOR MVAC SYSTEM:
Preparing works:
+ Shop drawings with detail installation of works.
+ Preparing Team for machinery Layout, equipment and Tools.
+ Crane, Lifting equipment, chain, wood to prop…
Machinery for erection works included:
+ Electric Arc Welding machine: 02 sets.
+ Volfram Electrode Welding machine: 01 set.
+ Hoist, chains: 01 set.
+ Oxyacetylene Welding: 01 set.
+ Thread piping Machine: 01 set.
+ Cutting Machine: 01 set.
+ Grillding machine: 02 set.
+ Wheel chair, lever..: 01 set.
+ Concrete drill Machine: 02 set.
+ Mechnical Tools: 01 lot.
+ Scarfold: 04 sets.
Water Cooled Chiller erection works:
+ Lifting Water Cooled Chiller from storage
and remove to Machine Room.
+ Checking Concrete foundation for
Isolator, ruber pad location fixed before
remove water chiller fix to foundation.
+ Removing Water Chiller to basement and
fix to machine location with isolator.
+ Installation Chiller coolled water supply
and Chiller cooling water return with
Chiller.
+ Installation Condenser water piping
connection Water Cooled Chiller with
Cooling Tower.
+ Connection Power supply wiring and Control cable wiring with
Water Cooled Chiller Control Panel.
+ Checking all of Items for Monitoring display of control system.
+ Checking and tesing with unloading test for Water
Cooled Chiller.
+ Checking and testing with Loading test for Water
Cooled Chiller and finished erection works.

Water Pump erection works:


+ Used Folk lift machine remove water pump to
Machine Room.
+ Checking Concrete foundation for Isolator, ruber
  JSC.,
VIET TRUONG THANH TRADING&ENGINEERING SERVICE   Page 6 
INSTALLATION METHOD OF THE M&E WORKS
   
VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,
Office: Room 310 - CT 2B – Me Tri Ha Urban – Tu Liem District – Ha Noi City – Viet Nam
  Tel : ( +84-4 ) 3 787 71 57 Fax : ( +84-4 ) 3 787 71 45
  E-mail : viettruongthanh.js@gmail.com

pad location fixed before remove water pump fixed to foundation.


+ Installation incharge, discharge and accessories piping for water pump.

+ Connection Power supply wiring cable to Motor and Control cable to Control Panel.
+ Checking and tesing with unloading test for
Water Pump.
+ Checking and testing with loading test for
Water Pump and finished erection works.

Air Handling Unit erection works:


+ Lifting Air Handling Unit remove from site
storage to Installed areas.
+ Checking isolator tie-down remove for Air
Handling Unit before lifting to installation.
+ Fixed Air Handling Unit with isolator fixed
follows hanger location.
+ Installation incharge and discharge ducting for
Air Handling Unit.

+ Installation water supply, water


return and drain piping for Air
Handling Unit.
+ Connection Power supply wiring
cable to Motor and Control cable to
Control Panel.

  JSC.,
VIET TRUONG THANH TRADING&ENGINEERING SERVICE   Page 7 
INSTALLATION METHOD OF THE M&E WORKS
   
VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,
Office: Room 310 - CT 2B – Me Tri Ha Urban – Tu Liem District – Ha Noi City – Viet Nam
  Tel : ( +84-4 ) 3 787 71 57 Fax : ( +84-4 ) 3 787 71 45
  E-mail : viettruongthanh.js@gmail.com

+ Checking proper drive alignment and belt tension measurement for Air Fan.
+ Checking and tesing with unloading test for Air Handling Unit.
+ Checking and testing with loading

test for Air Handling Unit and finished erection works.

Fan Coil Unit erection works:


+ Lifting Fan Coil Unit remove from site storage
to installed areas.
+ Checking isolator tie-down remove for Fan Coil
Unit before lifting to installation.
+ Fixed Fan Coil Unit with isolator fixed follows
hanger location.
+ Installation incharge and discharge ducting
for Fan Coil Unit.
+ Installation water supply, water return and
drain piping for Fan Coil Unit.
+ Connection Power supply wiring cable to
Motor and Control cable to Control Panel.
+ Checking proper drive alignment and belt
tension measurement for Air Fan.
+ Checking and tesing with unloading test for
Fan Coil Unit.
+ Checking and testing with loading test for
Fan Coil Unit and finished erection works.

Ventilation Fan erection works:

  JSC.,
VIET TRUONG THANH TRADING&ENGINEERING SERVICE   Page 8 
INSTALLATION METHOD OF THE M&E WORKS
   
VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,
Office: Room 310 - CT 2B – Me Tri Ha Urban – Tu Liem District – Ha Noi City – Viet Nam
  Tel : ( +84-4 ) 3 787 71 57 Fax : ( +84-4 ) 3 787 71 45
  E-mail : viettruongthanh.js@gmail.com

+ To specify erection location and marking fixed holes for installation supports/ hangers.
+ Removing Ventilation Fan from Site storage to installed areas.
+ Lifting Ventilation Fan fixed with support/hangers with isolators.
+ Connection Canvas joint between Ventilation and ducting.
+ Connection Power supply wiring cable to Motor and Control cable to Control Panel.
+ Checking proper drive alignment for Air Fan.
+ Checking and tesing with unloading test for Air Fan.
+ Checking and testing with Loading test for Air Fan and finished erection works.

B. PIPING WORKS FOR MVAC SYSTEM:


Preparing works:
+ Shop drawings with detail installation of piping works.
+ Preparing Team for machinery Layout, equipment and Tools.
+ To set up scaffolding for specify Main piping and branch pipe, used portable scaffolding with
wheel chair for installation piping works.
+ Checking safety statement in installation progress.
+ Cleaning inside and outside for piping before installation piping work.

Machinery for piping works included:


+ Electric Arc Welding machine : 02 sets.
+ Volfram Electrode Welding machine : 01 set.
+ Electric AC/DC Welding Machine : 01 set.
+ Thread piping Machine : 01 set.
+ Cutting Machine : 01 set.
+ Belding Machine : 01 set.
+ Grillding machine. : 02 sets.
+ Vertical drilling machine. : 02 sets.
+ Hoist, chains. : 02 set.
+ Wheel chair, lever. : 01 set.
+ Portable Drilling Machine : 06 sets
+ Concrete drilling Machine :
05 sets.
+ Paiting ejector Gun :
03 sets.
+ Portable Air Compressor :
01 sets.
+ High pressure Pump :
01 sets.
+ Mechnical Tools :
01 lot.
+ Scarfolding :
100 sets.

Water Cooled Chiller piping erection


works:
+ To specify main piping of Water Cooled Chiller pipe from Chiller to AHU and FCU.

  JSC.,
VIET TRUONG THANH TRADING&ENGINEERING SERVICE   Page 9 
INSTALLATION METHOD OF THE M&E WORKS
   
VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,
Office: Room 310 - CT 2B – Me Tri Ha Urban – Tu Liem District – Ha Noi City – Viet Nam
  Tel : ( +84-4 ) 3 787 71 57 Fax : ( +84-4 ) 3 787 71 45
  E-mail : viettruongthanh.js@gmail.com

+ Installation hanger and support for Water Cooled Chiller pipe (see detail for support and
hangers).
+ Installation Water Cooled Chiller main piping and fixed main pipe with Hangers/ supports, if
piping diameter is over DN 65 shall be connect by welding connection.
+ Installation water cooled chiller branch pipe and fixed branch pipe with hangers/ supports, if
piping diameter is over DN 65 shall be connect by welding connection and if piping diameter
belows DN65 shall connection by thread connection.
+ Separation to each branch pipe with main pipe for leaked testing with high pressure.
+ After leaked testing for each branch pipe, contractor will be start to insulation work for
water cooled chiller pipe.

+ After finished insulation works for


branch pipe and main pipe, the
contractor will be connection with
AHU and FCU equipments with
accessories and insulation for
connection work.
+ Final leaked testing for Water Cooled
Chiller pipe with high pressure
(repair if need).
+ To water filled up in system with two
time for cleaning piping system.
+ Operating piping system with
working pressure for loading test and
final erection work.

Condensing Water piping erection works:


+ To specify main piping of condensing water
pipe from cooling tower to Chillers.
+ Installation hanger and support for Codensing
water pipe (see detail for support and
hangers).
+ Installation Condensing water main piping and
fixed main pipe with Hangers/ supports, if
piping diameter is over DN 65 shall be connect
by welding connection.
+ Separation to each branch pipe with main pipe for leaked testing with high pressure.
VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,   Page 10 
INSTALLATION METHOD OF THE M&E WORKS
   
VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,
Office: Room 310 - CT 2B – Me Tri Ha Urban – Tu Liem District – Ha Noi City – Viet Nam
  Tel : ( +84-4 ) 3 787 71 57 Fax : ( +84-4 ) 3 787 71 45
  E-mail : viettruongthanh.js@gmail.com

+ Final leaked testing for Codensing water pipe with high pressure (repair if need).
+ To water filled up in system with two times for cleaning piping system.
+ Operating piping system with working pressure for loading test and final erection work.

C. DUCTING WORKS FOR MVAC SYSTEM:


Preparing works:
+ Shop drawings with detail installation of piping works.
+ Preparing Team for machinery Layout, equipment and Tools.
+ To set up scaffolding for specify Main ducting and branch duct, used portable scaffolding
with wheel chair for installation ducting works.
+ Checking safety statement in installation progress.
+ Cleaning inside and outside for ducting before installation ducting work.

Machinery for ducting works included:


+ Electric AC/DC Welding Machine : 01 set.
+ Lock Former Machine : 01 set.
+ Cutting Machine : 01 set.
+ Hydraulic Press Machine : 01 set.
+ Grillding machine. : 02 sets.
+ Vertical drilling machine. : 02 sets.
+ Wheel chair, lever. : 01 set.
+ Portable Drilling Machine : 05 sets
+ Concrete drilling Machine : 03 sets.
+ Mechnical Tools : 01 lot.
+ Scarfolding : 50 sets.

Ducting erection works:


+ To specify main
ducting from
AHU and FCU
to Supply Air
Diffuser.
+ Checking shop
drawing and
fabrication
ducting at
workshop
follows
technical
specification.
+ Marking and Installation hanger and support for Ducting work (see detail for support and
hangers).
+ Installation ducting and accessories from AHU and FCU to Air Diffusers.
+ Checking and correctly location of Air Duct, insulation at connection joint between two part
of ducting.
+ Checking and testing leaked for ducting works.
+ Operating system and finished installation works.

VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,   Page 11 


INSTALLATION METHOD OF THE M&E WORKS
   
VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,
Office: Room 310 - CT 2B – Me Tri Ha Urban – Tu Liem District – Ha Noi City – Viet Nam
  Tel : ( +84-4 ) 3 787 71 57 Fax : ( +84-4 ) 3 787 71 45
  E-mail : viettruongthanh.js@gmail.com

D. AIR COMPRESSOR MACHINE ERECTION WORKS:


Preparing works:
+ Shop drawings with detail installation of works.
+ Preparing Team for machinery Layout, equipment and
Tools.
+ Crane, Lifting equipment, chain, wood to prop…
Machinery for erection works included:
+ AC Welding machine: 02 sets.
+ Hoist, chains: 01 set.
+ Thread piping Machine: 01 set.
+ Cutting Machine: 01 set.
VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,   Page 12 
INSTALLATION METHOD OF THE M&E WORKS
   
VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,
Office: Room 310 - CT 2B – Me Tri Ha Urban – Tu Liem District – Ha Noi City – Viet Nam
  Tel : ( +84-4 ) 3 787 71 57 Fax : ( +84-4 ) 3 787 71 45
  E-mail : viettruongthanh.js@gmail.com

+ Grillding machine: 02 set.


+ Wheel chair, lever..: 01 set.
+ Concrete drill Machine: 02 set.
+ Mechnical Tools: 01 lot.
+ Scarfold: 04 sets.
Air Compressor installation works:
+ Shop drawings and Manual installation of Manufacturer with detail installation of works.
+ Lifting by Forklift and transportation to Air Compressor
Room.
+ After civil engineering of Air Compressor Room is
finished, installation illumination and power supply,
ventilation device for installation.
+ Checking foundation complied with requirement for
torelance of platness and linearlity which guarantee the
installation of Air Compressor.

+ The Installation Air Compressor, Air Dryer and Air Receiver to foundation of Compressor
Room fixed equipment with basement by expansion bolts with ruber pad.
+ The Installation Air piping system connect Air Compressed outlet with Air Dyer, Pre Filter,
After Filter and Air Receiver tanks. Also installation drains piping for Air Compressor system.
+ The Installation Ventilation system for Air Compressor as: Ducting, Air intake Louver and Air
Exhaust for Compressor Room.
+ The connection power supply and control wiring for Air Compressor, Air Dryer and others for
this system.
+ Checking Monitoring Controller and displays devices, as well as instruments for controllers.
+ Checking overall the connection correctly and reliably, all conditions must be fulfilled.
+ Testing unloading and loading with normal condition and
finished installation works.

E. FIRE FIGHTING PIPING SYSTEM WORKS:


Preparing works:
+ Shop drawings with detail installation of works.
+ Preparing Team for machinery Layout, equipment and
Tools.
+ Crane, Lifting equipment, chain, wood to prop…

VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,   Page 13 


INSTALLATION METHOD OF THE M&E WORKS
   
VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,
Office: Room 310 - CT 2B – Me Tri Ha Urban – Tu Liem District – Ha Noi City – Viet Nam
  Tel : ( +84-4 ) 3 787 71 57 Fax : ( +84-4 ) 3 787 71 45
  E-mail : viettruongthanh.js@gmail.com

Machinery for erection works included:


+ AC Welding machine: 02 sets.
+ Hoist, chains: 01 set.
+ Thread piping Machine: 01 set.
+ Cutting Machine: 01 set.
+ Grillding machine: 02 set.
+ Wheel chair, lever..: 01 set.
+ Concrete drill Machine: 02 set.
+ Mechnical Tools: 01 lot.
+ Scarfold: 04 sets.
Fire fighting installation works:
+ Shop drawings and Manual installation of Manufacturer with
detail installation of works.
+ Installation hanger and support for Fire fighting water pipe
(see detail for support and hangers).
+ Installation Fire fighting water main piping and fixed main pipe
with Hangers/ supports, if piping diameter is over DN 65 shall
be connect by welding connection.
+ The Installation Fire fighting piping system connects to Fire
Hydrant Box Outdoor, Hydrant box indoor.
+ Separation to each branch pipe with main pipe for leaked
testing with high pressure.
+ Final leaked testing for Fire Fighting water pipe
with high pressure (repair if need).
+ To water filled up in system with two times for
cleaning piping system.
+ Operating piping system with working pressure
for loading test and final erection work.

F. PLUMPING SYSTEM WORKS:


Preparing works:
+ Shop drawings with detail installation of works.
+ Preparing Team for machinery Layout, equipment and Tools.
Machinery for erection works included:
+ AC Welding machine: 01 sets.
+ Hoist, chains: 01 set.
+ Thread piping Machine: 01 set.
+ Cutting Machine: 01 set.
+ Grillding machine: 02 set.
+ Wheel chair, lever..: 01 set.
+ Concrete drill Machine: 02 set.
+ Mechnical Tools: 01 lot.
+ Scarfold: 04 sets.
Plumbing installation works:
+ Shop drawings and Manual installation of Manufacturer with
detail installation of works.

VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,   Page 14 


INSTALLATION METHOD OF THE M&E WORKS
   
VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,
Office: Room 310 - CT 2B – Me Tri Ha Urban – Tu Liem District – Ha Noi City – Viet Nam
  Tel : ( +84-4 ) 3 787 71 57 Fax : ( +84-4 ) 3 787 71 45
  E-mail : viettruongthanh.js@gmail.com

+ Making location of faucets, valves, pipes or appliances on the floor or slab concrete for
preparing main line of Sewer or water service piping.
+ Installation of sewer and water service sleeves underground of building.
+ Installation of sewer and water service branch piping from the main to the property line,
when installed by authorized municipal utility employees or
sewer water utility installers under contract with a
municipality.
+ Installation of water service mains piping works, connect
water service Main pipe with Valve box (included Water
Meter) and connect with Main Pipe of Industrial Park.
+ Construction Manholes, Great Trap and Septic Tank for Sewer
water system and then connect Sewer main pipe with
Manhole of Sewer system outside of Industrial Park.
+ Leaking test one by one with each branch pipe
of water service system.
+ Flows test one by one with each Manholes and
branch pipe of Sewer water system.
+ Final leaked testing for water service pipe with
high pressure (repair if need).
+ Final checking with Manholes, Great Trap,
Septick Tank for water flows of Sewer water
system.
+ To water filled up in system with two times for
cleaning piping system.
+ Operating piping system with working pressure
for loading test and final erection work.

VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,   Page 15 


INSTALLATION METHOD OF THE M&E WORKS
   
VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,
Office: Room 310 - CT 2B – Me Tri Ha Urban – Tu Liem District – Ha Noi City – Viet Nam
  Tel : ( +84-4 ) 3 787 71 57 Fax : ( +84-4 ) 3 787 71 45
  E-mail : viettruongthanh.js@gmail.com

INSTALLATION METHOD OF ELETRICAL WORKS


A. ELECTRICAL EQUIPMENT ERECTION WORKS:
Preparing works:
+ Shop drawings with detail installation of works.
+ Preparing Team for machinery Layout, equipment and Tools.
+ Crane, Lifting equipment, chain, wood to prop…
Machinery for erection works included:
+ Crane and Lifting equipment : 01 set.
+ Hoist, chains : 01 set.
+ Wheel chair, lever.. : 01 set.
+ Concrete drill Machine : 02 sets.
+ Mechnical Tools : 01 lot.
+ Electrical Tools : 01 lot.
+ Electrical measuring equipment : 01 lot.
+ Scarfolding : 04 sets.

TRANSFORMER:
+ Shop drawings Manual installation of Manufacturer
with detail installation of works.
+ Lifting and Removing Transformer from site storage
to Transformer Room.
+ Checking transformer foundation and marking fixed
location of transformer.
+ The installation transformer shall accord to safety
requirements. For those without enclosure, grounded
disconnection fence shall be placed around the
transformer. Hazard-warning signs shall be put up on
the main body of the transformer, on the striking
places of the cabinet anf the fence.
+ The connection of cables and busbars must be up to standards and the safe insulation
distance regulations descripble. Cables and busbars must be supported with fixed braces,
and excessive mechanical force and torque must not be exerted on the terminal.
+ Checking Temperature controlling and displays
devices, as well as instruments for automatic
voltage controllers.
+ Checking overall the connection correctly and
reliably, all conditions must be fulfilled.
+ Testing unloading and loading with normal
condition and finished installation works.

SWITCHGEAR INSTALLATION WORKS:


+ Shop drawings and Manual installation of
Manufacturer with detail installation of works.
+ Lifting by Crane and transportation to
Switchgear location.

VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,   Page 16 


INSTALLATION METHOD OF THE M&E WORKS
   
VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,
Office: Room 310 - CT 2B – Me Tri Ha Urban – Tu Liem District – Ha Noi City – Viet Nam
  Tel : ( +84-4 ) 3 787 71 57 Fax : ( +84-4 ) 3 787 71 45
  E-mail : viettruongthanh.js@gmail.com

+ After civil engineering of distribution room is finished, installation illumination and power
supply, ventilation device for installation.
+ Checking foundation complied with requirement for torelance of platness and linearlity which
guarantee the installation of switchgear.
+ The installation of fundamental fra me, adjust the height and levelness of fundamental
frame.

+ The installation of the switchgear fixed with fundamental frame with bolts.
+ The installation of the burbar, used socket bolt to connect the busbar to corresponding
branched busbars.
+ Switchgear earthing: connect all lines that need to be earthed in the cubicle.
+ The epilog of the installation: check bolt connecting, cleaning switchgear carefully.
+ Check overall conditions of switchgear, energize the auxiliary control power. Inspect the
effectiveness of mechanical and electrical interlock.
+ Testing unloading and loading with normal condition and finished installation works.

DISTRIBUTION BOARD PANEL INSTALLATION WORKS:


+ Shop drawings and Manual installation of Manufacturer with detail installation of works.
+ Lifting by Crane and transportation to Distribution Panel location.
+ After civil engineering of distribution room is finished, installation illumination and power
supply, ventilation device for installation.
+ Checking foundation complied with requirement for torelance of platness and linearlity which
guarantee the installation of Distribution Panel.
+ The installation of fundamental frame, adjust the height and levelness of fundamental
frame.
+ The installation of the Distribution Panel fixed with fundamental frame with bolts.
+ The installation of power cable with ACB, MCCB, MCB.., used cable plug to connect the
power cable to corresponding ACB, MCCB, MCB.
+ Distribution Panel earthing: connect all lines that need to be earthed in the cubicle.
VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,   Page 17 
INSTALLATION METHOD OF THE M&E WORKS
   
VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,
Office: Room 310 - CT 2B – Me Tri Ha Urban – Tu Liem District – Ha Noi City – Viet Nam
  Tel : ( +84-4 ) 3 787 71 57 Fax : ( +84-4 ) 3 787 71 45
  E-mail : viettruongthanh.js@gmail.com

+ The epilog of the installation: check bolt connecting, cleaning Distribution panel carefully.
+ Check overall conditions of distribution panel, energize the auxiliary control power. Inspect
the effectiveness of mechanical and electrical interlock.
+ Testing unloading and loading with normal condition and finished installation works.

B. CABLE TRUNKING AND CABLE LEADER INSTALLATION WORKS:


Preparing works:
+ Shop drawings with detail installation of works.
+ Preparing Team for machinery Layout, equipment and Tools.
+ Scafolding, Lifting equipment, chain, wood to prop…
Machinery for erection works included:
+ Thread piping Machine : 01 set.
+ Cutting Machine : 01 set.
+ Grillding machine : 02 set.
+ Wheel chair, lever.. : 01 set.
+ Concrete drill Machine : 02 set.
+ Mechnical Tools : 01 lot.
+ Electrical Tools : 01 lot.
+ Scarfolding : 20 sets.
Cable & trunking installation works:
+ Checking and marking Cable trunking and Cable leader lines
in factory.
+ Installation supports (with vertical type) and hangers for
horizontal type of Cable trunking and Cable leader. Distance
between two support (vertical type) is lower 3m and
hangers (horizontal type) is 2m.
+ Installation Cable trunking and cable leader with fixed point
between support (vertical type) and Cable trunking is 100-
150mm, also fixed point between hanger to Cable trunking
is 100-200mm.
+ Installation Fixed support for Cable trunking and cable leader has been installed, normally
01 cable trunking space shall be installation 02 fixed support (horizontal type) and 01 fixed
support for vertical cable trunking.
+ Installation earthing cable for connection point between two cable trunking and leader and
installation earthing cable for the end of cable trunking and cable leader.

+ Cheking overall cable trunking and cable


leader has been installed with vertical view, alighment and across of lines, also checking
earthing cable connection.
+ Finished installation works.

VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,   Page 18 


INSTALLATION METHOD OF THE M&E WORKS
   
VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,
Office: Room 310 - CT 2B – Me Tri Ha Urban – Tu Liem District – Ha Noi City – Viet Nam
  Tel : ( +84-4 ) 3 787 71 57 Fax : ( +84-4 ) 3 787 71 45
  E-mail : viettruongthanh.js@gmail.com

C. LIGHTING INSTALLATION WORKS:


Preparing works:
+ Shop drawings with detail installation of works.
+ Preparing Team for machinery Layout, equipment and Tools.
+ Scafolding, Lifting equipment, chain, wood to prop…
Machinery for erection works included:
+ Thread piping Machine : 01 set.
+ Cutting Machine : 01 set.
+ Grillding machine : 02 set.
+ Wheel chair, lever.. : 01 set.
+ Concrete drill Machine : 02 set.
+ Mechnical Tools : 01 lot.
+ Electrical Tools : 01 lot.
+ Scarfolding : 20 sets.
Lighting installation works:
+ Checking and marking lighting lines location at the ceiling and the roof.

VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,   Page 19 


INSTALLATION METHOD OF THE M&E WORKS
   
VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,
Office: Room 310 - CT 2B – Me Tri Ha Urban – Tu Liem District – Ha Noi City – Viet Nam
  Tel : ( +84-4 ) 3 787 71 57 Fax : ( +84-4 ) 3 787 71 45
  E-mail : viettruongthanh.js@gmail.com

+ Installation lighting support and hanger at the ceiling


and the roof with location has been marking.

+ Installation conduit pipe for lighting cable at


the ceiling and the roof follows lighting support and hangers.
+ Installation lighting at the ceiling and the roof connetion with support and hanger.
+ Lighting cable connection with lighting fixture at the ceiling and the roof and connect
lighting cable with lighting panel.
+ Cheking overall lighting condition and cleaning all of lighting fixture.
+ Checking and testing with loading test for lighting fixture and finished installation.

D. CABLING INSTALLATION AND CONNECTION WORK


PREPARING WORKS:
• Shop drawings with detail installation of works.
• Preparing Team for machinery Layout, equipment and Tools.
• Testing equipment.
1. Machinery for erection works included:
+ Cable Roller Support : 04 set.
+ Cable Winch : 01 lot.
+ Hydraulic cable winch : 02 sets.
+ Cable cutter : 01 lot.
+ Cable grip : 01 lot.
+ Ladder indication : 01 set.
+ Indication plate : 01 lot.
+ Mechanical Tools : 01 lot.
+ Electrical Tools : 01 lot.
+ Electronic Metering : 01 lot.
+ Mobilization Crane : 01 lot.
+ Clout and accessories : 01 lot.
2. Preparing for Material:
+ Checking shop drawing for Cable pulling and connection with position of cable pulling at
the site
VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,   Page 20 
INSTALLATION METHOD OF THE M&E WORKS
   
VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,
Office: Room 310 - CT 2B – Me Tri Ha Urban – Tu Liem District – Ha Noi City – Viet Nam
  Tel : ( +84-4 ) 3 787 71 57 Fax : ( +84-4 ) 3 787 71 45
  E-mail : viettruongthanh.js@gmail.com

+ Receiving cable from SEC’s storage/HTG site storage day by day comply with technical
specification and quantity of cable lines.
+ Checking location put in Cable Drum at site with a convenient location for security and
carries out at the site.
3. Preparing for Labor:
+ Assume of Technical: Electrical Supervisors (Engineering).
+ Labor for Cable Pulling:
- 01 team for preparing cable pulling location at the site.
- 01 team for transportation, loading and unloading cable drum.
- 01 team for preparing Cable Roller support, cable winch, extension cable roller.
METHOD EXCECUTIVE OF INSTALLATION WORKS
1. Pulling Cable
• Used Roller metering for length of cable lines.
• Checking Cable Drum with correct with specify, dimension and marking location of cable pulling,
Cable plug must be cover for damp-proof.
• Installation cable winch and cable roller for Cable lines, checking carefully with support and
cable lines.
• Testing Cable insulation by Metering MΩ, private for HV cable shall be checking insulation
before and after cable terminal procedures.
• Loading and Unloading Cable Drum on Cable roller support.
• From Cable Drum to let out cable on the Cable roller to protect grazed of insulation cable.
• Used Hydraulic Cable Winch pulling cable on the Cable Roller has been installed with double-
headed cable, at the manholes some labor will be inside to strengthen and reduced friction of
cable and duct bank pipes.
• Pulling cable inside Cable duct bank/trunking to arrange cable in order of Cable layers.
• Cable longer will be pulling first and then pulling shorter cables; big side will be pulling and then
pulling smaller side.
• Cable pulling must be finished in one day (force majeure: Weather….e.t.c, HTG will be cover
this cable, protect cable length for damp-proof, to be victim of a burglary and set up 01 security
commanding post for this cable line).
2. Cable gland, testing and connection works
• Checking cable gland for each panels, must be to provide for additional cable at any time. In
side Panel, power cable and control cable must be separation with 02 areas. After to press cable
body with cable gland, connection part and cable stomach must be freedom state, not in twist
state or broken line, then execution connects to one cable for each panel.
• Remove Cable rubber and insulation cut the cores to the required
length (follows cable gland). Installation follows sequence of cable
gland, to press carefully with Panel cover.
• To glue up Cable name and tag number with each cable.
• After pulling cable and cable gland installation finished, checking
insulation and put cable plug, cable plug must be correct parallel
with to contact surface at the equipment will be connects. When
connecting cable plug with terminal, must be used mechanical tool
comply with measuring pressure for ensure contact surface is
absolute.

E. HV CABLE TERMINAL INSTALLATION WORKS:

VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,   Page 21 


INSTALLATION METHOD OF THE M&E WORKS
   
VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,
Office: Room 310 - CT 2B – Me Tri Ha Urban – Tu Liem District – Ha Noi City – Viet Nam
  Tel : ( +84-4 ) 3 787 71 57 Fax : ( +84-4 ) 3 787 71 45
  E-mail : viettruongthanh.js@gmail.com

Preparing works:
+ Shop drawings with detail installation of works.
+ Preparing Team for machinery Layout, equipment and Tools.
+ Testing equipment.
Machinery for erection works included:
+ Hydraulic Press pliers : 01 set.
+ Handle Press pliers : 02 set.
+ Mechnical Tools : 01 lot.
+ Electrical Tools : 01 lot.
+ Clout and accessories : 01 lot.
HV Cable terminal installation works:
+ Shop drawings with detail installation of works and Installation guide of manufacturer.
+ Cut the cable to the required length and remove the oversheath. Leave enough length to set
the cores into their final positon. Clean and degrease the end of the oversheath for about
100 mm (A1)

+ Remove the release paper and wrap one layer of sealant tape (red) with a small overlap and
slight tension around the end of the oversheath for 80 mm. Bend the shielding wires back
onto the oversheath. Avoid crossing individual wires. Temporarily fix the shielding wires well
below the red sealant tape to the oversheath (A2).
+ Bend and shape the cores into their final position. Cut the cores to the required length.
Thoroughly remove the core screen according to dim. The surface of the insulation should
be free from all traces of conductive material. Smooth out any irregularities (A3).

VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,   Page 22 


INSTALLATION METHOD OF THE M&E WORKS
   
VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,
Office: Room 310 - CT 2B – Me Tri Ha Urban – Tu Liem District – Ha Noi City – Viet Nam
  Tel : ( +84-4 ) 3 787 71 57 Fax : ( +84-4 ) 3 787 71 45
  E-mail : viettruongthanh.js@gmail.com

+ Remove the release paper and wrap the void filling strip (yellow) around the end of the core
screen. Cover 20 mm of the core screen and continue onto the insulation for 10 mm. Stretch
the strip to half of its original width to achieve a fine, thin edge onto the insulation (A4)
+ Cut the cable to the required length and remove the oversheath. Leave enough length to set
the cores into the final position. Clean and degrease the end of the oversheath for about
100 mm. (B1)

+ Separate the cores. Wrap an earth lead round each core and soldertack it to the metal tape
shield (or attach the earth lead by any other equivalent method). Fill the earth lead with
solder to form a 30 mm moisture block 30 mm from the oversheath end. Remove the
release paper and wrap one layer of sealant tape (red) round the oversheath end for 80 mm
underneath the earth lead. (B2)
+ Bend and shape the cores into their final position. Cut the cores to the required length.
Place a temporary wire binder around the cores at the position shown in the drawing. Tear
off the tape shield against the wire binder. Remove the metal tape shield according to
dimension b. Thoroughly remove the core screen to 20 mm above the metal tape shield cut.
The surface of the insulation should be free from all traces of conductive material (B3).
+ Remove the wire binder from the end of the metal tape shield. Remove the release paper
and wrap the void filling strip (yellow) for 5 mm onto the metal tape shield, continuing over
the core screen and 10 mm onto the insulation. Stretch the strip to half of its original width
to achieve a fine, thin edge onto the insulation (B4)

VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,   Page 23 


INSTALLATION METHOD OF THE M&E WORKS
   
VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,
Office: Room 310 - CT 2B – Me Tri Ha Urban – Tu Liem District – Ha Noi City – Viet Nam
  Tel : ( +84-4 ) 3 787 71 57 Fax : ( +84-4 ) 3 787 71 45
  E-mail : viettruongthanh.js@gmail.com

+ Place the stress control


tubing (black) over the cores and position them 70 mm above the end of the oversheath
cut. Shrink down the tubing starting at the bottom and working upwards.(B5)
+ Remove the release paper and slide the breakout over the cores. Pull the breakout as far
down the crutch as possible. Shrink the breakout into place starting at the centre. Work
first towards the lower end and then shrink the turrets onto the cores. The numbers in the
drawing indicate the shrinking sequence (B6).
+ Cut back the insulation according to dimension K = depth of cable lug barrel hole + 5 mm.
Install the cable plugs. Clean and degrease the insulation and the lugs (B7).

+ Remove the release paper and wrap the sealant tape (red) around the barrel of the cable
lug with a small overlap and slight tension (B8).
+ Remove the release paper from the red tubing. Place the tubing over the cores with the
sealant coated end downwards. Push the tubing over the breakout turrets as far as possible
and shrink it down starting at the crutch and working upwards (B9).
+ Tie the shielding wires or the earth lead with a wire binder to the oversheath below the
breakout. Gather the shielding wires together to form an earth lead (B10)
+ Cut the tubing back onto the connector barrel if neccesary. Postheat the palm of the lug
until a bead of mastic appears around the top of the tubing. Indoor termination up to 17.5

VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,   Page 24 


INSTALLATION METHOD OF THE M&E WORKS
   
VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,
Office: Room 310 - CT 2B – Me Tri Ha Urban – Tu Liem District – Ha Noi City – Viet Nam
  Tel : ( +84-4 ) 3 787 71 57 Fax : ( +84-4 ) 3 787 71 45
  E-mail : viettruongthanh.js@gmail.com

kV completed. Allow the terminations to cool before applying any mechanical strain. For
indoor terminations above 17.5 kV and outdoor terminations shrink the skirts into place

F. LV CABLE TERMINAL INSTALLATION WORKS:


Preparing works:
+ Shop drawings with detail installation of works.
+ Preparing Team for machinery Layout, equipment and Tools.
+ Testing equipment.
Machinery for erection works included:
+ Hydraulic Press pliers : 01 set.
+ Handle Press pliers : 02 set.
+ Mechnical Tools : 01 lot.
+ Electrical Tools : 01 lot.
+ Clout and accessories : 01 lot.
LV Cable terminal installation works:
+ Shop drawings with detail installation of works.

+ Used Electrical Plier cutting and removed ruber cover outside LV cable with distance follows
technical guide lines installation works.
+ The installation Electrical Plug with the same sized of LV Cable and to used Handle or
Hydraulic Press plier to press electrical plug with LV bare cable location correctly.
+ Checking connection point and cleaning all of terminal before installation LV cable terminal.
+ To used electrical tools for installation LV terminal and checking phase and terminal color
correctly and finished installation work.

G. CCTV SYSTEM INSTALLATION WORKS:


Preparing works:
+ Shop drawings with detail installation of works.
+ Preparing Team for machinery Layout, equipment and Tools.
+ Testing equipment.
Machinery for erection works included:
+ Handle Press pliers : 02 set.
+ Mechnical Tools : 01 lot.
+ Electrical Tools : 01 lot.
+ Testing equipment : 01 lot
VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,   Page 25 
INSTALLATION METHOD OF THE M&E WORKS
   
VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,
Office: Room 310 - CT 2B – Me Tri Ha Urban – Tu Liem District – Ha Noi City – Viet Nam
  Tel : ( +84-4 ) 3 787 71 57 Fax : ( +84-4 ) 3 787 71 45
  E-mail : viettruongthanh.js@gmail.com

+ Scarfolding : 10 sets.
CCTV system installation works:
+ Checking and marking cameras location inside and out side Factory following Shop drawing.
+ The installation conduit from Control Room to cameras location.
+ The installation support and bracket for Cameras inside and outside factory.
+ Pulling CCTV cable from Control Room to Cameras location.
+ Set up CCTV equipment inside Control included: Digital Recorder, Keyboard Controller,
Monitors, UPS backup with CCTV terminal connection.
+ The installation Cameras fixed with support and bracket has been installed and connection
CCTV cable with cameras by terminal.
+ Checking controller and displays devices, as well as instruments for automatic controllers.
+ Checking overall the connection correctly and reliably, all conditions must be fulfilled.
+ Setup program, software and start to setting system with technical condition follows this
tender.
+ Testing unloading and loading with normal condition and finished installation works.

H. DATA AND TELEPHONE SYSTEM INSTALLATION WORKS:


Preparing works:
+ Shop drawings with detail installation of works.
+ Preparing Team for machinery Layout, equipment and Tools.
+ Testing equipment.
Machinery for erection works included:
+ Handle Press pliers : 02 set.
+ Mechnical Tools : 01 lot.
+ Electrical Tools : 01 lot.
+ Testing equipment : 01 lot.
+ Scarfolding : 15 sets.
Telephone system installation works:
+ Checking and marking Telephone socket location following Shop drawing.
+ The installation conduit from Telephone Room to telephone socket location and installation
telephone box inside brick wall or on the floor.
+ The installation IDF and MDF box inside the brick wall.
+ Pulling Telephone cable from Telephone Room to telephone socket location.
+ The installation telephone terminal and telephone socket cover with telephone socket.
+ Set up Telephone equipment inside Telephone Room included: PABX, Keypad programme
and switch, MDF Panel with Telephone terminal connection.
+ The connection terminal telephone cable with IDF, from IDF to MDF and from telephone
connection point to PABX and MDF. Checking controller and displays devices, as well as
instruments for automatic controllers.
+ Checking overall the connection correctly and reliably, all conditions must be fulfilled.
+ Setup program, software and start to setting system with technical condition follows this
tender.
+ Testing unloading and loading with normal condition and finished installation works.
LAN system installation works:
+ Checking and marking LAN socket location following Shop drawing.

VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,   Page 26 


INSTALLATION METHOD OF THE M&E WORKS
   
VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,
Office: Room 310 - CT 2B – Me Tri Ha Urban – Tu Liem District – Ha Noi City – Viet Nam
  Tel : ( +84-4 ) 3 787 71 57 Fax : ( +84-4 ) 3 787 71 45
  E-mail : viettruongthanh.js@gmail.com

+ The installation conduit from Server Room to Hub Switch managed for each ares and
conduit from Sub-Switch to LAN socket location and installation LAN box inside brick wall or
on the floor.
+ The installation support and bracket for Sub-Switch location at each others.
+ Pulling LAN cable from Server Room to Sub-Switch at each areas and from Sub- Switch to
LAN socket box location.
+ The installation LAN terminal and LAN socket cover with LAN socket.
+ Set up LAN equipment inside Server Room included: Router, ADSL Modem, Main Server,
Main Switch managed and UPS.
+ The connection terminal LAN cable with Sub-Switch and from Sub-Switch to Main switch and
Server. Checking controller and displays devices, as well as instruments for LAN system.
+ Checking overall the connection correctly and reliably, all conditions must be fulfilled.
+ Setup program, software and start to setting system with technical condition follows this
tender.
+ Testing unloading and loading with normal condition and finished installation works.

VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,


GENERAL DIRECTOR

VIET TRUONG THANH TRADING&ENGINEERING SERVICE JSC.,   Page 27 


INSTALLATION METHOD OF THE M&E WORKS