OptiX Metro 500

Installation Manual Contents

Contents

2 Installation of the OptiX Metro 500 I 2-1

2.1 Wall Mounting 2-1


2.1.1 Overview 2-1
2.1.2 Installation Procedure 2-3
2.2 Installation in 19-inch Rack 2-5
2.2.1 Overview 2-5
2.2.2 Installation Procedure 2-6
2.3 Installation in 300mm-deep ETSI Cabinet 2-8
2.3.1 Overview 2-8
2.3.2 Installation Procedure 2-9
2.4 Installation in 600mm-deep ETSI Cabinet 2-11
2.5 Desktop Mounting 2-11
2.6 Board Installation 2-12

Huawei Technologies Proprietary

i
OptiX Metro 500
Installation Manual Figures

Figures

Figure 2-1 Wall mounting 2-1


Figure 2-2 Parts of wall mounting 2-2
Figure 2-3 Mounting panel 2-2
Figure 2-4 Expansion bolt 2-2
Figure 2-5 Inserting expansion bolt 2-3
Figure 2-6 Attaching the mounting panel and the chassis 2-4
Figure 2-7 Securing the chassis 2-4
Figure 2-8 Installation in 19-inch rack 2-5
Figure 2-9 Parts of installation in 19-inch rack 2-5
Figure 2-10 Attaching two ear brackets 2-6
Figure 2-11 Attaching the pallet 2-6
Figure 2-12 Securing the chassis 2-7
Figure 2-13 Installation in the 300mm-deep ETSI cabinet 2-8
Figure 2-14 Parts of installation in the 300mm-deep ETSI cabinet 2-9
Figure 2-15 Attaching the mounting panel to the chassis 2-10
Figure 2-16 Fixing the chassis into the cabinet 2-10
Figure 2-17 Ear bracket 2-11
Figure 2-18 Self-adhesive pads 2-11
Figure 2-19 Inserting the board 2-12
Figure 2-20 Fixing the board 2-12

Huawei Technologies Proprietary

ii
OptiX Metro 500
Installation Manual 2 Installation of the OptiX Metro 500 I

2 Installation of the OptiX Metro 500 I

This chapter describes the installation of the OptiX Metro 500 I.

2.1 Wall Mounting


2.1.1 Overview

1. Illustration

Figure 2-1 illustrates the wall mounting of the equipment.


Note that the chassis is installed with the interfaces downwards.

Figure 2-1 Wall mounting

Huawei Technologies Proprietary

2-1
OptiX Metro 500
Installation Manual 2 Installation of the OptiX Metro 500 I

2. Parts

Figure 2-2 illustrates the necessary parts in wall mounting.

Wall

Expansion bolt

Mounting panel

Nut,plat washer,spring washer

Chassis

Figure 2-2 Parts of wall mounting

The parts include expansion bolt, mounting panel and chassis. Figure 2-3 illustrates
the mounting panel. Figure 2-4 illustrates the expansion bolt. The type of the
expansion bolt is M6×60.

Chassis mount hole

Panel mount hole

Bounding hole

Figure 2-3 Mounting panel

Expansion tube

Expansion bolt
Spring washer

Flat washer

Nut

Figure 2-4 Expansion bolt

Huawei Technologies Proprietary

2-2
OptiX Metro 500
Installation Manual 2 Installation of the OptiX Metro 500 I

2.1.2 Installation Procedure

Follow the steps below to install the OptiX Metro 500 on the wall.
Step Action
1 Decide where the unit is to be mounted.

2 Hold the mounting panel against the wall, align it vertically, and mark the
positions of the four mounting holes on the wall.

3 Put aside the mounting panel and drill four holes (ф12) at the marked
locations. Be sure that the drill bit isф12 and the depth of the four holes is 52 ~
60mm.

3 Put aside the nut, spring washer and flat washer from the expansion bolts, and
insert the expansion bolts and the expansion tubes into the holes. Be sure that
the guiding ribs of the expansion bolts are aligned with the guiding slots of the
expansion tubes. Figure 2-5 illustrates the process.

4 Attach the mounting panel to the chassis using four M3 screws. Figure 2-6
illustrates the procedure.

5 Secure the chassis and the mounting panel to the wall together using nuts,
spring washers and flat washers which are removed from the expansion bolts
in Step2. Figure 2-7 illustrates the procedure.

E xpa nd tu b
B o lt M 6 ¡ Á60

Figure 2-5 Inserting expansion bolt

Huawei Technologies Proprietary

2-3
OptiX Metro 500
Installation Manual 2 Installation of the OptiX Metro 500 I

M3 screw

Figure 2-6 Attaching the mounting panel and the chassis

Figure 2-7 Securing the chassis

Huawei Technologies Proprietary

2-4
OptiX Metro 500
Installation Manual 2 Installation of the OptiX Metro 500 I

2.2 Installation in 19-inch Rack


2.2.1 Overview

1. Illustration

Figure 2-8 illustrates the installation in 19-inch rack.

Figure 2-8 Installation in 19-inch rack

2. Parts

Figure 2-9 illustrates the necessary parts: pallet, chassis, ear bracket and rack.

19-inch rack
Chassis
Ear bracket

Pallet

Figure 2-9 Parts of installation in 19-inch rack

Huawei Technologies Proprietary

2-5
OptiX Metro 500
Installation Manual 2 Installation of the OptiX Metro 500 I

2.2.2 Installation Procedure

Follow the steps below to install the OptiX Metro 500 in 19-inch rack.
Step Action
1 Attach two ear brackets to the chassis using four M3 screws. See Figure 2-10.

2 Attach the pallet to the cabinet using four panel fasteners. See Figure 2-11

3 Slide the chassis into the cabinet and secure it using four panel fasteners. See
Figure 2-12.

M3 screw

Figure 2-10 Attaching two ear brackets

19-inch rack

M6 screw

Figure 2-11 Attaching the pallet

Huawei Technologies Proprietary

2-6
OptiX Metro 500
Installation Manual 2 Installation of the OptiX Metro 500 I

M6 screw

Figure 2-12 Securing the chassis

Huawei Technologies Proprietary

2-7
OptiX Metro 500
Installation Manual 2 Installation of the OptiX Metro 500 I

2.3 Installation in 300mm-deep ETSI Cabinet


2.3.1 Overview

1. Illustration

Figure 2-13 illustrates the installation in the 300mm-deep ETSI cabinet.

Figure 2-13 Installation in the 300mm-deep ETSI cabinet

2. Parts

Figure 2-14 illustrates the necessary parts. The mounting panel is the same as that
of wall mounting.

Huawei Technologies Proprietary

2-8
OptiX Metro 500
Installation Manual 2 Installation of the OptiX Metro 500 I

Cabinet

Mounting panel
M6 screw

Chassis

Figure 2-14 Parts of installation in the 300mm-deep ETSI cabinet

2.3.2 Installation Procedure

Follow the steps below to install the OptiX Metro 500 in 300mm-deep ETSI cabinet.
Step Action
1 Attach the chassis to the mounting panel using four supplied M3 screws. See
Figure 2-15.

2 Attach the mounting panel and the chassis to the cabinet together using four
supplied M6 screws. See Figure 2-16.

Huawei Technologies Proprietary

2-9
OptiX Metro 500
Installation Manual 2 Installation of the OptiX Metro 500 I

Figure 2-15 Attaching the mounting panel to the chassis

M6 screw

Figure 2-16 Fixing the chassis into the cabinet

Huawei Technologies Proprietary

2-10
OptiX Metro 500
Installation Manual 2 Installation of the OptiX Metro 500 I

2.4 Installation in 600mm-deep ETSI Cabinet


The installation is the same as installation in 19-inch rack. But the ear bracket is not
same as that in 19-inch rack. See “2.2 Installation in 19-inch Rack”.

Ear bracket in 19-inch rack

Ear bracket in 600mm-deep ETSI cabinet

Figure 2-17 Ear bracket

2.5 Desktop Mounting


Before the installation on a table top, it is necessary to fix the four supplied
self-adhesive pads under the equipment. See Figure 2-18.

Self-adhesive
pads

Self-adhesive
pads
Self-adhesive
pads

Self-adhesive
pads

Figure 2-18 Self-adhesive pads

Huawei Technologies Proprietary

2-11
OptiX Metro 500
Installation Manual 2 Installation of the OptiX Metro 500 I

2.6 Board Installation


SP2D, ET1D and N64 boards can be installed in the extend slot of the OptiX Metro
500 I.
Follow the steps below to install boards.
Step Action
1 With the locking lever in the open position, slide the board into the slot until the
card connector meets the backplane connector.

2 Lock the board in position by mating the locking lever with the shelf rails and
rotating the lever until it is flush with the board faceplate.

3 Fasten the two float screws.

Figure 2-19 Inserting the board

Figure 2-20 Fixing the board