To,
22-3-26/5,Yakutpura,
Charminar, Hyderabad.
Gentleman,
Referring to the subject and reference cited above ,it is to inform that the above
work was sanctioned for an amount of Rs 2.55 lakhs the Work order was also given to you on
11-05-2017 and after a lapse of more than (08) months, you have failed to start the work despite of
repeated request.
Therefore you are hereby requested to start the work within (7) days and see that the work is
completed within the stipulated period of agreement, since there is lot of pressure from the Hon’ble
MLA and higher authorities. Failing which, the action would be initiated as per Clause 60 C of
APDSS for terminating the agency
Yours faithfully
Executive Engineer
Circle No:6,SZ,GHMC
Date: -01-2018
To,
22-3-26/5,Yakutpura,
Charminar, Hyderabad.
Gentleman,
Referring to the subject and reference cited above ,it is to inform that the above
work was sanctioned for an amount of Rs 3.55 lakhs the Work order was also given to you on
11-05-2017 and after a lapse of (08) months, you have failed to start the work despite of repeated
request.
Therefore you are hereby requested to start the work within (7) days and see that the work is
completed within the stipulated period of agreement, since there is lot of pressure from the Hon’ble
MLA and higher authorities. Failing which, the action would be initiated as per Clause 60 C of
APDSS for terminating the agency
Yours faithfully
Executive Engineer
Circle No:6,SZ,GHMC
Date: -01-2018
To,
Hyderabad.
Gentleman,
Referring to the subject and reference cited above ,it is to inform that the above
work was sanctioned for an amount of Rs 3.9 lakhs the Work order was also given to you on
11-05-2017and after a lapse of (08) months, you have failed to start the work despite of repeated
request.
Therefore you are hereby requested to start the work within (7) days and see that the work is
completed within the stipulated period of agreement, since there is lot of pressure from the Hon’ble
MLA and higher authorities. Failing which, the action would be initiated as per Clause 60 C of
APDSS for terminating the agency
Yours faithfully
Executive Engineer
Circle No:6,SZ,GHMC
Date: -01-2018
To,
Gentleman,
Referring to the subject and reference cited above ,it is to inform that the above
work was sanctioned for an amount of Rs 5.55 lakhs the Work order was also given to you on
11-05-2017and after a lapse of (08) months, you have failed to start the work despite of repeated
request.
Therefore you are hereby requested to start the work within (7) days and see that the work is
completed within the stipulated period of agreement, since there is lot of pressure from the Hon’ble
MLA and higher authorities. Failing which, the action would be initiated as per Clause 60 C of
APDSS for terminating the agency
Yours faithfully
Executive Engineer
Circle No:6,SZ,GHMC
Date: -01-2018
To,
Hyderabad.
Gentleman,
Referring to the subject and reference cited above ,it is to inform that the above
work was sanctioned for an amount of Rs 4.66 lakhs the Work order was also given to you on
31-05-2017and after a lapse of (07) months, you have failed to start the work despite of repeated
request.
Therefore you are hereby requested to start the work within (7) days and see that the work is
completed within the stipulated period of agreement, since there is lot of pressure from the Hon’ble
MLA and higher authorities. Failing which, the action would be initiated as per Clause 60 C of
APDSS for terminating the agency
Yours faithfully
Executive Engineer
Circle No:6,SZ,GHMC
Date: -01-2018
To,
Hyderabad.
Gentleman,
Referring to the subject and reference cited above ,it is to inform that the above
work was sanctioned for an amount of Rs 18.35 lakhs the Work order was also given to you on
11-12-2017and after a lapse of (01) month, you have failed to start the work despite of repeated
request.
Therefore you are hereby requested to start the work within (7) days and see that the work is
completed within the stipulated period of agreement, since there is lot of pressure from the Hon’ble
MLA and higher authorities. Failing which, the action would be initiated as per Clause 60 C of
APDSS for terminating the agency
Yours faithfully
Executive Engineer
Circle No:6,SZ,GHMC
Date: -01-2018
To,
Hyderabad.
Gentleman,
Referring to the subject and reference cited above ,it is to inform that the above
work was sanctioned for an amount of Rs 10.5 lakhs the Work order was also given to you on
11-12-2017 and after a lapse of (01) month, you have failed to start the work despite of repeated
request.
Therefore you are hereby requested to start the work within (7) days and see that the work is
completed within the stipulated period of agreement, since there is lot of pressure from the Hon’ble
MLA and higher authorities. Failing which, the action would be initiated as per Clause 60 C of
APDSS for terminating the agency
Yours faithfully
Executive Engineer
Circle No:6,SZ,GHMC
Date: -01-2018
To,
Gentleman,
Referring to the subject and reference cited above ,it is to inform that the above
work was sanctioned for an amount of Rs 19.9 lakhs the Work order was also given to you on
11-12-2017and after a lapse of (01) month, you have failed to start the work despite of repeated
request.
Therefore you are hereby requested to start the work within (7) days and see that the work is
completed within the stipulated period of agreement, since there is lot of pressure from the Hon’ble
MLA and higher authorities. Failing which, the action would be initiated as per Clause 60 C of
APDSS for terminating the agency
Yours faithfully
Executive Engineer
Circle No:6,SZ,GHMC
Date: -01-2018
To,
H.NO. 17-1-382/VP/12/A/2,
Hyderabad, T.S
Gentleman,
Referring to the subject and reference cited above ,it is to inform that the above
work was sanctioned for an amount of Rs16.10 lakhs the Work order was also given to you on
11-12-2017and after a lapse of (01) month, you have failed to start the work despite of repeated
request.
Therefore you are hereby requested to start the work within (7) days and see that the work is
completed within the stipulated period of agreement, since there is lot of pressure from the Hon’ble
MLA and higher authorities. Failing which, the action would be initiated as per Clause 60 C of
APDSS for terminating the agency
Yours faithfully
Executive Engineer
Circle No:6,SZ,GHMC
Date: -01-2018
To,
Hyderabad
Gentleman,
Referring to the subject and reference cited above ,it is to inform that the above
work was sanctioned for an amount of Rs 8 lakhs the Work order was also given to you on
11-12-2017 and after a lapse of (01) month, you have failed to start the work despite of repeated
request.
Therefore you are hereby requested to start the work within (7) days and see that the work is
completed within the stipulated period of agreement, since there is lot of pressure from the Hon’ble
MLA and higher authorities. Failing which, the action would be initiated as per Clause 60 C of
APDSS for terminating the agency
Yours faithfully
Executive Engineer
Circle No:6,SZ,GHMC
Date: -01-2018
To,
Hyderabad.
Gentleman,
Referring to the subject and reference cited above ,it is to inform that the above
work was sanctioned for an amount of Rs 7 lakhs the Work order was also given to you on
11-12-2017 and after a lapse of (01) month, you have failed to start the work despite of repeated
request.
Therefore you are hereby requested to start the work within (7) days and see that the work is
completed within the stipulated period of agreement, since there is lot of pressure from the Hon’ble
MLA and higher authorities. Failing which, the action would be initiated as per Clause 60 C of
APDSS for terminating the agency
Yours faithfully
Executive Engineer
Circle No:6,SZ,GHMC
Date: -01-2018
To,
Hyderabad.
Gentleman,
Sub:Esst-Cir-6-SC-GHMC-laying of CC Road with RMC from from H.No: 16-2-570 to 16-2-558 and
16-2-553 to 16-2-537/38 of lane 5 in Palton in Akbarbagh Div-27,GHMC. –Work still not started-
Notice-I.Issued as per APDSS Clause 60-C – Regarding
Referring to the subject and reference cited above ,it is to inform that the above
work was sanctioned for an amount of Rs 8 lakhs the Work order was also given to you on
11-12-2017and after a lapse of (01) months, you have failed to start the work despite of repeated
request.
Therefore you are hereby requested to start the work within (7) days and see that the work is
completed within the stipulated period of agreement, since there is lot of pressure from the Hon’ble
MLA and higher authorities. Failing which, the action would be initiated as per Clause 60 C of
APDSS for terminating the agency
Yours faithfully
Executive Engineer
Circle No:6,SZ,GHMC
Date: -01-2018
To,
H.NO-20-5-512/A,Shakergunj,Shalibanda,
Hyderabad.
Gentleman,
Referring to the subject and reference cited above ,it is to inform that the above
work was sanctioned for an amount of Rs 9 lakhs the Work order was also given to you and after a
lapse of(01) month, you have failed to start the work despite of repeated request.
Therefore you are hereby requested to start the work within (7) days and see that the work is
completed within the stipulated period of agreement, since there is lot of pressure from the Hon’ble
MLA and higher authorities. Failing which, the action would be initiated as per Clause 60 C of
APDSS for terminating the agency
Yours faithfully
Executive Engineer