Sunteți pe pagina 1din 7

PENAL CLAUSE on February 4, 1925, the defendant sold his rights in said trucks Nos.

77197 and 92744 to the intervenor, and that as the latter did not sign
1. Bachrach v Espiritu the mortgage deeds, such trucks cannot be considered as mortgaged.

Facts: 6. But there is positive proof that they were included at the time
1. This is a consolidated case(Cases no. 28497 and 28948) the defendant signed these documents. Besides, there were
involving two separate sale transactions. One made in Feb. 18, 1925 presented two of defendant's letters to Hidalgo, an employee of the
(case 28498), when the defendant earlier bought a truck on instalment plaintiff's written a few days before the transaction, acquiescing in the
from the petitioner and said truck was mortgaged together with the inclusion of all his White trucks already paid for, in the mortgage
two others (no. 77197 & 92744 in the the subsequent sale transaction (Exhibit H-I).
dated July 28, 1925. The said two of the other trucks were also
purchased (but already paid previously) from the plaintiff. The Issue: W/N the 25% penalty upon the debt in addition to the 25% p.a.
defendant failed to pay the balance. In July 1925, defendant again is usurious
purchased another truck from Bachrach. The said truck, together with
the 3 other vehicles were mortgaged to the plaintiff to secure the Ruling: No, Article 1152 of the Civil Code permits the agreement upon
remaining balance. The defendant failed to pay the balance for the a penalty apart from the interest. Should there be such an agreement,
latest truck obtained. the penalty, as was held in the case of Lopez vs. Hernaez (32 Phil.,
631), does not include the interest, and which may be demanded
2. It was agreed in both sales that 12% interest will be paid on the separately. The penalty is not to be added to the interest for the
unpaid price, and in case of the non-payment of the total debt at determination of whether the interest exceeds the rate fixed by the
maturity, 25% shall be the penalty. The defendant also signed a law, since said rate was fixed only for the interest. But considering
promissory note solidarily with his brother Rosario (acting as that the obligation was partly performed, and making use of the power
intervenor), the sums secured by the mortgages. Rosario is alleged to given to the court by article 1154 of the Civil Code, this penalty is
be the owner of the two white trucks no. 77197 & 92744 mortgaged. reduced to 10 per cent of the unpaid debt. The penalty is however
reduced from 25 % upon the sum owed, the defendants need pay
3. While these two cases were pending in the lower court the only 10 % thereon as penalty. (Judgment appealed from is affirmed in
mortgaged trucks were sold by virtue of the mortgage, all of them all other respects).
together bringing in, after deducting the sheriff's fees and
transportation charges to Manila, the net sum of P3,269.58.
2. Robes-Francisco v CFI
4. The lower court ordered the defendants and the intervenor to
pay plaintiff in case 28497 the sum of P7,732.09 with interest at the FACTS:
rate of 12 per cent per annum from May 1, 1926 until fully paid, and
25 per cent thereof in addition as penalty. In case 28498, the trial This is an appeal from the decision of the CFI of Rizal
court ordered the defendant and the intervenor to pay plaintiff the sum rendering judgment against Robes-Francisco Corporation to register
of P4,208.28 with interest at 12 per cent per annum from December 1, the deed of absolute sale in favor of Millan with the Register of Deeds
1925 until fully paid, and 25 per cent thereon as penalty. of Caloocan City and secure the corresponding title within ten days
and if not possible said Corporation shall pay Millan the total amount
5. The appellants contend that trucks 77197 and 92744 were not she paid P5,193.63 with interest at 4% per annum from June 22, 1972
mortgaged, because, when the defendant signed the mortgage deeds until fully paid. In either case Robes Corporation is sentenced to pay
these trucks were not included in those documents, and were only put Millan nominal damages of P20,000.00 plus P5,000.00 attorney’s
in later, without defendant's knowledge. Appellants also alleged that fees.
of P20,000.00 is excessive.” Bad faith can not be
Petitioner Corporation questions the award of P20,000.00 presumed. Petitioner Corporation expected that arrangements were
nominal damages and P5,000.00 attorney’s fees alleging such to be possible for the GSIS to make partial releases of the subdivision lots
excessive and unjustified. from the overall real estate mortgage. It was only unfortunate for it
not to succeed in that regard. Hence, the sum of ten thousand pesos
In May 1962, Robes Corporation entered into a contract of by way of nominal damages is fair and just.
sale with Millan for a parcel of land in the amount of 3,864.00 payable
in installments. Millan complied with her obligation and made her final 3. Pamintuan v CA
payment on December 22, 1971 for a total payment of P5,193.63
including interests and expenses for registration of title. On March 2, FACTS:
1973 the deed of absolute sale was executed but the transfer Mariano Pamintuan was in an agreement with Yu Ping Kun
certificate of title could not be executed because the parcel of land Co., Inc. to sell plastic sheetings imported by the former from Japan
conveyed to Millan was included among other properties of the through a barter license he had for the export of white flint corn to
corporation mortgaged to GSIS to secure an obligation of P10 million, Toyo Menka Kaisha, Ltd. While the plastic sheetings were arriving in
hence, the owner’s duplicate certificate of title of the subdivision was Manila, Pamintuan informed the President of Yu Ping Kun that he was
in the possession of the GSIS. in dire need of cash and requested that he be paid immediately for the
plastic sheetings. Consequently, the two parties fixed a price to the
plastic sheetings regardless of the kind, quality or actual invoice value
ISSUE: thereof and based it on dividing the total price of the shipment with its
aggregate quantity. After the shipments arrived in Manila (4 shipments
Is the 4% interest provision of the contract a penal clause? in total), Pamintuan only delivered a portion or 224, 150 yards of the
expected 339, 440 yards of plastic sheetings he received to Yu Ping
Kun's warehouse. Furthermore, he delivered plastic sheetings of
RULING: inferior quality that were valued at a lesser price than what Yu Ping
Kun had paid. Subsequently, Yu Ping Kun filed an action to enforce a
No. Said clause does not convey any penalty, for even provision in their contract of sale which states that any violation of the
without it, pursuant to Article 2209 of the Civil Code, the vendee would stipulations of that contract would entitle the aggrieved party to
be entitled to recover the amount paid by her with legal rate of interest liquidated damages in the amount of 10, 000 Php from the offending
which is even more than the 4% provided for in the clause. party.

A penal clause is an accessory undertaking to assume greater ISSUE:


liability in case of breach. From this alone, the 4% provision does not Whether or not compensatory damages may be awarded for
come to be penal in character, hence, Robes Corporation’s contention breach of a contract of sale in addition to liquidated
that the penalty shall substitute the indemnity for damages and the damages/stipulated penalty in the said contract.
payment of interest in case of non-compliance does not hold water.
HELD:
Unfortunately, Millan failed to show the actual damages she Yes, compensatory damages may be awarded for breach of a
suffered as a result of the nonperformance. Nonetheless, the facts contract of sale in addition to liquidated damages/stipulated penalty in
show that the right of the vendee was violated and this entitles her at the said contract. Paragraph 1 of Article 1226 of the New Civil Code
the very least to nominal damages. states that:
“In obligations with a penal
“In the situation before Us, We are of the view that the amount clause, the penalty shall
substitute the indemnity for ‘2. Declaring as lawful, the forfeiture clause under paragraph 12 of the
damages and the payment of said Lease Agreement, and confirming the forfeiture of the plaintiff’s
interests in case of remaining cash deposit of P290,000.00 in favor of the defendant
noncompliance, if there is no thereunder, as of February 11, 1980;
stipulation to the contrary.
Nevertheless, damages shall be ‘3. Ordering the plaintiff to pay the defendant the sum of P289,534.78,
paid if the obligor refuses to pay representing arrears in rentals, unremitted amounts for amusement
the penalty or is guilty of fraud in tax delinquency and accrued interest thereon, with further interest on
the fulfillment of the obligation.” said amounts at the rate of 12% per annum (per lease agreement)
Thus, as a general rule, the penalty takes the place of the from December 1, 1980 until the same is fully paid;
indemnity for damages and the payment of interest. However
there are exceptions to this rule under the Civil Code, and one of ‘4. Ordering the plaintiff to pay the defendant the amount of
them is; when the obligor is guilty of fraud in the fulfillment of P100,000.00, representing the P10,000 portion of the monthly lease
the obligation, indemnity for damages may be awarded in rental which were not deducted from the cash deposit of the plaintiff
addition to and apart from the penalty stipulated. from February to November, 1980, with interest thereon at the rate of
The factual findings of the lower courts that Pamintuan 12% per annum on each of the said monthly amounts of P10,000.00
was guilty of fraud because he did not make a complete delivery from the time the same became due until it is paid;
of the plastic sheetings and he overpriced the same is
conclusive upon the Supreme Court. Hence, based on this fact, ‘5. Ordering the plaintiff to pay the defendant through the injunction
Pamintuan should pay damages. However, in case of fraud the bond, the sum of P100,000.00, representing the P10,000.00 monthly
creditor (in this case Yu Ping Kun), in addition to and apart from increase in rentals which the defendant failed to realize from February
the stipulated penalty, may only recover the difference between to November 1980 resulting from the injunction, with legal interest
the actual proven damages and the stipulated penalty. thereon from the finality of this decision until fully paid;

‘6. Ordering the plaintiff to pay the defendant the sum equivalent to
4. Country Bankers v CA ten per centum (10%) of the above-mentioned amounts of
P289,534.78, P100,000.00 and P100,000.00, as and for attorney’s
Nature Petition for certiorari to review the decision of the Court of fees; and
Appeals.
‘7. Ordering the plaintiff to pay the costs.’”
 -Respondent Oscar
FACTS Ventanilla Enterprises Corporation (OVEC), as lessor, and the
petitioner Enrique F. Sy, as lessee entered into a lease agreement
- The CA affirmed the RTC’s decision, to wit:
 “WHEREFORE, THE over the Avenue, Broadway and Capitol Theaters and the land on
COMPLAINT OF THE PLAINTIFF Enrique F. Sy is dismissed, which they are situated in Cabanatuan City. The term of the lease was
for six years from June 13, 1977 to June 12, 1983. After more than
and on the counterclaim of the defendant O. Ventanilla Enterprises two years of operation of the theaters, the lessor OVEC
Corporation, judgment is hereby rendered:
made demands for the repossession of the said leased properties in
‘1. Declaring as lawful, the cancellation and termination of the Lease view of Sy’s arrears in monthly rentals and non-payment of
Agreement (Exh. A) and the defendant’s re-entry and repossession of amusement taxes. On August 8, 1979, OVEC and Sy had a
the Avenue, Broadway and Capitol theaters under lease on February conference and by reason of Sy’s request for reconsideration, he was
11, 1980; allowed to continue operating the leased premises upon his
conformity to certain conditions imposed by the latter in a theaters upon Sy’s filing of a P500,000.00 bond supplied by Country
supplemental agreement dated August 13, 1979. Bankers Insurance Corporation (CBISCO). Respondents'
Counterclaim
- In pursuance to their latter agreement, Sy reduced his arrears in
rental. However, the accrued amusement liability tax had accumulated - By reason of Sy’s violation of the lease agreement, OVRC became
to 84,000.00 despite the fact that Sy had been deducting amounts authorized to enter and possess the theaters as well as to terminate
from his monthly rental with the obligation to remit said deductions to said agreement so the balance of deposits given by Sy had thus
the city government. Hence, letters of demand dated January 7, 1980 become forfeited.
 - OVEC would be losing P50,000.00 for every
and February 3, 1980 were sent to Sy demanding payment of the month that the possession and operation of the theaters remain with
arrears in rentals and amusement tax delinquency. The latter demand Sy.
was with the warning that OVEC will repossess the theaters on
February 11, 1980 in pursuance with their lease contract and their - OVEC incurred P500,000.00 for attorney’s fees.
supplemental letter-agreement. But notwithstanding the said demands
and warnings Sy failed to pay the above- mentioned amounts in full. ISSUE
 WON respondent is unjustly enriched at the expense of
Consequently, OVEC took possession thereof in the morning of petitioners
February 11, 1990.
HELD
- Sy filed the present action for reformation of the lease agreement,
damages and injunction. And by virtue of a restraining order dated NO.
February 12, 1980 followed by an order to issue a writ of preliminary
injunction, Sy regained possession of the theaters. Ratio As a general rule, in obligations with a penal clause, the penalty
shall substitute the indemnity for damages and the payment of
Petitioners' Claim interests in case of non- compliance. However, there are exceptions:

- Sy alleged that the amount of deposit—P600,00.00 as agreed upon, 1) when there is a stipulation to the contrary
 2) when the obligor is
P300,000.00 of which was to be paid on June 13, 1977 and the sued fro refusal to pay the agreed penalty 3) when the obligor is guilty
balance on December 13, 1977— was too big; and OVEC assured of fraud
him that said forfeiture will not come to pass.
 - Sy sought to recover
from OVEC the sums of P100,000.00 for repairs in the Broadway Reasoning The forfeiture clause in the lease agreement would not
theater; P48,000.00 for electrical cost of OVEC’s “illegal connection” unjustly enrich OVEC at expense of Sy and CBISCO—contrary to law,
in the Capitol theater; and P31,000.00 for electrical cost of OVEC’s morals, good customs, public order or policy. A penal clause is an
“illegal connection” in the Broadway theater and for damages suffered accessory obligation which the parties attach to a principal obligation
by SY as a result of each connection. for the purpose of insuring the performance thereof by imposing on
the debtor a special prestation (generally consisting in the payment of
- It is also alleged that on February 11, 1980, OVEC had the three a sum of money) in case the obligation is not fulfilled or is irregularly
theaters padlocked with the use of force, and as aresult, Sy suffered or inadequately fulfilled.
damages at the rate of P5,000 a day because of his failure to go thru
the contracts with movie and booking companies for the showing of In the case at bar, the penalty cannot substitute for the P100,000.00
movies. supposed damage suffered by OVEC from opportunity cost. It
represents the P10,000 per month in additional rental during the ten
- Finally, Sy prayed for the issuance of a restraining order/ preliminary months of injunction period. Thus, it must be applied against the
injunction to enjoin OVEC from entering and taking possession of the injunction bond.
Disposition ACCORDINGLY, finding no merit in the grounds relied are clear and leave no doubt as to the intention of the parties, the
upon by petitioners in their petition, the same is hereby DENIED and literal meaning of its stipulation should govern.
the decision dated June 15, 1988 and the resolution dated September
21, 1988, both of the respondent Court of Appeals are AFFIRMED The Kasunduan contained a penal clause which provides that a party
who violates any of its provisions shall be liable to pay the aggrieved
party a penalty fixed at P50K, together with the attorney’s fees and
5. Heirs of Manuel Uy v Meer Castillo litigation expenses incurred by the latter should judicial resolution of
the matter becomes necessary. The obligor would then be bound to
FACTS: pay the stipulated indemnity without the necessity of proof of the
Respondents in this case were petitioners in a civil case to annul the existence and the measure of damages caused by the breach. The
title of PMPCI over respondents’ land. Respondents entered into an penalty clause generally substitutes the indemnity for damages
AGREEMENT whereby in exchange for the legal services of Atty. and the payment of interests in case of noncompliance. The rule
Zepeda and the financial assistance of MANUEL UY EK LIONG, in is settled that a penal clause is not limited to actual and
the event of a favorable decision in the civil case, Atty Zepeda and compensatory damages.
Manuel would be entitled to 40% of the realties and/or monetary The RTC’s award of attorney’s fees in the sum of P50,000.00 is,
benefits which may be adjudicated in favor of the respondents. however, proper. Aside from the fact that the penal clause included a
Respondents, on the same day entered into a Kasunduan, agreeing liability for said award in the event of litigation over a breach of the
to sell the remaining 60% share in the land in favor of Manuel for the Kasunduan, petitioners were able to prove that they incurred said sum
sum of 180k. Manuel would pay a 1K down payment upon execution in engaging the services of their lawyer to pursue their rights and
of the Kasunduan. They agreed that any party violating the protect their interests.
Kasunduan would pay the aggrieved party a penalty fixed in the sum
of P50K, together with the attorney’s fees and litigation expenses
incurred should a case be subsequently filed in court. 6. Lo v CA (wala case digest sa net)
The respondents won in the CIVIL CASE. The land was divided in
accordance with the Agreement but the respondents refused to
comply with the KASUNDUAN, despite Manuel’s offer to pay the ANTONIO LO, petitioner, vs. THE HON. COURT OF APPEALS
remaining 179K balance, claiming that the same was void ab initio for AND NATIONAL ONIONS GROWERS COOPERATIVE
being violative violative of Art 1491 of the NCC and the Canons of MARKETING ASSOCIATION, INC., respondents.
Professional Responsibility. Article 1491 prohibits lawyers from
acquiring by purchase or assignment the property /rights involved in DECISION
the litigation in which they intervene by virtue of their profession. CORONA, J.:
Manuel instituted an action for Specific Performance and Damages
against respondents.
Assailed in the instant petition for review on certiorari under Rule
ISSUE: w/n the Kasunduan should be given effect
45 of the Rules of Court is the May 26, 1998 decision[1] of the Court of
HELD: The Kasunduan is valid. The prohibition applies only during the
Appeals modifying the decision of the Regional Trial Court of
pendency of the suit and generally does not cover contracts for
Malabon, Branch 74:
contingent fees where the transfer takes effect only after the finality of
a favorable judgment. The Agreement and the Kasunduan are not
independent contracts, with parties, objects and causes different from WHEREFORE, the assailed decision is hereby AFFIRMED with the
that of the other. Obligations arising from contracts have the force of MODIFICATION that the penalty imposed for each day of delay in
law between the contracting parties. When the terms of the contract surrendering the leased property is reduced fromP5,000.00
to P1,000.00 per day of delay.[2]
At the core of the present controversy are two parcels of land 3) To pay the sum of P36,000.00 a month from January 1996
measuring a total of 2,147 square meters, with an office building until it finally vacates the premises as payment for
constructed thereon, located at Bo. Potrero, Malabon, Metro Manila reasonable compensation for the use and occupancy
and covered by TCT Nos. M-13166 and M-13167. thereof;
Petitioner acquired the subject parcels of land in an auction sale
4) To pay the sum of P20,000.00 by way of reasonable
on November 9, 1995 for P20,170,000 from the Land Bank of the
attorneys fees; and
Philippines (Land Bank).
Private respondent National Onion Growers Cooperative 5) To pay the costs of suit.[3]
Marketing Association, Inc., an agricultural cooperative, was the
occupant of the disputed parcels of land under a subsisting contract of On appeal to the Regional Trial Court of Malabon, Branch 74, the
lease with Land Bank. The lease was valid until December 31, 1995. MTC decision was affirmed in toto on August 29, 1997.[4] Private
Upon the expiration of the lease contract, petitioner demanded respondents subsequent motion for reconsideration of the RTC
that private respondent vacate the leased premises and surrender its decision was denied on November 26, 1997.
possession to him. Private respondent refused on the ground that it From the adverse decision of the trial court, private respondent
was, at the time, contesting petitioners acquisition of the parcels of elevated the case to the Court of Appeals via a petition for review.
land in question in an action for annulment of sale, redemption and
damages. On May 26, 1999, the Court of Appeals rendered its assailed
decision affirming the decision of the trial court, with the modification
On February 23, 1996, petitioner filed an action for ejectment that the penalty imposed upon private respondent for the delay in
before the Metropolitan Trial Court of Malabon, Branch 55. He turning over the leased property to petitioner was reduced
asked, inter alia, for the imposition of the contractually stipulated from P 5,000 to P 1000 per day.
penalty of P5,000 per day of delay in surrendering the possession of
the property to him. On September 3, 1996, the trial court decided the Unsatisfied with the decision of the Court of Appeals, petitioner
case in favor of petitioner: filed the instant petition for review, raising the sole issue of the alleged
lack of authority of the Court of Appeals to reduce the penalty
WHEREFORE, premises considered, the Court considers the awarded by the trial court, the same having been stipulated by the
allegations of the complaint to be true and duly substantiated except parties in their Contract of Lease.
as to the amount of damages and attorneys fees, which are reduced The petition has no merit.
accordingly, a decision is hereby rendered in favor of the plaintiffs and
against the defendant, ordering the latter and all persons claiming Generally, courts are not at liberty to ignore the freedom of the
rights under it: parties to agree on such terms and conditions as they see fit as long
as they are not contrary to law, morals, good customs, public order or
1) To vacate the leased premises immediately and turn over public policy. Nevertheless, courts may equitably reduce a stipulated
the same peacefully to the plaintiffs; penalty in the contract if it is iniquitous or unconscionable, or if the
principal obligation has been partly or irregularly complied with.[5]
2) To pay plaintiff Antonio Lo the sum of P5,000.00 for every This power of the courts is explicitly sanctioned by Article 1229 of
day of delay from the time defendant is supposed to the Civil Code which provides:
have vacated the premises;
Article 1229. The judge shall equitably reduce the penalty when the
principal obligation has been partly or irregularly complied with by the
debtor. Even if there has been no performance, the penalty may also
be reduced by the courts if it is iniquitous or unconscionable.

The question of whether a penalty is reasonable or iniquitous is


addressed to the sound discretion of the court and depends on
several factors, including, but not limited to, the following: the type,
extent and purpose of the penalty, the nature of the obligation, the
mode of breach and its consequences, the supervening realities, the
standing and relationship of the parties.[6]
In this case, the stipulated penalty was reduced by the appellate
court for being unconscionable and iniquitous. As provided in the
Contract of Lease, private respondent was obligated to pay a monthly
rent of P30,000. On the other hand, the stipulated penalty was
pegged at P5,000 for each day of delay or P150,000 per month, an
amount five times the monthly rent. This penalty was not only
exorbitant but also unconscionable, taking into account that private
respondents delay in surrendering the leased premises was because
of a well-founded belief that its right of preemption to purchase the
subject premises had been violated. Considering further that private
respondent was an agricultural cooperative, collectively owned by
farmers with limited resources, ordering it to pay a penalty
of P150,000 per month on top of the monthly rent of P30,000 would
seriously deplete its income and drive it to bankruptcy. In Rizal
Commercial Banking Corp. vs. Court of Appeals,[7] the Court tempered
the penalty charges after taking into account the debtors pitiful
financial condition.
Accordingly, we rule that the Court of Appeals did not commit any
reversible error in the exercise of its discretion when it reduced the
award of penalty damages fromP5,000 to P1,000 for each day of
delay.
WHEREFORE, petition is hereby DENIED. The decision of the
Court of Appeals reducing the amount of penalty damages against
private respondent is AFFIRMED.
SO ORDERED.

S-ar putea să vă placă și