Sunteți pe pagina 1din 5

Sadara Business Complex

TAMIMI GLOBAL COM. LTD. - TAFGA

Client SADARA : SADARA


Contract No. 00192-2016 : 00192-2016

Technical Proposal
Modification and Installation of the
Water supply Booster standby system
for the SBC

07-sept- Issue for Review & Razi ullah Khan


01 TAMIMI HSE
2017 Approval (Utility Engineer) Nelson Ty

Approved by
Rev. Date Status Prepared By Approved by
SADARA
SADARA BUSINESS COMPLEX
RENOVATION PROJECT
Modification and
Installation of the Water
supply Booster standby
system for the SBC

Date:07-Sept-2017 Page 1 of 4

INDEX

Section Title Page

1 Proposal 2

2 Scope of Work 2

3 List of Equipment & Personnel 2

4 Sequence of Activities 2

5 Responsibilities 2

6 Procedure 3

7 Compliance to Safety & Protection 3

8 Quality Control 4

9 Test & Quality Records 4

10 Attachments 4
SADARA BUSINESS COMPLEX
RENOVATION PROJECT
Modification and
Installation of the Water
supply Booster standby
system for the SBC

Date:07-Sept-2017 Page 2 of 4

1. Purpose
This proposal is for the water supply network modification and installation of the standby
booster system in cases of the repair of existing booster pumps for the Sardara business
complex at the NH1 Pump room.
2. Scope of Work
2.1 Modification of the existing piping system (Main Header line and Fittings.)
2.2 Grouting of the Pump base for installation of the new booster pumps
2.3 Installation of the 2 new booster system in series connection with the piping connections
to the existing Admin and other SBC facilities main Water supply headers.

3. List of Equipment
3.1 Booster pump.
3.2 Plumbing tool kit for the relocation of expansion tank and installation of the booster
pump.
3.3 Differential pressure switch
3.4 Electrical disconnect switch

4. Sequence of Activities

4.1. Ensure that proper Lock out /Tag out is done prior to carrying out any activity , ensure that Line
opening procedure is taken into consideration.

4.2. Ensure that proper safe work permit is acquired for carrying out the activity.

4.3 Ensure that the activity is lead by an efficient supervisor and qualified manpower.

4.4. Remove the expansion tank for the booster pumps (NH1 service line) and relocate it to the
designated area as represented in the revision or modification drawing.

4.5. Ensure that proper equipment handling is done in shifting the expansion tank.

4.6. Ensure that proper concrete base is provided for the installation of the new booster pump as
standby service.

4.7 Ensure that proper structural support is provided and proper allingment procedure is carried out
before the final installation of the pumps.
SADARA BUSINESS COMPLEX
RENOVATION PROJECT
Modification and
Installation of the Water
supply Booster standby
system for the SBC

Date:07-Sept-2017 Page 3 of 4

4.8 Carry out all the piping connection and fitting to be installed for the installation of the booster
pumps inline as per SADARA standards.

4.9 Make sure that proper electrical conducting , breaker panel and proper termination is provided as
per the required RLA for the pumps.
4.10 Proper post activity housekeeping have to be performed once the accomplishment of the work
activity.
4.11 The differential pressure of the pump will be set at the pressure 5 bar in order to
accommodate the water supply pressure for both Admin Building and other SBC facilities in their
individual maintenance shutdowns.
4.12 All the civil , Electrical and plumbing work carried out in order is accomplish the proposal is
inspected by the SADARA QC before the final energization , commissioning and turnover of the
system

5. Procedure
- Refer to attached detailed modification procedure.

6. Responsibilities
6.1 Maintenance Engineer
6.1.1 Supervise and plan the activity.
6.2 Technician
6.2.1 Take the steps according to above method statement and perform the activity.
6.3 Pipe fitter
Installation of the booster pump and necessary piping connection.
6.4 Civil team
Preperation for the booster pump concrete foundation with proper grouting.

7. Compliance to Safety & Protection


Prior to start any work activities following major steps would be carefully followed,
following the necessary approval and work permit received from Sadara.

Potential hazard in Executing Procedure and mitigation.


a. Improper material used.
b. Proper procedure for the lifting.
c. Proper Emergency evacuation access to be provided.
SADARA BUSINESS COMPLEX
RENOVATION PROJECT
Modification and
Installation of the Water
supply Booster standby
system for the SBC

Date:07-Sept-2017 Page 4 of 4

Preventive Measures
7.1 Wear rubber hand gloves & safety glasses.
7.2 Measure taken to ensure the activity is carried out with proficient personnel’s.
7.3 No any hot work activity near.
7.4 Work area shall be isolated with barricade.
7.5 Hazard awareness signages must be posted.

8. Test & Quality Record


All the tests and record shall document the compliance to the project quality plan and
other project requirements and to be submitted to Sadara at the close of the project.