ID Task Name Start Finish Duration Resource Names ID % Work 21 Jan '18 28 Jan '18 4 Feb '18 11 Feb

Resource Names ID % Work 21 Jan '18 28 Jan '18 4 Feb '18 11 Feb '18 18 Feb '18
Complete 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
1 Process & Plant Design I 18/1/2018 27/4/2018 74 days 1 2%
2 Project Schedule and Milestones 18/1/2018 13/4/2018 64 days 2 5%
3 Gather Data & Assignments Familiarization 18/1/2018 21/1/2018 3 days All 3 100% All
4 First Meeting 22/1/2018 22/1/2018 1 day All 4 100% All
5 Construction of Preliminary Chart 23/1/2018 23/1/2018 1 day Teck Ming 5 100% Teck Ming
6 Draft Amendments 24/1/2018 26/1/2018 3 days All 6 100% All
7 First Submission 27/1/2018 27/1/2018 1 day All 7 0% 27/1
8 Adjustment of Preliminary Chart 28/1/2018 28/2/2018 25 days Teck Ming 8 0%
9 Construction of Progress Report 1 28/1/2018 28/2/2018 25 days Ming Shern,Jia Shinn 9 0%
10 Submission of Gantt Chart & Progress Report 1 2/3/2018 2/3/2018 1 day All 10 0%
11 Adjustment of Gantt Chart 3/3/2018 12/4/2018 30 days Teck Ming 11 0%
12 Construction of Progress Report 2 3/3/2018 12/4/2018 30 days Christopher,Alvin 12 0%
13 Submission of Gantt Chart & Progress Report 2 13/4/2018 13/4/2018 1 day All 13 0%
14 Feasibility Study/Location 27/1/2018 9/2/2018 12 days 14 0%
15 Gather Data & Assignments Familiarization 27/1/2018 28/1/2018 2 days All 15 0% All
16 First Meeting 29/1/2018 29/1/2018 1 day All 16 0% All
17 Draft Construction 29/1/2018 3/2/2018 6 days 17 0%
18 Process Analysis & Background Research 29/1/2018 2/2/2018 5 days Teck Ming 18 0% Teck Ming
19 Identify Process Pathway 29/1/2018 2/2/2018 5 days Alvin 19 0% Alvin
20 Selection of Plant Capacity & Location 29/1/2018 2/2/2018 5 days Christopher,Jia Shinn 20 0% Christopher,Jia Shinn
21 Process Safety Analysis 29/1/2018 2/2/2018 5 days Ming Shern 21 0% Ming Shern
22 Compilation of First Draft 3/2/2018 3/2/2018 1 day Teck Ming 22 0% Teck Ming
23 Adjustment of the Draft 4/2/2018 8/2/2018 5 days All 23 0% All
24 Final Submission 9/2/2018 9/2/2018 1 day All 24 0% 9/2
25 Preliminary Process Synthesis & Heuristics 9/2/2018 9/3/2018 21 days 25 0%
26 First Meeting (BFD Discussion) 9/2/2018 9/2/2018 1 day All 26 0% All
27 Construction of BFD Draft 10/2/2018 12/2/2018 2 days Teck Ming,Ming Shern 27 0% Teck Ming,Ming Shern
28 Second Meeting (Task Allocation) 13/2/2018 13/2/2018 1 day All 28 0% All
29 Plant Designation 14/2/2018 22/2/2018 7 days 29 0%
30 Reactor Design 14/2/2018 22/2/2018 7 days Alvin,Christopher,Jia Shinn 30 0%
31 Separator Design 14/2/2018 22/2/2018 7 days Ming Shern,Teck Ming 31 0%
32 Third Meeting 23/2/2018 23/2/2018 1 day All 32 0%
33 Addition of Pumps and Other Equipments 24/2/2018 1/3/2018 5 days All 33 0%
34 Draft Submission 2/3/2018 2/3/2018 1 day All 34 0%
35 Amendments of Draft 5/3/2018 6/3/2018 2 days Jia Shinn,Christopher 35 0%
36 Compilation of Plant Diagrams 6/3/2018 7/3/2018 2 days Ming Shern 36 0%
37 Amendments of Final Draft 8/3/2018 8/3/2018 1 day Alvin,Teck Ming 37 0%
38 Final Submission 9/3/2018 9/3/2018 1 day All 38 0%
39 Simulation and Manual Calculation on Material & Energy Balances 5/3/2018 2/4/2018 21 days 39 0%
40 First Meeting 5/3/2018 5/3/2018 1 day All 40 0%
41 Aspen HYSYS Simulation 6/3/2018 16/3/2018 9 days All 41 0%
42 Identification of Problems and Data Analysis 17/3/2018 18/3/2018 2 days All 42 0%
43 Second Meeting (Task Allocation) 19/3/2018 19/3/2018 1 day All 43 0%
44 Manual Calculation on Material & Energy Balances 20/3/2018 26/3/2018 5 days 44 0%
45 Reactor Calculation 20/3/2018 26/3/2018 5 days Alvin 45 0%
46 Flash Drum Calculation 20/3/2018 26/3/2018 5 days Christopher 46 0%
47 Separator Calculation 20/3/2018 26/3/2018 5 days Teck Ming 47 0%
48 Heat Exchanger Calculation 20/3/2018 26/3/2018 5 days Jia Shinn 48 0%
49 Absorber Calculation 20/3/2018 26/3/2018 5 days Ming Shern 49 0%
50 Third Meeting (Problem Identification) 27/3/2018 27/3/2018 1 day All 50 0%
51 Amendments on Calculations Draft 28/3/2018 29/3/2018 2 days Ming Shern,Teck Ming,Alvin 51 0%
52 Compilation of Project Data 30/3/2018 30/3/2018 1 day Teck Ming 52 0%
53 Final Checking 1/4/2018 1/4/2018 1 day Jia Shinn,Christopher 53 0%
54 Final Submission 2/4/2018 2/4/2018 1 day All 54 0%
55 Process Flow Diagram (PFD) 3/4/2018 13/4/2018 9 days 55 0%
56 First Meeting (Task Allocation) 3/4/2018 4/4/2018 2 days All 56 0%
57 Adjustment of Previous Work 5/4/2018 5/4/2018 1 day All 57 0%
58 Construction of Process Flow Diagram 6/4/2018 6/4/2018 1 day Ming Shern,Teck Ming 58 0%
59 Preparation of Stream Table 6/4/2018 6/4/2018 1 day Jia Shinn,Christopher,Alvin 59 0%
60 Third Meeting (Problem Identification) 8/4/2018 8/4/2018 1 day All 60 0%

Task Summary Duration-only Start-only External Milestone Manual Progress Sub-Task


Project: Gantt
Split Project Summary Manual Summary Rollup Finish-only Deadline Project Milestone
Date: 24/1/2018
Milestone Manual Task Manual Summary External Tasks Progress Main Task

Page 1
ID Task Name Start Finish Duration Resource Names ID % Work 21 Jan '18 28 Jan '18 4 Feb '18 11 Feb '18 18 Feb '18
Complete 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
61 Compilation of Project Data 9/4/2018 10/4/2018 2 days Teck Ming 61 0%
62 Final Checking 11/4/2018 12/4/2018 2 days All 62 0%
63 Final Submission 13/4/2018 13/4/2018 1 day All 63 0%
64 Completion of Project I 14/4/2018 27/4/2018 11 days 64 0%
65 Compilation of Assignments 14/4/2018 20/4/2018 6 days Teck Ming 65 0%
66 Final Checking 21/4/2018 26/4/2018 5 days All 66 0%
67 Final Submission 27/4/2018 27/4/2018 1 day All 67 0%

Task Summary Duration-only Start-only External Milestone Manual Progress Sub-Task


Project: Gantt
Split Project Summary Manual Summary Rollup Finish-only Deadline Project Milestone
Date: 24/1/2018
Milestone Manual Task Manual Summary External Tasks Progress Main Task

Page 2
18 Feb '18 25 Feb '18 4 Mar '18 11 Mar '18 18 Mar '18 25 Mar '18 1 Apr '18 8 Apr '18 15 Apr '18 22 Apr '18 29 Apr '18
18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29

Teck Ming
Ming Shern,Jia Shinn
2/3
Teck Ming
Christopher,Alvin
13/4

k Ming,Ming Shern

Alvin,Christopher,Jia Shinn
Ming Shern,Teck Ming
All
All
All
Jia Shinn,Christopher
Ming Shern
Alvin,Teck Ming
9/3

All
All
All
All

Alvin
Christopher
Teck Ming
Jia Shinn
Ming Shern
All
Ming Shern,Teck Ming,Alvin
Teck Ming
Jia Shinn,Christopher
2/4

All
All
Ming Shern,Teck Ming
Jia Shinn,Christopher,Alvin
All

Task Summary Duration-only Start-only External Milestone Manual Progress Sub-Task


Project: Gantt
Split Project Summary Manual Summary Rollup Finish-only Deadline Project Milestone
Date: 24/1/2018
Milestone Manual Task Manual Summary External Tasks Progress Main Task

Page 3
18 Feb '18 25 Feb '18 4 Mar '18 11 Mar '18 18 Mar '18 25 Mar '18 1 Apr '18 8 Apr '18 15 Apr '18 22 Apr '18 29 Apr '18
18 19 20 21 22 23 24 25 26 27 28 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29
Teck Ming
All
13/4

Teck Ming
All
27/4

Task Summary Duration-only Start-only External Milestone Manual Progress Sub-Task


Project: Gantt
Split Project Summary Manual Summary Rollup Finish-only Deadline Project Milestone
Date: 24/1/2018
Milestone Manual Task Manual Summary External Tasks Progress Main Task