Documente Academic
Documente Profesional
Documente Cultură
ABSTRACT: A soil nailing technique was used to stabilize a 9-m-deep permanent cut in residual soil for an
expressway project in Singapore. This paper describes the construction details, instrumentation, and performance
of the nailed soil wall and the results of a field pullout test on a grouted nail. Results of numerical analysis are
compared with the measured performance of the wall. The nailed soil wall performed well. Postconstruction
performance of the wall showed moderate increase in wall displacements and nail forces due to loss of soil
suction resulting from seepage of rainwater into the soil.
Downloaded from ascelibrary.org by USP - Universidade De Sao Paulo on 11/23/17. Copyright ASCE. For personal use only; all rights reserved.
Excavation
The excavation was carried out using a backhoe in lifts of NTU C.\NPUS ROAD
'Prof., School of Civ. and Struct. Engrg., Nanyang Tech. Univ., Sin-
SHOTCRffi WAll. 0 L NAIL
gapore 639798.
2Sr. Lect., School of Civ. and Struct. Engrg., Nanyang Tech. Univ.,
Singapore 639798.
3 Asst. Chf. Civ. Engr., Public Works Dept., MND Build., 5 Maxwell ;8
Rd., Singapore 06911 O.
4Geotech. Engr., Maunsell Consultants (Singapore) Pte. Ltd., The Con-
course, 300 Beach Rd., Singapore 199555; formerly, Civ. Engr., Promet
Engrg. (Singapore) Pte. Ltd., 21 Pandan Rd., Singapore 609273.
Note. Discussion open until January J. 1998. To extend the closing
date one month, a written request must be filed with the ASCE Manager
of Journals. The manuscript for this paper was submitted for review and
possible publication on April 11, 1996. This paper is part of the JOUTIUlI rOOTING
of Performance of Constructed Facilities, Vol. 11, No.3, August, 1997.
©ASCE, ISSN 0887-3828/97/0003-0105-01121$4.00 + $.50 per page. FIG. 1. Ground Profile at Site Before and After Construction
Paper No. 13042. and Instrumentation
PLASTIC CENTRAliZERS
AT 1000mm INIERVAlS.
--
SIEH FABRIC
0811UI
___
--4.A-.!OOO
-. :J"" "t....
.,.. ;~' "'"mm niN.
---------------J .rt1RtH~,
li
_______ .' O~
Facing tying the bent portion of the nail to the wale bars. The details
of the nail connection at the facing are shown in Fig. 2. The
After the nails were grouted, the excavated soil face was construction detail of the nail-facing connection at the site is
covered with a steel welded mesh (lO-mm bars at 100-mm shown in Fig. 3.
intervals in both directions), placed with its center 50 mm from The process of installing the nails and shotcreting the facing
the soil face, and covered with a 100-mm-thick layer of shot- was repeated with an incremental depth of excavation of 1.0
crete (with a 28-day characteristic strength of 30 N/mm 2 ) m each time until the required 9-m excavation depth was
sprayed on to the soil face. A second layer of BRC welded reached. In order to distribute the weight of the shotcrete wall
mesh was thcn placed with its center 50 mm from the shotcrete on the soil at the toe of the wall, a 300-mm-thick cantilever
surface, and another layer of shotcrete 100-mm thick was then footing was provided. The footing was then backfilled to a
sprayed over it. Thus the total thickness of the shotcrete facing depth of 1.8 m as shown in Fig. I.
was 200 mm.
The connection of each nail to the facing was made by Drainage
bcnding a SOO-mm length of nail onto the BRC welded mesh. Drainage of the soil nailed wall was provided to prevent the
To provide rigid support to the nails at these connections, three buildup of pore pressure on the facing. In this project, the
bars 25 mm in diameter at 2S0-mm intervals were used as surface water was prevented from coming into contact with
wales running throughout the length of the wall at each nail the facing by means of a surface drain provided at the top of
head level. The nail head was then covered with shotcrete after the wall as shown in Fig. I. The presence of the pavement
also helped in preventing the rainwater from seeping into the
nailed zone. The drainage of the soil was achieved by the
provision of a number of weep holes spaced at 2-m intervals
in both directions. These weep holes consisted of 7S-mm-di-
ameter heavy duty polyvinyl chloride (PVC) pipes perforated
all around with 13-mm-diameter holes staggered at IOO-mm
intervals. Each PVC pipe was wrapped with a geotextile to act
as a filter prior to installation in the weep hole. The length of
each weep hole was 1.5 m. These weep holes sloped down-
wards toward the facing at an inclination of 4°.
Typical details of the nailed cross section of the wall at the
deepest excavation zone are shown in Fig. I. The completed
wall with the expressway is shown in Fig. 4.
PULLOUT TEST ON IN SITU GROUTED NAILS
To understand the load transfer mechanism between soil and
FIG. 3. Details of Nail-Facing Connection nail and to estimate the quality of bond achieved between the
1061 JOURNAL OF PERFORMANCE OF CONSTRUCTED FACILITIES 1 AUGUST 1997
----- ment at the nail head was measured using a dial gauge. The
movement of the concrete pad was also monitored and was
Downloaded from ascelibrary.org by USP - Universidade De Sao Paulo on 11/23/17. Copyright ASCE. For personal use only; all rights reserved.
~.I.~i
two points where the difference in force is considered.
The variation of the axial tensile force and mobilized bond
• i . stress along the nail length at loads of 50 and 78 kN is shown
; i ,
-
0
Distance from facing (m) u.
:l
40 'Nailbardia;:;;eie~25
(b) ~ I ,
mm
"5 Grout hole diameter
;
100
Q.
FIG. 5. Nail Force Variation in Pullout Test: (a) At 50 kN Pullout 20 ......... ··--···1·····.. . + .. -.._.- f·
Load; (b) At Failure Load ,
1
nail and the in situ soil, a pullout test was conducted on a o I ' ' , , i ' , ' ,
specially installed nail at the project site. o 5 10 15 20 25
The pullout test was conducted on a 7-m-long nail installed
Displacement of Nail Head (mm)
in the same way as the actual nails used in the project. The
nail for the pullout test was installed at a depth of 1.5 m below FIG. 6. Pullout Test Results on Nail
-
'0 60
c _ 50
4)E E
4)_ E 40
0_
«S In
- CI) 30
c.~
.~ <.> 20
C- (~
-ca
Es: 10
-CI)
«S
..J
o
o 200 400 600 800 1000 1200 1400
Start date 3rd July 1992 Time (days)
FIG. 8. Lateral Displacement History at Crest of Wall
0.1
0.2
0.3
•
~
..
.s:.
Q,
0.4
•
Downloaded from ascelibrary.org by USP - Universidade De Sao Paulo on 11/23/17. Copyright ASCE. For personal use only; all rights reserved.
41
0.5
">
41
•
eo .----r---,--r--.--,-----r-.., ~ 0.6
!: +--- 'ii
•
(d) !:t::::l::.:~~.~.-.~. -~,..::;;;~.~~
··1·········-+..·....-..·1-··
,fow_·-..l---_>----4-_4--
o J...-N.........
-+- . . .-+---.,
=:.==
_~
0::
0.7
0.8
0.9
60 ~----.-!- - - - , - i --------r'---I;--.--~I---.'I-----'
50 . . .End..oi:..w alL...·..
I
l-.' .· _. ·.·.·.. . ·-f.. . . ._.......§.!.~~1.~. .~~~f.~~~.~.!~~~ . .
i i , ;
'iii
z
~~ ~--+=:::*~:::=:~::::::l~---t---J
O-+--''--'--'---\----'--'--'--!--'--'--'-+-L-...........-t-..........'-'--t-............-'--+-'-----'---'--j
o 200 400 600 800 1000 1200 1400
Start date 9th June Time (days)
FIG. 10. Nail Force Variation with Time
LEGEND
3/02/1995 16:59
2.00
.lep 11
-4.306E+00 <x< 3.181E+Ol
-8.056E+00 <y< 2.806E+Ol
1.50
Grid plot
Downloaded from ascelibrary.org by USP - Universidade De Sao Paulo on 11/23/17. Copyright ASCE. For personal use only; all rights reserved.
I , , , , , , , , , !
0 1E 1
8oundory plot
\ \ \ 1.00
I I ! I ! I I I I ! I
0 1E 1
\ \ \ \ \\ \ \\1
\ \ \ \ 1\
.50
\ \ \ \\
\ \
\ \ ,\ \ \ \
\ \ \ \ \ \ \\l \11\1\\\\\\1\ \ .00
-.50
FIG. 12. FLAC Grid Used In Numerical Analysis of Soil Nailed Wall
with time. The history of the nail forces are shown in Fig. 10 Contiguous bored piles US$60S/m 2
for a typical strain gauge. For strain gauge location A1 (Fig.
1), the nail forces progressively increased at a slow rate during Contiguous bored piles are commonly used as cantilever walls
the excavation stages and the period immediately after con- in Singapore and Malaysia. The system consists of 0.8-1.2-
struction. The axial force in the nail at this location six months m-diameter contiguous bored piles connected by a capping
after the end of wall construction was about 36% more than beam
immediately after the end of wall construction. There was a These figures are at the 1992 price level in Singapore. Soil
slight reduction in the nail force during the subsequent 30 nail walls, which offer the same technical advantages as con-
months. tiguous bored pile walls in the construction of retaining sys-
The measured maximum nail forces at the end of wall con- tems for steep cut slopes, also offer savings in material
struction are compared in a nondimensional form (TN = Tm•.I usage-in this case, savings of 21 % compared to gravity wall
-y-H·Sv·Sh ) in Fig. 11, with the range of forces corresponding and 28.7% compared to contiguous bored piles. Each system
to Terzaghi and Peck's (1967) earth pressure diagram used in has its own advantages. The gravity wall results in an aes-
the design of braced excavations in stiff clays. For stiff clays thetically appealing facing. The contiguous bored piles mini-
the suggested maximum design lateral pressure is between mize lateral displacements and do not require any open ex-
0.2-yH and O.4-yH. The measured nail forces approximately cavation; hence they are suitable in situations where soil
correspond to a maximum lateral pressure of 0.2-yH in Ter- nailing cannot be used.
zaghi and Peck's design diagram. The measured forces in the
lower two rows of nails were very small because they were NUMERICAL ANALYSIS
installed after most of the displacements due to excavation had
already taken place. The soil nailed retaining wall was modeled using the finite
difference program FLAC (Cundall 1991). The problem was
analyzed by discretizing the soil mass in the vicinity of the
COST ANALYSIS structure into 650 soil elements. A finer grid was used in the
The savings realized by using soil nailing in this project can nailed zone due to expected higher stress gradients, and a
be shown by cost comparisons with other alternative retaining coarser grid was used in the unreinforced zone. The finite dif-
systems. In Singapore, the commonly used alternatives for re- ference grid used in the analysis is shown in Fig. 12.
taining structures are gravity walls and contiguous bored piles.
The cost of each system per unit surface area of the excavated PARAMETERS FOR ANALYSIS
face for this project are compared as follows:
Soil
2
Soil nailing US$470/m A saturated undrained analysis was performed. The soil is
Gravity retaining wall US$S70/m2 modeled as a Mohr-Coulomb material. The relationship be-
110/ JOURNAL OF PERFORMANCE OF CONSTRUCTED FACILITIES / AUGUST 1997
;- 30
; i
·····..._·····_··t·_····_············I········_· .... t·
M .... 'R.M"· .. ,.~ ....-.+ Moment of inertia (m4 ) 6.67 X 10- 4
.. +
•
D
~ 20 Q .
... 10 ..... +i ;! . RESULTS OF NUMERICAL ANALYSIS
(d) :; i
c 0 +-~-i--~--i-~+-~-;-~-+-~+-~-l
(eJ l;j f_·.=· ~· .=N_O:;.; I+-1=R_O;.; ;W:5!~. ....._... -+.'-_ ~ +- ~· -;· ·_ · ·_ · · _· · +· · _· _· · " " -:I
.... ..._.
to represent the road immediately above the wall. The first
excavation was modeled by removing the elements in front of
the facing to a depth of I m. To model the time lapse between
the excavation and nail installation, the model was stepped to
~ 0 4 5 6 7 equilibrium after the excavation, i.e., prior to installing the
wfH~j
~ /
. 2
/
~ 01234567
Distance from facing (m)
3 ....
~//
/
FIG. 13. Comparison of Measured and Computed Nail Forces
~
.//
4 0 Measured
tween the undrained shear strength s. and the standard pene- /
tration test (SPT) N-value is assumed to be s. = 5N, based on :§: I --Computed
1/
Q,
from the charts proposed by Duncan and Buchigani (1976) ell
Q
as a function of the overconsolidation ratio (OCR). The ini- ~
6
tial tangent modulus Ei used in the analysis was twice the un-
:-!
drained secant modulus E•. The OCR was estimated from the
charts in Bowles (1988) using a constant value of A = s.IP; = 7
0.3 (where p; is the effective existing overburden pressure) for
normally consolidated clay. The bulk and shear moduli of the
soil were calculated by assuming a Poisson's ratio of 0.49. 8 •
•
The coefficient of earth pressure at rest was calculated using :
the relationship K o = (I - sin<!>') OCR'i."'· (Mayne and Kul- .". ................
9
hawy 1982), where <!>' is the drained friction angle. Displacements at the end
! of wall construction
Nails 10
The nails were modeled as two-dimensional (2D) cable el- FIG. 14. Comparison of Measured and Computed Lateral Wall
ements that are effective in tension only. They were assumed Displacements
The writers would like to thank the Public Works Department of Sin- (J' y yield stress of nail;
gapore for providing the technical details of this project. The instrumen- 'Tull = mobilized maximum shear stress at nail/soil interface; and
tation data was provided by Mis L & M Foundation Pte. Ltd., Singapore. <1>' effective friction angle of soil.