Documente Academic
Documente Profesional
Documente Cultură
Manual
Contents
1 500PLUS REIDBAR Construction Systems 24 Installation of Resin Anchors
3 500PLUS REIDBAR Specifications 25 Rock Anchorage with 500PLUS REIDBAR
4 Anchorage of 500PLUS REIDBAR in Concrete Expansion Anchors
6 500PLUS REIDBAR Constuction Systems 26 Mechanical Soil Anchors
8 Common Questions and Answers 28 Anchoring 500PLUS REIDBAR into
10 Typical 500PLUS REIDBAR Details Existing Concrete
14 500PLUS REIDBAR Swift-Floors 31 500PLUS REIDBAR for Wind Wracing
19 Reidscreed System 32 500PLUS REIDBAR for Tie-down Bars
20 500PLUS REIDBAR Rock and Soil Anchors
22 Transfer of Anchor Loads into the Ground.
23 Anchorage into Rock and Soils with Resins
1
Construction
Systems
An ideal bar could be used in straight lengths: eliminating bends and simplifying transport and
handling.
• at any time,
• in any position,
500PLUS REIDBAR! Is the ideal rebar. It is a hot rolled, threaded reinforcing bar which is easily
joined at any point.
The System! Comprises a full range of bars and threaded fittings for joining and terminating
500PLUS REIDBAR, which simplify the detailing and fixing of rebar.
The extent of engineering and materials technology and specifications are constantly
changing. To the best of our knowledge the information presented in this manual was correct
at the time of printing, however we reserve the right to change specifications without notice. If
specifications are critical to your project please check with OneSteel Reinforcing or Reid
Construction Systems.
3
Specifications
Specifications of 500PLUS REIDBAR.
Table 1.
CODE Nominal Yield Stress* Yield Load* Ultimate Load* Shear Load* Component
Area Rek.l Rm / Re =1.08 0.62Rm Design
Breaking Load
mm2 MPa kN kN kN kN
RB12 113 500 56.5 61.0 37.8 90.4
RBA16 201 500 100.5 108.5 67.3 161.0
RBA20 314 500 157.0 169.6 105.1 251.4
RB25 491 500 245.5 265.1 164.4 392.8
RB32 804 500 402.0 434.2 269.2 643.4
*Characteristic value (Note Characteristic Values are as defined in new draft standard for reinforcing steel. They represent at probability of
95% that 95% of the strength values are above the characteristic values listed above.
The rugged threads permit rapid coupling and resist damage. 500PLUS REIDBAR is part of a
system using complementary fittings to simplify reinforcement detailing (nuts, threaded inserts,
couplers, grout splices, anchorage plates etc).
A construction system fittings develop the breaking strength of 500PLUS REIDBAR, with
the exception of locknuts.
Anchorage in Concrete
Hooked or bent (cogged) rebars require an embedment depth of approximately 15 bar
diameters if they are to meet concrete design standards and are going to be fully effective as
flexural reinforcement.
This is often not possible in thin structural panels.
Detail 1 Detail 1a
Ldh
Ldh<15db
Standard 90° or
180° hook
500PLUS REIDBAR inserts and footplates overcome the under strength and slip deflection
problems caused by using bent bars, which have insufficient embedment.
Anchorage in Concrete
Minimum embedment depths for threaded inserts & footplate to develop the yield strength or ultimate
Table 2.
limit state load capacity of 500PLUS REIDBAR in concrete of f’c=25MPa and f’c=30MPa.
CODE Characteristic L1 Depth to L1 Depth to Characteristic L2 Depth to L2 Depth to
Develop Yield Develop Yield Ultimate Load Develop Develop
Load f’c=25MPa Load f’c=30MPa Rm / Re=1.08 Ultimate Load Ultimate Load
f’c=25MPa f’c=30MPa
kN mm mm kN mm mm
RB12 56.5 81 76 61.0 85 80
RBA16 100.5 119 112 108.5 125 118
RBA20 157.0 160 151 169.6 169 159
RB25 245.5 216 203 265.1 227 214
RB32 402.0 300 282 434.2 315 297
Note 1: The adoption of embedment depth L2 will ensure that the failure mechanism will be ductile rather than by brittle shear cone pullout.
Note 2: Embedment are calculated by AC1 318 Concrete Capacity Design equation, Technical paper 92-S35 May June 1995.
Construction Systems
500PLUS REIDBAR Coupler Code - RB C
Bar Overall Hex Thread OD WT
Size Length Length Depth kg
RB12C 90 30 43 22 0.23
RBA16C 102 33 47 30 0.31
RBA20C 116 2x20 60 33 0.46
RB25C 162 50 78 43 1.16
RB32C 210 50 102 55 2.30
* 500PLUS REIDBAR Locknuts are designed to load the threads and prevent accidental loosening through vibration.
500PLUS REIDBAR nuts are designed to develop the minimum breaking strength of the bar (1.15 Re).
** 500PLUS REIDBAR Torque Nuts and Foot Plates are designed to exceed the maximum breaking strength of the bar (1.4Re).
***
500PLUS REIDBAR Foot Plate Code - RB FP
Bar Overall Foot OD WT
Size Length OD kg
RB12FP 40 38 22 0.11
RBA16FP 51 50 30 0.22
RBA20FP 65 64 35 0.34
RB25FP 70 80 43 0.60
RB32FP 95 101 55 1.27
The flange nut / foot plate is free running. If used as a foot plate the thread must be
stopped at the flange end or the nut screwed against an end stop to minimise slip.
The flange nut may be used where a torque nut is required for sizes larger than RB12.
Construction Systems
500PLUS REIDBAR Grout Sleeve Code - RB GS
Bar Overall Max Thread Embed WT
Size Length OD Depth Depth kg
RB12GS 190 40 43 120 N/A
RBA16GS 240 50 48 160 1.36
RBA20GS 290 60 60 200 2.27
RB25GS 360 70 78 250 3.67
RB32GS 385 75 102 265 4.4
Light type indicates
Enquire about setting equipment non-availability at time of printing.
the full breaking strength of the bar e.g. terminations for rock bolts,
ground anchors, hold-down bolts, tensioning applications etc.
A3 Locknuts (thin nuts) Cyclic loading
+ 0.95fy -0.95fy
These are not designed to develop the full bar strength and are Deflections measured at less
used together with a primary fitting to prevent loosening if severe than 1.1 times the gauge length
of an equivalent length of bar.
vibration is expected.
A4 In critical applications (in plastic hinge zones) additional nuts may Diagram of test arrangement
be required to fully transfer load reversals under seismic events. In
this case full strength nuts or torque nuts are used.
Q What testing has been done for 500PLUS REIDBAR?
During the development of 500PLUS REIDBAR extensive tests have been conducted by RCS,
A OneSteel and an independent accredited testing laboratory to ensure that the bars and
components comply with all applicable codes. Tests have included cyclic tension load tests, pullout
tests to check embedment anchorage, slip tests, etc. Contact your local OneSteel RP or RCS Site
for copies of tests concerning your application.
A Yes. 500PLUS REIDBAR is a TEMPCORE® bar with stable properties and low silicon content.
This ensures a sound coating with better finish and durability.
(Note: Heavy coatings of galvanising on 500PLUS REIDBAR may prevent components being
fitted. Refer all galvanising applications to RCS or OneSteel Reinforcing).
Q How do I connect one precast concrete element to another using 500PLUS REIDBAR?
A Easily with the 500PLUS REIDBAR grout sleeve. A 500PLUS REIDBAR grout sleeve is cast into
the top of the lower element and a coupler into the bottom of the upper element. This eliminates
the need for any starter bars protruding from the precast elements and which are liable to damage
and to be bent which makes erection difficult. Immediately prior to final placing a starter bar of the
correct length is screwed into the coupler and a special non-shrink grout is poured into the grout
sleeve cup. The units are then brought together into the final position, levelled and propped.
Note: this pre-grout method avoids the necessity for casting-in grout tubes and the need for a
separate grouting operation. (See typical details 14 and 15).
Q What are the minimum cover requirements for 500PLUS REIDBAR and 500PLUS REIDBAR
components.
A1 500PLUS REIDBAR AS3600 code requirements must be observed.
A2
Components The main factors to be considered are Fire and Corrosion. Sufficient protection for
the components should be specified by the designer according to the fire, corrosion and other
serviceability requirements of the application, taking into consideration the relevant codes and the
following notes which provide a guide for designers.
Fire The temperature of the steel reinforcing is affected by the cover of concrete over
the full extent of the embedded bar. The temperature is averaged over the steel
by conduction along its length which acts to quickly dissipate any localised
temperature variations. A minor reduction in the cover in a very localised area (e.g.
at a coupler) would therefore not lead to any significant increase in steel
temperature and no reduction in strength.
Corrosion (1) 12mm (RB12 series) 500PLUS REIDBAR components are made from normal
steels and require the same cover as the bar itself unless galvanised or otherwise
protected.
(2) 500PLUS REIDBAR components in sizes larger than RB12 are manufactured from
specially alloyed, high strength, ductile iron. This corrodes at a much lower rate
than reinforcing steels and does not lead to the spalling and flaking problems
associated with the corrosion of steels in concrete. Cover to these components
can be reduced because of the good corrosion resistance. We would suggest
that cover be maintained to at least 50% of code requirements for reinforcing
steel.
10
Typical Details
4. Domestic
RB12LN
Basement DPC Timber
Wall HD PVC tube around
bar if wanting to
bottom
plate
screw in verticals
after laying blocks Typically RB12 at
600 centres
RB12NP to
RB12TI at 600 centres support
threaded
insert
(until
concrete
cures)
5. Common RB12LN
Retaining DPC
2~RB12 bars
Wall Footing RB12 at 600 centres (typical)
Typical Details
7. Connecting Prefab 8. Pre-cast Column
Column Cages Before Elements
Boxing
RB___C
RB___NP
Screw or nail to timber liner or
directly to mould
RB___NP
Screw through mould
into nail plate
12
Typical Details
11. Grout Sleeve to RB___GS
Plastic plug
(Grout tubes
Edge of Precast Panel optional)
Steel
panel
mould
RB___GSP
RR___ RB___
RB___WN
Used where anchorage depth varies from standard
Threaded Insert Length.
RB___
Typical Details
14. Horizontal 15. Horizontal
Structural Joint for Two Structural Joint for
Precast Panels Rebated Precast Panels
RB___
RB___C
RB___GS
RB___
6mm FILLET
6mm 306
FILLET
RIGHT
ROUND
C
68
SECTION BB SECTION AA
190
A B
MESH OMITTED FROM THIS VIEW
PART SECTION CC
A B NOTE: THIS DETAIL COULD ALSO BE USED WITH FLAT SLABS AND TEE SECTIONS
14
Introduction
Whilst it is not possible to entirely eliminate cracking in concrete floors and structures, active reinforcing using post-
tensioning minimises these problems. Traditional (passive) reinforcing methods using bars and mesh rely on the
concrete to crack before the reinforcing begins to work! Designers therefore directed their efforts to controlling the
position of cracks (by jointing, saw cutting, placement of crack inducers etc) and minimisation of the crack widths
by reinforcement density.
These measures are not entirely successful. Most floors suffer random cracking away from joints. The joints and
cracks themselves create durability and maintenance problems and poor floor performance.
Saw cuts are a problem for Tilt-up builders because of the unsightly lines of the saw cuts are imprinted on wall
panels cast on the floor slab. This is totally unacceptable for residential and high quality commercial developments
where finish excellence is mandatory.
Post tensioning in Swiftfloors is designed to overcome the internal concrete stresses which result from the
shrinkage of the concrete and the frictional resistance from the subgrade. These internal stresses lead to drying
shrinkage which is the principle cause of cracking. It is not always possible to completely eliminate other forms of
cracking (or indeed all shrinkage cracking) because cracking results from the interaction of many variables. These
include the floor design; subgrade quality, compaction and finishing; concrete chemistry, placing and finishing
quality; curing; ambient temperatures during and after placement; rate of shrinkage; degree of restraint leading to
curling; level of prestress retained etc.
Minor cracking of less than 0.8mm width and cracks which do not extend through the complete section do not
result in a loss of floor performance or durability in service because aggregate interlock is maintained.
}
Density of concrete Wc = 24kN/m3 Note: higher values than 850 microstrain
concrete shrinkage may be appropriate
Load in bar initial = 53kN (95%fy) in some climates. If so bar spacing in
long term load (after 850 microstrain concrete shrinkage) = 34kN (60%fy) Table A. should be reduced accordingly.
The following is an example of a floor that has been recently built: A 48m x 60m slab 120mm thick was
constructed in a single pour with RB12@ 1.0m centres (2La) in the 48m direction and RB12@ 0.8m
centres (2La) in the 60m direction.
Note: 120mm thick floor slabs larger than 60m would require an infill pour as detailed below at mid slab.
5 METRE MAX.
16_102 CONVENTIONALLY REINFORCED INFILL STRIP
COMPRESSION SEAL 150 THICK POST
IN 25mm x 12mm JOINT
400 16_102
TENSIONED SWIFT FLOOR
WITH RB12 @ 0.8 CENTRES
COMPRESSION SEAL
RB12 BAR WRAPPED IN IN 25mm x 12mm JOINT
TAPE TO PREVENT BOND
WITH CONCRETE
The following table has been calculated using these assumptions to provide the maximum stressing
lengths for RB12 bars in various slab thickness and at different bar spacings.
2 Compact the subgrade to a smooth finish. Consider using granular fill or fine aggregate which can
be compacted to a better flatness with less risk for disturbance during later placing operations.
3 Trim about 50mm from each end of the 500PLUS REIDBAR saw to remove the crop-end burrs. This
is best achieved using bolt cutters for smaller bars (not a shear) or an abrasive disk or friction saw.
4 Slide the appropriate conduit over each bar leaving approximately 120mm of 500PLUS REIDBAR
exposed at each end.
5 Screw the appropriate 500PLUS REIDBAR fitting to the bar ends and tighten with a spanner or pipe
wrench. Tip: wet the end of the 500PLUS REIDBAR first - this lubricates it, making it easier to fit.
6 Place two layers of 200-250 micron polythene sheeting onto the smooth compacted hardfill over the
full slab area. Lay out the sheathed 500PLUS REIDBARS as close as possible to their final positions.
7 Starting on one side, pass the sheathed bars through the edge formwork leaving sufficient
protruding for subsequent stressing. The protruding length will be 150-400mm depending upon the
jacking method and equipment which should be determined with RCS before commencement.
Join the free end to the next sheathed bar by fitting a coupler and then passing a 400mm length of
8 large diameter conduit over the end. Screw the second bar into the coupler by rotating only the
second bar, holding the coupler to prevent it from turning!
9 Position the large sheath centrally over the coupler and securely tape each end of the large sheath
onto the main (smaller diameter) conduit to prevent ingress of concrete laitance.
10 It is important when assembling long lengths of 500PLUS REIDBAR in this way not to rotate the
previously laid bar otherwise it could unscrew.
11 Pass the last bar through the formwork on the other side and leave sufficient protruding for
connection of the jack (see point 7 previous).
12 With all the bars securely coupled, wire tie the bars at every second intersection. Support on bar
chairs placed at every two metre centres.
13 Pour and finish the floor. As soon as the “bleed” water has left, apply a good quality membrane
curing agent e.g. Reid Seal & Tilt, an alkyd resin or chlorinated rubber material. It is essential to
apply curing agents on large slabs progressively working behind the finishing helicopters to minimise
the risk for plastic shrinkage cracking. The risk for plastic shrinkage cracking increases with high
temperatures and or winds, high water cement ratios in the concrete, thin slabs and long times
between finishing and application of the curing agent. We do not reccommend the use of PVA and
similar water soluble materials for curing. Plastic or steel fibres can provide additional resistance to
plastic shrinkage in difficult circumstances.
14 Experience has shown that if plastic shrinkage cracks occur, they will often close up after stressing.
This is a real advantage of the Swiftfloor over conventional floors. Both floors are equally prone to
plastic cracking but the cracks in normal floors only get wider and bigger because they provide sites
for large concrete shrinkage cracks.
15 Partial stressing (about 25% of the final stress) may be applied when the concrete has hardened
(fc=2MPa approx). This can be useful when severe conditions are encountered (high temperatures,
winds, etc) to arrest any plastic shrinkage crack propagation.
16 Ideally the full stress should be applied as soon as the concrete has sufficient strength to resist edge
compression failure at the anchorages. Experience has shown that under normal curing conditions,
structural grade slabs can be fully stressed after 24 hours when the concrete has reached a
compressive strength of approximately 7MPa.
17 Delay the pouring of infill strips, column blockouts, adjoining footings and structures etc which could
hang up the slab for as long as possible (two weeks preferably) to allow the slab to shrink freely
without early restraint. Infill strips and column blockouts must be permanently isolated from the
stressed slab area.
Whilst single tilt-up panels can be cast on floors successfully, avoid stack casting panels on tilt up
18 slabs immediately after pouring the floor. The additional mass of the stack acts as an anchor and
differential shrinkage between the slab and the panel stack can cause radial floor cracking which
may not be closed by the prestress after panel removal.
18
not to exceed LA
ie RB12 @ 0.8m ctrs (LA = 42m for 120 slab)
Adopting the principle that the
size of floor that can be poured
at any one time is limited to
not to exceed LA
twice the maximum stressing
length shown in Table A. on
previous page 20.
Reidscreed System
Introduction
Swiftfloor and Reidscreed for Perfectly Level Floors.
Over recent years the design of special use
buildings and the development of high speed
materials handling equipment has led to an
increasing requirement for concrete floors that are
super flat.
The Swiftfloor system on its own improves the
durability of these floor slabs and removes the
need for saw cuts for shrinkage control.
When teamed up with the patented “Reidscreed”
system however it is possible to produce an
economical durable floor that is also perfectly flat.
The Reidscreed system utilises an adjustable heavy
duty disposable
screed support
chair using the
unique
Stair-Lok™
adjustment
mechanism.
Features:
• Can be used with conventionally reinforced • Safe to use - designed not to puncture DPC
slabs or Swiftfloors. moisture barriers
• Fast and easy to use • Designed for use with 25 or 30mm re-usable
pipe screed rails
• Economical, cost effective
• Simple, accurate height adjustment from 115
• No special equipment required
to 167mm using 25 & 30mm pipe screed rails
• Controls floor flatness and level to +/-2mm
• The Stair-Lok™ maintains the set height when
• Variable suface of the sub-base is acceptable using vibratory screed
for conventionally reinforced floor slabs
• Does not weaken the floor slab, will not corrode
Installation:
1. Measure the width of your screed. The rails are normally placed with approx. 100mm overhang per
side. e.g. for a screed of 4metre length, place the rails 3.8metres apart. The example below
assumes a 4 metre screed.
2. If the boxing is being used as a rail then place the row of R-S chairs at 3.8metres distance from the
boxing. On the second pour the screeded concrete of the first pour can be used instead of a rail.
An overhang of about 500mm of screed is used on the concrete side. Install the next row 3.5metres
from the edge of the last pour. R-S chairs are usually placed at intervals of approximately 1-1.5
metres to minimise the the rail deflection.
3. Insert the rails into the R-S chairs. Establish levels for the rails using a laser or string line. Hold the
rail up to the level with one hand on the cradle support of the R-S chair and turn the base to adjust
the height. When the correct height is found lock the R-S chair by pushing the lug into the Stair-
Lok™. Best results are obtained by setting the rail at each end and then adjusting the R-S chair between
the ends.
4. Some builders prefer to set the base into concrete mortar to prevent movement during concrete pouring.
5. Check to ensure that the rail is stable with the screed placed upon it and that the deflections are within
the required tolerance. Add more R-S chairs if required.
6. Pour the concrete, screed and remove the rail. Finish the slab by floating in the normal way.
20
500PLUS REIDBAR
Rock Anchors
500PLUS REIDBAR
Systems are ideal for
Rock and Soil
Anchoring
applications.
A range of chemical
and expansion
anchors enhance the
versatility of the
500PLUS REIDBAR
System.
21
• Fully weldable
• Simplicity in applying the prestress with jacks. torque wrenches or air operated tools
• The rigidity of the anchors makes them easy to install especially in overhead applications
• High shear bond development. 500PLUS REIDBAR deformations are designed for shear interlock with
concrete. 500PLUS REIDBAR transmit the anchor forces efficiently to the grout body without additional
fittings.
• Standard stock lengths may be stored and cut to suit the application.
• Efficient resin mixing and bond interlock from the thread deformations
• Offcut bars may be used for all standard concrete reinforcement applications in the
construction site whilst small pieces are ideal for formwork, starter bars or hangers in
underground works.
22
The load transfer mechanism between the grout and the rock is less certain in fissured rock and it
is advisable to consolidate and seal the cracked rock by pregrouting before installation of the the
500PLUS REIDBAR anchor. The following tables (Tables 5 & 6) give guide values for the load
transfer capacity of various broad classifications of non-cohesive and cohesive soils. A test anchor
should be made to reliably determine the load capacity. The following information is provided for
guidance only. A Geotechnical Engineer should be consulted to determine the appropriate design
Table 5. A guide to working bond strengths between non-cohesive soils and cement grout.
Table 6. A guide to working adhesive strengths between cohesive soils and cement grout.
Clay Field Test Unconfined Typical Working
Condition Compressive Undrained *Strength ** Working
Strength
Strength (qu) Shear Strength Adhesion Adhesion
kPa (Cu) kPa Short Term Long Term
(kPa) (kPa)
Very soft Exudes between fingers
when squeezed in fist 10 5 1 2
Soft Easily penetrated by thumb 18 9 2 4
Medium Difficult to penetrate
strength with thumb 40 20 4 8
Firm Easily indented with thumb nail 75 37 7 14
Stiff Readily indented with thumb nail 150 75 15 30
Hard Difficult to indent with thumb nail 300 150 30 60
* Working strength short term based on 0.5Cu/2.5 as the drilling operation causes temporary remoulding of the clay at the edge of the bore hole.
** Working strength long term based on Cu/2.5
23
Note :The above resin usage does not include a waste allowance for over-drilling. Site trials should be
conducted to confirm resin requirements.
For rock bolts in hard, fissure free rock, 500PLUS REIDBAR Expansion Anchors can be used.
In hard rock the yield capacity of 500PLUS REIDBAR can be reached with Expansion Anchors.
Table 9. Bore hole diameters. Hole diameters are critical for correct anchor performance.
RBA16 40 RB16EA
RBA20 45 RB20EA
RB25 50 RB25EA
RB32 64 RB32EA
Installation
1 Screw the 500PLUS REIDBAR Expansion Anchor onto the end of the 500PLUS REIDBAR until the
bar end contacts the spring and starts to expand the shields.
2 With the expansion shields providing slight friction against the top & bottom of the bore hole wall,
carefully push the whole assembly to the bottom of the bore hole.
3 For deep bore holes special 500PLUS REIDBAR Threaded Couplers can be used to join shorter
lengths of 500PLUS REIDBAR as the assembly is being installed.
4 If cement grout protection is being provided, a plastic tube can be slid over the unbonded length
of 500PLUS REIDBAR and the gap between the bore hole wall and the plastic tube filled with grout.
5 Position the bearer plate, domed washer (if used) and flange nut and apply stressing load with
either:
MR-SR For loose/wet soils MR-1 For average/normal soils MR-2 For dense hard silts and clays
(Fill swamp/marsh) (clays/Firm sands/Dense Gravels)
MR-3 For dense soils/hard silt and clays MR-4 For clays/Firm sands/Dense Gravels) MR-88 For dense hard silts and clays
Made from galvanised ductile iron they are driven with a removable drive steel and can be proof loaded to
your required loading capacity.
The anchors can be readily driven into most soil types without disturbing or displacement. In harder
ground a pilot hole may need to be augered but this does not affect the holding capacity.
The anchors are driven with conventional hydraulic/pneumatic equipment. Once driven to the
required depth, the 500PLUS REIDBAR attached to the anchor is pulled to rotate the anchor into
undisturbed soil - like a toggle bolt and actually compacts the soil around itself. The anchor is
pulled upon to reach the holding capacity required. This is measured by gauge and each anchor is
immediately proof loaded to the exact capacity required.
The following data courtesy of Ancor-Loc N.Z.
RECOMMENDED PROOF LOADING CHART - kN (Working Load is generally 50% of proof load)
Common Soil-Type Standard Penetration test MR-88 with MR-4 with MR-3 with MR-2 with MR-1 with MR-SR with
Description Blows/300mm (ASTM-D1586) RB12 Reidbar RB12 Reidbar RBA16 Reidbar RBA20 Reidbar RBA20 Reidbar RBA20 Reidbar
kN kN kN kN kN kN
INSTALLATION
This is carried out on-site by certified installers using manual or mechanised methods depending
on site accessability and conditions. Contact RCS for further details on your nearest installer.
RBLN
TYPICAL SET UP USING 20 FSW
LOCK NUT
500PLUS REIDBAR & Ancor-Loc FLAT WASHER
500PLUS REIDBAR and Ancor-Loc RBA16/20
BAR RBC
offer the complete anchoring
CENTRALISER COUPLER
system, using hot-dipped
galvanised, epoxy coated or
stainless steel components.
500PLUS REIDBAR
RB12 RBA16 RBA20
refer chart for correct match
RCBP
ANCOR-LOC MANTA RAY CONE WASHER & BEARER PLATE
1. Thread 500PLUS REIDBAR 2. Insert drive steel into anchor. 3. Position anchor at proper
into coupling. location and angle.
4. Drive anchor to proper depth. 5. Remove drive steel. 6. Use load locker to proof anchor
into load lock position.
If starter bars are not in a critical stress zone, i.e. floor topping starters which will act
mainly in shear, the hole depths and amount of resins can be reduced.
As a general rule, RCS epoxy and polyester injection systems as well as standard glass phials
can be expected to develop a 14MPa adhesion between the resin plug and a good quality
30MPa concrete substrate. Hammer-in glass capsules can be expected to provide approximately
12MPa adhesion.
Expansive grouts will only provide an adhesion of approximately 3MPa and consequently require
deeper embedment depths or undercut holes if full breaking strength of the 500PLUS REIDBAR is
to be reached.
Method 1 -
Using Selfix Capsules
Description
Selfix Capsules will
anchor 500PLUS
REIDBAR starter bars into
rock, concrete or other
homogeneous substrates.
The capsule contains a
measured volume of resin
with the correct quantity of activator. The two components are separately contained within a
‘sausage-like’ soft plastic, laminated skin. The resin component is the major part and the
activator is seen as a contrasting stripe along the length of the capsule.
Capsules are used by inserting the recommended capsule into a predrilled hole. The 500PLUS
REIDBAR starter bar is then mechanically rotated through the capsule. The 500PLUS REIDBAR
ruptures the skin and the rotation of the bar mixes the two components.
Directions for Use
1. Holes of the correct diameter and depth should be drilled using good quality drilling
equipment, e.g. RCS Multi-shank Carbide Drills.
2. Drilling debris and dust should be thoroughly cleaned from the hole using a suitable technique
such as the stiff nylon bottle brushes available from RCS. Compressed air or clean water is also
commonly used.
Table 10. Selection chart. Method 2 - Using Reid 'Hammer In' Capsules
Bar Size Hole Capsule Capsules Capsule *Rec Hole Set Time
Diameter Diameter per Hole Length mm Depth mm 5°C 25°C
RBA16 20 16 2 100 250 6min 2min
RBA20 25 22 2 100 250 6min 2min
RB25 32 28 2 150 350 6min 2min
*Recommended hole depths can be halved and capsule numbers reduced to one capsule per hole if starter bars
are located in non-critical stress zones.
29
4. Attach the starter bar to a suitable anti-clockwise rotary drill by means of a RCS Spindapter™
which is available from RCS. Commence rotating the bar progressively through the capsule until
the bottom of the hole is reached. Bar rotation should be between 150-250 revolutions per
minute. Once at the bottom of the hole continue to rotate the bar for a further two seconds.
Quickly detach the drill from the adapter and leave the resin to set.
5. Once the setting time of the capsule/s is elapsed bar connectors, plates or fixtures can be attached.
Method 2 -
Using RCS 'Hammer In'
Capsules
Description
RCS 'Hammer In' Capsules
will anchor 500PLUS
REIDBAR into rock,
concrete or other
homogeneous substrates.
Because of the unique
design of the glass
capsules the 500PLUS
REIDBAR can be simply
hammered into the drilled
hole in the substrate without
any spinning of the bar, eliminating the need for starter bars.
The glass capsule contains a measure of resin and hardener with the hardener arranged in such
a way that mixing will occur without the need to spin the bar.
Description
RCS offer a range of high
strength epoxy and
polyester chemical
injection systems which
will anchor 500PLUS
REIDBAR into rock,
concrete or other
homogeneous substrates.
*Hole depths can be reduced where the 500PLUS REIDBARS are located in non-critical stress zones.
31
Example
A tilt-up building wall resits lateral wind/seismic loads by means of a cantilevered footing and an
in-plane truss at roof level.
Detail 24
Use RCS
Liebig anchors
Detail 25
R=2kN/m
W=0.5kPa
R=2kN/m
Max load in diagonal tie = (24-6) x √152 + 62
15
= 19.4 kN
Use RB12 diagonal tension ties
32
In extreme wind conditions such as Northern Australia or NZ Alpine regions, 12mm 500PLUS
REIDBAR (RB12) greatly simplifies compliance with building code requirements for cyclone tie-
downs for all types of building construction.
Using 500PLUS REIDBAR designers can simply and economically provide a continuous tie from
the building footing to roof truss that can even be post tensioned to improve the structural
performance of the wall unit.
Detail 26
L Bkt
Masonry RB12TN Timber Solid
RB12 bar framing timber
RB12TI