Sunteți pe pagina 1din 25

PHATECO TECHNICAL SERVICES JOINT STOCK COMPANY

Head Office:
5A/613 Thien Loi str., Vinh Niem wd, Le Chan dist., Hai Phong city, Vietnam
Tel: +84 (0) 313 870 870 Fax: +84 (0) 313 559 448
Email: admin@phateco.com Website: www.phateco.com

Project : Long Phu 1 Thermal Power Plant


Contractor : AGRIMECO
Location : Km 10 1A National Road, Thanh Tri District, Ha Noi City, Vietnam
Item : Circulation Water Piping

No. PTC.LP1.RT.01ASME
Revision No. 0
Date: 18/Aug/2016

Accepted by AGRIMECO Accepted by Owner

PHATECO
Prepared by Reviewed by Approved by
RT Level II ASNT RT Level III ACCP RT Level III

NGUYEN QUANG HUY NGUYEN DUC HIEU TRAN VAN VUONG


Deputy Manager of Industrial Deputy Manager of Quality & Deputy General Director
Technical Dept. Training Dept.
No. : PTC.LP1.RT.01ASME
RADIOGRAPHIC Rev. :0
EXAMINATION PROCEDURE Date : 18-Aug-2016

REVISION RECORD SHEET

No Rev No Content of revision Date of Revision

1 0 First issued Aug 18th, 2016

10

11

12

13

14

15

Note: Third column is to be filled in, when the document is being updated/ modified

Page 2 of 25
No. : PTC.LP1.RT.01ASME
RADIOGRAPHIC Rev. :0
EXAMINATION PROCEDURE Date : 18-Aug-2016

CONTENTS

1 INTRODUCTION .................................................................................................................. 4
2 SCOPE .................................................................................................................................... 4
3 APPLICABLE DOCUMENTS .............................................................................................. 4
4 PERSONNEL ......................................................................................................................... 4
5 RADIATION SAFETY .......................................................................................................... 4
6 GENERAL .............................................................................................................................. 4
6.1 RADIATION .......................................................................................................................... 4
6.2 RADIOGRAPHIC FILM ........................................................................................................ 4
6.3 INTENSIFYING SCREEN .................................................................................................... 4
6.4 SCATTERED RADIATION .................................................................................................. 5
6.5 SYSTEM OF IDENTIFICATION.......................................................................................... 5
6.6 RADIOGRAPHIC DENSITY ................................................................................................ 5
6.7 GEOMETRIC UNSHAPNESS .............................................................................................. 6
6.8 FILM PROCESSING.............................................................................................................. 7
6.9 SURFACE PREPARATION .................................................................................................. 8
6.10 VIEWING FACILITIES ......................................................................................................... 8
7 IMAGE QUALITY INDICATOR (IQI) ................................................................................ 8
7.1 IQI MATERIAL ..................................................................................................................... 8
7.2 IQI SELECTION .................................................................................................................... 8
7.3 PLACEMENT OF IQIS ........................................................................................................ 10
7.4 NUMBER OF IQIS............................................................................................................... 10
7.5 IQI SENSITIVITY................................................................................................................ 11
8 LOCATION MARKERS ...................................................................................................... 11
8.1 SINGLE-WALL VIEWING ................................................................................................. 12
8.2 DOUBLE-WALL VIEWING ............................................................................................... 13
9 RADIOGRAPHIC TECHNIQUE ........................................................................................ 13
9.1 SINGLE-WALL TECHNIQUE............................................................................................ 13
9.2 DOUBLE-WALL TECHNIQUE.......................................................................................... 13
10 ACCEPTANCE STANDARDS ........................................................................................... 13
10.1 ASME B31.3 ......................................................................................................................... 13
10.2 ASME Section IX, QW-191.1.2.2 ........................................................................................ 16
11 EVALUATION BY PHATECO........................................................................................... 16
12 RADIATION SAFETY ........................................................................................................ 16
13 RECORDS ............................................................................................................................ 17
14 Annex 1 - Rounded Indications Charts Acceptance Standard .............................................. 17
15 Annex 2- ASME Section IX, Maximum acceptable types of rounded indications .............. 24
16 Annex 3 - Radiographic Examination Report Form ............................................................. 25

Page 3 of 25
No. : PTC.LP1.RT.01ASME
RADIOGRAPHIC Rev. :0
EXAMINATION PROCEDURE Date : 18-Aug-2016

1 INTRODUCTION
This procedure is given to cover the radiographic testing requirements for PHATECO
inspectors to perform their works achieving the quality level of services as well as the
requirements of Long Phu 1 Extension Thermal Power Plant Project’s Specification.
2 SCOPE
This procedure defines the conditions of performing the radiographic testing for the objects
with penetrated thickness up to 62.5 mm.
The procedure covers the radiographic examination of materials including castings and
welds.
3 APPLICABLE DOCUMENTS
3.1. ASME Section V, 2015 Edition, Article 2;
3.2. ASME Section IX, 2015 Edition;
3.3. ASME B31.3, 2014 Edition;
3.4. ASNT's Recommended Practice SNT-TC-1A: Personnel Qualifications and Certification in
Non-destructive Testing, 2006 and 2011 edition
3.5. PHATECO's written practice No. PTC.TDD.NDT.P01.
4 PERSONNEL
4.1. All individual carries out RT examination shall be qualified in accordance with the
requirements of PHATECO’s Written Practice based on SNT-TC-1A.
4.2. Only qualified and certified Level II or Level III personnel shall interpret test results to
determine acceptability.
5 RADIATION SAFETY
All radiographic operations shall follow PHATECO’s Radiation Safety Procedure.
6 GENERAL
6.1 RADIATION
6.1.1. Gamma ray sources such as Ir-192 may be used as following table. The radiation energy
employed for any radiographic technique shall be achieved the requirements of density and
sensitivity in this procedure.
6.1.2. The source size, source to film distance (SFD) and distance from source side of object to the
film (OFD) shall be recorded in the report, and the geometric un-sharpness shall meet the
requirements of this procedure.
6.1.3. The distance between the source side of the object and the film surface shall be as small as
possible. The unsharpness as described of this procedure shall be satisfied. If the film is not
close to the object, the thickness of metal penetrated plus the gap thickness shall be taken
instead of specimen thickness described in this procedure.
6.2 RADIOGRAPHIC FILM
Radiographs shall be made using industrial radiographic film. Film brand name is Fuji # 50,
# 80, #100 or AGFA D7, D5, D4 (ASTM System Class I or II)
6.3 INTENSIFYING SCREEN
Lead intensifying screen shall be used; however fluorescent shall not be permitted. The
minimum thickness of the front screen shall be 0.005 in. (0.13 mm) for Ir-192.

Page 4 of 25
No. : PTC.LP1.RT.01ASME
RADIOGRAPHIC Rev. :0
EXAMINATION PROCEDURE Date : 18-Aug-2016

6.4 SCATTERED RADIATION


6.4.1. To reduce back scattered radiation, back lead screen or back lead plate shall be placed in the
film holder or behind the film holder during exposure.
6.4.2. As a check on backscattered radiation, a lead symbol "B", with minimum dimensions of ½
in. (13 mm) in height and 1/16 in. (1.5 mm) in thickness, shall be attached to the back of
each film holder.
6.4.3. If a light image of the "B”, appears on a darker background of the radiograph, protection
from backscatter is insufficient and the radiograph shall be considered unacceptable. A dark
image of the "B" on a lighter background is not cause for rejection.
6.5 SYSTEM OF IDENTIFICATION
6.5.1 A system shall be used to produce permanent identification on each radiograph traceable to
the contract, component, weld seam, or part numbers, as appropriate. In addition, the
organization's symbol and the date of the radiograph shall be plainly and permanently
included on the radiograph. In any case, this information shall not obscure the area of
interest.
The content of identification shall be agreed upon Client’s requirement.
6.5.2 Repair radiographs shall be identified by R1, R2, etc., as applicable.
6.5.3 All radiographs shall be free from mechanical, chemical, or other blemishes to the extent
that they do not mask and are not confused with the image of any discontinuity in the
interest of the object being radiographed, such blemishes included, but are not limited to;
a) Fogging
b) Processing defect such as streaks, water marks, or chemical stains
c) Scratches, finger marks, crimps, dirtiness, static marks, smudges, or tears
d) False indication due to defective screens.
6.6 RADIOGRAPHIC DENSITY
6.6.1 Density Limitation
6.6.1.1 The transmitted film density through the radiographic image adjacent to the designated wire
of a wire IQI and the area of interest shall be 1.8 minimum for single film viewing for
radiographs made with an X-ray source and 2.0 minimum for radiographs made with a
gamma ray source.
6.6.1.2 For composite viewing of multiple film exposures, each film of the composite set shall have
a minimum density of 1.3.
6.6.1.3 The maximum density shall be 4.0 for either single or composite viewing.
6.6.2 Density Variation
If the density of the radiograph anywhere through the area of interest varies by more than
minus 15% or plus 30% from the density through the body of the hold IQI or adjacent to the
designated wire of a wire IQI, within the minimum/maximum allowable density ranges
specified in this procedure, then an additional IQI shall be used for each exceptional area or
areas and the radiograph retaken. When calculating the allowable variation in density, the
calculation shall be rounded to the nearest 0.1 within the range specified in this procedure.
6.6.3 Densitometer and Step Wedge Comparison Films
6.6.3.1 Densitometers.
Densitometers shall be calibrated at least every 90 days during use as follows:

Page 5 of 25
No. : PTC.LP1.RT.01ASME
RADIOGRAPHIC Rev. :0
EXAMINATION PROCEDURE Date : 18-Aug-2016

(a) A national standard step tablet or a step wedge calibration film, traceable to a
national standard step tablet and having at least 5 steps with neutral densities from at
least 1.0 through 4.0, shall be used. The step wedge calibration film shall be verified
within the last year by comparison with a national standard step tablet unless, prior
to first use, it was maintained in an original light-tight and waterproof sealed
package as supplied by the Film Manufacturer. Step wedge calibration films may be
used without verification for one year upon opening, provided it is within the
Manufacturer stated shelf life.
(b) The densitometer manufacturer step-by-step instructions for the operation of the
densitometer shall be followed.
(c) The density steps closest to 1.0, 2.0, 3.0, and 4.0 on the national standard step tablet
or step wedge calibration film shall be read.
(d) The densitometer is acceptable if the density readings do not vary by more than
±0.05 density units from the actual density stated on the national standard step tablet
or step wedge calibration film.
6.6.3.2 Step Wedge Comparison Films
Step wedge comparison films shall be verified prior to first use, unless performed by the
film manufacturer, as follows:
(a) The density of the steps on a step wedge comparison film shall be verified by a
calibrated densitometer.
(b) The step wedge comparison film is acceptable if the density readings do not vary by
more than ±0.1 density units from the density stated on the step wedge comparison
film.
6.6.3.3 Periodic Verification
(a) Densitometers. Periodic calibration verification checks shall be performed as
described above paragraph at the beginning of each shift, after 8 hour of continuous
use, or after change of apertures, whichever comes first.
(b) Step Wedge comparison Films. Verification checks shall be performed annually per
above paragraph.
6.7 GEOMETRIC UNSHAPNESS
6.7.1 The geometric unsharpness of the radiographic shall not exceed the following values:
Material thickness, mm Ug, Maximum, mm

Under 50.8 0.51

50.8 through 76.2 0.76

Over 76.2 through 101.6 1.02

Greater than 101.6 1.78

6.7.2 Geometric unsharpness of the radiograph shall be determined in accordance with below
formula:
Ug = Fd/D
Where,
Ug = geometric un-sharpness

Page 6 of 25
No. : PTC.LP1.RT.01ASME
RADIOGRAPHIC Rev. :0
EXAMINATION PROCEDURE Date : 18-Aug-2016

F = source size, the maximum projected dimension of the radiating source (or
effective focal spot) in the plane perpendicular to the distance D from the weld or
object being radiographed, mm.
D = distance from source of radiation to weld or object being radiographed, mm.
d = distance from source side of weld or object being radiographed to the film
6.8 FILM PROCESSING
6.8.1 Development
Normal development is 5 to 8 min in 200C. Longer development time generally yields faster
film speed and slightly more contrast. The chemical manufacturer’s recommendation should
be followed in choosing a development time. When the temperature is higher or lower,
development time must be changed. Again, consult’s chemical manufacturer –
recommended development time versus temperature charts. Other recommendations of the
chemical manufacturer to be followed are replenishment rates, renewal of solutions, and
other specific instructions.
6.8.2 Agitation
Shake the film horizontally and vertically, ideally for a few seconds each minute during
development. This will help film develop evenly.
6.8.3 Stop Bath or Rinse
After development is complete, the activity of developer remaining in the emulsion should
be neutralized by an acid stop bate or, if this is not possible, by rinsing with vigorous
agitation in clear water. Follow the film manufacturer's recommendation of stop bath
composition. (Or length of alternative rinse), time immersed, and life of bath.
6.8.4 Fixing
The films must not touch one another in the fixer. Agitate the hangers vertically for about
10s and again at the end of the first minute, to ensure uniform and rapid fixation. Keep them
in the fixer until fixation is complete (that is, at least twice the clearing time), but not more
than 15 min in relatively fresh fixer. Frequent agitation will shorten the time of fixation.
6.8.5 Fixer Neutralizing
The use of a hypo eliminator or fixer neutralizer between fixation and washing may be
advantageous. These materials permit a reduction of both time and amount of water
necessary for adequate washing. The recommendations of the manufacturer’s as to
preparation, use, and useful life of the baths shall be observed rigorously.
6.8.6 Washing
The washing efficiency is a function of wash water, its temperature, and flow, and the film
being washed. Generally, washing is very slow below 16oC. When washing at temperatures
above 30oC, care should be exercised not to leave films in the water too long. The films
should be washed in batches without contamination from new film brought over from the
fixer. If pressed for capacity, as more films are put in the wash, partially washed film should
be moved in the direction of the inlet.
- The cascade method of washing uses less water and gives better washing for the same
length of time. Divide the wash tank into two sections (may be two tanks). Put the films
from the fixer in the outlet section. After partial washing, move the batch of film to the
inlet section. This completes the wash in fresh water.
- For specific washing recommendations, consult the film manufacturer.
6.8.7 Wetting Agent

Page 7 of 25
No. : PTC.LP1.RT.01ASME
RADIOGRAPHIC Rev. :0
EXAMINATION PROCEDURE Date : 18-Aug-2016

Dip the film for approximately 30's in a wetting agent. This makes water drain evenly off
film, which facilitates quick, even drying.
6.8.8 Drying
Drying is a function of film (base and emulsion); processing (hardness of emulsion after
washing, use of wetting agent); and drying air (temperature, humidity, flow).
Manual drying can vary from still air drying at ambient temperature to as high as 60°C with
air circulated by a fan. Film manufacturers should again be contacted for recommended
drying conditions. Take precaution to tighten film on hangers, so that it cannot touch in the
dryer.
Too hot a drying temperature at low humidity can result in uneven drying and should be
avoided.
6.9 SURFACE PREPARATION
6.9.1 Materials Including Castings
Surfaces shall satisfy the requirements of the applicable materials specification or
referencing Code Section, with additional conditioning, if necessary, by any suitable
process to such a degree that the resulting radiographic image due to any surface
irregularities cannot mask or be confused with the image of any discontinuity.
6.9.2 Welds
The weld ripples or weld surface irregularities on both the inside (where accessible) and
outside shall be removed by any suitable process to such a degree that the resulting
radiographic image due to any surface irregularities cannot mask or be confused with the
image of any discontinuity. The finished surface of all butt-welded joints shall be flush with
the base material or shall have reasonably uniform crowns, with reinforcement not to
exceed that specified in the referencing Code Section.
6.10 VIEWING FACILITIES
Viewing facilities shall provide subdued background lighting of an intensity that will not
cause troublesome reflections, shadows, or glare on the radiograph. Equipment used to view
radiographs for interpretation shall provide a variable light source sufficient for the
designated wire to be visible for the specified density range. The viewing conditions shall
be such that light from around the outer edge for the radiograph or coming through low-
density portions of the radiograph does not interfere with interpretation.
7 IMAGE QUALITY INDICATOR (IQI)
7.1 IQI MATERIAL
IQIs shall be selected from either the same alloy material group or grade as identified in SE-
747 or from an alloy material group or grade with less radiation absorption than the material
being radiographed.
7.2 IQI SELECTION
7.2.1 The designated wire diameter shall be as specified in Table 1. The alternative wire IQI
essential wire diameter is equal to or less than the required standard IQI essential wire in
Table 1.

Page 8 of 25
No. : PTC.LP1.RT.01ASME
RADIOGRAPHIC Rev. :0
EXAMINATION PROCEDURE Date : 18-Aug-2016

TABLE 1 - IQI SELECTION


Wire type IQI
Nominal Single-Wall
SOURCE SIDE FILM SIDE
Material Thickness
Range (mm) Wire Wire Dia. Wire Wire Dia.
IQI set IQI set
Essential (mm) Essential (mm)
Up to 6.4 Incl. 5 1A 0.20 4 1A 0.16
Over 6.4 Through 9.5 6 1A, 1B 0.25 5 1A 0.20
Over 9.5 Through 12.7 7 1B 0.33 6 1A, 1B 0.25
Over 12.7 Through 19.0 8 1B 0.41 7 1B 0.33
Over 19.0 Through 25.4 9 1B 0.51 8 1B 0.41
Over 25.4 Through 38.1 10 1B 0.64 9 1B 0.51
Over 38.1 Through 50.8 11 1B, 1C 0.81 10 1B 0.64
Over 50.8 Through 63.5 12 1C 1.02 11 1B, 1C 0.81
Over 63.5 Through 101.6 13 1C 1.27 12 1C 1.02
Over 101.6Through 152.4 14 1C 1.60 13 1C 1.27
Over 152.4 Through 203.2 16 1C, 1D 2.54 14 1C 1.60
Over 203.2 Through 254.0 17 1D 3.20 16 1C, 1D 2.54
Over 254.0 Through 304.8 18 1D 4.06 17 1D 3.20
Over 304.8 Through 406.4 20 1D 6.35 18 1D 4.06
Over 406.4 Through 508.0 21 1D 8.13 20 1D 6.35

7.2.2 If there is not any special requirement, wire type IQI, in accordance with Table 3, shall be
used.
7.2.3 Welds with Reinforcements
The thickness on which the IQI is based is the nominal single wall thickness plus the estimated
weld reinforcement not to exceed the maximum permitted by the referencing code section as
flowing table 3. Backing rings or strips shall not be considered as part of the thickness in IQI
selection. The actual measurement of the weld reinforcement is not required.

Table 3: Weld reinforcement Height


(ASME B31.3, Table 341.3.2)
Weld Thickness, Tw Weld reinforcement
mm Height, mm
Tw ≤ 6 1.5
6 < Tw ≤ 13 3
13 < Tw ≤ 25 4
Tw > 25 5

6.2.4 Welds without Reinforcements


The thickness on which IQI is based is the nominal single wall thickness. Backing rings or
strips shall not be considered as part of the weld thickness in IQI selection.

Page 9 of 25
No. : PTC.LP1.RT.01ASME
RADIOGRAPHIC Rev. :0
EXAMINATION PROCEDURE Date : 18-Aug-2016

Table 2- WIRE IQI DESIGNATION, WIRE DIAMETER, AND WIRE IDENTIFY


Set A Set B
Wire diameter Wire Wire Diameter, Wire
In. (mm) Identify In. (mm) Identify
0.0032 (0.08) 1 0.010 (0.25) 6
0.004 (0.10) 2 0.013 (0.33) 7
0.005 (0.13) 3 0.016 (0.41) 8
0.0063 (0.16) 4 0.020 (0.51) 9
0.008 (0.20) 5 0.025 (0.64) 10
0.010 (0.25) 6 0.032 (0.81) 11
Set C Set D
Wire diameter Wire Wire Diameter, Wire
In. (mm) Identify In. (mm) Identify
0.032 (0.81) 11 0.100 (2.54) 16
0.040 (1.02) 12 0.126 (3.20) 17
0.050 (1.27) 13 0.160 (4.06) 18
0.063 (1.60) 14 0.200 (5.08) 19
0.080 (2.03) 15 0.250 (6.35) 20
0.100 (2.54) 16 0.320 (8.13) 21

7.3 PLACEMENT OF IQIS


7.3.1 Source Side IQIs
The IQIs shall be placed on the source side of the part being examined, except in the
condition described as below.
7.3.2 Film Side IQIs
Where inaccessibility prevents hand placing the IQIs on the source side, it shall be placed
on the film side in contact with the part being examined.
A lead letter "F" at least as high as the IQI identification number(s) shall be placed adjacent
to or on the IQIs.
7.3.3 IQI Placement for Welds - Wire IQIs
The IQIs shall be placed on the weld so that the length of the wires is perpendicular to the
length of the weld. The identification numbers and, when used, the lead letter “F”, shall not
be in the area of interest, except when geometric configuration makes it impractical.
7.3.4 IQI Placement for Materials Other Than Welds
The IQIs with the IQI identification number(s), and, when used, the lead letter "F", may be
placed in the area of interest.
7.4 NUMBER OF IQIS
When one or more film holders are used for an exposure, at least one IQI image shall appear
on each radiograph except as outlined below.
7.4.1 Multiple IQIs

Page 10 of 25
No. : PTC.LP1.RT.01ASME
RADIOGRAPHIC Rev. :0
EXAMINATION PROCEDURE Date : 18-Aug-2016

If the requirements of paragraph 7.6 are met by using more than one IQI, one shall be
representative of the lightest area of interest and the other the darkest area of interest; the
intervening densities on the radiograph shall be considered as having acceptable density.
7.4.2 Special Case
7.4.2.1 For cylindrical components where the source is placed on the axis of the object and one or
more film holders are used for a single exposure of a complete circumference, at least three
IQIs shall be spaced approximately 120deg. apart. Where sections of longitudinal welds are
required under the following conditions:
a. When the complete circumference is radiographed using one or more film holders,
or;
b. When a section or sections of the circumference, where the length between the ends
of the outermost sections span 240 or more deg., is radiographed using one or more
film holders. Additional film locations may be required to obtain necessary IQI
spacing.
7.4.2.2 For cylindrical components where the source is placed on the axis of the component for a
single exposure, at least three IQIs, with one placed at each end of span of the
circumference radiographed and one in the approximate center of the span, are required
under the following conditions:
c. When a section of a circumference, the length of which is greater than 120deg. And
less than 240deg. is radiographed using just one film holder, or;
d. When a section or sections of the circumference, where the length between the ends
of the outermost sections span less than 240deg., is radiographed using more than
one film holder.
7.4.2.3 In 7.4.2.1 and 7.4.2.2 above, where sections of longitudinal welds adjoining the
circumferential weld are radiographed simultaneously with the circumferential weld, an
additional IQI shall be placed on each longitudinal weld at the end of section most remote
from the junction with the circumferential weld being radiographed.
7.4.2.4 For segments of a flat or a curved (i.e., ellipsoidal, torispherical, toriconical, elliptical, etc.)
component where the source is placed perpendicular to the center of a length of weld for a
single exposure when using more than three film holders, at least three IQIs, one placed at
each end of the radiographed span and one in the approximate center of the span, are
required.
7.4.2.5 When an array of components in a circle is radiographed, at least one IQI shall show on
each component image.
7.4.2.6 In order to maintain the continuity of records involving subsequent exposures, all
radiographs exhibiting IQIs which qualify the techniques permitted in accordance with
6.4.2.1 through 6.4.2.4 above shall be retained.
7.5 IQI SENSITIVITY
Radiography shall be performed with a technique of sufficient sensitivity to display the
essential wire of a wire IQI as show in this procedure. The radiographs shall also display the
IQI identifying numbers and letters. If the essential wire, do not show on any film in a
multiple film technique, but do show in composite film viewing, interpretation shall be
permitted only by composite film viewing.
8 LOCATION MARKERS
Location markers (see Figure-1 below), which are to appear as radiographic images on the
film, shall be placed on the part, not on the exposure holder/cassette. Their locations shall
be permanently marked on the surface of the part being radiographed when permitted, or on

Page 11 of 25
No. : PTC.LP1.RT.01ASME
RADIOGRAPHIC Rev. :0
EXAMINATION PROCEDURE Date : 18-Aug-2016

a map, in a manner permitting the area of interest on a radiograph to be accurately traceable


to its location on the part, for the required retention period of the radiograph. Evidence shall
also be provided on the radiograph that the required coverage of the region being examined
has been obtained. Location markers shall be placed as follows.
8.1 SINGLE-WALL VIEWING
8.1.1 Source Side Markers
Source side location markers shall be used when radiographing the following:
(1) Flat components or longitudinal joints in cylindrical or conical components;
(2) Curved or spherical components whose concave side is toward the source and when the
"source-to-material" distance is less than the inside radius of the component;
(3) Curved or spherical components whose convex side is toward the source.
8.1.2 Film Side Markers
(1) Film side location markers shall be used when radiographing either curved or spherical
components whose concave side is toward the source and when the "source-to-material"
distance is greater than the inside radius.
(2) As an alternative for source side markers, film side markers may be used when the
radiograph shows coverage beyond the location markers to the extent demonstrated by
Figure-1 (e) and when this alternate is documented in the record.

Figure 1 – Location Marker Sketches


8.1.3 Either Side Markers

Page 12 of 25
No. : PTC.LP1.RT.01ASME
RADIOGRAPHIC Rev. :0
EXAMINATION PROCEDURE Date : 18-Aug-2016

Either source side or film side location markers may be used when radiographing either
curved or spherical components whose concave side is toward the source and the "source-
to-material" distance equals the inside radius of the component.
8.2 DOUBLE-WALL VIEWING
At least one location marker shall be placed on the outside surface adjacent to the weld (or
on the material in the area of interest) for each radiograph.
9 RADIOGRAPHIC TECHNIQUE
A single-wall exposure technique shall be used for radiography whenever practical. When it
is not practical to use a single-wall technique, a double-wall technique shall be used. An
adequate number of exposures shall be made to demonstrate that the required coverage has
been obtained
9.1 SINGLE-WALL TECHNIQUE
In the single-wall technique, the radiation passes through only one wall of the weld
(material), which is viewed for acceptance on the radiograph.
9.2 DOUBLE-WALL TECHNIQUE
When it is not practical to use a single-wall technique, one of the following double-wall
techniques shall be used.
9.2.1 Single-Wall Viewing
For materials and for welds in components, a technique may be used in which the radiation
passes through two walls and only the weld (material) on the film side wall is viewed for
acceptance on the radiograph. When complete coverage is required for circumferential
welds (materials), a minimum of three exposures taken 120 deg. to each other shall be
made.
9.2.2 Double-Wall Viewing
For materials and for welds in components 3½ in.(89mm) or less in nominal outside
diameter, a technique may be used in which the radiation passes through two walls and the
weld (material) in both walls is viewed for acceptance on the same radiograph. For double-
wall viewing, only a source side IQI shall be used. Care shall be exercised to ensure that the
required geometric un-sharpness is not exceeded. If the geometric un-sharpness requirement
cannot be met, then single-wall viewing shall be used.
(1) For welds, the radiation beam may be offset from the plane of the weld at an angle
sufficient to separate the images of the source side and film side portions of the weld so
that there is no overlap of the areas to be interpreted. When complete coverage is
required, a minimum of two exposures taken 90deg. to each other shall be made for
each joint.
(2) As an alternative, the weld may be radiographed with the radiation beam positioned so
that the images of both walls are superimposed. When complete coverage is required, a
minimum of three exposures taken at either 60deg. or 120deg. to each other shall be
made for each joint.
(3) Additional exposures shall be made if the required radiographic coverage cannot be
obtained using the minimum number of exposures indicated in (a) or (b) above.
10 ACCEPTANCE STANDARDS
10.1 ASME B31.3
Acceptance Criteria refer to ASME B31.3, Table 341.3.2 Acceptance criteria for welds and
examination methods for evaluating weld imperfections.

Page 13 of 25
No. : PTC.LP1.RT.01ASME
RADIOGRAPHIC Rev. :0
EXAMINATION PROCEDURE Date : 18-Aug-2016

Criteria (A to M) for Types of Welds and for Service Conditions [Note (1)]
Normal and
Severe Cyclic
Category M Fluid Category D Fluid Service
Conditions
Service
Type of Weld Type of Weld Type of Weld
Longitudinal Groove [Note (3)]

Longitudinal Groove [Note (3)]

Longitudinal Groove [Note (3)]


Girth, Miter Groove & Branch
Girth, Miter groove & Branch

Branch Connection [Note (2)]


Connection [Note (2)]

Girth, Miter Groove


Weld Imperfections
connection (note 2)

Fillet [Note (4)]

Fillet [Note (4)]

A A A A A A A A Fillet [Note (4)]


A A Crack
A A A A A A C A N/A A Lack of fusion
B A N/A A A N/A C A N/A B Incomplete penetration
E E N/A D D N/A N/A N/A N/A N/A Round indication
Internal slag inclusion,
G G N/A F F N/A N/A N/A N/A N/A tungsten inclusion, or
elongated indication
H A H A A A I A H H Undercutting

K K N/A K K N/A K K N/A K Concave surface

Page 14 of 25
No. : PTC.LP1.RT.01ASME
RADIOGRAPHIC Rev. :0
EXAMINATION PROCEDURE Date : 18-Aug-2016

Criterion
Sym Acceptable Value limits (Note 5)
Measurement
-bol
A Extent of imperfection Zero (no evident imperfection)
B Cumulative length of Incomplete penetration ≤ 38 mm in any 150 mm weld length
or 25% of total weld length, whichever is less
C Cumulative length of lack of fusion and incomplete ≤ 38mm (1.5in.) in any 150mm weld length
penetration or 25% of total weld length, whichever is less
D Size and distribution of round indication See BPV Code, Section VIII, Division l.
Appendix 4 (see Annex I in this procedure)

E Size and distribution of round indication For Tw ≤ 6mm, limit is same as D


For Tw > 6mm, limit is 1.5 x D
F Slag inclusion, tungsten inclusion, or elongated
indication
Individual length ≤ Tw/3
Individual width ≤ 2.5mm and ≤ Tw/2
Cumulative length ≤ Tw in any 12Tw weld length
G Slag inclusion, tungsten inclusion, or elongated
indication
Individual length ≤ 2Tw
Individual width ≤ 3 mm and ≤Tw/2
Cumulative length ≤ 4Tw in any 150mm weld length
H Depth of undercut ≤ 1 mm and ≤ Tw/4
(*)
I Depth of undercut ≤ 1.5 mm and ≤ (Tw/4 or 1mm)
(*)
K Depth of surface concavity Total joint thickness, incl. weld reinf., ≥ Tw
(**)
N/A None Application

Notes:
(1) Criteria given are for required examination. More stringent criteria may be specified in the
engineering design.
(2) Branch connection weld includes pressure containing welds in branches and fabricated laps
(3) Longitudinal groove weld includes straight and spiral seam.
(4) Fillet weld includes socket and seal welds, and attachment welds for slip-on flanges, branch
reinforcement, and supports.

Page 15 of 25
No. : PTC.LP1.RT.01ASME
RADIOGRAPHIC Rev. :0
EXAMINATION PROCEDURE Date : 18-Aug-2016

(5) Where two limiting values are separated by "and," the lesser of the values determines
acceptance. Where two sets of values is separated by "or," the larger value is acceptable. Tw is
the nominal wall thickness of the thinner of two components joined by a butt weld.
(*) Undercuts shall be inspected by visual examination, if appeared on the radiograph it shall be
checked against visual examination result for the final acceptance.
(**) When surface concavity appears on radiograph with the density more than the density on base
metal, it shall be rejected. Otherwise it will be accepted.
10.2 ASME Section IX, QW-191.1.2.2
Welder and welding operator performance tests by radiography of welds in test assemblies
shall be judged unacceptable when the radiograph exhibits any imperfections in excess of
the limits specified below
(a) Linear Indications
(1) any type of crack or zone of incomplete fusion or penetration
(2) any elongated slag inclusion which has a length greater than
(-a) 1/8 in. (3 mm) for t up to 3 /8 in. (10 mm), inclusive
(-b) 1/3t for t over 3/8 in. (10 mm) to 2 ¼ in. (57 mm), inclusive
(-c) ¾ in. (19 mm) for t over 2 ¼ in. (57 mm)
(3) any group of slag inclusions in line that have an aggregate length greater than t in a
length of 12t , except when the distance between the successive imperfections
exceeds 6L where L is the length of the longest imperfection in the group
(b) Rounded Indications
(1) The maximum permissible dimension for rounded indications shall be 20% of
t or 1/8 in. (3 mm), whichever is smaller.
(2) For welds in material less than 1/ 8 in. (3 mm) in thickness, the maximum
number of acceptable rounded indications shall not exceed 12 in a 6 in. (150
mm) length of weld. A proportionately fewer number of rounded indications
shall be permitted in welds less than 6 in. (150 mm) in length.
(3) For welds in material 1/ 8 in. (3 mm) or greater in thickness, the charts in
ASME Section IX Figure QW-191.1.2.2(b)(4) (see Annex 2 in this procedure)
represent the maximum acceptable types of rounded indications illustrated in
typically clustered, assorted, and randomly dispersed configurations. Rounded
indications less than 1/32 in. (0.8 mm) in maximum diameter shall not be
considered in the radiographic acceptance tests of welders and welding
operators in these ranges of material thicknesses.
11 EVALUATION BY PHATECO
The PHATECO shall be responsible for the review, interpretation, evaluation, and
acceptance of the completed radiographs to assure compliance with the requirements of
Article 2, ASME Section V and the referencing Code Section. The radiographic technique
details and the radiograph review form documentation shall accompany the radiographs.
Acceptance shall be completed prior to presentation of the radiographs and accompanying
documentation to the Inspector.
12 RADIATION SAFETY
All radiographic work carried out by PHATECO personnel will conform to PHATECO
safety procedure and local statutory safety equipment. PHATECO Safety Officer will
conduct periodic safety inspection at all work locations and will have the authority to

Page 16 of 25
No. : PTC.LP1.RT.01ASME
RADIOGRAPHIC Rev. :0
EXAMINATION PROCEDURE Date : 18-Aug-2016

suspend work if not satisfied with safety procedures adopted. Personnel found not adhering
to the standard safety procedures may be subjected to disciplinary action.
13 RECORDS
13.1 The results shall be recorded in the attached form by the certified personnel who perform
the radiographic examination. Radiographic examination records including radiographic
films shall be handover to the Manufacturer and Manufacturer shall retain as requirement in
Manufacturer’s manual.
13.2 The PHATECO shall prepare and document the radiographic technique details. As a
minimum, the following information shall be provided.
(1) Identification
(2) Dimensional map (if used) of marker placement
(3) Number of radiographs (exposures)
(4) X-ray voltage or isotope type used
(5) Source size
(6) Base material type and thickness, weld thickness, weld reinforcement thickness, as
applicable
(7) Source-to-object distance
(8) Distance from source side of object to film
(9) Film manufacturer and their assigned type/ designation
(10) Number of film in each film holder/cassette
(11) Single- or double-wall exposure
(12) Single-or double-wall viewing
14 Annex 1 - Rounded Indications Charts Acceptance Standard
(1) Applicability of These Standards
These standards are applicable to ferritic, austenitic, and nonferrous materials.
(2) Terminology
(a) Rounded Indications. Indications with a maximum length of three times the width or
less on the radiograph are defined as rounded indications. These indications may be
circular, elliptical, conical, or irregular in shape and may have tails. When evaluating
the size of an indication, the tail shall be included. The indication may be from any
imperfection in the weld, such as porosity, slag, or tungsten.
(b) Aligned Indications. A sequence of four or more rounded indications shall be
considered to be aligned when they touch a line parallel to the length of the weld
drawn through the center of the two outer rounded indications.
(c) Thickness t. t is the thickness of the weld, excluding any allowable reinforcement. For
a butt weld joining two members having different thickness at the weld, t is the thinner
of these two thicknesses. If a full penetration weld includes a fillet weld, the thickness
of the throat of the fillet shall be included in t.
(3) Acceptance Criteria
(a) Image Density. Density within the image of the indication may vary and is not a
criterion for acceptance or rejection.
(b) Relevant Indications. Only those round indications which exceed the following
dimensions shall be considered relevant.

Page 17 of 25
No. : PTC.LP1.RT.01ASME
RADIOGRAPHIC Rev. :0
EXAMINATION PROCEDURE Date : 18-Aug-2016

- 1/10 t for t less than 3 mm


- 0.4 mm for t equal to 3 mm to 6 mm, incl.
- 0.8 mm for t greater than 6 mm to 50 mm, incl
- 1.6 mm for t greater than 50 mm
(c) Maximum Size of Rounded Indication. (See table 4.1 for example)
The maximum permissible size of any indication shall be 1/4t, or 4 mm, whichever is
smaller; except that an isolated indication separated from an adjacent indication by 25
mm or more may be 1/3t, or 6 mm, whichever is less. For t greater than 50 mm, the
maximum permissible size of an isolated indication shall be increased to 10 mm.

Table 4.1 Maximum Size of Acceptable Rounded Indication

(d) Aligned Rounded Indications.


Aligned rounded indications are acceptable when the summation of the diameters of
the indications is less than t in a length of 12t. The length of groups of aligned
rounded indications and the spacing between the groups shall meet the requirements
of following Figure.
(e) Spacing
The distance between adjacent rounded indications is not a factor in determining
acceptance or rejection, except as required for isolated indications or groups of aligned
indications.
(f) Rounded Indication Charts.
The rounded indications characterized as imperfections shall not exceed that shown in
the charts. The following charts illustrate various types of assorted, randomly

Page 18 of 25
No. : PTC.LP1.RT.01ASME
RADIOGRAPHIC Rev. :0
EXAMINATION PROCEDURE Date : 18-Aug-2016

dispersed and clustered rounded indications for different weld thicknesses greater than
3 mm. These charts represent the maximum acceptable concentration limits for
rounded indications. The charts for each thickness range represent full scale 150 mm
radiographs, and shall not be enlarged or reduced. The distributions shown are not
necessarily the patterns that may appear on the radiograph, but are typical of the
concentration and size of indications permitted.
(g) Weld Thickness t less than 3 mm
For t less than 3 mm, the maximum number of rounded indications shall not exceed 12
in a 150 mm length of weld. A proportionally fewer number of indications shall be
permitted in welds less than 150 mm in length.
(h) Clustered Indications.
The illustrations for clustered indications show up to four times as many indications in
a local area, as that shown in the illustrations for random indications. The length of an
acceptable cluster shall not exceed the lesser of 25 mm or 2t. Where more than one
cluster is present, the sum of the lengths of the clusters shall not exceed 25 mm in a
150 mm length weld.

Page 19 of 25
No. : PTC.LP1.RT.01ASME
RADIOGRAPHIC Rev. :0
EXAMINATION PROCEDURE Date : 18-Aug-2016

Page 20 of 25
No. : PTC.LP1.RT.01ASME
RADIOGRAPHIC Rev. :0
EXAMINATION PROCEDURE Date : 18-Aug-2016

Page 21 of 25
No. : PTC.LP1.RT.01ASME
RADIOGRAPHIC Rev. :0
EXAMINATION PROCEDURE Date : 18-Aug-2016

Page 22 of 25
No. : PTC.LP1.RT.01ASME
RADIOGRAPHIC Rev. :0
EXAMINATION PROCEDURE Date : 18-Aug-2016

Page 23 of 25
No. : PTC.LP1.RT.01ASME
RADIOGRAPHIC Rev. :0
EXAMINATION PROCEDURE Date : 18-Aug-2016

15 Annex 2- ASME Section IX, Maximum acceptable types of rounded indications

Page 24 of 25
No. : PTC.LP1.RT.01ASME
RADIOGRAPHIC Rev. :0
EXAMINATION PROCEDURE Date : 18-Aug-2016

16 Annex 3 - Radiographic Examination Report Form

AGRIMECO

Page 25 of 25

S-ar putea să vă placă și