COST ESTIMATION OF REVISED PROPOSED SEVEN STORIED

BUILDING WITH ONE UNDER GROUND STORAGE AND WITH


EIGHT STORIED FOUNDATION
AT PLOT NO-616, ROAD NO-31, MOUZA-CHAKULI, PALLABI,
MIRPUR DOHS, DHAKA.
2)PILE CAP& FOOTING WORK
Name of item Quantity Unit Rate Amount Cumilitive cost
Earth Excavation work for
15825 cft 16 253200
basement
Earth Excavation for cap work 2150 cft 16 34400
C.C 210 cft
Cement 36 bag 475 17100
sand 90 cft
local sand 90 cft 14 1260
Sylhet sand cft 45 0
Brick Chips 180 cft 95 17100
R.C.C Casting 2230 cft
Cement 487 bag 475 231109
sand 912 cft
local sand cft 14 0
Sylhet sand 912 cft 45 41052
Stone 1825 cft 152 277331
Reinforcement
20mm 3975 kg 52 206700
16mm 920 kg 52 47840
12mm 75 kg 52 3900
10mm 250 kg 52 13000
Labour cost sft 130 0
TOTAL 1143992 1143992

3)U.G.W.R
Name of item Quantity Unit Rate Amount Cumilitive cost
Casting 350 cft
Cement 60 bag 475 28500
sand 150 cft
local sand 75 cft 14 1050
Sylhet sand 75 cft 45 3375
Brick Chips 300 cft 152 45600
Reinforcement
12mm 635 kg 52 33020
10mm 400 kg 52 20800
Labour cost sft 150 0
TOTAL 132345 1276337
3)BASEMENT SLAB
Name of item Quantity Unit Rate Amount Cumilitive cost
Brick flat solling 1900 sft 52 98800
Casting 1845 cft
Cement 316 bag 475 150236
sand 791 cft
local sand 395 cft 14 5535
Sylhet sand 395 cft 45 150236
Brick Chips 1581 cft 152 240377
Reinforcement
12mm 6320 kg 52 328640
Labour cost sft 150 0
TOTAL 973824 2250161
3)RETAINING WALL
Name of item Quantity Unit Rate Amount Cumilitive cost
Casting 1025 cft
Cement 176 bag 475 83464
sand 439 cft
local sand 220 cft 14 3075
Sylhet sand 220 cft 45 9884
Brick Chips 879 cft 152 133543
Reinforcement
12mm 535 kg 52 27820
10mm 1665 kg 52 86580
Labour cost sft 150 0
TOTAL 344366 2594527

4)COLUMN BELOW GF
Name of item Quantity Unit Rate Amount Cumilitive cost
Casting 236 cft
Cement 51 bag 475 24458
sand 97 cft
local sand cft 14 0
Sylhet sand 97 cft 45 4345
Stone 193 cft 152 29350
Reinforcement
25mm 1200 kg 52 62400
20mm 1085 kg 52 56420
10mm 620 kg 52 32240
Labour cost 130 0
TOTAL 209213 2803739

5)Ground floor BEAM


Name of item Quantity Unit Rate Amount Cumilitive cost
Casting 166 cft
Cement 28 bag 475 13517
sand 71 cft
local sand 18 cft 14 249
Sylhet sand 53 cft 45 2401
Stone Chips 142 cft 95 13517
reinforcement
20mm 610 kg 52 31720
16mm 95 kg 52 4940
10mm 210 kg 52 10920
Labour cost 0
TOTAL 77264 2881004
6)Ground Floor slab
Name of item Quantity Unit Rate Amount Cumilitive cost
Casting 975 cft
Cement 167 bag 475 79393
sand 418 cft
local sand 418 cft 14 5850
Sylhet sand cft 45 0
Brick Chips 836 cft 95 79393
Reinforcement
12mm 160 kg 52 8320
10mm 2040 kg 52 106080
Labour cost 2150 sft 140 301000
TOTAL 580036 3461040

7)COLUMN GF UPTO 1ST


Name of item Quantity Unit Rate Amount Cumilitive cost
Casting 276 cft
Cement 60 bag 475 28604
sand 113 cft
local sand cft 14 0
Sylhet sand 113 cft 45 5081
Stone 226 cft 152 34324
Reinforcement
25mm 1200 kg 52 62400
20mm 1085 kg 52 56420
10mm 470 kg 52 24440
Labour cost 0
TOTAL 211269 3672308

8)GF ROOF FLOOR BEAM


Name of item Quantity Unit Rate Amount Cumilitive cost
Casting 320 cft
Cement 55 bag 475 26057
sand 137 cft
local sand 34 cft 14 480
Sylhet sand 103 cft 45 4629
Stone chips 274 cft 95 26057
reinforcement
20mm 1540 kg 52 80080
16mm 240 kg 52 12480
10mm 630 kg 52 32760
Labour cost cft 0
TOTAL 182543 3854851

9)GF ROOF FLOOR SLAB


Name of item Quantity Unit Rate Amount Cumilitive cost
Casting 945 cft
Cement 162 bag 475 76950
sand 405 cft
local sand 203 cft 14 2835
Sylhet sand 203 cft 45 76950
Brick Chips 810 cft 95 76950
reinforcement
12mm 475 kg 52 24700
10mm 1720 kg 52 89440
Labour cost 1945 sft 152 295640
TOTAL 643465 4498316
10)STAIR per floor
Name of item Quantity Unit Rate Amount Cumilitive cost
Casting 145 cft
Cement 25 bag 475 11807
Sand 62 cft
Local sand 31 cft 25 777
Sylhet sand 31 cft 45 1398
Brick Chips 124 cft 95 11807
Reinforcement
20mm 45 kg 52 2340
16mm 15 kg 52 780
12mm 390 kg 52 26975
10mm 175 kg 52 11807
Labour cost cft 130 0
TOTAL 67691 4566008

11)COLUMN 1St to 2nd


Name of item Quantity Unit Rate Amount Cumilitive cost
Casting 276 cft
Cement 60 bag 475 28604
sand 113 cft
local sand cft 14 0
Sylhet sand 113 cft 45 5081
Stone 226 cft 152 34324
Reinforcement
25mm 1200 kg 52 62400
20mm 1085 kg 52 56420
10mm 470 kg 52 24440
Labour cost 140 0
TOTAL 211269 4777277

12)2ND FLOOR BEAM


Name of item Quantity Unit Rate Amount Cumilitive cost
Casting 320 cft
Cement 55 bag 475 26057
sand 137 cft
local sand 34 cft 14 480
Sylhet sand 103 cft 45 4629
Brick chips 274 cft 95 26057
reinforcement
20mm 1540 kg 52 80080
26mm 240 kg 52 12480
10mm 630 kg 52 32760
Labour cost cft 130 0
TOTAL 182543 4959819

13)2ND FLOOR SLAB


Name of item Quantity Unit Rate Amount Cumilitive cost
Casting 945 cft
Cement 162 bag 475 76950
sand 405 cft
local sand 203 cft 14 2835
Sylhet sand 203 cft 45 9113
Brick Chips 810 cft 95 76950
reinforcement
12mm 475 kg 52 24700
10mm 1720 kg 52 89440
Labour cost 1945 152 295640
TOTAL 575628 5535447
14)STAIR per floor
Name of item Quantity Unit Rate Amount Cumilitive cost
Casting 145 cft
Cement 25 bag 475 11807
Sand 62 cft
Local sand 31 cft 25 777
Sylhet sand 31 cft 45 1398
Brick Chips 124 cft 95 11807
Reinforcement
20mm 45 kg 52 2340
16mm 15 kg 52 780
12mm 390 kg 52 20280
10mm 175 kg 52 9100
Labour cost 130 0
TOTAL 58289 5593736

15)COLUMN 2nd to 3rd


Name of item Quantity Unit Rate Amount Cumilitive cost
Casting 276 cft
Cement 60 bag 475 28604
sand 113 cft
local sand cft 14 0
Sylhet sand 113 cft 45 5081
Stone 226 cft 152 34324
Reinforcement
25mm 460 kg 52 23920
20mm 1195 kg 52 62140
16mm 200 kg 52 10400
10mm 470 kg 52 24440
Labour cost 140 0
TOTAL 188909 5782645

16)3rd FLOOR BEAM


Name of item Quantity Unit Rate Amount Cumilitive cost
Casting 320 cft
Cement 55 bag 475 26057
sand 17 cft
local sand 4 cft 14 59
Sylhet sand 13 cft 45 568
Brick chips 34 cft 95 3200
reinforcement
20mm 1540 kg 52 80080
16mm 240 kg 52 12480
10mm 630 kg 52 32760
Labour cost cft 130 0
TOTAL 155205 5937850

17)3rd FLOOR SLAB


Name of item Quantity Unit Rate Amount Cumilitive cost
Casting 945 cft
Cement 162 bag 475 76950
sand 405 cft
local sand 203 cft 14 2835
Sylhet sand 203 cft 45 9113
Brick Chips 810 cft 95 76950
reinforcement
12mm 475 kg 52 24700
10mm 1720 kg 52 89440
Labour cost 1945 sft 152 295640
TOTAL 575628 6513477
18)STAIR 3rd floor
Name of item Quantity Unit Rate Amount Cumilitive cost
Casting 145 cft
Cement 25 bag 475 11807
Sand 62 cft
Local sand 31 cft 25 777
Sylhet sand 31 cft 45 1398
Brick Chips 124 cft 95 11807
Reinforcement
20mm 45 kg 52 2340
16mm 15 kg 52 780
12mm 390 kg 52 20280
10mm 175 kg 52 9100
Labour cost 130 0
TOTAL 58289 6571766

19)COLUMN 3rd to 4th


Name of item Quantity Unit Rate Amount Cumilitive cost
Casting 276 cft
Cement 60 bag 475 28604
sand 113 cft
local sand cft 14 0
Sylhet sand 113 cft 45 5081
Stone 226 cft 152 34324
Reinforcement
25mm 460 kg 52 23920
20mm 1195 kg 52 62140
16mm 200 kg 52 10400
10mm 470 kg 52 24440
Labour cost 140 0
TOTAL 188909 6760675

20)4th FLOOR BEAM


Name of item Quantity Unit Rate Amount Cumilitive cost
Casting 320 cft
Cement 55 bag 475 26057
sand 137 cft
local sand 34 cft 14 480
Sylhet sand 103 cft 45 4629
Brick chips 274 cft 95 26057
reinforcement
20mm 1540 kg 52 80080
16mm 240 kg 52 12480
10mm 630 kg 52 32760
Labour cost cft 0
TOTAL 182543 6943218

21)4th FLOOR SLAB


Name of item Quantity Unit Rate Amount Cumilitive cost
Casting 945 cft
Cement 162 bag 475 76950
sand 405 cft
local sand 203 cft 14 2835
Sylhet sand 203 cft 45 9113
Brick Chips 810 cft 95 76950
reinforcement
12mm 475 kg 52 24700
10mm 1720 kg 52 89440
Labour cost 1945 sft 152 295640
TOTAL 575628 7518846
22)STAIR per floor
Name of item Quantity Unit Rate Amount Cumilitive cost
Casting 145 cft
Cement 25 bag 475 11807
Sand 62 cft
Local sand 31 cft 25 777
Sylhet sand 31 cft 45 1398
Brick Chips 124 cft 95 11807
Reinforcement
20mm 45 kg 52 2340
16mm 15 kg 52 780
12mm 390 kg 52 20280
10mm 175 kg 52 2340
Labour cost 0
TOTAL 51529 7570375

23)COLUMN 4TH to 5TH


Name of item Quantity Unit Rate Amount Cumilitive cost
Casting 276 cft
Cement 60 bag 475 28604
sand 113 cft
local sand cft 14 0
Sylhet sand 113 cft 45 5081
Stone 226 cft 152 34324
Reinforcement
25mm 460 kg 52 23920
20mm 1195 kg 52 62140
16mm 200 kg 52 10400
10mm 470 kg 52 24440
Labour cost 140 0
TOTAL 188909 7759284

24)5th FLOOR BEAM


Name of item Quantity Unit Rate Amount Cumilitive cost
Casting 320 cft
Cement 55 bag 475 26057
sand 137 cft
local sand 34 cft 14 480
Sylhet sand 103 cft 45 4629
Brick chips 274 cft 95 26057
reinforcement
20mm 1540 kg 52 80080
16mm 240 kg 52 12480
10mm 630 kg 52 32760
Labour cost cft 130 0
TOTAL 182543 7941827

25)5th FLOOR SLAB


Name of item Quantity Unit Rate Amount Cumilitive cost
Casting 945 cft
Cement 162 bag 475 76950
sand 405 cft
local sand 203 cft 14 2835
Sylhet sand 203 cft 45 9113
Brick Chips 810 cft 95 76950
reinforcement
12mm 475 kg 52 24700
10mm 1720 kg 52 89440
Labour cost 1945 sft 152 295640
TOTAL 575628 8517454
26)STAIR per floor
Name of item Quantity Unit Rate Amount Cumilitive cost
Casting 145 cft
Cement 25 bag 475 11807
Sand 62 cft
Local sand 31 cft 25 777
Sylhet sand 31 cft 45 1398
Brick Chips 124 cft 95 11807
Reinforcement
20mm 45 kg 52 2340
16mm 15 kg 52 780
12mm 390 kg 52 20280
10mm 175 kg 52 9100
Labour cost 130 0
TOTAL 58289 8575744

27)COLUMN 5TH to 6TH


Name of item Quantity Unit Rate Amount Cumilitive cost
Casting 276 cft
Cement 60 bag 475 28604
sand 113 cft
local sand cft 14 0
Sylhet sand 113 cft 45 5081
Stone 226 cft 152 34324
Reinforcement
20mm 1285 kg 52 66820
16mm 465 kg 52 24180
10mm 470 kg 52 24440
Labour cost 140 0
TOTAL 183449 8759192

28)6th FLOOR BEAM


Name of item Quantity Unit Rate Amount Cumilitive cost
Casting 320 cft
Cement 55 bag 475 26057
sand 137 cft
local sand 34 cft 14 480
Sylhet sand 103 cft 45 4629
Brick chips 274 cft 95 26057
reinforcement
20mm 1540 kg 52 80080
16mm 240 kg 52 12480
10mm 630 kg 52 32760
Labour cost cft 130 0
TOTAL 182543 8941735

29)6th FLOOR SLAB


Name of item Quantity Unit Rate Amount Cumilitive cost
Casting 945 cft
Cement 162 bag 475 76950
sand 405 cft
local sand 203 cft 14 2835
Sylhet sand 203 cft 45 76950
Brick Chips 810 cft 95 76950
reinforcement
12mm 475 kg 52 24700
10mm 1720 kg 52 89440
Labour cost 1945 sft 152 295640
TOTAL 643465 9585200
30)STAIR per floor
Name of item Quantity Unit Rate Amount Cumilitive cost
Casting 145 cft
Cement 25 bag 475 11807
Sand 62 cft
Local sand 31 cft 25 777
Sylhet sand 31 cft 45 1398
Brick Chips 124 cft 95 11807
Reinforcement
20mm 45 kg 52 2340
16mm 15 kg 52 780
12mm 390 kg 52 20280
10mm 175 kg 52 11807
Labour cost 130 0
TOTAL 60996 9646197
27)COLUMN 6TH to TOP
Name of item Quantity Unit Rate Amount Cumilitive cost
Casting 276 cft
Cement 60 bag 475 28604
sand 113 cft
local sand cft 14 0
Sylhet sand 113 cft 45 5081
Stone 226 cft 152 34324
Reinforcement
20mm 1285 kg 52 66820
16mm 465 kg 52 24180
10mm 470 kg 52 24440
Labour cost 140 0
TOTAL 183449 9829646

28)ROOF FLOOR BEAM


Name of item Quantity Unit Rate Amount Cumilitive cost
Casting 320 cft
Cement 55 bag 475 26057
sand 137 cft
local sand 34 cft 14 480
Sylhet sand 103 cft 45 4629
Brick chips 274 cft 95 26057
reinforcement
20mm 1540 kg 52 80080
16mm 240 kg 52 12480
10mm 630 kg 52 32760
Labour cost cft 130 0
TOTAL 182543 10012189

29)ROOF FLOOR SLAB


Name of item Quantity Unit Rate Amount Cumilitive cost
Casting 945 cft
Cement 162 bag 475 76950
sand 405 cft
local sand 203 cft 14 2835
Sylhet sand 203 cft 45 76950
Brick Chips 810 cft 95 76950
reinforcement
12mm 475 kg 52 24700
10mm 1720 kg 52 89440
Labour cost 1945 sft 152 295640
TOTAL 643465 10655654
30)STAIR per floor
Name of item Quantity Unit Rate Amount Cumilitive cost
Casting 145 cft
Cement 25 bag 475 11807
Sand 62 cft
Local sand 31 cft 25 777
Sylhet sand 31 cft 45 1398
Brick Chips 124 cft 95 11807
Reinforcement
20mm 45 kg 52 2340
16mm 15 kg 52 780
12mm 390 kg 52 20280
10mm 175 kg 52 11807
Labour cost 130 0
TOTAL 60996 10716650

35)Machine room + O.H.W.T


Name of item Quantity Unit Rate Amount Cumilitive cost
Casting 380 cft
Cement 65 bag 475 30943
Sand 163 cft 0
Local sand 81 cft 25 2036
Sylhet sand 81 cft 45 3664
Brick Chips 326 cft 95 30943
Reinforcement 0
20mm 340 kg 52 17680
16mm 285 kg 52 14820
12mm 575 kg 52 29900
10mm 680 kg 52 35360
Labour cost 200 sft 100 20000
TOTAL 185346 10901996

36)SEPTIC TANK
Name of item Quantity Unit Rate Amount Cumilitive cost
Casting 52 cft
Cement 9 bag 475 4234
Sand 22 cft 0
Local sand 11 cft 25 279
Sylhet sand 11 cft 45 501
Brick Chips 45 cft 150 6686
Reinforcement 0
10mm 140 kg 52 7280
Labour cost 100 0
TOTAL 18980 10920976

Total cost for civil work .


in Word (tk): One core four lac ninety nine thousand one hundred.