Sunteți pe pagina 1din 15

Credtrans Effects of Guaranty

the Shoppers Gold Building, located at Dr. A. Santos Avenue Respondent then made, on 3 January 2001, a written
corner Palayag Road, Sucat, Paraaque City. Respondent demand[10] on petitioner, as guarantor of Macrogen Realty, to
commenced civil, structural, and architectural works on the pay the P6,000,000.00, or to point out available properties of
THIRD DIVISION construction project by May the Macrogen Realty within the Philippines sufficient to cover
1997. However, Macrogen Realty failed to settle respondents the obligation guaranteed. It also made verbal demands on
progress billings. Petitioner, through his representatives and petitioner. Yet, respondents demands were left unheeded.
BENJAMIN BITANGA, G.R. No. 173526 agents, assured respondent that the outstanding account
Petitioner, of Macrogen Realty would be paid, and requested respondent Thus, according to respondent, petitioners
Present: to continue working on the construction project.Relying on the obligation as guarantor was already due and demandable. As
assurances made by petitioner, who was no less than the to Marilyns liability, respondent contended
YNARES- President of Macrogen Realty, respondent continued the that MacrogenRealty was owned and controlled by petitioner
SANTIAGO, J., construction project. and Marilyn and/or by corporations owned and controlled by
- versus - Chairperson, them. Macrogen Realty is 99% owned by the Asian Appraisal
AUSTRIA-MARTINEZ, In August 1998, respondent suspended work on the Holdings, Inc. (AAHI), which in turn is 99% owned by
CHICO-NAZARIO, construction project since the conditions that it imposed for Marilyn. Since the completion of the construction project
NACHURA, and the continuation thereof, including payment of unsettled would have redounded to the benefit of both petitioner and
REYES, JJ. accounts, had not been complied with Marilyn and/or their corporations; and considering, moreover,
PYRAMID by Macrogen Realty. On 1 September 1999, respondent Marilyns enormous interest in AAHI, the corporation which
CONSTRUCTION instituted with the Construction Industry Arbitration controls Macrogen Realty, Marilyn cannot be unaware of the
ENGINEERING Promulgated: Commission (CIAC) a case for arbitration obligations incurred by Macrogen Realty and/or petitioner in
CORPORATION, against Macrogen Realty seeking payment by the latter of its the course of the business operations of the said corporation.
Respondent. August 28, 2008 unpaid billings and project costs. Petitioner, through counsel,
x- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - then conveyed to respondent his purported willingness to Respondent prayed in its Complaint that the RTC,
- - - - - - -x amicably settle the arbitration case. On 17 April 2000, before after hearing, render a judgment ordering petitioner and
the arbitration case could be set for trial, respondent Marilyn to comply with their obligation under the Contract of
and MacrogenRealty entered into a Compromise Guaranty by paying respondent the amount
Agreement,[5] with petitioner acting as signatory for and in of P6,000,000.000 (less the bank deposit of Macrogen Realty
DECISION behalf of Macrogen Realty. Under the Compromise with Planters Bank in the amount of P20,242.23)
Agreement, MacrogenRealty agreed to pay respondent the and P400,000.000 for attorneys fees and expenses of
total amount of P6,000,000.00 in six equal monthly litigation. Respondent also sought the issuance of a writ of
installments, with each installment to be delivered on the preliminary attachment as security for the satisfaction of any
CHICO-NAZARIO, J.: 15th day of the month, beginning 15 June judgment that may be recovered in the case in its favor.
2000. Macrogen Realty also agreed that if it would default in
the payment of two successive monthly installments, Marilyn filed a Motion to Dismiss,[11] asserting that respondent
Assailed in this Petition for Review under Rule 45[1] of the immediate execution could issue against it for the unpaid had no cause of action against her, since she did not co-sign
Revised Rules of Court are: (1) the Decision[2] dated 11 April balance, without need of judgment or decree from any court the Contract of Guaranty with her husband; nor was she a
2006 of the Court of Appeals in CA-G.R. CV No. 78007 which or tribunal. Petitioner guaranteed the obligations party to the Compromise Agreement between respondent
affirmed with modification the partial Decision[3] dated 29 of Macrogen Realty under the Compromise Agreement by and Macrogen Realty. She had no part at all in the execution
November 2002 of the Regional Trial Court (RTC), Branch 96, executing a Contract of Guaranty[6] in favor of respondent, by of the said contracts. Mere ownership by a single stockholder
of Quezon City, in Civil Case No. Q-01-45041, granting the virtue of which he irrevocably and unconditionally guaranteed or by another corporation of all or nearly all of the capital stock
motion for summary judgment filed by respondent Pyramid the full and complete payment of the principal amount of of another corporation is not by itself a sufficient ground for
Construction and Engineering Corporation and declaring liability of Macrogen Realty in the sum disregarding the separate personality of the latter
petitioner Benjamin Bitanga and his wife, of P6,000,000.00. Upon joint motion of respondent corporation. Respondent misread Section 4, Rule 3 of the
Marilyn Bitanga (Marilyn), solidarily liable to and Macrogen Realty, the CIAC approved the Compromise Revised Rules of Court.
pay P6,000,000.000 to respondent; and (2) the Agreement on 25 April 2000.[7]
Resolution[4] dated 5 July 2006 of the appellate court in the The RTC denied Marilyns Motion to Dismiss for lack
same case denying petitioners Motion for Reconsideration. However, contrary to petitioners of merit, and in its Order dated 24 January 2002 decreed that:
assurances, Macrogen Realty failed and refused to pay all the
The generative facts are: monthly installments agreed upon in the Compromise The Motion To Dismiss Complaint
Agreement.Hence, on 7 September 2000, respondent moved Against Defendant
On 6 September 2001, respondent filed with the RTC a for the issuance of a writ of Marilyn Andal Bitanga filed
Complaint for specific performance and damages with execution[8] against Macrogen Realty, which CIAC granted. on November 12, 2001 is denied for lack
application for the issuance of a writ of preliminary attachment of merit considering that Sec. 4, Rule 3,
against the petitioner and Marilyn. The Complaint was On 29 November 2000, the sheriff[9] filed a return of the Rules of Court (1997) specifically
docketed as Civil Case No. Q-01-45041. stating that he was unable to locate any property provides, as follows:
of Macrogen Realty, except its bank deposit of P20,242.33,
Respondent alleged in its Complaint that on 26 March 1997, with the Planters Bank, Buendia Branch. SEC. 4. Spouses as
it entered into an agreement with Macrogen Realty, of which parties. Husband
petitioner is the President, to construct for the latter
1
Credtrans Effects of Guaranty

and wife shall sue or proper notice was received by and he did not waive his right thereto. He never received the
be sued jointly, Benjamin Bitanga; respondents demand letter dated 3 January 2001, as
except as provided Ms. Dette Ramos, the person who received it, was not an
by law. (4) if damages are due, which party is employee of Macrogen Realty nor was she authorized to
liable; and receive the letter on his behalf. As a guarantor, petitioner
and that this case does not come within could resort to the benefit of excussion at any time before
the exception.[12] (5) whether the benefit of excussion can judgment was rendered against him.[19] Petitioner reiterated
still be invoked by the that Macrogen Realty had uncollected credits which were
defendant guarantor even more than sufficient to satisfy the claim of respondent.
Petitioner filed with the RTC on 12 November 2001, his after the notice has been On 29 November 2002, the RTC rendered a partial Decision,
Answer[13] to respondents Complaint averring therein that he allegedly sent by the plaintiff the dispositive portion of which provides:
never made representations to respondent although proper receipt is
that Macrogen Realty would faithfully comply with its denied.[14] WHEREFORE, summary judgment is
obligations under the Compromise Agreement. He did not rendered ordering defendants
offer to guarantee the obligations of Macrogen Realty to SPOUSES BENJAMIN BITANGA and
entice respondent to enter into the Compromise Agreement On 20 September 2002, prior to the trial proper, respondent MARILYN ANDAL BITANGA to pay the
but that, on the contrary, it was respondent that filed a Motion for Summary Judgment.[15] Respondent alleged [herein respondent], jointly and severally,
required Macrogen Realty to offer some form of security for its therein that it was entitled to a summary judgment on account the amount of P6,000,000.00,
obligations before agreeing to the compromise. Petitioner of petitioners admission during the pre-trial of the less P20,242.23 (representing the
further alleged that his wife Marilyn was not aware of the genuineness and due execution of the Contract of amount garnished bank deposit of
obligations that he assumed under both the Compromise Guaranty. The contention of petitioner and Marilyn that they MACROGEN in the Planters
Agreement and the Contract of Guaranty as he did not inform were entitled to the benefit of excussion was not a genuine Bank, Buendia Branch); and the costs of
her about said contracts, nor did he secure her consent issue. Respondent had already exhausted all legal remedies suit.
thereto at the time of their execution. to collect from Macrogen Realty, but its efforts proved
unsuccessful. Given that the inability of Macrogen Realty as Within 10 days from receipt of this partial
As a special and affirmative defense, petitioner argued that debtor to pay the amount of its debt was already proven by decision, the [respondent] shall inform
the benefit of excussion was still available to him as a the return of the writ of execution to CIAC unsatisfied, the the Court whether it shall still pursue the
guarantor since he had set it up prior to any judgment against liability of petitioner as guarantor already arose.[16] In any rest of the claims against the defendants.
him. According to petitioner, respondent failed to exhaust all event, petitioner and Marilyn were deemed to have forfeited Otherwise, such claims shall be
legal remedies to collect from Macrogen Realty the amount their right to avail themselves of the benefit considered waived.[20]
due under the Compromise Agreement, considering of excussion because they failed to comply with Article
that Macrogen Realty still had uncollected credits which were 2060[17] of the Civil Code when petitioner ignored respondents
more than enough to pay for the same. Given these premise, demand letter dated 3 January 2001 for payment of the Petitioner and Marilyn filed a Motion for Reconsideration of
petitioner could not be held liable as guarantor. Consequently, amount he guaranteed.[18] The duty to collect the supposed the afore-quoted Decision, which the RTC denied in an Order
petitioner presented his counterclaim for damages. receivables of Macrogen Realty from its creditors could not be dated 26 January 2003.[21]
imposed on respondent, since petitioner and Marilyn never
At the pre-trial held on 5 September 2002, the parties informed respondent about such uncollected credits even In time, petitioner and Marilyn filed an appeal with the Court
submitted the following issues for the resolution of the RTC: after receipt of the demand letter for payment. The allegation of Appeals, docketed as CA-G.R. CV 78007. In its Decision
of petitioner and Marilyn that they could not respond to dated 11 April 2006, the appellate court held:
(1) whether the defendants were liable respondents demand letter since they did not receive the
under the contract of same was unsubstantiated and insufficient to raise a genuine UPON THE VIEW WE TAKE OF THIS
guarantee dated April 17, issue of fact which could defeat respondents Motion for CASE, THUS, the judgment appealed
2000 entered into between Summary Judgment. The claim that Marilyn never from must be, as it hereby is, MODIFIED
Benjamin Bitanga and the participated in the transactions that culminated in petitioners to the effect that defendant-appellant
plaintiff; execution of the Contract of Guaranty was nothing more than Marilyn Bitanga is adjudged not liable,
a sham. whether solidarily or otherwise, with her
(2) whether defendant wife husband the defendant-appellant
Marilyn Bitanga is liable in this In opposing respondents foregoing Motion for Summary Benjamin Bitanga, under the
action; Judgment, petitioner and Marilyn countered that there were compromise agreement or the contract of
genuinely disputed facts that would require trial on the guaranty. No costs in this instance.[22]
(3) whether the defendants are entitled to merits. They appended thereto an affidavit executed by
the benefit of excussion, the petitioner, in which he declared that his spouse Marilyn could
plaintiff on the one hand not be held personally liable under the Contract of Guaranty In holding that Marilyn Bitanga was not liable, the
claiming that it gave due notice or the Compromise Agreement, nor should her share in the Court of Appeals cited Ramos v. Court of Appeals,[23] in which
to the guarantor, conjugal partnership be made answerable for the guaranty it was declared that a contract cannot be enforced against one
Benjamin Bitanga, and the petitioner assumed, because his undertaking of the guaranty who is not a party to it. The Court of Appeals stated further
defendants contending that no did not in any way redound to the benefit of their family. As that the substantial ownership of shares in Macrogen Realty
guarantor, petitioner was entitled to the benefit of excussion, by Marilyn Bitanga was not enough basis to hold her liable.

2
Credtrans Effects of Guaranty

relief may, at any time after the pleading between the hours of eight in the morning
The Court of Appeals, in its Resolution dated 5 July in answer thereto has been served, move and six in the evening, at the partys or
2006, denied petitioners Motion for Reconsideration[24] of its with supporting affidavits, depositions or counsels residence, if known, with a
earlier Decision. admissions for a summary judgment in person of sufficient age and discretion
his favor upon all or any part thereof. then residing therein.
Petitioner is now before us via the present Petition with the
following assignment of errors:
For a summary judgment to be proper, The affidavit of Mr. Robert O. Pagdilao, messenger
I the movant must establish two requisites: (a) there must be of respondents counsel states in part:
no genuine issue as to any material fact, except for the
THE COURT OF APPEALS GRAVELY amount of damages; and (b) the party presenting the motion 2. On 4 January 2001, Atty. Jose Vicente
ERRED IN AFFIRMING THE VALIDITY for summary judgment must be entitled to a judgment as a B. Salazar, then one of the
OF THE PARTIAL SUMMARY matter of law. Where, on the basis of the pleadings of a Associates of the ACCRA Law
JUDGMENT BY THE REGIONAL TRIAL moving party, including documents appended thereto, no Offices, instructed me to
COURT OF QUEZON CITY, BRANCH genuine issue as to a material fact exists, the burden to deliver to the office of Mr.
96, DESPITE THE CLEAR EXISTENCE produce a genuine issue shifts to the opposing party. If the Benjamin Bitanga a letter
OF DISPUTED GENUINE AND opposing party fails, the moving party is entitled to a summary dated 3 January 2001,
MATERIAL FACTS OF THE CASE judgment.[27] pertaining to Construction
THAT SHOULD HAVE REQUIRED A Industry Arbitration
TRIAL ON THE MERITS. In a summary judgment, the crucial question is: are Commission (hereafter, CIAC)
the issues raised by the opposing party not genuine so as to Case No. 99-56, entitled
II justify a summary judgment?[28] Pyramid Construction
Engineering Corporation
THE COURT OF APPEALS GRAVELY First off, we rule that the issue regarding the vs. Macrogen Realty
ERRED IN NOT UPHOLDING THE propriety of the service of a copy of the demand letter on the Corporation.
RIGHT OF PETITIONER BENJAMIN M. petitioner in his office is a sham issue. It is not a bar to the
BITANGA AS A MERE GUARANTOR issuance of a summary judgment in respondents favor. 3. As instructed, I
TO THE BENEFIT OF EXCUSSION immediately proceeded to the
UNDER ARTICLES 2058, 2059, 2060, A genuine issue is an issue of fact which requires office of Mr. Bitanga located at
2061, AND 2062 OF THE CIVIL CODE the presentation of evidence as distinguished from an issue the
OF THE PHILIPPINES.[25] which is a sham, fictitious, contrived or false claim. To 12th Floor, Planters Developm
forestall summary judgment, it is essential for the non-moving ent Bank Building, 314
party to confirm the existence of genuine issues, as to which Senator
As in the two courts below, it is petitioners position he has substantial, plausible and fairly arguable Gil Puyat Avenue, Makati Ci
that summary judgment is improper in Civil Case No. Q-01- defense, i.e.,[29] issues of fact calling for the presentation of ty. I delivered the said letter to
45041 because there are genuine issues of fact which have evidence upon which reasonable findings of fact could return Ms. Dette Ramos, a person of
to be threshed out during trial, to wit: a verdict for the non-moving party, although a mere scintilla of sufficient age and discretion,
evidence in support of the party opposing summary judgment who introduced herself as one
(A) Whether or not there was proper will be insufficient to preclude entry thereof. of the employees of
service of notice to petitioner considering Mr. Bitanga and/or of the
the said letter of demand was allegedly Significantly, petitioner does not deny the receipt of latters
received by the demand letter from the respondent. He merely raises a companies.[31] (Emphasis
one Dette Ramos at Macrogen office howl on the impropriety of service thereof, stating that the supplied.)
and not by him at his residence. address to which the said letter was sent was not his
residence but the office of Macrogen Realty, thus it cannot be
(B) Whether or not petitioner is entitled to considered as the correct manner of conveying a letter of We emphasize that when petitioner signed the
the benefit of excussion?[26] demand upon him in his personal capacity.[30] Contract of Guaranty and assumed obligation as guarantor,
his address in the said contract was the same address where
Section 6, Rule 13 of the Rules of Court states: the demand letter was served.[32] He does not deny that the
We are not persuaded by petitioners arguments. said place of service, which is the office of Macrogen, was
SEC. 6. Personal service. Service of the also the address that he used when he signed as guarantor in
Rule 35 of the Revised Rules of Civil Procedure papers may be made by delivering the Contract of Guaranty. Nor does he deny that this is his
provides: personally a copy to the party or his office address; instead, he merely insists that the person who
counsel, or by leaving it in his office received the letter and signed the receiving copy is not an
Section 1. Summary with his clerk or with a person having employee of his company. Petitioner could have easily
judgment for claimant. A party seeking to charge thereof. If no person is found in substantiated his allegation by a submission of an affidavit of
recover upon a claim, counterclaim, or his office, or his office is not known, or he the personnel manager of his office that no such person is
cross-claim or to obtain a declaratory has no office, then by leaving the copy, indeed employed by petitioner in his office, but that evidence

3
Credtrans Effects of Guaranty

was not submitted.[33] All things are presumed to have been latter. However, the guarantor cannot be compelled to pay the by Sheriff Joseph F. Bisnar, who affirmed
done correctly and with due formality until the contrary is creditor unless the latter has exhausted all the property of the that, after exerting diligent efforts, he was
proved. This juris tantum presumption stands even against debtor and resorted to all the legal remedies against the not able to locate any property belonging
the most well-reasoned allegation pointing to some possible debtor. This is what is otherwise known as the benefit to the Macrogen Realty, except for a
irregularity or anomaly.[34] It is petitioners burden to overcome of excussion.[37] bank deposit with the Planters Bank
the presumption by sufficient evidence, and so far we have at Buendia, in the amount
not seen anything in the record to support petitioners charges Article 2060 of the Civil Code reads: of P20,242.23. It is axiomatic that the
of anomaly beyond his bare allegation. Petitioner cannot now liability of the guarantor arises when the
be heard to complain that there was an irregular service of the Art. 2060. In order that the guarantor may insolvency or inability of the debtor to pay
demand letter, as it does not escape our attention that make use of the benefit of excussion, he the amount of debt is proven by the
petitioner himself indicated 314 Sen. must set it up against the creditor upon return of the writ of execution that had not
Gil Puyat Avenue, Makati City as his office address in the the latters demand for payment from him, been unsatisfied.[40]
Contract of Guaranty. and point out to the creditor available
property of the debtor within Philippine
Moreover, under Section 6, Rule 13 of the Rules of territory, sufficient to cover the amount of IN ALL, we fail to point out any impropriety in the
Court, there is sufficiency of service when the papers, the debt.[38] rendition of a summary judgment in favor of the respondent.
or in this case, when the demand letter is personally delivered WHEREFORE, premises considered, the instant
to the party or his counsel, or by leaving it in his office with The afore-quoted provision imposes a condition for petition is DENIED for lack of merit. The Decision of the Court
his clerk or with a person having charge thereof, such as the invocation of the defense of excussion. Article 2060 of the of Appeals dated 11 April 2006 and its Resolution dated 5
what was done in this case. Civil Code clearly requires that in order for the guarantor to July 2006 are AFFIRMED. Costs against petitioner.
make use of the benefit of excussion, he must set it up against
We have consistently expostulated that in summary the creditor upon the latters demand for payment and point SO ORDERED.
judgments, the trial court can determine a genuine issue on out to the creditor available property of the debtor within the
the basis of the pleadings, admissions, documents, affidavits Philippines sufficient to cover the amount of the debt.[39]
or counter affidavits submitted by the parties. When the facts
as pleaded appear uncontested or undisputed, then there is It must be stressed that despite having been served a demand
no real or genuine issue or question as to any fact, and letter at his office, petitioner still failed to point out to the
summary judgment is called for.[35] respondent properties of Macrogen Realty sufficient to cover
its debt as required under Article 2060 of the Civil Code. Such
The Court of Appeals was correct in holding that: failure on petitioners part forecloses his right to set up the
defense of excussion.
Here, the issue of non-receipt of the letter Worthy of note as well is the Sheriffs return stating that the
of demand is a sham or pretended issue, only property of Macrogen Realty which he found was its
not a genuine and substantial deposit of P20,242.23 with the Planters Bank.
issue. Indeed, against the positive
assertion of Mr. Roberto O. Pagdilao (the Article 2059(5) of the Civil Code thus finds application and
private courier) in his affidavit that he precludes petitioner from interposing the defense
delivered the subject letter to a certain of excussion. We quote:
Ms. Dette Ramos who introduced herself
as one of the employees of [herein Art. 2059. This excussion shall not take place:
petitioner] Mr. Benjamin Bitanga and/or xxxx
of the latters companies, said [petitioner]
merely offered a bare denial. But bare (5) If it may be presumed that an
denials, unsubstantiated by facts, which execution on the property of the principal
would be admissible in evidence at a debtor would not result in the satisfaction
hearing, are not sufficient to raise a of the obligation.
genuine issue of fact sufficient to defeat
a motion for summary judgment.[36]
As the Court of Appeals correctly ruled:

We further affirm the findings of both the RTC and We find untenable the claim that the
the Court of Appeals that, given the settled facts of this case, [herein petitioner]
petitioner cannot avail himself of the benefit of excussion. Benjamin Bitanga cannot be compelled
to pay Pyramid because
Under a contract of guarantee, the guarantor binds himself to the Macrogen Realty has allegedly
the creditor to fulfill the obligation of the principal debtor in sufficient assets. Reason:The said
case the latter should fail to do so. The guarantor who pays [petitioner] had not
for a debtor, in turn, must be indemnified by the genuinely controverted the return made

4
Credtrans Effects of Guaranty

[G.R. No. 151060. August 31, 2005] 1983, JN, through Rodrigo Sta. Ana, proposed to settle the court explained that while the provision states that the
obligation by way of development and sale of the mortgaged guarantor cannot be compelled to pay unless the properties
property.[11]PhilGuarantee, however, rejected the proposal. of the debtor are exhausted, the guarantor is not precluded
from waiving the benefit of excussion and paying the
PhilGuarantee thus filed a Complaint[12] for collection of obligation altogether.[25]
JN DEVELOPMENT CORPORATION, and SPS. RODRIGO money and damages against herein petitioners.
and LEONOR STA. ANA, petitioners, Finally, the CA found that Narciso Cruz was unable to
vs. PHILIPPINE EXPORT AND FOREIGN LOAN In its Decision dated 20 August 1998, the RTC prove the alleged forgery of his signature in the Undertaking,
GUARANTEE CORPORATION, respondent. dismissed PhilGuarantees Complaint as well as the the evidence presented not being sufficient to overcome the
counterclaim of petitioners. It ruled that petitioners are not presumption of regularity of the Undertaking which is a
liable to reimburse PhilGuarantee what it had paid to TRB. notarized document. [26]
Crucial to this holding was the courts finding that TRB was
able to foreclose the real estate mortgage executed by JN, Petitioners sought reconsideration of the Decision and
[G.R. No. 151311. August 31, 2005] thus extinguishing petitioners obligation.[13] Moreover, there prayed for the admission of documents evidencing the
was no showing that after the said foreclosure, TRB had foreclosure of the real estate mortgage, but the motion for
demanded from JN any deficiency or the payment of the reconsideration was denied by the CA for lack of merit. The
difference between the proceeds of the foreclosure sale and CA ruled that the documentary evidence presented by
the actual loan.[14] In addition, the RTC held that since petitioners cannot be considered as newly discovered
NARCISO V. CRUZ, petitioner, vs. PHILIPPINE EXPORT PhilGuarantees guarantee was good for only one year from evidence, it being already in existence while the case was
and FOREIGN LOAN GUARANTEE 17 December 1979, or until 17 December 1980, and since it pending before the trial court, the very forum before which it
CORPORATION, respondent. was not renewed after the expiry of said period, should have been presented. Besides, a foreclosure sale per
PhilGuarantee had no more legal duty to pay TRB on 10 se is not proof of petitioners payment of the loan to
March 1981.[15] The RTC likewise ruled that Cruz cannot be PhilGuarantee, the CA added.[27]
DECISION held liable under the Undertaking since he was not the one
who signed the document, in line with its finding that his So now before the Court are the separate petitions for
TINGA, J.: review of the CA Decision. JN and the spouses Sta. Ana,
signature found in the records is totally different from the
signature on the Undertaking.[16] petitioners in G.R. No. 151060, posit that the CA erred in
Before us are consolidated petitions questioning interpreting Articles 2079, 2058, and 2059 of the Civil Code in
the Decision[1] of the Court of Appeals (CA) in CA-G.R. CV According to the RTC, the failure of TRB to sue JN for its Decision.[28] Meanwhile, petitioner Narciso Cruz in G.R.
No. 61318, entitled Philippine Export and Foreign Loan the recovery of the loan precludes PhilGuarantee from No. 151311 claims that the CA erred when it held that
Guarantee Corporation v. JN Development Corporation, et seeking recoupment from the spouses Sta. Ana and Cruz petitioners are liable to PhilGuarantee despite its payment
al., which reversed the Decision of the Regional Trial Court what it paid to TRB. Thus, PhilGuarantees payment to TRB after the expiration of its contract of guarantee and the lack of
(RTC) of Makati, Branch 60. amounts to a waiver of its right under Art. 2058 of the Civil PhilGuarantees consent to the extensions granted by TRB to
Code.[17] JN. Moreover, Cruz questions the reversal of the ruling of the
On 13 December 1979, petitioner JN Development trial court anent his liability as a signatory to the
Corporation (JN) and Traders Royal Bank (TRB) entered into Aggrieved by the RTC Decision, PhilGuarantee Undertaking.[29]
an agreement whereby TRB would extend to JN an Export appealed to the CA. The appellate court reversed the RTC
Packing Credit Line for Two Million Pesos (P2,000,000.00). and ordered petitioners to pay PhilGuarantee Nine Hundred On the other hand, PhilGuarantee maintains that the
The loan was covered by several securities, including a real Thirty Four Thousand Six Hundred Twenty Four Pesos and date of default, not the actual date of payment, determines the
estate mortgage[2] and a letter of guarantee from respondent Thirty Four Centavos (P934,624.34), plus service charge and liability of the guarantor and that having paid TRB when the
Philippine Export and Foreign Loan Guarantee Corporation interest.[18] loan became due, it should be indemnified by petitioners.[30] It
(PhilGuarantee), now Trade and Investment Development argues that, contrary to petitioners claim, there could be no
In reaching its denouement, the CA held that the RTCs waiver of its right to excussion more explicit than its act of
Corporation of the Philippines, covering seventy percent
finding that the loan was extinguished by virtue of the payment to TRB very directly.[31] Besides, the right to
(70%) of the credit line.[3] With PhilGuarantee issuing a
foreclosure sale of the mortgaged property had no factual excussion is for the benefit of the guarantor and is not a
guarantee in favor of TRB,[4] JN, petitioner spouses Rodrigo
support,[19] and that such finding is negated by Rodrigo Sta. defense for the debtor to raise and use to evade
and Leonor Sta. Ana[5] and petitioner Narciso Cruz[6]executed
Anas testimony that JN did not receive any notice of liability.[32]Finally, PhilGuarantee maintains that there is no
a Deed of Undertaking[7] (Undertaking) to assure repayment
foreclosure from PhilGuarantee or from TRB. [20] Moreover, sufficient evidence proving the alleged forgery of Cruzs
to PhilGuarantee.
Sta. Ana even offered the same mortgaged property to signature on the Undertaking, which is a notarized document
It appears that JN failed to pay the loan to TRB upon its PhilGuarantee to settle its obligations with the latter.[21] and as such must be accorded the presumption of
maturity; thus, on 8 October 1980 TRB requested regularity.[33]
The CA also ruled that JNs obligation had become due
PhilGuarantee to make good its guarantee.[8] PhilGuarantee
and demandable within the one-year period of effectivity of the The Court finds for PhilGuarantee.
informed JN about the call made by TRB, and inquired about
guarantee; thus, PhilGuarantees payment to TRB conformed
the action of JN to settle the loan.[9] Having received no
with its guarantee, although the payment itself was effected Under a contract of guarantee, the guarantor binds
response from JN, on 10 March 1981 PhilGuarantee paid
one year after the maturity date of the loan.[22] Contrary to the himself to the creditor to fulfill the obligation of the principal
TRB Nine Hundred Thirty Four Thousand Eight Hundred
trial courts finding, the CA ruled that the contract of guarantee debtor in case the latter should fail to do so.[34] The guarantor
Twenty Four Pesos and Thirty Four Centavos
was not extinguished by the alleged lack of evidence on who pays for a debtor, in turn, must be indemnified by the
(P934,824.34).[10] Subsequently, PhilGuarantee made
PhilGuarantees consent to the extensions granted by TRB to latter.[35] However, the guarantor cannot be compelled to pay
several demands on JN, but the latter failed to pay. On 30 May
JN.[23] Interpreting Art. 2058 of the Civil Code,[24] the appellate the creditor unless the latter has exhausted all the property of
5
Credtrans Effects of Guaranty

the debtor and resorted to all the legal remedies against the under Art. 2079 is for the benefit of the guarantor. As such, it against TRB, as per the pari-passu provision[46] in the contract
debtor.[36] This is what is otherwise known as the benefit of is likewise waivable by the guarantor. Thus, even assuming of guarantee.[47] We disagree.
excussion. that extensions were indeed granted by TRB to JN,
PhilGuarantee could have opted to waive the need for The foreclosure was made on 27 August 1993, after the
It is clear that excussion may only be invoked after legal consent to such extensions. Indeed, a guarantor is not case was submitted for decision in 1992 and before the
remedies against the principal debtor have been expanded. precluded from waiving his right to be notified of or to give his issuance of the decision of the court a quo in 1998. [48] Thus,
Thus, it was held that the creditor must first obtain a judgment consent to extensions obtained by the debtor. Such waiver is foreclosure was resorted to by TRB against JN when they
against the principal debtor before assuming to run after the not contrary to public policy as it is purely personal and does both had become aware that PhilGuarantee had already paid
alleged guarantor, for obviously the exhaustion of the not affect public interest.[41] In the instant case, TRB and that there was a pending case filed by PhilGuarantee
principals property cannot even begin to take place before PhilGuarantees waiver can be inferred from its actual against petitioners. This matter was not raised and proved in
judgment has been obtained.[37] The law imposes conditions payment to TRB after the latters demand, despite JNs failure the trial court, nor in the appeal before the CA, but raised for
precedent for the invocation of the defense. Thus, in order that to pay the renewal/guarantee fee as indicated in the the first time in petitioners motion for reconsideration in the
the guarantor may make use of the benefit of excussion, he guarantee.[42] CA. In their appellants Brief, petitioners claimed that there
must set it up against the creditor upon the latters demand for was no need for the defendant-appellee JNDC to present any
payment and point out to the creditor available property of the For the above reasons, there is no basis for petitioners evidence before the lower court to show that indeed
debtor within the Philippines sufficient to cover the amount of claim that PhilGuarantee was a mere volunteer payor and had foreclosure of the REM took place.[49] As properly held by the
the debt.[38] no legal obligation to pay TRB. The law does not prohibit the CA,
payment by a guarantor on his own volition, heedless of the
While a guarantor enjoys the benefit of excussion, benefit of excussion. In fact, it recognizes the right of a
nothing prevents him from paying the obligation once demand Firstly, the documents evidencing foreclosure of mortgage
guarantor to recover what it has paid, even if payment was
is made on him. Excussion, after all, is a right granted to him cannot be considered as newly discovered evidence. The said
made before the debt becomes due,[43] or if made without
by law and as such he may opt to make use of it or waive it. documents were already subsisting and should have been
notice to the debtor,[44] subject of course to some conditions.
PhilGuarantees waiver of the right of excussion cannot presented during the trial of the case. The alleged foreclosure
prevent it from demanding reimbursement from petitioners. Petitioners invocation of our ruling in Willex Plastic sale was made on August 23, 1993 while the decision was
The law clearly requires the debtor to indemnify the guarantor Industries, Corp. v. Court of Appeals[45] is misplaced, if not rendered by the trial court on August 20, 1998 about five (5)
what the latter has paid.[39] irrelevant. In the said case, the guarantor claimed that it could years thereafter. These documents were likewise not
not be proceeded against without first exhausting all of the submitted by the defendants-appellees when they submitted
Petitioners claim that PhilGuarantee had no more properties of the debtor. The Court, finding that there was an their appellees Brief to this Court. Thus, these cannot be
obligation to pay TRB because of the alleged expiration of the express renunciation of the benefit of excussion in the considered as newly discovered evidence but are more
contract of guarantee is untenable. The guarantee, dated17 contract of guarantee, ruled against the guarantor. correctly ascribed as suppressed forgotten evidence
December 1979, states: Secondly, the alleged foreclosure sale is not proof of payment
The cited case finds no application in the case a quo. of the loan by defendant-appellees to the plaintiffs-
PhilGuarantee is not invoking the benefit of excussion. It appellants.[50]
In the event of default by JNDC and as a consequence
cannot be overemphasized that excussion is a right granted
thereof, PHILGUARANTEE is made to pay its obligation
to the guarantor and, therefore, only he may invoke it at his
arising under the aforesaid guarantee PHILGUARANTEE Besides, the complaint a quo was filed by
discretion.
shall pay the BANK the amount of P1.4 million or 70% of the PhilGuarantee as guarantor for JN, and its cause of action
total obligation unpaid The benefit of excussion, as well as the requirement of was premised on its payment of JNs obligation after the latters
consent to extensions of payment, is a protective device default. PhilGuarantee was well within its rights to demand
pertaining to and conferred on the guarantor. These may be reimbursement for such payment made, regardless of
.... whether the creditor, TRB, was subsequently able to obtain
invoked by the guarantor against the creditor as defenses to
bar the unwarranted enforcement of the guarantee. However, payment from JN. If double payment was indeed made, then
This guarantee shall be valid for a period of one (1) year from PhilGuarantee did not avail of these defenses when it paid its it is JN which should go after TRB, and not PhilGuarantee.
date hereof but may be renewed upon payment by JNDC of obligation according to the tenor of the guarantee once Petitioners have no one to blame but themselves, having
the guarantee fee at the same rate of 1.5% per annum.[40] demand was made on it. What is peculiar in the instant case allowed the foreclosure of the property for the full value of the
is that petitioners, the principal debtors themselves, are loan despite knowledge of PhilGuarantees payment to TRB.
muddling the issues and raising the same defenses against Having been aware of such payment, they should have
The guarantee was only up to 17 December 1980. JNs opposed the foreclosure, or at the very least, filed a
obligation with TRB fell due on 30 June 1980, and demand on the guarantor, which only the guarantor may invoke against
the creditor, to avoid payment of their own obligation to the supplemental pleading with the trial court informing the same
PhilGuarantee was made by TRB on 08 October 1980. That of the foreclosure sale.
payment was actually made only on 10 March 1981 does not guarantor. The Court cannot countenance their self-seeking
take it out of the terms of the guarantee. What is controlling is desire to be exonerated from the duty to reimburse
Likewise, petitioners cannot invoke the pari-
that default and demand on PhilGuarantee had taken place PhilGuarantee after it had paid TRB on their behalf and to
passu clause in the guarantee, not being parties to the said
while the guarantee was still in force. unjustly enrich themselves at the expense of PhilGuarantee.
agreement. The clause is clearly for the benefit of the
Petitioners assert that TRBs alleged foreclosure of the guarantor and no other.
There is likewise no merit in petitioners claim that
PhilGuarantees failure to give its express consent to the real estate mortgage over the land executed as security for
The Court notes the letter[51] of Rodrigo Sta. Ana
alleged extensions granted by TRB to JN had extinguished the loan agreement had extinguished PhilGuarantees
offering, by way of settlement of JNs obligations to
the guarantee. The requirement that the guarantor should obligation; thus, PhilGuarantees recourse should be directed
PhilGuarantee, the very same parcel of land mortgaged as
consent to any extension granted by the creditor to the debtor security for the loan agreement. This further weakens the

6
Credtrans Effects of Guaranty

position of petitioners, since it becomes obvious that they


acknowledged the payment made by PhilGuarantee on their
behalf and that they were in fact willing to negotiate with
PhilGuarantee for the settlement of the said obligation before
the filing of the complaint a quo.

Anent the issue of forgery, the CA is correct in reversing


the decision of the trial court. Save for the denial of Narciso
Cruz that it was not his signature in the Undertaking and the
perfunctory comparison of the signatures, nothing in the
records would support the claim of forgery. Forgery cannot be
presumed and must be proved by clear, positive and
convincing evidence and the burden of proof lies on the party
alleging forgery.[52] Mere denial will not suffice to overcome
the positive value of the Undertaking, which is a notarized
document, has in its favor the presumption of regularity, and
carries the evidentiary weight conferred upon it with respect
to its due execution.[53] Even in cases where the alleged
forged signature was compared to samples of genuine
signatures to show its variance therefrom, this Court still found
such evidence insufficient.[54] Mere variance of the signatures
cannot be considered as conclusive proof that the same were
forged.[55]

WHEREFORE, the consolidated petitions are DENIED.


The Decision of the Court of Appeals in CA-G.R. CV No.
61318 is AFFIRMED.

No pronouncement as to costs.

SO ORDERED.

7
Credtrans Effects of Guaranty

8
Credtrans Effects of Guaranty

G.R. No. L-48979 September 29, 1943 Compañia de Seguros refused to pay the balance, contending Thus there was an issue of fact between the two surety
that so long as the liability of the Tobacconists did not exceed companies, viz.: whether the understanding between the
P3,000, it was not bound to pay anything because its bond plaintiff and the three defendants was, that the bond of P2,000
MIRA HERMANOS, INC., plaintiff-appellee,
referred only to the obligation of the Tobacconists in excess given by the Manila Compañia de Seguros was limited to and
vs.
of P3,000 and up to P5,000. Hence Mira Hermanos, Inc., responded for the obligation of the Tobacconists only insofar
MANILA TOBACCONISTS, INC., ET AL., defendants.
brought this action against the Manila Tobacconists, Inc., as it might exceed the amount of P3,000 secured by the bond
PROVIDENT INSURANCE CO., defendant-appellant.
Provident Insurance Co., and Manila Compañia de Seguros of the Provident Insurance Co. That issue of fact was decided
to recover from them jointly and severally the sum of P909.12 by the trial court in favor of the contention of the Manila
E. V. Filamor for appellant. with legal interest thereon from the date of the complaint. Compañia de Seguros; and judgment was rendered by it
Ramirez and Ortigas for appellee. against the Provident Insurance Co. alone for the amount
Ernesto Zaragoza for defendant, Manila Compañia de claimed by the plaintiff.
The controversy is mainly between the two surety companies.
Seguras.
In its answer the defendant Manila Compañia de Seguros
alleged as a special defense: Appellant's first two assignments of error (the third being a
OZAETA, J.: mere consequence of the first two) read as follows:
4. — Que la fianza otorgada por esta demandada
This appeal has been certified to this court by the Court of 'Manila Compania de Seguros', el Octubre de 1940 1. El juzgado inferior incurrio en error al hacer caso
Appeals because it involves only a question of law arising fue exigida por la demandante solo cuando el omiso del beneficio de division reclamado por la
from the following facts: importe de las mercancias servidas por esta y demandada Provident Insurance Co. of the
pedidas por la demandada Manila Tobacconists, Philippines con arreglo a lo dispuesto en el Art.
Inc., excedio de la suma de P3,000 garantizada por 1837 del Codigo Civil.
By virtue of a written contract (Exhibit A) entered into between la otra demandada Provident Insurance Co.; por lo
Mira Hermanos, Inc., and Manila Tobacconists, Inc., the que quedo entendido entre la demandante y las
former agreed to deliver to the latter merchandise for sale on 2. El juzgado erro al aplicar, en lugar de lo
tres demandadas que la fianza de P2,000 prestada
consignment under certain specified terms and the latter dispuesto en el Art. 1837 del Codigo Civil, una
el Octubre de 1940 por esta demandada, 'Manila
agreed to pay to the former on or before the 20th day of each teoria suya, declarando que la fianza de P3,000.00
Compañia de Seguros', se limitaba y era para
month the invoice value of all the merchandise sold during the prestada por Provident Insurance Co. of the
responder solamente del importe de mercancias
preceding month. Mira Hermanos, Inc., required of the Manila Philippines y la fianza de P2,000 de Manila
servidad a la demandada Manila Tobacconists,
Tobacconists, Inc., a bond of P3,000, which was executed by Compañia de Seguros, cada una tiene una esfera
Inc., en tanto en cuanto el valor de esas mercancias
the Provident Insurance Co., on September 2, 1939 (Exhibit de responsabilidad propia e independiente la una
excediese de P3,000 asegurada por la fianza
B), to secure the fulfillment of the obligation of the de la otra.
P3,000 de la Manila Tobacconists, Inc.
Tobacconists under the contract (Exhibit A) up to the sum of
P3,000.
Discussing these two assignments of error jointly, counsel
To that the defendant Provident Insurance Co. replied:
says:
In the month of October, 1940, the volume of the business of
the Tobacconists having increased so that the merchandise Que no es verdad el hecho alegado por la
La unica cuestion que se presenta en esta causa
received by it on consignment from Mira Hermanos exceeded demandada 'Manila Compañia de Seguros' en el
es puramente de derecho. Si el saldo deudor de
P3,000 in value, Mira Hermanos required of the Tobacconist parrafo 4 de su contestacion que dice: 'que quedo
P2,272.79 que Tobacconists ha dejado de pagar,
an additional bond of P2,000, and in compliance with that entendido entre la demandante y las tres
deben pagarlo en su lugar, los dos fiadores
requirement the defendant Manila Compañia de Seguros, on demandadas que la fianza de P2,000 prestada el
proporcionalmente a la cuantia en que se obligaron
October 16, 1940, executed a bond of P2,000 (Exhibit C) with Octubre de 1940 por esta demandada "Manila
o debe pagarlo sola y exclusivamente la fiadora
the same terms and conditions (except as to the amount) as Compañia de Seguros" se limitaba y era para
Provident Insurance Co., como ordena la sentencia
the bond of the Provident Insurance Co. responder solamente del importe de mercancias
opelada.
servidas a la demandada Manila Tocacconists,
Inc., en tanto en cuanto el valor de esas mercancias
On June 1, 1941, a final and complete liquidation was made excediese de P3,000 asegurada por la fianza de Thus it appears that the issue of fact raised by and between
of the transactions between Mira Hermanos and the P3,000 de la "Manila Tobacconists, Inc." the two surety companies before the trial court and decided
Tobacconists, as a result of which there was found a balance
by the latter in favor of the appellee Manila Compañia de
due from the latter to the former of P2,272.79, which
Seguros is no longer raised before this Court, appellant
indebtedness the Tobacconists recognized but was unable to Que la demandada, aqui compareciente, nunca ha
Provident Insurance Co. having limited the issue in this appeal
pay. Thereupon Mira Hermanos made a demand upon the tenido conocimiento ni menos prestado su
to whether or not it is entitled to the "benefit of division"
two surety companies for the payment of said sum. consentimiento a esa supuesta inteligencia.
provided in article 1837 of the Civil Code, which reads as
follows:
The Provident Insurance Co., paid only the sum of P1,363.67, Que esta demandada no puede ser privada del
which is 60% of the amount owned by the Tobacconists to beneficio de division a que tiene derecho como co-
Art. 1837. Should there be several sureties of only
Mira Hermanos, alleging that the remaining 40% should be fiador, sin que conste expresamente, por escrito, su
one debtor for the same debt, the liability therefor
paid by the other surety, Manila Compañia de Seguros, in conformidad y consentimiento de renunciar a su
shall be divided among them all. The creditor can
accordance with article 8137 of the Civil Code. The Manila derecho.
claim from each surety only his proportional part
9
Credtrans Effects of Guaranty

unless liability in solidum has been expressly of P2,000 was, more than a year later, required by the creditor
stipulated. of the principal debtor for the protection of said creditor and
certainly not for the benefit of the original surety, which was
not entitled to expect any such benefit.
The right to the benefit of division against the co-
sureties for their respective shares ceases in the
same cases and for the same reason as that to an The foregoing considerations, which fortify the trial court's
exhaustion of property against the principal debtor. conclusion as to the real intent and agreement of the parties
with regard to the bond of P2,000 given by the Manila
Compañia de Seguros, destroys at the same time the theory
With particular reference to the second assignment of error,
of the appellant regarding the applicability of article 1837 of
we find that the statement of the trial court to the effect that
the Civil Code.
the bond of P3,000 responded for the obligation of the
Tobacconists up to the sum of P3,000 and the bond of P2,000
responded for the obligation of the Tobacconists only insofar That article refers to several sureties of only one debtor for the
as it might exceed P3,000 and up to P5,000, is not a mere same debt. In the instant case, altho the two bonds on their
theory but a finding of fact based upon the undisputed face appear to guarantee the same debt co-extensively up to
testimony of the witnesses called by the defendant Manila P2,000 — that of the Provident Insurance Co. alone extending
Compañia de Seguros in support of its special defense beyond that sum up to P3,000 — it was pleaded and
hereinbefore quoted. While on its face the bond given by the conclusively proven that in reality said bonds, or the two
Manila Compañia de Seguros contains the same terms and sureties, do not guarantee the same debt because the
conditions (except as to the amount) as those of the bond Provident Insurance Co. guarantees only the first P3,000 and
given by the Provident Insurance Co., nevertheless it was the Manila Compañia de Seguros, only the excess over and
pleaded by the Manila Compañia de Seguros and found above said amount up to P5,000. Article 1837 does not apply
proven by the trial court "que la intencion realmente que se to this factual situation.
habia perseguido, por lo menos en lo que respecta a la Manila
Tobacconists, Inc., y la Manila Compañia de Seguros, era la
The judgment of the trial court is affirmed, with the only
de que esta fianza de P2,000 habria de responder solamente
modification that it shall be entered against the defendants
por todo aquello que excediera de los P3,000."
Manila Tobacconists, Inc., and Provident Insurance Co. jointly
and severally. Appellant shall pay the costs of this instance.
The evidence upon which that finding is based is not only
undisputed but perfectly reasonable and convincing. For, as
Yulo, C.J., Moran, Paras and Bocobo, JJ., concur.
the trial court observed, there would have been no need for
the additional bond of P2,000 if its purpose were to cover the
first P2,000 already covered by the P3,000 bond of the
Provident Insurance Co. Indeed, we might add, if the purpose
of the additional bond of P2,000 were to cover not the excess
over and above P3,000 but the first P2,000 of the obligation
of the principal debtor like the bond of P3,000 which covered
only the first P3,000 of said obligation, then it would result that
had the obligation of the Tobacconists exceeded P3,000,
neither of the two bonds would have responded for the
excess, and that was precisely the event against which Mira
Hermanos wanted to protect itself by demanding the
additional bond of P2,000. For instance, suppose that the
obligation of the principal debtor, the Tobacconists, amounted
to P5,000; if both bonds were co-extensive up to P2,000 — as
would logically follow if appellant's contention were correct —
the result would be that the first P2,000 of the obligation would
have to be divided between and paid equally by the two surety
companies, which should pay P1,000 each, and of the
balance of P3,000 the Provident Insurance Co. would have to
pay only P1,000 more because its liability is limited to the first
P3,000, thus leaving the plaintiff in the lurch as to the excess
of P2,000. That was manifestly not the intention of the parties.
As a matter of fact, when the Provident gave its bond and fixed
the premiums thereon it assumed an obligation of P3,000 in
solidum with the Tobacconists without any expectation of any
benefit of division with any other surety. The additional bond
10
Credtrans Effects of Guaranty

G.R. No. L-9353 May 21, 1957 defendants to deliver to the plaintiff such sufficient security as about to remove and dispose of his properties, because he
shall protect plaintiff from the any proceedings by the creditors has no property; that has been no liquidation of the expenses
on the Surety Bond aforementioned and from the danger of incurred in the construction of the Bacarra Bridge, Project PR-
MANILA SURETY AND FIDELITY, INC., plaintiff-appellant,
insolvency of the defendants; and to allow costs to the herein 72(3) to determine whether there would be a balance of the
vs.
plaintiff," and " for such other measures of relief as may be contract price which may be applied to pay the claim for
BATU CONSTRUCTION AND COMPANY, CARLOS N.
proper and just in the premises." Attached to the complaint unpaid wages of Ricardo Fernandez et al. sought to be
BAQUIRAN, GONZALO P. AMBOY and ANDRES
are a verification and affidavit of attachment; and copies of the collected in civil case No. 198 of the Justice of the Peace
TUNAC, defendants-appellees.PADILLA, J.:
surety bond marked Annex A; of the indemnity contract Court of Laoag, Ilocos Norte, and not until after such
marked Annex B; and of the letter of the Acting Director of liquidation shall have been made could his liability and that of
In a complaint filed in the Court of First Instance of Manila, the Public Works to the plaintiff dated 30 May 1951, marked his co-defendants be determined and fixed; that if after proper
plaintiff, a domestic corporation engaged in the bonding Annex C. liquidation's there be a deficit of the contract price the
business, hereafter called the company, alleges that the Batu defendants are willing to pay the claim for unpaid wages of
Construction & Company, a partnership the members of Ricardo Fernandez et al. Upon these allegations he prays that
Andres Tunac admits in his answer the allegations in
which are the other three defendants, requested it to post, as the issuance of the writ of attachment prayed for by the
paragraphs 1, 2, 3 and 4 of the complaint, but denies the
it did, a surety bond for P8,812 in favor of the Government of plaintiff be held in abeyance until after civil case No. 198 of
allegations in paragraphs 5, 6, 7, 8 and 9 of the complaint,
the Philippines to secure the faithful Performance of the the Justice of the Peace Court of Laoag, Ilocos Norte, shall
because he has never promised to put up an indemnity bond
construction of the Bacarra Bridge, Project PR-72 (3), in Ilocos have been disposed of.
in favor of the plaintiff nor has he ever entered into any
Norte, undertaken by the partnership, as stipulated in a
indemnity agreement with it; because the partnership or the
construction on contract entered into on 11 July 1950 by and
Batu Construction & Company was fulfilling its obligations in Carlos N. Baquiran admits in his answer the allegations in
between the partnership and the Government of the
accordance with the terms of the construction contract; paragraphs 1, 2, 3,4, 5, 6, and 11 of the complaint but alleges
Philippines, on condition that the defendants would "indemnify
because the Republic of the Philippines, through the Director that he has no sufficient knowledge to form a belief as to the
the COMPANY for any damage, loss, costs, or charges, or
of Public, Works, had no authority to annul the contract at its truth of the claim of Ricardo Fernandez et al. set forth in
expenses of whatever kind and nature, including counsel or
own initiative; because the Justice of the Peace court of paragraph 7 of the complaint, for there has never been a
attorney's fees, which the COMPANY may, at any time,
Laoag, Ilocos Norte had no jurisdiction to hear and decide a liquidation between the defendants and the Bureau of Public
sustain or incur, as a consequence of having become surety
case for collection of P5,960.10; and because the defendants Works. He further denies specifically paragraphs 8, 9 and 10
upon the above mentioned bond; said attorney's fees shall not
were not in imminent danger of insolvency, neither did they of the complaint. By way of special defenses he alleges that
be less than fifteen (15%) per cent of the total amount claimed
remove or dispose of their properties with intent to defraud there has been no liquidation by and between the defendants
in any action which the COMPANY may institute against the
their creditors. By way of affirmative defenses, he alleges that and the Bureau of Public Works on Project PR-72(3) to
undersigned (the defendants except Andres Tunac) in Court,"
the signing by Carlos N. Baquiran of the indemnity agreement determine whether the total amount spent for the construction
and that "Said indemnity shall be paid to the COMPANY as
for and in behalf of the partnership Batu Construction & of the bridge exceeded the contract price; that after the
soon as it has become liable for the payment of any amount,
Company did not bind the latter to the plaintiff and as the determination of the respective liabilities of the parties in civil
under the above-mentioned bond, whether or not it shall have
partnership is not bound, he (Andres Tunac), as a member case No. 198 of the Justice of the Peace Court of Laoag,
paid such sum or sums of money, or any part thereof," as
thereof, is also not bound; that he not being a party to the said Ilocos Norte, if any there be against the defendants herein,
stipulated in a contract executed on 8 July 1950 (Exhibit B);
agreement, the plaintiff has no cause of action against him; and such liability could not be paid out of the balance of the
that on 30 May 1951 because of the unsatisfactory progress
that in the event the partnership is bound by the indemnity contract price of Project PR-72(3), the defendants are ready
of the work on the bridge, the Director of Public Works, with
agreement he invokes his right of exhaustion of the property and willing to assume their respective responsibilities. Upon
the approval of the Secretary of Public Works and
of the partnership before the plaintiff may proceed against his these allegations he prays that the complaint of the plaintiff be
Communications, annulled, the construction contract referred
property. And as a counterclaim he alleges that the plaintiff dismissed; that the issuance of the writ of attachment prayed
to and notified the plaintiff Company that the Government
brought the action against him maliciously and in bad faith for for be denied; and that he be granted such other relief as may
would hold it (the Company) liable for any amount incurred by
the purpose of annoying him and damaging his professional be just and equitable, with costs against the plaintiff.
the Government for the completion of the bridge, in excess of
reputation, he having a flourishing and successful practice as
the contract price (Exhibit D); that on 19 December 1951
engineer in Ilocos Norte, thereby compelling him to defend
(should be 23 November 1951), Ricardo Fernandez and 105 At the hearing, the plaintiff presented its evidence. After the
himself; that to secure the issuance of a writ of attachment the
other persons brought an action in the Justice of the Peace plaintiff had rested its case, defendant Gonzalo P. Amboy
plaintiff made false representations; and that the issuance of
Court of Laoag, Ilocos Norte, against the partnership, the moved for the dismissal of the complaint, on the ground that
the writ upon such false representations of the plaintiff caused
individual partners and the herein plaintiff Company for the the remedy provided for in the last paragraph of article 2071
him damages in the sum of P10,000 including expenses of
collection of unpaid wages amounting to P5,960.10, lawful of the new Civil Code may be availed of by the guarantor only
litigation and attorney's fees. Upon the foregoing he prays that
interests thereon and costs (Exhibit E); that the defendants and not by a surety.
the complaint be dismissed as to him and the defendant Batu
are in imminent danger of becoming insolvent, and are
Construction & Company, with costs against the plaintiff; that
removing and disposing, or about to remove and dispose, of
the latter be ordered to pay him the sum of P10,000; and that Acting upon this motion to dismiss the trial court made the
their properties with intent to defraud their creditors,
he be granted such other remedies as may be just, equitable following findings:
particularly the plaintiff Company; and that the latter has no
and proper.
other sufficient security to protect its rights against the
defendants. Upon these allegations, the plaintiff prays that, . . . That on July 8, 1950, the defendant Batu
upon the approval of a bond and on the strength of the Gonzalo P. Amboy denies in his answer the allegations of the Construction & Company, as principal, and the
allegations of the verified complaint, a writ attachment be complaint, except those that may be deemed admitted in the plaintiff Manila Surety & Fidelity Co. Inc., as surety,
issued and levied upon the properties of the defendants; and special defenses, and alleges that he is not in imminent executed a surety bond for the sum of P8,812.00 to
that after hearing, judgment be rendered " ordering the danger of insolvency and is not removing and disposing or insure faithful performance of the former's

11
Credtrans Effects of Guaranty

obligation as contractor for the construction of the A guarantor is the insurer of the solvency of the debtor; a plaintiff, the Manila Surety and Fidelity Co., Inc., and
Bacarra Bridge, Project PR-72 (No. 3) Ilocos Norte surety is an insurer of the debt. A guarantor binds himself to paragraph 1 of article 2071 of the new Civil Code provides that
Province. On the same date, July 8,1950, the Batu pay if the principal is unable to pay; a surety undertakes to the guarantor, even before having paid, may proceed against
Construction & Company and the defendants pay if the principal does not pay.1 The reason which could be the principal debtor "to obtain release from the guaranty, or to
Carlos N. Baquiran and Gonzales P. Amboy invoked for the non-availability to a surety of the provisions of demand a security that shall protect him from any proceedings
executed an indemnity agreement to protect the the last paragraph of article 2071 of the new Civil Code would by the creditor or from the danger of insolvency of the debtor,
Manila Surety & Fidelity Co. Inc.., against damage, be the fact that guaranty like commodatum2 is gratuitous. But when he (the guarantor) is sued for payment. It does not
loss or expenses which it may sustain as a guaranty could also be for a price or consideration as provided provide that the guarantor be sued by the creditor for the
consequence of the surety bond executed by it for in article 2048. So, even if there should be a consideration payment of the debt. It simply provides that the guarantor of
jointly with Batu Construction & Company. or price paid to a guarantor for him to insure the performance surety be sued for the payment of an amount for which the
of an obligation by the principal debtor, the provisions of article surety bond was put up to secure the fulfillment of the
2071 would still be available to the guarantor. In suretyship obligation undertaken by the principal debtor. So, the suit filed
On or about May 30, 1951, the plaintiff received a
the surety becomes liable to the creditor without the benefit of by Ricardo Fernandez and 105 persons in the Justice of the
notice from the Director of Public Works (Exhibit B)
the principal debtor's exclusion of his properties, for he (the Peace Court of Laoag, province of Ilocos Norte, for the
annulling its contract with the Government for the
surety) maybe sued independently. So, he is an insurer of the collection of unpaid wages earned in connection with the work
construction of the Bacarra Bridge because of its
debt and as such he has assumed or undertaken a done by them in the construction of the Bacarra Bridge,
failure to make satisfactory progress in the
responsibility or obligation greater or more onerous than that Project PR-72(3), is a suit for the payment of an amount for
execution of the works, with the warning that ,any
of guarantor. Such being the case, the provisions of article which the surety bond was put up or posted to secure the
amount spent by the Government in the
2071, under guaranty, are applicable and available to a faithful performance of the obligation undertaken by the
continuation of the work, in excess of the contract
surety. The reference in article 2047 to, the provisions of principal debtors (the defendants) in favor of the creditor, the
price, will be charged against the surety bond
Section 4, Chapter 3, Title 1, Book IV of the new Civil Code, Government of the Philippines.
furnished by the plaintiff. It also appears that a
on solidary or several obligations, does not mean that
complaint by the laborers in said project of the Batu
suretyship which is a solidary obligation is withdrawn from the
Construction & Company was filed against it and The order appealed from dismissing the complaint is reversed
applicable provisions governing guaranty.
the Manila Surety and Fidelity Co., Inc., for unpaid and set aside, and the case remanded to the court below for
wages amounting to P5,960.10. determination of the amount of security that would protect the
The plaintiff's cause of action does not fall under paragraph 2 plaintiff Company from any proceedings by the creditor or
of article 2071 of the new Civil Code, because there is no from the danger of insolvency of the defendants, the principal
and, being of the opinion that the provisions of article 2071 of
proof of the defendants' insolvency. The fact that the contract debtors, and direction to the defendants to put up such
the new Civil Code may be availed of by a guarantor only and
was annulled because of lack of progress in the construction amount of security as may be established by competent
not by a surety the complaint, with costs against the plaintiff.
of the bridge is no proof of such insolvency. It does not fall evidence, without pronouncement as to costs.
under paragraph 3, because the defendants have not bound
From this order the plaintiff Company has appealed to this themselves to relieve the plaintiff from the guaranty within a
The writ of attachment having been issued improvidently
Court, because it proposes to raise only a question of law. specified period which already has expired, because the
because, although there is an allegation in the verified
surety bond does not fix any period of time and the indemnity
complaint that the defendants were in imminent danger of
agreement stipulates one year extendible or renewable until
After the order dismissing the complaint had been entered, on insolvency and that they were removing or disposing, or about
the bond be completely cancelled by the person or entity in
16 and 20 July 1953, the defendants Gonzalo P. Amboy and to remove or dispose, of their properties, with intent to defraud
whose behalf the bond was executed or by a Court of
Andres Tunac moved for leave to prove damages they their creditors, particularly the plaintiff Company, still such
competent jurisdiction. It does not come under paragraph 4,
allegedly suffered as a result of the attachment levied upon allegation was not proved, the fact that a complaint had been
because the debt has not become demandable by reason of
their properties. On 15 August 1953 the Court heard the filed against the defendants and the plaintiff Company in the
the expiration of the period for payment. It does not come
evidence on damages. On 23 September 1953 the Court Justice of the Peace Court of Laoag, Ilocos Norte, for the
under paragraph 5 because of the lapse of 10 years, when the
found and held that the defendant Gonzalo P. Amboy is collection of an amount for unpaid wages of the plaintiffs
principal obligation has no period for its maturity, etc., for 10
entitled to recover from the plaintiff damages equivalent to 6 therein who claimed to have worked in the construction of the
years have not yet elapsed. It does not fall under paragraph
per cent interest per annum on the sum of P35 in possession bridge, being insufficient to prove it, and because the relief
6, because there is no proof that "there are reasonable
of the Provincial Treasurer of Ilocos Norte, which was prayed for in the complaint for security that shall protect it from
grounds to fear that the principal debtor intends to abscond."
garnished pursuant to the writ of attachment, from the date of any proceedings by the creditor and from the danger of the
It does not come under paragraph 7, because the defendants,
garnishment until its charge; but the claims for damages of defendants becoming insolvent is inconsistent with the state
as principal debtors, are not in imminent danger of becoming
Andres Tunac and Gonzalo P. Amboy allegedly suffered by of insolvency of the defendants or their being in imminent
insolvent, there being no proof to that effect.
them in their business, moral damages and attorney's fees danger of insolvency, the order awarding 6 per cent on the
were without basis in law and in fact. Hence their recovery sum of P35 in possession of the Provincial Treasurer owned
was denied. The Court dissolved the writ of attachment. From But the plaintiff's cause of action comes under paragraph 1 of by the defendant Gonzalo P. Amboy garnished by virtue of the
this last order only the plaintiff Company has appealed. article 2071 of the new Civil Code, because the action brought writ of attachment, from the date of the garnishment until its
by Ricardo Fernandez and 105 persons in the Justice of the discharge, and denying recovery of the amounts of damages
Peace Court of Laoag, province of Ilocos Norte, for the claimed to have been suffered by the defendants, is affirmed,
The main question to determine is whether the last paragraph collection of unpaid wages amounting to P5,960.10, is in the defendants not having appealed therefrom.
of article 2071 of the new Civil Code taken from article 1843
connection with the construction of the Bacarra Bridge,
of the old Civil Code may be availed of by a surety. Project PR-72 (3), undertaken by the Batu Construction &
Bengzon, Montemayor, Reyes, A., Bautista Angelo, Labrador,
Company, and one of the defendants therein is the herein
Concepcion, Reyes, J.B.L., Endencia and Felix, JJ.,concur.
12
Credtrans Effects of Guaranty

G.R. No. L-22177 December 2, 1924 alleges that it had paid "Manila Compañia de Seguros" the principal debtor even before the surety pays the debt, but it
sum of P12,197.27, the amount of the judgment against it. The clearly appears in the complaint that this is not the action
dispositive part of the judgment appealed from is as brought by the plaintiff. Moreover this article 1843 provided
TUASON, TUASON, INC., plaintiff-appellee,
follows:itc-a1f several cumulative remedies in favor of the surety, at his
vs.
election, and the surety who brings an action under this article
ANTONIO MACHUCA, defendant-appellant.
must choose the remedy and apply for it specifically. At any
Judgment is rendered against the defendant
rate this article does not provide for the reimbursement of any
Antonio Machuca, and he is hereby ordered to pay
Marcaida, Capili & Ocampo for appellant. amount, as is sought by the plaintiff.lawphi1.net
the plaintiff company the sum of fifteen thousand
Antonio M. Opisso for appellee.
three hundred fifty-three pesos and nineteen
centavos (15,353.19), with compound interest But although the plaintiff has not as yet paid "Manila
thereon at the rate of ten per cent (10%) per annum, Compañia de Seguros" the amount of the judgment against it,
to be computed quarterly, that is, one thousand one and even considering that this action cannot be held to come
hundred eighty pesos and forty-six centavos under article 1843 of the Civil Code, yet the plaintiff is entitled
(1,180.46), which is ten per cent interest on the to the relief sought in view of the facts established by the
AVANCEÑA, J.:
amount of fifteen thousand three hundred fifty-three evidence. The plaintiff became bound, by virtue of a final
pesos and nineteen centavos (P15,353.19) from judgment, to pay the value of the note executed by it in favor
By giving a bond in the sum of P9,663 executed by "Manila October 8, 1922, to July 8, 1923, and ten per cent of "Manila Compañia de Seguros." According to the document
Compañia de Seguros," the Universal Trading Company was on the sum of sixteen thousand five hundred thirty- executed solidarily by the defendant and the Universal
allowed by the Insular Collector of Custom to withdraw from three pesos and sixty-five centavos (P16,533.65) Trading Company, the defendant bound himself to pay the
the customhouse sundry goods imported by it and consigned from July 8, 1923, until full payment, to be plaintiff as soon as the latter may have become bound and
through the bank of the Philippine Islands. Subsequently, the computed quarterly, besides the sum of one liable, whether or not it shall have actually paid. It is
Bank of the Philippine Islands claimed the value of the goods, thousand six hundred fifty-three pesos and sixty- indisputable that the plaintiff became bound and liable by a
and the Insular Collector of Customs obligated the "Manila five centavos (P1,653.65), which is ten per cent final judgment to pay the value of the note to "Manila
Compañia de Seguros" to pay the sum of P9,663, the amount (10%) on the amount due and the interest thereon, Compañia de Seguros."
of the bond. Before paying this amount to the Insular Collector which said defendant promised to pay as penalty
of Customs, the "Manila Compañia de Seguros" obtained and attorney's fees in the event of a suit being
The defendant also contends that the document executed by
from the Universal Trading Company and Tuason, Tuason & necessary to recover the debt, and the costs. So
Albina Tuason in favor of "Manila Compañia de Seguros"
Co., a solidary note for the sum of P9,663 executed by said ordered.
assuming and making hers the obligation of Tuason, Tuason
companies in its favor. Before signing said note, Tuason, & Co., was a novation of the contract by substitution of the
Tuason & Co., in turn, caused the Universal Trading Company It appears from the evidence that what the plaintiff alleged to debtor, and relieved Tuason, Tuason & Co. from all obligation
and its president Antonio Machuca, personally, to sign a be a payment made to "Manila Compañia de Seguros", for the in favor of "Manila Compañia de Seguros." As to this, it is
document (Exhibit B), wherein they bound themselves satisfaction of the judgment rendered in favor of the latter is enough to say that if this was what Albina Tuason
solidarily to pay, reimburse, and refund to the company all the execution by Albina Tuason of a document Exhibit D in contemplated in signing the document, evidently it was not
such sums or amounts of money as it, or its representative,
favor of "Manila Compañia de Seguros." In this document what "Manila Compañia de Seguros" accepted. As above
may pay or become bound to pay, upon its obligation with Albina Tuason declares that she assumes and makes hers stated, "Manila Compañia de Seguros" accepted this
"Manila Compañia de Seguros," whether or not it shall have the obligation to pay the amount of said judgment to "Manila document only as additional security for its credit and not as
actually paid such sum or sums or any part thereof. The
Compañia de Seguros" within one year and mortgages a a novation of the contract.
Universal Trading Company having been declared insolvent, property described in the document as security for this
"Manila Compañia de Seguros" brought an action in the lower obligation. This obligation of Albina Tuason was accepted by
court against Tuason, Tuason & Co. to recover the value of Our conclusion is that the plaintiff has the right to recover of
the "Manila Compañia de Seguros," in the following terms: "I
the note for P9,663 and obtained final judgment therein, which the defendant the sum of P9,663, the value of the note
accept the foregoing security executed by Miss Albina Tuason
was affirmed by this court on appeal, for the total sum of executed by the plaintiff in favor of "Manila Compañia de
in favor of `Manila Compañia de Seguros.'" It, thus, appears
P12,197.27, which includes the value of the note with interest Seguros" which the plaintiff is under obligation to pay by virtue
that the plaintiff has not in fact paid the amount of the
thereon. 1 Subsequently, all the rights of Tuason, Tuason & judgment to "Manila Compañia de Seguros." The action
of final judgment. We do not believe, however, that the
Co. were transferred to the plaintiff Tuason, Tuason, Inc. defendant must pay the plaintiff the expenses incurred by it in
brought by the plaintiff is that which surety, who pays the debt
the litigation between it and "Manila Compañia de Seguros."
of the debtor, is entitled to bring to recover the amount thus
That litigation was originated by the plaintiff having failed to
Later on Tuason, Tuason, Inc., brought this action to recover paid (art. 1823, Civil Code). It is evidence that such a payment
fulfill its obligation with "Manila Compañia de Seguros," and it
of Antonio Machuca the sum of P12,197.27 which it was not having been made the alleged cause of action does not
cannot charge the defendant with expenses which it was
sentenced to pay in the case filed against it by "Manila exist.
compelled to make by reason of its own fault. It is entitled,
Compañia de Seguros," plus P3,000 attorney's fees, and however, to the expenses incurred by it in this action brought
P155.92 court's costs and sheriff's fees, that is, a total of The plaintiff company argues that, at all events, it is entitled to against the defendant, which are fixed at P1,653.65 as
P15,353.19, together with P1,180.46 as interest upon the sum
bring this action under article 1843 of the Civil Code, which attorney's fees.
of P15,353.19 at the rate of 10 per cent per annum from provides that the surety may, even before making payment,
October 8, 1922, to July 8, 1923, and interest on the sum of bring action against the principal debtor. This contention of the
P16,535.65 at the rate of 10 per cent from July 8, 1923, until The judgment appealed from is modified, and the defendant
plaintiff is untenable. The present action, according to the
this sum was paid, and, in addition the sum of P1,653.65 for is sentenced to pay the plaintiff the sum of P9,663, with
terms of the complaint, is clearly based on the fact of payment.
attorney's fees in this case. For its cause of action, the plaintiff interest thereon at the rate of 10 per cent per annum from July
It is true that, under article 1843, an action lies against the
13
Credtrans Effects of Guaranty

19, 1923, when the complaint was filed until full payment
thereof, plus the sum of P1,653.65 for attorney's fees, without
special pronouncement as to costs. So ordered.

14
Credtrans Effects of Guaranty

G.R. No. L-5208 December 1, 1909 said executions were enjoined pending the determination practices between the surety and his principal would be
thereof. These are the admitted facts.lawphi1.net offered which might result to the injury and prejudice of the
creditor who holds the claim against them.
KUENZLE AND STREIFF, plaintiff-appellant,
vs. The plaintiff in this action contends that said four judgments
JOSE TAN SUNCO ET AL., defendants-appellees. ought to be set wholly aside on account of their having been The judgement of the court below is, therefore, affirmed, with
obtained, as he claims, by collusion and fraud, because the costs against the appellant. But the said Sunco shall not
debtor did not owe anything to Sunco at the time the four execute said judgments against the property of the judgment
Hartigan and Rohde, and Roman Lacson, for appellant.
judgments were secured, basing that contention on the fact, debtor until he has paid the debt for which he stands surety.
which is admitted, that Sunco and not yet paid the sums for So ordered.
Antonio Constantino, for appellees. which he had become surety and in connection with which he
obtained the judgments.
MORELAND, J.:
We think that the article 1843 of the Civil Code is applicable
to this case.lawphi1.net In their purposes articles 1838 and
This is an action to set aside four judgments rendered by a 1843 are quite distinct, although in perfect harmony, the latter
justice of the peace of the city of Manila upon the ground that making more clearly effective the purpose of the former.
they were procured by collision and fraud, to the injury and
Article 1838 provides for the enforcement of the right of the
damage of the plaintiff. surety against the debtor after he has paid the debt. Article
1843 provides for his protection before he has paid but after
The court below, after hearing the evidence offered upon the he has become liable to do so. The one gives a right of action
trial, found against the plaintiff and rendered a judgment in after payment, the other a protective remedy before payment.
favor of the defendant dismissing the plaintiff's complaint, with (Supreme court of Spain, March 22, 1901.) The one is a
costs. substantive right, the other of the nature of a preliminary
remedy. The one gives a right of action which, without the
provisions of the of the other, might be worthless. The remedy
The plaintiff did not make a motion for a new trial in the court given in article 1843 purposes to obtain for the surety "relief
below and this court can not, therefore, look into the evidence from the burden of his suretyship or a guaranty to defend him
but must confine itself to the facts stated in the opinion of the against any proceedings of the creditor and from the danger
court below for the purpose of ascertaining whether or not the of insolvency of the debtor." (Last paragraph of art. 1843.)
judgment of that court can be sustained. article 1838, speaking under this article become available, he
is past the point where a preliminary protective remedy is of
It appears from the opinion of the court below that Tan Sunco any value to him.lawphi1.net
was a surety for Chung Chu Sing for the payment by the latter
of the purchase price of certain merchandise purchased by It being evident that the purpose of article 1843 is to give to
said Chung Chu Sing of Ed. and A. Keller and Co., that the the surety a remedy in anticipation of the payment of the debt,
time within which said merchandise was to be paid for under which debt, being due, he could be called upon to pay at any
the terms of its purchase had expired long before said four time, it remains only to say, in this connection, that the only
judgments were obtained, and that the debt remained unpaid; procedure known under our present practice to enforce that
that the total debt was composed of four invoices of varying right is by action. (Manresa, Civil Code, vol. 12, p. 320.) The
amounts — P395.50, P450, P565, and P320.20; that an defendant Sunco availed himself of that right against the
action had been commenced against the said debtor, Chung debtor. The methods employed by him to realize his end were
Chu Sing, by the present plaintiff for the recovery of the unusual but not of themselves fraudulent. We agree with the
indebtedness due it; that shortly before judgment was secured trial court that the evidence adduced is entirely insufficient to
in that action the said Tan Sunco began four separate action establish such fraud and collusion as would justify a decision
against the said debtor upon the said invoices in the court of setting aside the judgment assailed. (Arts. 1291, 1297, Civil
the justice of the peace of the city of Manila; that soon Code; Pena vs. Mitchell, 9 Phil. Rep., 587; Jones vs. Brittan,
thereafter the said sunco and the said debtor appeared before 13 Fed. Cas., No. 7455; Oberly vs. Oberly, 190 Pa. st., 341;
the said court, and the said debtor then and there confessed Caldwell vs. Finfield, 24 n. J. L., 150.) The facts stated in the
judgment in favor of said Tan Sunco in each one of said opinion of the court below abundantly justify the conclusion.
actions, Tan Sunco thereby obtaining against the said debtor
four separate judgments; that immediately upon the recovery
of said judgments the plaintiff in those actions, Sunco caused But while the surety has the right to obtain as he did the
to be levied thereunder executions upon all of the property of judgments against the principal debtor, he ought not to be
said debtor, which property was not more than sufficient to allowed to realize the said judgments to the point of actual
pay to the judgments under which the levies were made; that collection of the same until he has satisfied or caused to be
thereupon the action at bar was begun and the sales under satisfied the obligation the payment of which he assures.
Otherwise, a great opportunity for collusion and improper

15

S-ar putea să vă placă și