Sunteți pe pagina 1din 4

Management, Procurement and Law Proceedings of the Institution of Civil Engineers

Management, Procurement and Law 165


Volume 165 Issue MP2
May 2012 Issue MP2
Pages 91–94 http://dx.doi.org/10.1680/mpal.10.00010
Paper 1000010
Construction arbitration in Sri Lanka Received 10/04/2010 Accepted 29/11/2010
Ranasinghe
Keywords: contracts & law/disputes & arbitration

ICE Publishing: All rights reserved

Construction arbitration
in Sri Lanka
Ananda Ranasinghe MEng, MTech, PGD, CEng, IPEng, AIStructE, FIE (SL), MICE
Attorney-at-Law, Battramulla, Sri Lanka

In the process of dispute resolution, arbitration has been practised by commercial personnel over a long period. With
the introduction of the Arbitration Act No. 11 of 1995, the process of arbitration has been refined and regularised in Sri
Lanka. As the grounds for appeal in the Sri Lanka Arbitration Act are very limited, arbitration has become a popular
way of resolving disputes. According to the Sri Lanka Arbitration Act, unless the parties agree otherwise, when an
arbitration clause is incorporated into the contract, the jurisdiction of the court is denied. The procedure followed in Sri
Lanka is a mostly ad hoc procedure. This is due to the fact that parties are reluctant to follow the institutionalised pro-
cedures as they are in some instances inconsistent with the Arbitration Act. There are three widely accepted procedures
adopted in Sri Lanka and they are namely – document only, the short procedure and full procedure. The full procedure
adopted in Sri Lanka is identical to the court procedure in Sri Lanka. It is important that arbitrators involved in arbitra-
tion must gain knowledge in construction law and technical knowledge in order to conduct arbitration successfully.

1. Introduction it becomes incumbent to briefly review the other methods that


Arbitration as a means of resolving disputes has been practised are available for resolving such disputes.
from the time man was old enough to argue. The first recorded
reference to a form of arbitration is in Plato’s ‘The Laws’ written Of these, litigation, which is conducted under the jurisdiction of
about 350 BC which stated that ‘in the first place there shall be the courts, can be placed in the category with arbitration which
elected judges in the courts who shall be chosen by the plaintiff is governed by a statute, usually the Arbitration Act. They are
and the defendant in common: these shall be called arbiters both well established and they produce results that are binding
rather than judges’. This was followed by the wide acceptance on the parties in dispute. Whereas there are clear rules of
of this procedure in Greece where the pressures on courts were procedure applicable to litigation, arbitration in Sri Lanka is
relieved by the appointment of private arbitrators for the equita- generally not subjected to any well accepted rules of procedure
ble settlement of disputes (Kanag-Iswaran and Wijeratne, 2007). such as International Chamber of Commerce (ICC) rules or the
United Nations Commission of International Trade Law
Other countries also began to accept arbitration as a means of (Uncitral) rules but are conducted in terms of ad hoc
dispute resolution and laws began to emerge which gave legal procedures agreed between the parties or imposed by the
recognition to the system and brought about a formalisation arbitral tribunal subject to the provisions relating to certain
of the procedures. procedures in the Sri Lankan Arbitration Act. Some parties
have agreements to arbitrate under ICC or Uncitral rules but
In Sri Lanka the first enactment was the Arbitration Ordinance situations may arise where these rules may stipulate certain
of 1886 which gave legal recognition to arbitration by agree- procedures to be followed which are not consistent with the
ment. This Ordinance and certain sections of the Civil Sri Lanka Arbitration Act.
Procedure Code dealing with arbitration have now been
repealed and replaced by the Sri Lankan Arbitration Act Mediation, conciliation and other forms of alternative dispute
(No. 11 of 1995) (Parliament of Sri Lanka, 1995) bringing all resolution which are independent of the processes in the first
arbitration in Sri Lanka within the purview of this Act. It is category and which are not adversarial and non-binding on
therefore in the context of this Act that it would be relevant the parties, fall into a second category. There are no laws
to examine the feasibility of adopting arbitration as a means governing these mechanisms for resolving a dispute. Various
of dispute resolution in the construction industry. institutions have laid down sets of rules of some of these
processes. For instance the Uncitral, ICC and a number of
2. Recognised forms of dispute resolution American arbitration associations have laid down rules for
When considering a particular system for the resolution of conciliation or mediation but they leave the procedural aspects
disputes in the construction industry, in this case arbitration, for their conduct in the hands of the conciliator or mediator.

91
Downloaded by [ UNIVERSITY OF TOKYO] on [10/02/17]. Copyright © ICE Publishing, all rights reserved.
Management, Procurement and Law Construction arbitration in Sri Lanka
Volume 165 Issue MP2 Ranasinghe

For instance, the ICC conciliation rules state: ‘the conciliator Reference is also made here to the more recent inclusion of
shall conduct the conciliation process as he thinks fit’. an adjudicator or a dispute adjudication board (DAB) in
the recent amendments to the Fédération Internationale des
The terms mediation and conciliation have no clear definitions Ingénieurs-Conseils (Fidic) forms of contract and the World
and different institutions use one term or the other to mean the Bank form, whose services must be sought to resolve any differ-
same process. The difference between the two processes is that ences that may arise. In contracts under these forms, a dispute is
in one case a neutral and independent person assists the two required to be referred to adjudication in the first instance, and
parties concerned to reach a mutually acceptable solution if the decision is not acceptable or the recommendation had not
whereas in the other case the person assisting plays a more become final and binding in terms of the procedure laid down in
active role and proceeds to make his own formal recommenda- the relevant contract, then the party who is not satisfied with the
tion for a settlement which may be either accepted or used as a decision of the adjudicator may refer the dispute to arbitration.
basis for the parties to further negotiate and reach a settlement. The special features of this process are that the adjudicator or
This latter process is well established in many countries and DAB is expected to be experienced in the construction work
institutions such as Uncitral, ICC and so on. related to the contract and in the interpretation of contracts,
and that they are appointed with the agreement of the parties
At this stage attention has to be drawn to a provision in the at the time of commencement of the work so that any differ-
Sri Lankan Arbitration Act (Parliament of Sri Lanka, 1995) ences are referred to them as they arise. Not all Fidic contracts
which permits an arbitral tribunal to encourage a settlement provide for the DAB to be in place from commencement of the
of the dispute using mediation or conciliation or other means contract – the Fidic Yellow Book (Fidic, 1999) provides for the
at any stage of the arbitral proceedings. Having understood DAB to be appointed when the dispute arises.
what these procedures are, it would seem unusual for an arbitra-
tor to assume the role of a conciliator or a mediator half way These developments indicate a clear trend, even when an agree-
through the arbitration and then to resume arbitration if ment to arbitrate exists, to initially attempt other more friendly
conciliation or mediation fails. There the wording seems to methods of resolving a dispute with the help of an independent
indicate that he may do so before the arbitration commences and neutral person or body, which is a desirable step in the right
and resumes arbitration proceedings if conciliation fails. In direction. It should be appreciated that the adoption of any of
Sri Lanka an adversarial procedure is used in arbitration similar the methods referred to under the second category; that is,
to litigation. Once an arbitrator commences an arbitration he other more friendly methods, does not always end in the dispute
does not involve himself directly in the process to the extent being resolved. In such a case it only amounts to a pre-arbitral
that he will not go on a voyage of discovery to seek documents, attempt to settle the dispute, which finally would have to be
evidence, etc. unlike in an inquisitorial system. The decision of resolved through arbitration or litigation.
the arbitrator is based on the information provided by the
parties. Therefore, when an arbitrator commences an arbitra- 3. Arbitration and litigation
tion it is the responsibility of the parties to lead evidence and Dispute resolution through arbitration is well entrenched in the
prove or disprove their assertions. Therefore, the arbitrator construction industry. In most construction contracts there is a
does not assume the role of mediator or conciliator not clause dealing with dispute resolution where the final recourse,
because the arbitrator lacks the skills needed by a mediator or if any other stipulated pre-arbitral alternate dispute resolution
conciliator, but the procedure prevents him from taking a mechanism fails, is to arbitrate. In a case where a party
different stand. However, there might be situations where the having had an agreement to submit all disputes to arbitration,
arbitrator lacks the skills and experience of a mediator or a wishes to litigate on a dispute, the Sri Lankan Arbitration Act
conciliator. of 1995 (Parliament of Sri Lanka, 1995) denies jurisdiction to
a court to hear and determine such a matter if the other party
The above-mentioned second category of dispute resolution objects. However, if, despite these provisions, for some reason
processes is usually adopted at a stage when there is a desire the parties agree to refer a dispute to court or if one party
on the part of the parties in dispute, with the assistance of a having taken up a matter in court the other party does not
neutral party, to reach an objective solution to the problem object, then the parties will proceed to resolve the dispute
without the entire process becoming adversarial in nature. through litigation. In this context attention is here drawn to
Unlike the first category, these forms of dispute resolution do some of the characteristics of litigation and arbitration in
not derive any authority from any statute and an agreement relation to construction disputes, which are likely to influence
between the parties is necessary to conclude a settlement. Never- ones decision to litigate if given the opportunity.
theless it has been found that resolving a dispute under this
second category is operating successfully outside the jurisdiction In litigation the tribunal ( judges), in the selection of whom the
of the courts and its usage is expanding. parties have no choice, are learned in the law and conduct the

92
Downloaded by [ UNIVERSITY OF TOKYO] on [10/02/17]. Copyright © ICE Publishing, all rights reserved.
Management, Procurement and Law Construction arbitration in Sri Lanka
Volume 165 Issue MP2 Ranasinghe

proceedings including giving evidence in court in terms of the rele- fully serve the purpose for which it was developed, and the
vant laws and the codes of procedure. In arbitration the parties user of this mechanism would like to see this process being
select the tribunal and all matters relating to procedures, docu- made more effective. Therefore an attempt should be made to
mentary evidence and the hearing will be determined by the tribu- examine the areas which need to be addressed in order to
nal in consultation with the parties. In practice, however, it is not bring about a change that will optimise the advantages of
uncommon to see that these procedures are identical with the arbitration and make the processes more attractive.
court proceedings. One of the main advantages of arbitration
over litigation is that the arbitrator can be chosen for their exper- One of the main shortcomings that continue to be highlighted
tise as regards the particular dispute in hand. For example, in a and which has drawn widespread comment is that arbitration
dispute involving costs/payment an arbitrator with quantity sur- procedures are being made identical to the court procedures
veying expertise is ideal, whereas in a dispute involving ground and as such are subject to undue delay and cost. The Sri
conditions an arbitrator with civil engineering expertise would Lankan Arbitration Act attempts to overcome this by casting
be most suitable. There is no such scope for choosing the back- a duty on the tribunal to deal with the arbitration in a practical
ground/expertise of the judge in litigation. and expeditious manner (Section 15). At the same time the Act
gives the freedom to the parties to agree on procedures for the
Generally, in litigations the parties are represented by lawyers conduct of the proceedings with no specific powers to the tribu-
and in arbitration the parties will be represented by lawyers or nal in this respect. It is the author’s view that his latter provision
technical persons. Proceedings before court are open to the negates the effect on the duty of expeditious procedure to be
public and take place on working days and during court exercised by the tribunal and it is here that arbitrators may
hours. Arbitral proceeding are conducted privately and fail to maintain a proper balance between the two provisions
awards are not usually available to others. Hearings are held and lose control over the proceedings.
at an agreed location and working times are not limited.
Questions of procedure arise throughout the proceedings in the
In litigation there is no payment made for the services of the submission of pleadings and their subsequent amendments,
judges and use of the courtroom, and payment of costs ordered production of documents, framing of issues, type of hearing,
by court are subject to taxing in terms of scale of fee and other presentation of evidence, examinations of witnesses and most
charges fixed by court, which are usually less than what an arbi- importantly on the timetable for the proceedings. These are all
tral tribunal would award. However, in both systems there is no matters which are influenced by the type and nature of the dispute,
control over fees that legal or other representatives may actually the remedies sought and the attitudes of the parties and their
charge from their clients, this being a matter for negotiation in representative and thus a common formula cannot be applied to
both systems. In arbitration, awards for costs are based on the procedures. The only common factor in any arbitration is
actual fees paid. the tribunal who is charged with the duty to be impartial, practical
and fair and conclude the arbitration expeditiously.
In litigation the parties have right to appeal against an award but
in arbitration the grounds for challenging an award are limited, Procedures should therefore be agreed at an early stage. As a
mainly on procedural matters. They are laid down in the Sri first step, the form of procedure that is most appropriate to
Lankan Arbitration Act (Parliament of Sri Lanka, 1995). From the dispute should be agreed. The three accepted forms of
the viewpoint of the construction industry, litigation provides procedure are listed here.
the opportunity for the development of the construction law in
the country. According to the Sri Lankan Arbitration Act, the (a) Documents only, which does not involve an oral evidence
arbitrator has the discretion to determine the actual cost incurred and the disputed sums are small and do not warrant the
at the arbitration that can be awarded to the innocent party. cost of oral evidence.
However, the tendency in Sri Lanka is to award as costs a (b) Short hearing which is based on written submissions of
minor sum which is disproportionate to the expenses made by claim and cross examination of witnesses is permitted but
the innocent party, and it is the author’s belief that this tendency the times allowed are very limited.
of awarding minimal costs is a reflection of court practice. (c) Full procedure, with written submissions, documentary
evidence, issues, oral submissions, examination of
4. Making arbitration attractive witnesses and experts, etc.
Arbitration has been developed as an alternative to litigation in
order to provide a mechanism for the fair, speedy and cost- In deciding the procedures, a tribunal should adopt a positive/
effective resolution of a dispute. However, judging from the active role rather than allowing the parties and their representa-
various commentaries on arbitration as a means of dispute tives to decide the course of the arbitration. Having obtained
resolution, there is general dissatisfaction in that it does not some idea of the dispute and material which the parties are relying

93
Downloaded by [ UNIVERSITY OF TOKYO] on [10/02/17]. Copyright © ICE Publishing, all rights reserved.
Management, Procurement and Law Construction arbitration in Sri Lanka
Volume 165 Issue MP2 Ranasinghe

on, the tribunal should be in a position to reject any procedures mechanisms such as mediation, conciliation, dispute review,
which would result in a long delay of the proceedings. It should adjudication, etc. have been woven into the dispute resolution
decide a procedure where it is possible to carry out proceedings system in the standard form of contract with arbitration retain-
in an expeditious manner. The procedure to be decided should ing its place as the last resort for achieving a binding and
be such that it is consistent with the importance and the value enforceable settlement. The decisions arrived through these
of the dispute and issues involved. In addition it must allow mechanisms, except through arbitration, are not final and
reasonable time for making submissions, oral evidence, etc. binding and its effectiveness depends on the will of the parties.

In the conduct of arbitration in Sri Lanka in particular, where A significant trend shown in the above changes to the dispute
most arbitrators do not have the training and experience of resolution mechanism in standard contract forms is the recogni-
functioning as arbitrators, tend to take the initiative to act in tion of the need to have independent, impartial persons with
the manner proposed above. Reference has already been made experience in the work related to the dispute as members of
to the provisions of the Act from which arbitrators may dispute review boards, a role the experienced engineering pro-
derive their power to rule on procedures. The provision on fessional in the construction industry will be called upon to fill.
determining procedures is brief and not properly defined.
Pressure is also building up for arbitration tribunals to be
With regard to cost, the practice followed by most of the arbi- assigned a more positive and active role which will make the
trators is that the unsuccessful party is ordered to reimburse arbitration process speedier and more cost effective. Regardless
the cost of the successful party. But the delay in arbitration of whether the arbitrators are lawyers or technical personnel, in
proceeding may also be caused by both parties and therefore future it will require them to play a more active role, and in
the cost has to be worked out depending on the lapses of the order to achieve this they would have to extend their knowledge
parties in participation at the proceedings. beyond their field of expertise. While all arbitrators will have
to extend their knowledge of the contract forms and their
Similar to the model law and other arbitration acts, the Sri interpretation, technical arbitrators will have to develop their
Lanka Arbitration Act (Parliament of Sri Lanka, 1995) also knowledge of the relevant laws and lawyers will have to be
attempts to resolve construction as well as other disputes in knowledgeable on how the construction industry operates and
order to give a finality to a dispute between the disputing parties. on construction matters.
The arbitration procedure in general leaves very little room for
further litigation and instances where a party could appeal an REFERENCES
arbitration decision is extremely limited according to the Sri Fidic (Fédération Internationale des Ingénieurs-Conseils)
Lankan Arbitration Act. This is equally applicable when enfor- (1999) Conditions of Contract for Plant and Design-Build,
cing awards where the arbitration had taken place in a foreign 1st edn. Fidic, Geneva, Switzerland.
country. In Sri Lanka, as the Arbitration Act has been intro- Kanag-Iswaran K and Wijeratne SS (eds) (2007) Arbitration
duced very recently, still the people who are participating in arbi- Law in Sri Lanka, 2nd edn. Institute for the Development
tration are reluctant to apply standard arbitration procedures of Commercial Law and Practice, Colombo, Sri Lanka.
like the Uncitral rules. Therefore, Sri Lankan arbitration pro- Parliament of Sri Lanka (1995) Arbitration Act (No. 11 of
cedures are mostly conducted using ad hoc procedures, which 1995). Parliament of Sri Lanka, Colombo, Sri Lanka.
would lead to delays and extra cost to the parties. The legal
and procedural issues also crop up in arbitration due to the
adoption of ad hoc procedures. Although the arbitration centres
WHAT DO YOU THINK?
in Sri Lanka have their own procedures, still the construction
To discuss this paper, please email up to 500 words to the
industry in Sri Lanka has not widely accepted these procedures.
editor at journals@ice.org.uk. Your contribution will be
Therefore, the industry has to link with these arbitration centres
forwarded to the author(s) for a reply and, if considered
in order to popularise these standards procedures.
appropriate by the editorial panel, will be published as a
discussion in a future issue of the journal.
5. Conclusion
Due to its tendency to follow court procedures the arbitration Proceedings journals rely entirely on contributions sent in
procedure is not always successful in serving as an expedient by civil engineering professionals, academics and students.
and cost-effective mechanism for resolution of disputes in the Papers should be 2000–5000 words long (briefing papers
construction industry. In order to meet this shortcoming, the should be 1000–2000 words long), with adequate illustra-
traditional institutions in the engineering field have searched tions and references. You can submit your paper online
and developed mechanisms which are more suited to the via www.icevirtuallibrary.com/content/journals, where you
needs of the industry. These non-adversarial, user-friendly will also find detailed author guidelines.

94
Downloaded by [ UNIVERSITY OF TOKYO] on [10/02/17]. Copyright © ICE Publishing, all rights reserved.

S-ar putea să vă placă și