Documente Academic
Documente Profesional
Documente Cultură
Patrick E. Durnal, Senior Engineer, Ben C. Gerwick, Inc. San Francisco, CA, USA
Henrik Dahl, Vice President, Ben C. Gerwick, Inc. San Francisco, CA, USA
A joint venture of Ben C. Gerwick Inc., Sverdrup (now Jacobs) and DMJM (now
DMJM Harris) designed the $779 mill seismic upgrade of the Richmond - San
Rafael Bridge over the San Pablo Bay in the San Francisco Bay Area and
provided construction support to Caltrans. Construction of the marine foundation
retrofit was completed by a joint venture of Tudor Saliba/Tidewater/Koch-
Skanska and their subcontractors: Pomeroy Precast Construction, AGRA
Foundations, Dutra Construction and Vortex Divers. Construction management
and inspection was performed by Caltrans with support of various consultants.
MARINE FOUNDATION RETROFIT SCOPE piers with grouted annulus. The precast pile
caps were founded with 14 inch diameter steel
The retrofit design of the submerged foundations pipe piles, which were either support piles or
included: seismic tension and compression piles. The
• A total of 476 tension and compression seismic piles were connected in grouted
micropiles (290-1140 kips) installed corrugated steel pipe sleeves cast into the new
through cored holes through the concrete pile caps.
underwater bells at 31 pier locations
• Fourteen 126/150/164 inch diameter
CISS concrete shear piles (1160-2660
kips) installed through new precast
concrete pile cap extensions. (See
Figure 1.)
• Twelve CIDH shear piles (1060-2130
kips) with 150 inch diameter steel shells
to top of bedrock and 30 ft long and 11 ft
diameter rock socket installed through
new precast concrete pile cap
extensions.
Divers cut the 14 inch piles and inserted Figure 9: Lowering Frame
spudded bearing plate landing pads and shims
to level the pile cap and transfer load to the
piles. The precast caps were fitted with guide The CIDH/CISS steel piles were pitched from
beams in order to be jacked together from each horizontal to vertical and slowly lowered through
side. (See Figures 8 and 9) Heavy lift crane the sleeves in the pile caps until they stopped in
barges and lowering frames were used to set the marine sediments. (See Figure 10.)
the shells.
An IHC S-500 hydro-hammer was placed on top
The precast shells were bolted to the belled of the large steel shells. (See Figure 11.) When
footing steel casing shells by divers. Tremie the top of the shell was low enough, a follower
concrete was pumped into the closure pour or conductor casing was added to the top of the
pockets. The seismic 14 inch pipe piles had shells to prevent the hammer sleeve from hitting
shear rings for connection in the pile cap and the pile caps and to allow cleanout of the piles
were driven through metal sleeves in the pile and over pour of the tremie concrete.
caps. This sleeved connection was sealed with
plywood at the soffit by divers for the final
placement of underwater neat cement grout.
large CIDH sockets were drilled with a Seacore
T40 pile top drill. Structural steel frames
connected to the existing pier prevented
conductor casing rotation and provided lateral
support for the drilling oscillations. The roller
cone drilling shield was equipped with a long
shroud casing on top to protect the tooling from
cave-ins and to increase the velocity of slurry
flow along the sides of the 11 ft diameter
sockets. The airlifted reverse circulation flow
rates were high, so the roller cones were
constantly cleaned free of cuttings. The drilling
went well on all the sockets.