Sunteți pe pagina 1din 1

Ma.

Trisha Anne De Vera Cayetano

Item Descrption Unit Qty. Material Cost Labor Cost Unit Cost Total Cost
Unit Total Unit Total
B Unit-2 Parking Area (Foundation, Columns, Beams, 2nd Basement Slab, Ground Floor Slab-Road Level)
Concrete (Footings) cu.m. 9.00 3,977.50 35,797.50 795.50 7,159.50 4,773.00 42,957.00
Concrete (Columns) cu.m. 8.00 3,977.50 31,820.00 795.50 6,364.00 4,773.00 38,184.00
Concrete (Roof Deck Beams) cu.m. 10.00 3,977.50 39,775.00 795.50 7,955.00 4,773.00 47,730.00
Concrete (Roof Deck Slab) cu.m. 10.00 3,977.50 39,775.00 795.50 7,955.00 4,773.00 47,730.00
Steel Reinforcements kg. 2,220.00 36.00 79,920.00 8.00 17,760.00 44.00 97,680.00
No. 16 Galvanized Iron Wire kg. 45.00 85.00 3,825.00 - - 85.00 3,825.00
Form Works and Scaffolding sq.m. 159.50 200.00 31,900.00 80.00 12,760.00 280.00 44,660.00
sub total 262,812.50 52,794.00 279,809.00
Masonry Works (Railing Enclosure at Ground Floor-Road Level)
4" C.H.B. pcs. 562.50 13.00 7,312.50 3.00 1,687.50 16.00 9,000.00
10ᴓ x 6m deformed bar (Grade 40) kg. 122.00 36.00 4,392.00 8.00 976.00 44.00 5,368.00
No.16 Galvanized Iron Wire kg. 2.44 85.00 207.40 - - 85.00 207.40
Portland Cement (mortar) bag 18.00 211.00 3,798.00 42.20 759.60 253.20 4,557.60
Sand (mortar) cu.m. 2.00 700.00 1,400.00 140.00 280.00 840.00 1,680.00
sub total 17,109.90 3,703.10 20,813.00
Total Labor Cost 279,922.40
Total Material Cost 56,497.10
Total Cost 336,419.50