Sunteți pe pagina 1din 1

Principle Perspective Engineering Sdn Bhd Matrix Project Schedule Date : 25-06-2015

ID Task Name Duration Start Finish Resource Names 2016


July August September October November December January February March April May June July
21280512192602091623300613202704111825010815222906132027031017243107142128061320270310172401081522290512192603101724
1 Mobilization 11 days Wed 01/07/15 Wed 15/07/15 Pile Cap Team 10

2 Pile Cap 21.3 days Thu 16/07/15 Fri 14/08/15 RC Works 30

3 Ground Floor 26 days Thu 30/07/15 Thu 03/09/15 RC Works 30

4 Mezzanine Floor 32 days Thu 20/08/15 Fri 02/10/15 RC Works 30

5 First Floor 52 days Thu 10/09/15 Fri 20/11/15 RC Works 30

6 Mezzanine Level 1A 30 days Mon 19/10/15 Fri 27/11/15 RC Works 30

7 Second Floor 50 days Mon 09/11/15 Fri 15/01/16 RC Works 30

8 Mezzanine Level 2A 30 days Mon 21/12/15 Fri 29/01/16 RC Works 30

9 Roof Level 36 days Mon 11/01/16 Mon 29/02/16 RC Works 30

10 Roof Steel Work 13 days Tue 01/03/16 Thu 17/03/16 Steel Workers 8

11 External Wall 93 days Mon 23/11/15 Wed 30/03/16 Brick Layer 40

12 Internal Wall 85 days Mon 30/11/15 Fri 25/03/16 Brick Layer 40

13 Window 88 days Tue 15/12/15 Thu 14/04/16 Window Installers

14 Door 92 days Wed 09/12/15 Thu 14/04/16 Door Installers

15 Painting 77 days Thu 28/01/16 Fri 13/05/16 Painter 3

16 External Works 158 days Fri 04/09/15 Tue 12/04/16 General 30

17 Lift, Elevator, ACMV, Electrical & Fire Protection Works 132 days Tue 15/12/15 Wed 15/06/16 -

18 Authority Inspection 21 days Thu 16/06/16 Thu 14/07/16 -

Task Project Summary Manual Task Start-only Deadline

Project: Matrix Project Schedule Split Inactive Task Duration-only Finish-only Progress
Date: Wed 24/02/16 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress
Summary Inactive Summary Manual Summary External Milestone

Page 1

S-ar putea să vă placă și