Including the cost of all materials and

labour etc. complete. But excluding


the cost of reinforcement.
Slab 1 11.4 11.4 0.12 15.636
Stair 2 3.15 0.9 0.12 0.6804
16.317 m3 9000 ₹146,849.76

6 Reinforcement for R.C.C works bent,tied


and placed in position . Using HYSD steel
including the cost of binding wire, all
materal and labour etc.complete.
Say item no 3,6,9,11 and 12 .Qty 29.983 m3
Say29.98 m3/100.00 kg 2998.3 kg 60 ₹179,895.12

7 Plastering CM 1:4.Using good


quality sand including the cost of
all materials and labour etc. complete.
Column 18 1.2 3.3 71.28
Walls 2 92.3 3.3 609.18
Beam 3 2 1 6
5 1.5 1 7.5
2 3.8 1.3 9.88
5 2.7 1.3 17.55
4 4.6 1.4 25.76
Slab 1 11.4 11.4 129.96
1 3.15 1 3.15
877.11 m2 410 ₹359,615.10

8 Laying Floor Tiles using good quality


ceramic Tiles 60x60cm including
the cost of all materials and labour etc.
floor 1 12.4 12.5 155
wall 1 18.2 3 54.54
209.54 m2 2300 ₹481,942.00

SECOND FLOOR
1 Reinforced cement concrete 1:1.5:3 for
column .Using 20mm aggregate
Including the cost of all materials and
labour etc. complete. But excluding
the cost of reinforcement.
column 18 0.2 0.4 3.5 5.04
5.04 m3 9000 ₹45,360.00

2 Solid block masonry(15cm thick)


in CM 1:5 .Using good quality Solid
block(30x15x15cm) .Including the
cost of all materials and labour etc.
outside 1 48.8 0.2 2.8 27.345
27.345

S3 4/9