Adrian Kiss
Hungarian Water Technology Corporation (HWTC)
Pristina, Kosovo, 1-3 November 2017
Table of Content
5. Biogas utilization
• Wastewater treatment
services in 200 settlements
for 570.000 consumers
• Unique features:
• The load doubbles during the summer
season
• The percentage of rainwater is high
The antecedents of wastewater treatment – main
deficiencies
The antecedents of wastewater treatment – main deficiencies
• Inadequate measurement
possibilities, the level of
automatization was low
Companies that carried out the construction work: Keszthely A-SZ konzorcium
Member of the consortium: Leader of the consortium:
New facilities:
Mechanical cleaning:
Construction of a new screen filter in a closed building, installation of 2 parallel,
mechanically-cleaned screens of 3 mm rod distance with 1250 m3/hour/unit capacity
Refurbishment of the pumps engine house and central pump, installation of 5 pumps,
18 000 m3/day
Construction of a new blast engine house with 4+1 air blower and 949-2
898 Nm3/d/unit capacity
The recovery of biogas
Facilities:
Biological cleaning:
Reconstruction of the old blast-engine house with 3+1 air blowers and
949- 2 898 Nm3/d/unit capacity
Specific energy
content of the biogas
• 6,3 kWh/m3
Energy availability • 85 %
Standby energy at
CHP
• 1109 kWh/m3
The prime contractor took care of the following tasks during the project implementation
process:
• Authorization procedures
• Pollution decrease in surface waters and future water reserves (Lake Balaton), improvment of
water quality
• Increase in the number of modern wastewater treatment systems that are in full compliance
with EU regulations
• Decrease in the operational costs of the WWTP and sludge is reused for energy purposes with
anaerobe digestion.