BREAD
lead time 6 days
every day demand 120
lead time CONSUMPTION 720 6*120
what is the ROL plus safety stock ?
variation from average std deviation 25
SLEVEL 0.95
ROL norminv(sl,mean lead time csn,sd) 558.0387891386
here lead time csn
sdvn
ROL
reorder level
720
25 safty stock 32
say 560
order 1788 or say 1800 whenever stock comes down to558 or say 560
ROL
317
521
163
189
104
146
111
p system
EOQ 3417.601
n 12.81601
review period 28.48001
once in 54 days