CRONOGRAMA DE AVANCE DE OBRA VALORIZADO

PROYECTO:“MEJORAMIENTO DEL SERVICIO DEL SISTEMA DE RIEGO DEL CANAL SAN MARCOS, DISTRITO DE PACARAN - PROVINCIA DE CAÑETE - REGION LIMA.

UBICACIÓN: PACARAN
PLAZO DE EJECUCION: 156 DIAS CALENDARIOS
VALOR REFERENCIAL S/. 4,837,124.85
FECHA: FEBRERO 2018

Item UND METRADO P.U PARCIAL 1 MES 2 MES 3 MES 4 MES 5 MES 6MES Total (S/.)

01 OBRAS PRELIMINARES 55,433.09 S/. 55,433.09


01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 7.20X4.80M und 1.00 1,310.49 1,310.49 S/. 1,310.49 S/. 1,310.49
01.02 CASETA PARA GUARDIANIA Y/O DEPOSITO m2 40.00 52.99 2,119.60 S/. 2,119.60 S/. 2,119.60
01.03 HABILITACION DE CAMINO DE ACCESO m2 4,950.00 3.94 19,503.00 S/. 19,503.00 S/. 19,503.00
01.04 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS Y MAQUINARIAS glb 1.00 32,500.00 32,500.00 S/. 32,500.00 S/. 32,500.00
02 SEGURIDAD Y SALUD 30,900.00 S/. 30,900.00
02.01 ELABORACION,IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE SEG glb 1.00 5,000.00 5,000.00 S/. 5,000.00 S/. 5,000.00
02.02 EQUIPOS DE PROTECCION INDIVIDUAL glb 1.00 7,500.00 7,500.00 S/. 7,500.00 S/. 7,500.00
02.03 EQUIPOS DE PROTECCION COLECTIVA glb 1.00 7,500.00 7,500.00 S/. 7,500.00 S/. 7,500.00
02.04 SEÑALIZACION TEMPORAL DE SEGURIDAD glb 1.00 1,200.00 1,200.00 S/. 1,200.00 S/. 1,200.00
02.05 CAPACITACION EN SEGURIDAD Y SALUD glb 1.00 2,500.00 2,500.00 S/. 2,500.00 S/. 2,500.00
02.06 RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN SEGURIDAD Y SA glb 1.00 7,200.00 7,200.00 S/. 7,200.00 S/. 7,200.00
03 CAPTACION (CAUDAL =0.250 m3/s) 96,987.92 S/. 96,987.92
03.01 BOCATOMA 80,599.24 S/. 80,599.24
03.01.01 OBRAS PRELIMINARES 982.00 S/. 982.00
03.01.01.01 LIMPIEZA Y DESBROCE DEL TERRENO MANUAL m2 200.00 3.03 606.00 S/. 606.00 S/. 606.00
03.01.01.02 TRAZO, NIVELES Y REPLANTEO m2 200.00 1.88 376.00 S/. 376.00 S/. 376.00
03.01.02 MOVIMIENTO DE TIERRAS 14,731.17 S/. 14,731.17
03.01.02.01 EXCAVACION MANUAL EN ROCA SUELTA m3 78.77 73.33 5,776.20 S/. 5,776.20 S/. 5,776.20
03.01.02.02 COMPACTACION MANUAL DE TERRENO m2 201.28 12.66 2,548.20 S/. 2,548.20 S/. 2,548.20
03.01.02.03 ELIMINACION DE MATERIAL EXCEDENTE CARGUÍO MANUAL, DIST = 30m3 102.40 31.28 3,203.07 S/. 3,203.07 S/. 3,203.07
03.01.02.04 EXTRACCION, SELECION Y ACOPIO DE PIEDRAS m3 28.63 51.25 1,467.29 S/. 1,467.29 S/. 1,467.29
03.01.02.05 CARGUIO DE PIEDRAS m3 28.63 60.65 1,736.41 S/. 1,157.61 S/. 578.80 S/. 1,736.41
03.01.03 OBRAS DE CONCRETO SIMPLE 17,610.43 S/. 17,610.43
03.01.03.01 CONCRETO F'c=100 (solado) m3 9.50 314.29 2,985.76 S/. 2,985.76 S/. 2,985.76
03.01.03.02 CONCRETO CICLOPEO f'c=175 kg/cm2 + 30% P.G. m3 20.00 501.26 10,025.20 S/. 10,025.20 S/. 10,025.20
03.01.03.03 ALBAÑILERIA DE PIEDRA E= 0.15m, ASENTADA F'C=175 kg/cm2 y E m2 114.50 40.17 4,599.47 S/. 4,599.47 S/. 4,599.47
03.01.04 OBRAS DE CONCRETO ARMADO 42,505.80 S/. 42,505.80
03.01.04.01 CONCRETO F'C=175 KG/CM2.+ 30%PM m3 61.03 507.26 30,958.08 S/. 27,518.29 S/. 3,439.79 S/. 30,958.08
03.01.04.02 ENCOFRADO Y DESENCOFRADO m2 183.05 35.64 6,523.90 S/. 6,523.90 S/. 6,523.90
03.01.04.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 1,350.49 3.72 5,023.82 S/. 5,023.82 S/. 5,023.82
03.01.05 TARRAJEOS Y ENLUCIDO 3,767.65 S/. 3,767.65
03.01.05.01 TARRAJEO IMPERMABILIZANTE SIKA 1:3 E=1" m2 124.14 30.35 3,767.65 S/. 3,767.65 S/. 3,767.65
03.01.06 CARPINTERIA METALICA 1,002.19 S/. 1,002.19
03.01.06.01 COMPUERTA METALICA C/SIST. IZAJE DE 0.80 X0.60m ,e=1/4" CANAL D und 1.00 687.56 687.56 S/. 687.56 S/. 687.56
03.01.06.02 REJILLAS METALICA EN VENTANA DE CAPTACION DE E1.00 x 0.20m und 1.00 314.63 314.63 S/. 314.63 S/. 314.63
03.02 DESARENADOR 16,388.68 S/. 16,388.68
03.02.01 OBRAS PRELIMINARES 324.06 S/. 324.06
03.02.01.01 LIMPIEZA Y DESBROCE DEL TERRENO MANUAL m2 66.00 3.03 199.98 S/. 199.98 S/. 199.98
03.02.01.02 TRAZO, NIVELES Y REPLANTEO m2 66.00 1.88 124.08 S/. 124.08 S/. 124.08
03.02.02 MOVIMIENTO DE TIERRAS 6,576.84 S/. 6,576.84
03.02.02.01 EXCAVACION MANUAL EN MATERIAL SUELTO m3 13.94 30.32 422.66 S/. 422.66 S/. 422.66
03.02.02.02 EXCAVACION EN TERRENO ROCOSO m3 20.91 119.25 2,493.52 S/. 2,493.52 S/. 2,493.52
03.02.02.03 RELLENO COMPACTADO CON MATERIAL PROPIO m3 13.94 44.18 615.87 S/. 615.87 S/. 615.87
03.02.02.04 REFINE, NIVELACION Y FONDOS m2 39.02 25.06 977.84 S/. 977.84 S/. 977.84
03.02.02.05 ELIMINACION DE MATERIAL EXCEDENTE m3 55.06 37.54 2,066.95 S/. 2,066.95 S/. 2,066.95
PROYECTO:“MEJORAMIENTO DEL SERVICIO DEL SISTEMA DE RIEGO DEL CANAL SAN MARCOS, DISTRITO DE PACARAN - PROVINCIA DE CAÑETE - REGION LIMA.

UBICACIÓN: PACARAN
PLAZO DE EJECUCION: 156 DIAS CALENDARIOS
VALOR REFERENCIAL S/. 4,837,124.85
FECHA: FEBRERO 2018

Item UND METRADO P.U PARCIAL 1 MES 2 MES 3 MES 4 MES 5 MES 6MES Total (S/.)

03.02.03 CONCRETO SIMPLE 381.91 S/. 381.91


03.02.03.01 ALBAÑILERIA DE PIEDRA ASENTADA EN CONCRETO F'C=175 KG/CM2 m3 0.94 323.51 304.10 S/. 304.10 S/. 304.10
03.02.03.02 SOLADO e=3" m2 1.94 40.11 77.81 S/. 77.81 S/. 77.81
03.02.04 OBRAS DE CONCRETO ARMADO 7,980.50 S/. 7,980.50
03.02.04.01 CONCRETO f'c=210 kg/cm2 e=0.10 m. Dosf. : C:A:P 1:1.75:2 m3 6.56 612.84 4,020.23 S/. 4,020.23 S/. 4,020.23
03.02.04.02 ENCOFRADO Y DESENCOFRADO CARAVISTA m2 28.11 57.11 1,605.36 S/. 535.12 S/. 1,070.24 S/. 1,605.36
03.02.04.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 633.04 3.72 2,354.91 S/. 588.73 S/. 1,766.18 S/. 2,354.91
03.02.05 JUNTAS Y SELLOS 34.94 S/. 34.94
03.02.05.01 JUNTAS DE DILATACION ASFALTICAS - 1" X 4" m 4.40 7.94 34.94 S/. 34.94 S/. 34.94
03.02.06 CARPINTERIA METALICA 496.33 S/. 496.33
03.02.06.01 COMPUERTA DE PLANCHA METALICA DE VOLANTE e=1/4" ancho 0.60m und 1.00 496.33 496.33 S/. 496.33 S/. 496.33
03.02.07 VARIOS 594.10 S/. 594.10
03.02.07.01 CURADO DE OBRAS DE CONCRETO CON ADITIVO m2 75.30 5.18 390.05 S/. 390.05 S/. 390.05
03.02.07.02 ENSAYO DE ROTURA DE TESTIGO DE CONCRETO und 7.00 29.15 204.05 S/. 204.05 S/. 204.05
04 CANAL DE CONDUCCION 2,454,743.95 S/. 2,454,743.95
04.01 OBRAS PRELIMINARES 35,646.60 S/. 35,646.60
04.01.01 LIMPIEZA Y DESBROCE DEL TERRENO MANUAL m2 7,260.00 3.03 21,997.80 S/. 21,997.80 S/. 21,997.80
04.01.02 TRAZO, NIVELES Y REPLANTEO m2 7,260.00 1.88 13,648.80 S/. 13,648.80 S/. 13,648.80
04.02 MOVIMIENTO DE TIERRAS 282,080.27 S/. 282,080.27
04.02.01 EXCAVACION A MANO EN TERRENO NORMAL m3 118.26 73.33 8,672.01 S/. 1,156.27 S/. 7,515.74 S/. 8,672.01
04.02.02 EXCAVACION EN ROCA FRACTURA m3 62.09 109.98 6,828.66 S/. 1,138.11 S/. 5,690.55 S/. 6,828.66
04.02.03 EXCAVACION EN ROCA MACIZA CON EQUIPO Y ESPLOSIVOS m3 17.74 138.14 2,450.60 S/. 1,633.73 S/. 816.87 S/. 2,450.60
04.02.04 PERFILADO Y COMPACTACION MANUAL m2 6,450.00 22.58 145,641.00 S/. 145,641.00 S/. 145,641.00
04.02.05 EXCAVACION MANUAL DE ZANJA PARA CANAL DE CONCRETO m3 118.26 46.37 5,483.72 S/. 1,096.74 S/. 4,386.98 S/. 5,483.72
04.02.06 PERFILADO Y COMPACTADO DE SUPERFICIE DE PARA CANAL DE CONCR m 3,300.00 30.06 99,198.00 S/. 99,198.00 S/. 99,198.00
04.02.07 RELLENO COMPACTADO CON MATERIAL PROPIO m3 66.00 66.79 4,408.14 S/. 4,408.14 S/. 4,408.14
04.02.08 ELIMINACION DE MATERIAL EXCEDENTE m3 250.35 37.54 9,398.14 S/. 4,699.07 S/. 4,699.07 S/. 9,398.14
04.03 MEJORAMIENTO DE SUELO 94,380.00 S/. 94,380.00
04.03.01 MEJORAMAIENTO DE SUELO (HORMIGON) m3 858.00 110.00 94,380.00 S/. 82,582.50 S/. 11,797.50 S/. 94,380.00
04.04 OBRAS DE CONCRETO 2,033,056.08 S/. 2,033,056.08
04.04.01 CONCRETO F'c=100kg/cm2 (solado) m3 765.00 287.61 220,021.65 S/. 220,021.65 S/. 220,021.65
04.04.02 CONCRETO f'c=175 kg/cm2 m3 1,895.40 459.95 871,789.23 S/. 406,834.97 S/. 464,954.26 S/. 871,789.23
04.04.03 ENCOFRADO Y DESENCOFRADO m2 14,760.00 35.64 526,046.40 S/. 526,046.40 S/. 526,046.40
04.04.04 TARRAJEO MUROS INTERIORES Y EXTERIORES m2 14,760.00 28.13 415,198.80 S/. 415,198.80 S/. 415,198.80
04.05 JUNTAS Y SELLOS 9,581.00 S/. 9,581.00
04.05.01 JUNTAS DE DILATACION CON ASFALTO RC-250 m 1,430.00 6.70 9,581.00 S/. 6,706.70 S/. 2,874.30 S/. 9,581.00
05 TOMA LATERAL 114,860.32 S/. 114,860.32
05.01 OBRAS PRELIMINARES 1,178.40 S/. 1,178.40
05.01.01 LIMPIEZA Y DESBROCE DEL TERRENO MANUAL m2 240.00 3.03 727.20 S/. 727.20 S/. 727.20
05.01.02 TRAZO Y REPLANTEO m2 240.00 1.88 451.20 S/. 451.20 S/. 451.20
05.02 MOVIMIENTO DE TIERRAS 31,131.31 S/. 31,131.31
05.02.01 EXCAVACION A MANO EN TERRENO NORMAL m3 144.00 73.33 10,559.52 S/. 10,559.52 S/. 10,559.52
05.02.02 RELLENO COMPACTADO CON MATERIAL PROPIO m3 98.40 44.18 4,347.31 S/. 4,347.31 S/. 4,347.31
05.02.03 REFINE, NIVELACION Y FONDOS m2 216.00 25.06 5,412.96 S/. 5,412.96 S/. 5,412.96
05.02.04 ELIMINACION DE MATERIAL EXCEDENTE m3 288.00 37.54 10,811.52 S/. 4,324.61 S/. 6,486.91 S/. 10,811.52
PROYECTO:“MEJORAMIENTO DEL SERVICIO DEL SISTEMA DE RIEGO DEL CANAL SAN MARCOS, DISTRITO DE PACARAN - PROVINCIA DE CAÑETE - REGION LIMA.

UBICACIÓN: PACARAN
PLAZO DE EJECUCION: 156 DIAS CALENDARIOS
VALOR REFERENCIAL S/. 4,837,124.85
FECHA: FEBRERO 2018

Item UND METRADO P.U PARCIAL 1 MES 2 MES 3 MES 4 MES 5 MES 6MES Total (S/.)

05.03 OBRAS DE CONCRETO 42,639.27 S/. 42,639.27


05.03.01 CONCRETO F'c=100kg/cm2 (solado) m3 4.08 287.61 1,173.45 S/. 1,173.45 S/. 1,173.45
05.03.02 CONCRETO f'c=175 kg/cm2 m3 25.27 459.95 11,622.94 S/. 11,622.94 S/. 11,622.94
05.03.03 CONCRETO F'C=210 KG/CM2 m3 43.20 490.55 21,191.76 S/. 21,191.76 S/. 21,191.76
05.03.04 ENCOFRADO Y DESENCOFRADO DE OBRAS DE ARTE m2 241.92 31.28 7,567.26 S/. 945.91 S/. 6,621.35 S/. 7,567.26
05.03.05 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 291.36 3.72 1,083.86 S/. 1,083.86 S/. 1,083.86
05.04 TARRAJEOS Y ENLUCIDO 9,023.82 S/. 9,023.82
05.04.01 TARRAJEO CON IMPERMABILIZANTE SIKA 1:3 E=1" m2 342.72 26.33 9,023.82 S/. 9,023.82 S/. 9,023.82
05.05 JUNTAS Y SELLOS 578.88 S/. 578.88
05.05.01 JUNTAS DE DILATACION CON ASFALTO RC-250 m 86.40 6.70 578.88 S/. 578.88 S/. 578.88
05.06 CARPINTERIA METALICA 30,308.64 S/. 30,308.64
05.06.01 TAPA DE REJILLA ACERO DE 3/4" CADA 0.15 CON BISAGRA und 48.00 286.84 13,768.32 S/. 13,768.32 S/. 13,768.32
05.06.02 BOCAL DE ENTRADA DE ACERO DE 1/2" (0.50x1.20) und 48.00 344.59 16,540.32 S/. 16,540.32 S/. 16,540.32
06 PASE PUENTE PEATONAL 1,506.15 S/. 1,506.15
06.01 TRABAJOS PRELIMINARES 61.96 S/. 61.96
06.01.01 LIMPIEZA DEL TERRENO MANUAL m2 13.80 2.61 36.02 S/. 36.02 S/. 36.02
06.01.02 TRAZO, NIVELES Y REPLANTEO m2 13.80 1.88 25.94 S/. 25.94 S/. 25.94
06.02 CONCRETO ARMADO 1,444.19 S/. 1,444.19
06.02.01 CONCRETO f'c=175 kg/cm2 m3 0.92 459.95 423.15 S/. 423.15 S/. 423.15
06.02.02 ENCOFRADO Y DESENCOFRADO CARAVISTA m2 9.95 57.11 568.24 S/. 568.24 S/. 568.24
06.02.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 121.72 3.72 452.80 S/. 452.80 S/. 452.80
TRANSICION DE ENTREGA (01UND)
07 492.28 S/. 492.28
07.01 TRABAJOS PRELIMINARES 7.37 S/. 7.37
07.01.01 TRAZO Y REPLANTEO m2 3.92 1.88 7.37 S/. 7.37 S/. 7.37
07.02 MOVIMIENTO DE TIERRAS 70.95 S/. 70.95
07.02.01 EXCAVACION MANUAL EN MATERIAL SUELTO m3 2.34 30.32 70.95 S/. 70.95 S/. 70.95
07.03 OBRAS DE CONCRETO 413.96 S/. 413.96
07.03.01 CONCRETO f'c=175 kg/cm2 m3 0.90 459.95 413.96 S/. 413.96 S/. 413.96
08 MODULO DE CAPACITACION 5,000.00 S/. 5,000.00
08.01 CAPACITACION DE OPERACION Y MANTENIMIENTO glb 1.00 5,000.00 5,000.00 S/. 5,000.00 S/. 5,000.00
09 ACONDICIONAMIENTO AMBIENTAL 12,700.00 S/. 12,700.00
09.01 INFORMACION A LA POBLACION DE LAS ACTIVIDADES glb 1.00 2,200.00 2,200.00 S/. 2,200.00 S/. 2,200.00
09.02 ACCESO A LOS BOTADORES glb 1.00 3,500.00 3,500.00 S/. 3,500.00 S/. 3,500.00
09.03 ACONDICIONAMIENTO DE BOTADROS glb 1.00 3,500.00 3,500.00 S/. 3,500.00 S/. 3,500.00
09.04 EXCAVACION Y CLAUSURA DE LETRINAS DE CAMPAMENTO glb 1.00 1,000.00 1,000.00 S/. 1,000.00 S/. 1,000.00
09.05 REACONDICIONAMIENTO DE AREA OCUPADA POR CAMPAMENTO glb 1.00 2,500.00 2,500.00 S/. 2,500.00 S/. 2,500.00
10 PLAN DE MONITOREO ARQUEOLOGICO 15,000.00 S/. 15,000.00
10.01 PLAN DE MONITOREO ARQUEOLOGICO glb 1.00 15,000.00 15,000.00 S/. 15,000.00 S/. 15,000.00
11 FLETE 130,852.71 S/. 130,852.71
FLETE TERRESTRE
11.01 glb 1.00 130,852.71 130,852.71 S/. 130,852.71 S/. 130,852.71
FLETE RURAL
12 476,354.51 S/. 476,354.51
FLETE RURAL POR PESO
12.01 kg 739,018.05 0.25 184,754.51 S/. 184,754.51 S/. 184,754.51
FLETE RURAL POR VOLUMEN
12.02 m3 486.00 600.00 291,600.00 S/. 291,600.00 S/. 291,600.00

SUB - TOTAL I : 3,394,830.93 778,749.72 423,379.18 1,184,315.92 912,475.67 86,925.53 8,984.91 3,394,830.93
GASTOS GENERALES 10.00% 339,483.09 77,874.97 42,337.92 118,431.59 91,247.57 8,692.55 898.49 339,483.09
UTILIDAD 5.00% 169,741.55 38,937.49 21,168.96 59,215.80 45,623.78 4,346.28 449.25 169,741.55
SUB - TOTAL II : 3,904,055.57 895,562.18 486,886.06 1,361,963.31 1,049,347.02 99,964.36 10,332.65 3,904,055.57
I. G. V. : 18.00% 702,730.00 161,201.19 87,639.49 245,153.40 188,882.46 17,993.58 1,859.88 702,730.00
VALOR REFERENCIAL: 4,606,785.57 1,056,763.37 574,525.55 1,607,116.70 1,238,229.48 117,957.94 12,192.52 4,606,785.57
PROYECTO:“MEJORAMIENTO DEL SERVICIO DEL SISTEMA DE RIEGO DEL CANAL SAN MARCOS, DISTRITO DE PACARAN - PROVINCIA DE CAÑETE - REGION LIMA.

UBICACIÓN: PACARAN
PLAZO DE EJECUCION: 156 DIAS CALENDARIOS
VALOR REFERENCIAL S/. 4,837,124.85
FECHA: FEBRERO 2018

Item UND METRADO P.U PARCIAL 1 MES 2 MES 3 MES 4 MES 5 MES 6MES Total (S/.)

SUPERVISION 5.00% 230,339.28 52,838.17 28,726.28 80,355.84 61,911.47 5,897.90 609.63 230,339.28
T O TAL G E N E RAL: 4,837,124.85 1,109,601.54 603,251.82 1,687,472.54 1,300,140.96 123,855.84 12,802.15 4,837,124.85

AVAN C E PAR C IAL ( % ) 22.94% 12.47% 34.89% 26.88% 2.56% 0.26% 100.00%

AVAN C E AC U M U LAD O ( % ) 22.94% 35.41% 70.30% 97.18% 99.74% 100.00%


CRONOGRAMA DE DESEMBOLSOS
PROYECTO:“MEJORAMIENTO DEL SERVICIO DEL SISTEMA DE RIEGO DEL CANAL SAN MARCOS, DISTRITO DE PACARAN - PROVINCIA DE
CAÑETE - REGION LIMA.
UBICACIÓN: PACARAN
PLAZO DE EJECUCION: 156 DIAS CALENDARIOS
VALOR REFERENCIAL S/. 4,837,124.85
FECHA: FEBRERO 2018

Item Descripción 1 MES 2 MES 3 MES 4 MES 5 MES 6 MES Total (S/.)

SUB - TOTAL I : 778,749.72 423,379.18 ### 912,475.67 86,925.53 8,984.91 3,394,830.93

GASTOS GENERALES 10.00% 77,874.97 42,337.92 118,431.59 91,247.57 8,692.55 898.49 339,483.09

UTILIDAD 5.00% 38,937.49 21,168.96 59,215.80 45,623.78 4,346.28 449.25 169,741.55

SUB - TOTAL II : 895,562.18 486,886.06 ### ### 99,964.36 10,332.65 3,904,055.57

I. G. V. : 18.00% 161,201.19 87,639.49 245,153.40 188,882.46 17,993.58 1,859.88 702,730.00

VALOR REFERENCIAL ### 574,525.55 ### ### 117,957.94 12,192.52 4,606,785.57

SUPERVICION 5.00% 52,838.17 28,726.28 80,355.84 61,911.47 5,897.90 609.63 230,339.28

T O TAL G E N E RAL: ### ### 603,251.82 ### 123,855.84 12,802.15 4,837,124.85

AVA N C E PA R C I A L ( % ) 22.94% 12.47% 34.89% 26.88% 2.56% 0.26% 100%

AVA N C E A C U M U LA D O ( % ) 22.94% 35.41% 70.30% 97.18% 99.74% 100.00% -