PROCEDURE FOR INPSECTION AND TESTING EXPORT HOSE

“Uncontrolled Copy when printed”


STRINGS
Santos Indonesia Operations

OYONG FSO TERMINAL RENTAL, OPERATION


AND MAINTENANCE SERVICES -
OPERATION PHASE

CONTRACT NO.: 902351

PROCEDURE FOR INSPECTION AND


TESTING EXPORT HOSE STRINGS

00 IJ DK DY
Rev Date Description Prepared by Checked by Project approved

Bidder: Client:

Document Title: Pages:


CONSORTIUM PT.CAKRA
PROCEDURE FORBAHANA – PT.DUTA
INSPECTION ANDMARINE
TESTING EXPORT HOSE STRINGS 8
Document No.: Client Document No.: Rev:

9018426-SPJ-014-CBDM 00

Santos Indonesia Business Document No: 9812-MO-014-S-E


Ratu Plaza Office Tower Date Printed: 26/02/2018
Jl. Jend Sudirman Kav. 9 Revision No: 0
Jakarta 10270 Revision Approval Date: 16/10/2010
PO Box 6221 JKS GN 12060 Page : 1 of 9
PROCEDURE FOR INPSECTION AND TESTING EXPORT HOSE
“Uncontrolled Copy when printed”
STRINGS
Santos Indonesia Operations

“We all go home from work without injury or illness”


and
“We will lighten the footprint of our activities”

INDONESIA OPERATIONS
OYONG STANDARD OPERATING PROCEDURE
9812-MO-014-S-E

PROCEDURE FOR INSPECTION


AND TESTING EXPORT HOSE
STRINGS

DOCUMENT CUSTODIAN RONNY DARMA

DOCUMENT SPONSOR RONNY DARMA

                                                   
                                               
  
                                               
  
                                               
  
                                               
  
0 16/10/10 First Issue Ronny D. Ronny D. Ronny D.
Rev Date Description Originator Checked By Approved By
Revision Details Approval Details

Santos Indonesia Business Document No: 9812-MO-014-S-E


Ratu Plaza Office Tower Date Printed: 26/02/2018
Jl. Jend Sudirman Kav. 9 Revision No: 0
Jakarta 10270 Revision Approval Date: 16/10/2010
PO Box 6221 JKS GN 12060 Page : 2 of 9
PROCEDURE FOR INPSECTION AND TESTING EXPORT HOSE
“Uncontrolled Copy when printed”
STRINGS
Santos Indonesia Operations

DOCUMENT CONTROL
The controlled version of this document is only available in electronic form in The Information Management
System (TIMS) for Indonesia or on the Santos Indonesia Operations Environmental Health Safety
Management System (EHSMS) Tracking Database.

All printed versions of this document are uncontrolled and should be verified by accessing the electronic
document in The Information Management System (TIMS) for Indonesia or on the Santos Indonesia
Operations EHSMS via the Tracking Database on the Santos Indonesia Operations Numbering System –
Operations (document No. 9000-AD-001-S-E).

AMENDMENT PROCEDURE

Proposals for amendments to documents should be formally submitted to the Document Custodian identified
on the front page of the document by using an Operating Procedure Document Control Form.

An Operating Procedure Document Control Form is available on “The Well” via the document link on
Santos Corporate EHS Management Standard : EHSMS11.08 – Operating Procedures and Safe Work
Practices- Appendix E or via Indonesia Operations Team Site.

If this form cannot be accessed via the intranet, personnel should contract their immediate supervisor for
help on submitting the Operating Procedure Document Control Form. All requests must be made via
Operating Procedure Document Control Form, and a separate form is required for each change requested.

In agreeing to any changes to the document, the Document Custodian will assign a priority rating to the
request which will directly relate to the urgency of the request. The Document Custodian shall then instigate
the approval process.

Once approved, the Document Custodian must ensure the amendment is incorporated into the relative
EHSMS document on the Santos Indonesia Operations server.

DISTRIBUTION SCHEDULE *if necessary


Copy Position Company
No.

RECEIPT
Copy No. Issued to
Received Date: Signature

Please acknowledge receipt by signing and sending a scanned copy of this page only to Sari
at keisari.pieta@santos.com or by fax at 021-720.4503

Santos Indonesia Business Document No: 9812-MO-014-S-E


Ratu Plaza Office Tower Date Printed: 26/02/2018
Jl. Jend Sudirman Kav. 9 Revision No: 0
Jakarta 10270 Revision Approval Date: 16/10/2010
PO Box 6221 JKS GN 12060 Page : 3 of 9
PROCEDURE FOR INPSECTION AND TESTING EXPORT HOSE
“Uncontrolled Copy when printed”
STRINGS
Santos Indonesia Operations

Santos Indonesia Business Document No: 9812-MO-014-S-E


Ratu Plaza Office Tower Date Printed: 26/02/2018
Jl. Jend Sudirman Kav. 9 Revision No: 0
Jakarta 10270 Revision Approval Date: 16/10/2010
PO Box 6221 JKS GN 12060 Page : 4 of 9
PROCEDURE FOR INPSECTION AND TESTING EXPORT HOSE
“Uncontrolled Copy when printed”
STRINGS
Santos Indonesia Operations

1. PROCEDURE AND INFORMATION


PROSEDUR DAN INFORMASI

A. SAFETY AND ENVIRONMENT PRECAUTION


1. Operation will be carried out in accordance with FSO Operation Manual SHAN-0320
2. JRA will be prepared.
3. Toolbox meeting with all parties involved in operations.
4. Deploy fenders on Port Side.
5. No oil spillage into the sea
6. All operation to be carried out day light only.
7. All operation to be carried out weather permitting.
8. Customs to be informed and permission to be obtained for breaking Export valve E4
seal.

B. FLUSHING HOSE
1. Support vessel to disconnect Export Hose from Sinker buoy and bring to Shanghai Port
Side manifold.
2. Export Hose to be connected to Port manifold and flushed with water.
3. Flushing to be carried out with sea water until a clean sample from the Port manifold
sample cock received (the hose volume must be displaced at least 3 times).
4. After flushing with water P Manifold Valve to be closed and from Aft Manifold a
compressed air to be introduced.
5. Pressure to be raised to 5.0kg/cm² and subsequently P Manifold Valve to be open
allowing the fluid to be displaced by the air. Stop air supply by shutting the air valves.
6. Keep open P manifold valve until air start passing trough the P/S manifold valve. Keep
open the manifold sample cock during the air flushing. When air start coming out from
the manifold sample cock shut the P/S manifold valve. Keep open the manifold sample
cock till the hose is depressurized.
7. Shut Aft Manifold Valve.
8. Shut and lock the Hose valve.
9. Disconnect the hose from P manifold.
10. Lower into the water in order to keep end free for turning hose on 180°

D. FSO END STRING DISCONNECTION AND TURNING HOSE BY 180°


1. Mark the flanges of FSO end hose and Export manifold. This mark will be as a guideline
for Hose connection.
2. Prepare aft mooring winch with wire rope for lowering Export hose.
3. Disconnect belly wire and rope.
4. Disconnect 2 winker lights on hose.
5. Transfer weight of Export hose from turnbuckles to chain blocks which can be hooked
on the special manifold of the hose fitted with lifting lugs.
6. Disconnect Export hose from Export manifold and slack down little bit to make easy
install blank flange.
7. Fix 12” blank flange ANSI 150 connected with the fitting if required on FSO export hose
end.
8. Turn the hose by 180° by changing position of chain blocks
9. Connect hose to export manifold

Santos Indonesia Business Document No: 9812-MO-014-S-E


Ratu Plaza Office Tower Date Printed: 26/02/2018
Jl. Jend Sudirman Kav. 9 Revision No: 0
Jakarta 10270 Revision Approval Date: 16/10/2010
PO Box 6221 JKS GN 12060 Page : 5 of 9
PROCEDURE FOR INPSECTION AND TESTING EXPORT HOSE
“Uncontrolled Copy when printed”
STRINGS
Santos Indonesia Operations

C. TANKER END STRING


1. Pick up hose from water
2. Secure the hose by snubbing chain and keep the hose onboard and hang up with crane
same as when the hose position still connect with manifold (as per standard practice)
3. Full up hose with water
4. Fix 12” blank flange ANSI 150 connected with fittings for pressurize and depressurize
(included recorder and pressure gauge). Mark the flanges of the hose and valve. The
marks will be used as a guideline during the assembling.

2. PROCEDURE PRE-REQUISITES
PROSEDUR PENDAHULUAN

Step Description Initial & Time

1. Verify that this procedure is the latest revision available from


the procedure database, print out and nominate one copy as
the master for recording all feedback.
Ensure that the other pre-sequenced procedures have been
fully completed and signed off prior to commencing this
procedure, as Appendix B at the end of this document.
Yakinkan bahwa procedure ini adalah versi terbaru yang
tersedia di database.

2. Read and understand the procedure in its entirely prior to


commencement. If not clear or you are unsure of anything
regarding this procedure, consult your supervisor.

Keseluruhan prosedur ini telah dibaca dan dipahami sebelum


memulai pekerjaan. Apabila kurang jelas atau anda tidak yakin
akan prosedur ini, konsultasikan dengan pengawas anda.

3. Ensure there are no bridges or standing orders in place that


would make this task unsafe to continue. If a bridge or standing
order, does impact on safety do not continue with the job. Re-
plan the work when safe conditions will be met.

Pastikan bahwa tidak ada By-pass (Bridge) atau Standing


Order yang terpasang yang bisa mengakibatkan proses ini
tidak aman bila dilanjutkan. Bila ada, jangan teruskan
pekerjaan. Rencanakan kembali pekerjaan apabila keadaan
sudah aman.

4. Identify the nearest location of the following Safety equipment:


 Fire monitors/Fire extinguisher.
 Safety shower/Eye wash station.
 ESD/PSD station
 Escape routes

Santos Indonesia Business Document No: 9812-MO-014-S-E


Ratu Plaza Office Tower Date Printed: 26/02/2018
Jl. Jend Sudirman Kav. 9 Revision No: 0
Jakarta 10270 Revision Approval Date: 16/10/2010
PO Box 6221 JKS GN 12060 Page : 6 of 9
PROCEDURE FOR INPSECTION AND TESTING EXPORT HOSE
“Uncontrolled Copy when printed”
STRINGS
Santos Indonesia Operations

Ketahui lokasi terdekat dari:


 Fire monitors/Fire extinguisher
 Safety shower/Eye wash station
 ESD/PSD station.
Escape routes

5. Conduct a STEPBACK prior to commencing work, to check for


workplace hazards that may not have been covered in the
Hazards section above.
Eg. Have conditions changed, has anything been missed?
Lakukan STEPBACK sebelum memulai pekerjaan untuk
memeriksa kemungkinan bahaya lain yang tidak tercantum
pada Potensial Hazard diatas.
Contoh: Apabila perubahan keadaan, dll.

Work sequence Status Initial


Urutan kerja

1.
2
3.
4.
5
6
7.
8
9
10.
11.
12

Shutdown & Isolation Sequence Status Initial

Santos Indonesia Business Document No: 9812-MO-014-S-E


Ratu Plaza Office Tower Date Printed: 26/02/2018
Jl. Jend Sudirman Kav. 9 Revision No: 0
Jakarta 10270 Revision Approval Date: 16/10/2010
PO Box 6221 JKS GN 12060 Page : 7 of 9
PROCEDURE FOR INPSECTION AND TESTING EXPORT HOSE
“Uncontrolled Copy when printed”
STRINGS
Santos Indonesia Operations

Suggested Improvements
Saran untuk progres

Suggested By:

Date:

Santos Indonesia Business Document No: 9812-MO-014-S-E


Ratu Plaza Office Tower Date Printed: 26/02/2018
Jl. Jend Sudirman Kav. 9 Revision No: 0
Jakarta 10270 Revision Approval Date: 16/10/2010
PO Box 6221 JKS GN 12060 Page : 8 of 9
Valve P&ID Line
Number Number Number Status (Open/Closed)
Location and Description